GSA Solicitation No.47PJ0023R0041
D-B – Dunseith LPOE Design & Construction
The Solicitation
Document: DB201-1/March 2023
Design Build Contract for: Design & Construction of Dunseith Land Port of Entry
The Solicitation, Phase 1 – Request for Qualifications
Project Location: Dunseith, North Dakota
Rolette County
Contracting Office Address: General Services Administration (GSA), Public Buildings Services (PBS)
Acquisition Division (8PQ)
One Denver Federal Center, Building 41
Denver, CO 80225
General Information: NAICS: 236220, Commercial & Institutional Building Construction
NAICS Side Standard: $45.0 Million
Government
Point of Contact:
Rhonda Widick, Contracting Officer
Rhonda.Widick@gsa.gov
Christie VandenDries, Contract Specialist
Christie.VandenDries@gsa.gov
Total Contract Estimated Price Range: Between $70,000,000 and $80,000,000
Questions: All questions related to solicitation 47PJ0023R0041 shall be submitted in writing via email, to both the
Contracting Officer and Contract Specialist, no later than 10:00 AM Mountain Time, June 26, 2023.
Questions received after this cutoff may not receive a response.
Submission Due
Date/Time:
10:00 AM Mountain time, July 27, 2023. (Changed via Amendment 0001)
Submission
Requirements:
Interested Offerors shall thoroughly review the solicitation documents for all submission requirements.
Offerors shall provide an executed Proprietary Information Agreement in accordance with Section II.D. Other Information to be
Submitted with Proposals.
The award of a firm-fixed-price contract with economic price adjustment is contemplated by the Government. The award is expected to include FAR clause 52.216-4, Economic Price Adjustment – Labor and Material, which would apply only after design is complete.
Stipend: In consideration for the preparation of a Phase 2 technical proposal, GSA will pay a stipend only to the Phase 2 Offerors submitting complete acceptable Phase 2 offers that are not selected for award of the resulting contract. Offerors that submit incomplete or unacceptable Phase 2 proposals will not be eligible for the stipend. For the avoidance of doubt, no stipend is paid during Phase 1. The stipend amount to be paid to each unsuccessful offeror who submits a complete and acceptable proposal is
$100,000.00.
NOTICE: Scope of Work documents are available. To receive a copy of the scope of work documents, offerors must first complete the provided CUI Information Request Form (Solicitation Attachment 01 – Request for Controlled Unclassified Information (CUI)) and return the completed/signed document to both the Contracting Officer at Rhonda.Widick@gsa.gov and the Contract Specialist at
Christie.VandenDries@gsa.gov. Documents will be distributed to Offerors who return properly completed forms.
Notice: A bid guarantee will be required under Phase 2 of the solicitation in accordance with FAR 52.228-1, Bid Guarantee. The amount of the bid guarantee shall be 20 percent of the bid price or $3,000,000, whichever is less.
mailto:Rhonda.Widick@gsa.gov mailto:Christie.VandenDries@gsa.gov
Table of Contents
I. General Information
A. The Project
B. The Solicitation and Contract
C. List of Phase 1 Solicitation Documents
D. Authorized Representatives
E. Pre-Proposal Conference
F. Estimated Price Range
G. Questions Regarding Phase 1
H. Receipt of Qualifications
II. Proposals
A. Proposal Contents
B. Proposal Format
C. Technical Proposal
D. Other Requirements
III. General Provisions
A. Availability of Funds
B. Requests for Clarification or Interpretation
C. Notice to Small Business Firms
D. Information Concerning the Disclosure of Solicitation Results
E. Affirmative Procurement Program
F. Notice Concerning Preparation of Proposals
G. Bond Requirements (Phase 2 Requirements)
H. Contractor Performance Information
I. Safeguarding and Dissemination of Controlled Unclassified Information (CUI) Building Information
J. INFORM
IV. FAR/GSAR Solicitation Provisions
To be issued in Phase 2
V. Additional Solicitation Provisions and Instructions
A. Additional Provisions
(i) GSAR 552.236-70, Evaluation of Options (MAR 2019)
(ii) GSAR Clause 552.236-77, Government’s Right to Exercise Options (MAR 2019)
VI. Method Of Award
A. Evaluation of Phase 1 Proposals
B. Evaluation of Phase 2 Proposals
C. Determination of Responsibility
D. Price Reasonableness/Price Realism
E. Unbalanced Price
F. Total Evaluated Price
G. Non-Price Factors
I. General Information
I.A. The Project
This project is for the design and construction of the Dunseith Land Port of Entry facilities, which will include a new main inspection building, primary inspection canopy, non-commercial secondary canopy, and hard inspection building adjacent to the main building.
