This Request for Proposal solicits design-build services for Phase 2B of the modernization and expansion of the Calexico West Land Port of Entry in Calexico, California. General Services Administration seeks a contractor to provide architectural, engineering, construction, and related services. The contractor must complete demolition and construction of a new Pedestrian Processing Facility, temporary pedestrian processing, and a vehicular crossing over railroad tracks. The contractor will also be responsible for options including video surveillance, access control, communications, public address systems, fencing, solar panels, parking structures, signage, and a basement connection. The estimated price range for base work and all options is $120-200 million. Proposals are due March 21, 2024. General Services Administration intends to award a firm-fixed-price design-build contract in July-August 2024. Subcontracting goals include 21% to small businesses, with 5% each to small disadvantaged, women-owned, and veteran-owned small businesses and 3% to HUBZone small businesses.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

Project: Design-Build Services for the Modernization and Expansion of the Calexico West Land Port of Entry Phase 2B in Calexico, California

Amendment 0002 is being issued to incorporate the attached 2 documents:

1) Pre-proposal Conference SIides dated 2/14/2024

2) Pre-proposal Conference Sign-in sheet dated 2/14/2024

TO ALL PROSPECTIVE OFFERORS GSA, PBS, Acquisition Management Division (9PQPC) 50 United Nations Plaza, Mail Box 9 San Francisco, CA 94102

47PK0124R0005

02/15/2024

01/18/2024

2/15/2024

INSTRUCTIONS (Back Page):

Instructions for items other than those that are self-explanatory, are as follows:

Item 1 (Contract ID Code). Insert the contract type identification code that appears in the title block of the contract being modified.

Item 3 (Effective date).

(1)

(2)

(3)

(4)

(5)

For a solicitation amendment, change order, or administrative change, the effective date shall be the issue date of the amendment, change order, or administrative change.

For a supplemental agreement, the effective date shall be the date agreed to by the contracting parties.

For a modification issued as an initial or confirming notice of termination for the convenience of the Government, the effective date and the modification number of the confirming notice shall be the same as the effective date and modification number of the initial notice.

For a modification converting a termination for default to a termination for the convenience of the Government, the effective date shall be the same as the effective date of the termination for default.

For a modification confirming the contracting officer's determination of the amount due in settlement of a contract termination, the effective date shall be the same as the effective date of the initial decision.

(a)

(b)

(c)

(d)

(e)

(f)

Item 6 (Issued By). Insert the name and address of the issuing office. If applicable, insert the appropriate issuing office code in the code block.

Item 8 (Name and Address of Contractor). For modifications to a contract or order, enter the contractor's name, address, and code as shown in the original contract or order, unless changed by this or a previous modification.

Items 9, (Amendment of Solicitation Number - Dated), and 10, (Modification of Contract/Order Number - Dated). Check the appropriate box and in the corresponding blanks insert the number and date of the original solicitation, contract, or order.

Item 12 (Accounting and Appropriation Data).

When appropriate, indicate the impact of the modification on each affected accounting classification by inserting one of the following entries:

(2) Accounting classification Net decrease $

Include subject matter or short title of solicitation/contract where feasible.

Item 16B. The contracting officer's signature is not required on solicitation amendments. The contracting officer's signature is normally affixed last on supplemental agreements.

(i)

NOTE: If there are changes to multiple accounting classifications that cannot be placed in block 12, insert an asterisk and the words "See continuation sheet".

Item 13. Check the appropriate box to indicate the type of modification. Insert in the corresponding blank the authority under which the modification is issued. Check whether or not contractor must sign this document. (See FAR 43.103.)

Item 14 (Description of Amendment/Modification).

Organize amendments or modifications under the appropriate Uniform Contract Format (UCF) section headings from the applicable solicitation or contract. The UCF table of contents, however, shall not be set forth in this document.

Indicate the impact of the modification on the overall total contract price by inserting one of the following entries:

(i) Total contract price increased by $

(ii) Total contract price decreased by $

(iii) Total contract price unchanged.

State reason for modification.

When removing, reinstating, or adding funds, identify the contract items and accounting classifications.

(g)

(h)

When the SF 30 is used to reflect a determination by the contracting officer of the amount due in settlement of a contract terminated for the convenience of the Government, the entry in Item 14 of the modification may be limited to --

(i) A reference to the letter determination; and

(ii) A statement of the net amount determined to be due in settlement of the contract.

(1)

(2)

(3)

(4)

(5)

(6)

STANDARD FORM 30 (REV. 11/2016) BACK

(1) Accounting classification Net increase $

Design-Build Services for Calexico Land Port of Entry Phase 2B - Solicitation #47PK0124R0005

Pre-Proposal Conference and Site Walk

February 14, 2024

Introduction

•General Services Administration is the owner

•Vince Gagliardo, GSA Project Manager

•Wesley Lau, GSA Contracting Officer

•Arianna Catalinotto, GSA Project Manager

•Uma Bhatia, GSA Contract Specialist

•Customs and Border Protection is the primary tenant

•Perkins and Will is the Bridging Document A/E

•Eric Spielman, Project Architect

•Construction Manager contract awarded around July/August 2024

Project Overview

•Phase 1

•October 2015 to September 2018

•Phase 2A

•Scheduled to be completed February 2024

•Phase 2B

•Period of performance of 54 months.

•Anticipated to begin July-August 2024

LPOE Project Overview

Site Overview

Temp Processing Site

Approximately 8,000 SF

Site Plan

Floor Plan

Main Inspection Hall

Paulin Ave Crossing

Phase 2A - Admin Building

Phase 2B - Pedestrian Building

Options

Option 7

Option 8

Option 9

Option 14

Option 14 - Tunnel

Not part of option.

Chillers part of base.

Section currently in design with UPRR.

Option 14 Tunnel

Evaluation Criteria Technical Evaluation Factors-

(a) Experience - 20%

(b)Technical and Management Approach – 15%

(c) Specialized Experience and Technical Competence – 15%

(d) Sustainability – 15%

(e) Past Performance – 15%

(f) Project Labor Agreement - 15%

(g) Small Business Utilization - 5%

Non-price factors, when combined, are significantly more important than Total Evaluated Price

Small Business Goals

•Total Subcontracted to Small Business 21%

•Of the 21% subcontracted to small business, the following % is required goals

•Small Disadvantaged Business (SDB) 5%

•Women-owned Small Business 5%

•HubZone Small Business 3%

•Service-Disabled Veteran-Owned Small Bus 3%

Important Dates

Questions regarding the RFP are due

Wednesday, February 21, 2024

Accepting questions until February 28, 2024 but can’t guarantee the questions will be answered in time to incorporate into proposal

Technical and Price Proposals are due

Thursday, March 21, 2024

Contract Award

Our anticipated contract award timeframe is

July - August 2024

Questions

Amendment 002 sf30P
DB preproposal site walk
Preproposal conference Sign-in sheet 02142024