Construction of four new covered primary inspection lanes, new commercial secondary inspection dock and facility, and NII building.
This project is designated as a GSA Design Excellence project.
I.B. The Solicitation and Contract
(1) This procurement is being conducted using the two-phase selection process found in FAR 36.3. Qualification proposals will be evaluated in Phase One to determine which offerors will submit proposals for Phase Two. One contract will be awarded using competitive negotiation. In Phase 1, GSA will select a short list of the most highly qualified offerors and request that those offerors submit Phase 2 proposals. All responsible sources may submit a Phase 1 proposal. A maximum of three (3) firms will be selected to submit Phase 2 proposals. Only those selected offerors are authorized to submit Phase 2 proposals. Those offerors not selected for participation in Phase 2 will be notified in accordance with FAR 15.503(a). In Phase 2, Offerors may submit a price proposal subject to the Project Labor Agreement (PLA) requirements set forth in the Phase 2 solicitation (a PLA proposal), a price proposal not subject to the PLA requirements set forth in the Phase 2 solicitation, or both. Any price proposal submitted in Phase 2 shall clearly identify whether it is subject to such PLA requirements.
(2) This Solicitation sets forth requirements for Phase 1 qualifications proposals and the evaluation factors for Phase 2 proposals for a
Contract to design and construct the Project. Proposals conforming to the Solicitation requirements will be evaluated in accordance with the Method of Award set forth herein. The Government will award the Contract to the selected Offeror, subject to the conditions set forth herein.
(3) Neither the Solicitation nor any part of an Offeror's proposal shall be part of the Contract except to the extent expressly incorporated therein by the Contracting Officer.
I.C. List of Phase 1 Solicitation Documents
The Solicitation Documents are comprised of:
A. The Solicitation – Phase 1
B. Standard Form (SF) 1442 – Solicitation Offer and Award
C. Solicitation Attachment 01 – Request for Controlled Unclassified Information (CUI)
D. Solicitation Attachment 02 – Offeror’s Representations and Certifications
E. Solicitation Attachment 03 – ASHRAE – Climatic Data for Building Design Standards
F. Solicitation Attachment 04 – Past Performance Questionnaire for General Contractor
G. Solicitation Attachment 05 – Past Performance Questionnaire for Architect-Engineer
H. Draft of The Agreement
I. Draft of the Scope of Work, Appendix, Exhibits, and Other Documents.
To receive draft copies of the scope of work, appendix, exhibits, and other documents, offerors must first complete the provided CUI Information Request Form (Solicitation Attachment 01 – Request for Controlled Unclassified
Information (CUI)) and return the completed/signed document to both the Contracting Officer at
Rhonda.Widick@gsa.gov and the Contract Specialist at Christie.VandenDries@gsa.gov. Documents will be distributed to Offerors who return properly completed forms.
I.D. Authorized Representatives
The following individuals are designated as the authorized GSA representatives under this Solicitation:
Authorized Representative Information:
Contracting Officer’s Information
Name: Rhonda Widick
Address:
General Services Administration (GSA), Public Buildings
Service (PBS), Acquisition Division (8PQ)
One Denver Federal Center, Building 41
Denver, CO 80225
Telephone: 402-601-8041
Email: rhonda.widick@gsa.gov
Authorized Representative Information:
Alternate POC Information
Name: Christie VandenDries
Address:
General Services Administration (GSA), Public Buildings
Service (PBS), Acquisition Division (8PQ)
One Denver Federal Center, Building 41
Denver, CO 80225
Telephone: 720-422-2588
Email: christie.vandendries@gsa.gov
I.E. Estimated Price Range
The estimated price range for the Project (including design, construction, and all optional items) is between $70,000,000 and
$80,000,000.
I.F. Questions Regarding Phase 1
Submit all questions regarding the Phase 1 to the Contracting Officer, electronically via email, on or before 10:00 AM Mountain Time, June 26, 2023. Any responses provided by GSA will be posted on the Governmentwide Point of Entry (GPE) as an Amendment to the
Solicitation.
I.G. Receipt of Qualifications
In order to be considered for Phase 2 and award, Phase 1 qualifications proposals conforming to the requirements of the Solicitation must be received electronically no later than 10:00 AM Mountain Time on the following date and at the following addresses.
Date: July 27, 2023 (changed via Amendment 0001)
Address: rhonda.widick@gsa.gov christie.vandendries@gsa.gov mailto:rhonda.widick@gsa.gov mailto:christie.vandendries@gsa.gov
II. Proposals
II.A. Proposal Contents
Proposals shall consist of the following documents, completed, and executed in accordance with this Solicitation:
1. Technical Proposal
2. Other Documents as Required
II.B. Proposal Format
All information shall be submitted in English. Proposals that do not follow these instructions, or otherwise include documentation that is difficult to read, may result in disqualification or a lower evaluation rating.
Proposals shall be submitted in the following format: All pages shall be 8 ½” x 11”, with lettered/numbered dividers for each section to correspond with the evaluation factors. Each page shall be numbered. Proposal text shall be in a standard font a minimum of ten
(10) points for a maximum of twelve (12) points in height, single-spaced.
Emailed submissions shall be received by the Government by the proposal closing date and time. No hard copy submissions will be accepted.
All Phase 1 proposal development costs shall be borne by the Offerors without reimbursement from GSA.
II.C. Technical Proposal
Proposals should address each of the Phase 1 evaluation factors stated in Section VI.G, Non-Price Factors.
II.D. Other Information to be Submitted with Proposals
By the due date for initial offers, each offeror is required to comply satisfactorily with (1)-(3) below. An offeror’s failure to comply satisfactorily with (1)-(3) below may result in the offer being unacceptable and the offeror being disqualified from the competition and ineligible for award of the contract.
(1) Representations and Certifications
Offerors are reminded their SAM registration status must be “Active”, at the time their offer is submitted, to be considered for award (see 52.204-7). Offerors submitting a proposal in response to this Solicitation shall complete electronic Annual
Representations and Certifications in conjunction with required Entity registration in System for Award Management (SAM), accessed via System for Award Management. Offerors shall also submit with their proposal, the Annual Representations and
Certifications (FAR 52.204-8), using Solicitation Attachment 02 - Offeror’s Representations and Certifications.
(2) Proof of Bonding to $110,000,000
(3) Proprietary Information Agreement(s)
Offerors are advised that employees of the firm(s) identified below may require access to your firm’s proprietary information in performing advisory and assistance services for the Government under separate contract. The employees of the firm identified below will be authorized access only to such information that is necessary to enable them to perform their respective duties. Such firm(s) are expressly prohibited from competing on the subject acquisition.
Jacobs Technology, Inc.
600 William Northern Blvd.
Tullahoma, TN 37388-4729
Jacobs Point of Contact: Maryellen Wikoff
Jacobs Point of Contact Phone: 267-303-5654 https://www.sam.gov/
Pursuant to FAR Part 9.505-4(b), firms performing such advisory and assistance services for the Government must execute an agreement with each offeror that states that they will (1) protect the offeror’s information from unauthorized use or disclosure for as long as it remains proprietary and (2) refrain from using the information for any purpose other than that for which it was furnished.
To expedite the evaluation process, each offeror must contact the above-listed firm(s) to effect execution of such an agreement prior to the submission of proposals. Each offeror should submit copies of such bilaterally executed agreement.
III. General Provisions
III.A. Availability of Funds
Issuance of this Solicitation does not warrant that funds are presently available for award of a Contract. Award of the contract shall be subject to the availability of appropriated funds, and the Government shall incur no obligation under this Solicitation in advance of such time as funds are made available to the Contracting Officer for the purpose of contract award.
III.B. Requests for Clarification or Interpretation
The Government will attempt to answer all requests for clarifications or interpretations of the Solicitation Documents prior to the date set for receipt of offers, but do not warrant that all such requests will be answered within 15 calendar days. Prospective Offerors should make such requests not less than 15 calendar days prior to the date set for receipt of offers.
III.C. Notice to Small Business Firms
A program for the purpose of assisting qualified small business concerns in obtaining certain bid, payment, or performance bonds that are otherwise not obtainable is available through the Small Business Administration (SBA) (Small Business Administration). For information concerning SBA's surety bond guarantee assistance, contact your SBA District Office.
III.D. Information Concerning the Disclosure of Solicitation Results
This acquisition is being conducted under the provisions of FAR Part 15 as a negotiated procurement. In accordance with FAR 3.104 and FAR 15.207, after receipt of proposals, no information regarding the identity of those submitting offers, the number of offers received, or the information contained in such offers will be made available until after award except as provided by FAR 15.503.
III.E. Affirmative Procurement Program
GSA has implemented an Affirmative Procurement Program (APP) intended to maximize the use of recovered materials, environmentally preferable, and bio-based products. Offerors should familiarize themselves with the requirements for using and reporting on the use of such materials in performance as set forth in the Agreement. Refer to Clause FAR 52.223-10 encouraging vendors to practice waste reduction.
III.F. Notice Concerning Preparation of Proposals
Offerors are cautioned to carefully read the entire Solicitation and the Agreement to be included in the Contract contemplated by the
Solicitation in order to be fully aware of all requirements and clauses in the contemplated Contract. Verify that all blanks requiring information to be supplied in an Offer have been properly filled out, that all pricing and other numerical data is accurately calculated, and that all copies of the Offer contain the same information.
III.G. Bond Requirements (Phase 2 Requirements)
If a bid guarantee is required to be submitted with your offer, any contract awarded will require a performance bond and payment bond as specified in the Agreement. Offerors who utilize individual sureties should note the requirement for a certified, audited, financial statement for each person acting as an individual surety under clause FAR 52.228-1 Bid Guarantee and the requirements of clause FAR 52.228-11 Pledge of Assets.
http://www.sba.gov/
III.H. Contractor Performance Information
1. Evaluating Contractor Performance: The General Services Administration is using the Contractor Performance Assessment
Reporting System (CPARS) module as the secure, confidential, information management tool to facilitate the performance evaluation process. CPARS enables a comprehensive evaluation by capturing comments from both GSA and the contractor.
The website for CPARS is Contractor Performance Assessment
Completed CPARS evaluations may then be used by the Federal acquisition community for use in making source selection decisions. CPARS assists acquisition officials by serving as the single source for contractor past performance data.
2. CPARS Registration: Each award requiring an evaluation must be registered in CPARS. The contractor will receive several automated emails. Within thirty days of award, the contractor will receive an e-mail that contains user account information, as well as the applicable contract and order number(s) assigned. Contractors will be granted one user account to access all evaluations.
3. Contractor CPARS Training: Contractors may sign up for CPARS training. A schedule of classes will be posted to the
CPARS training site (CPARS Training) and updated as needed.
4. Contractor Representative (CR) Role: All evaluations will be sent the Contractor Representative (CR) named on your award.
The CR will be able to access CPARS to review and comment on the evaluation. If your CR is not already in the CPARS system, the contracting officer will request the name and email address of the person that will be responsible for the CR role on your award.
Once an evaluation is ready to be released the CR will receive an email alerting them the evaluation is ready for their review and comment. The email will indicate the time frame the CR has to respond to the evaluation; however, the CR may return the evaluation earlier than this date.
GSA shall provide for review at a level above the contracting officer (i.e., contracting director) to consider any disagreement between
GSA and the contractor regarding GSA’s evaluation of the contractor. Based on the review, the individual at a level above the contracting officer will issue the ultimate conclusion on the performance evaluation.
Copies of the evaluations, contractor responses, and review comments, if any, will be retained as part of the contract file.
III.I. Safeguarding and Dissemination of Controlled Unclassified Information (CUI) Building Information
Certain information contained in the Solicitation Documents may have been designated as Controlled Unclassified Information
(CUI) building information. With respect to such information, Offerors shall agree to the terms for receipt of such information, as set forth in the provision “Administrative Matters” in Section III of the Agreement, as a condition of receipt of such information.
III.J INFORM
A. Overview of the IN-depth Feedback through Open Reporting Methods (INFORM) Process
This solicitation is part of GSA’s post award communication process called INFORM. The process is designed to enhance the quality and usefulness of post-award communications by providing greater transparency and openness into the procurement process. INFORM seeks to increase GSA-industry communication by providing clearer and more complete information to explain the award decision.
Through the INFORM process, GSA will seek to share additional information with offerors in writing and/or through an oral feedback meeting that is not required by statute or regulation. For Part 15 including mandatory debriefs and
Part 16, and in addition to any information required by FAR 15.503 and 15.506, GSA is providing each offeror with the opportunity to participate in the INFORM process as further discussed below.
http://www.cpars.gov/ https://www.cpars.gov/lc.htm
B. Detailed Description of the INFORM Process
B.1 Component 1 – Notification of Award
After award and in accordance with any post-award notification timeframes required by regulation (i.e., FAR
Parts 15.503(b) and 16,505(b)(6)), the contracting officer will issue written notices to the successful and unsuccessful offerors (the Notification Letter and Evaluation Statement (NLES)). The notices will contain:
• All information required by statute or regulation;
• An unredacted copy of the complete technical evaluation for that particular offeror that includes a full description of the unsuccessful offeror’s strengths, weaknesses, risks, and deficiencies;
• An overall technical evaluation summary for that particular offeror and the successful offeror that includes evaluated price; overall technical ranking, rating, or score.
B.2 Component 2 – Request for Oral Feedback Meeting or Written Questions
Within three business days after receipt of the NLES, an offeror may, but is not required to:
• Submit a written request to the contracting officer for an oral feedback meeting;
• Submit a list of written questions to the contracting officer; or
• Take no further action.
If the offeror timely elects to request an oral feedback meeting or submit a list of written questions, GSA will consider any such request to constitute a required debriefing pursuant to FAR 15.506. If an offeror does not request an oral feedback meeting or submit a list of written questions within the three day time period, the receipt of the NLES concludes the INFORM process and satisfies the FAR requirement for debriefs pursuant to FAR 15.506.
If the offeror submits a list of written questions in lieu of the oral feedback meeting, the contracting officer will attempt to respond within five business days of receipt of the written questions. Unless otherwise stated, the contracting officer’s response to the written questions will conclude the INFORM process and any corresponding post-award debriefing as further set forth at FAR 15.506.
If the offeror requests an oral feedback meeting, the offeror should provide the following information:
• Primary point of contact;
• List of participants with titles (e.g., Senior Vice President);
• List of topics to assist GSA better prepare for the oral feedback meeting; and
• Preference for in-person, telephone, or web-based conferencing (if available)
B.3 Component 3 – Oral Feedback Meeting
During the oral feedback meeting, GSA’s objectives are to provide:
• Reasonable responses to written questions submitted by the offeror;
• Explanations for the evaluation conclusions and contract award decisions;
• Any additional information about the fairness and impartiality of the evaluation and why the award decision was rational;
• Reasonable responses to additional questions raised during the meeting;
• Additional transparency to the underlying competition process; and,
• A greater understanding of the evaluation and award process.
GSA will not provide any information that is prohibited by law or regulation.
B.4 Component 4 – Post Oral Feedback Meeting Questions
Within two business days after the conclusion of the oral feedback meeting, the offeror may submit a list of written questions to the contracting officer. The contracting officer will provide a written response within five business days and, unless otherwise noted by the contracting officer, the INFORM process and any corresponding post-award debriefing as further set forth at FAR 15.506 will have concluded.
If the offer elects to not submit a list of written questions within two days after the oral feedback meeting, the
INFORM process and any corresponding post-award debriefing as further set forth at FAR 15.506 is concluded.
IV. FAR/GSAR/GSAM Solicitation Provisions
FAR/GSAR/GSAM solicitation provisions applicable to Phase 2 will be issued with Phase 2 Solicitation.
V. Additional Solicitation Provisions and Instructions
V.A. Additional Provisions
i. GSAR 552.236-74, Evaluation of Options (MAR 2019)
The Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. Evaluation of options will not obligate the Government to exercise the option(s).
ii. GSAR 552.239-77, Government’s Right to Exercise Options (MAR 2019)
a. The Government may exercise any option in writing in accordance with the terms and conditions of the contract within the period of time specified on each CLIN as provided on the Standard Form 1442.
b. If the Government exercises the option, the contract shall be considered to include this option clause.
VI. Method of Award
VI.A. Evaluation of Phase 1 Proposals
The Government will evaluate Phase 1 proposals based on the following evaluation factors. The Contracting Officer will select a shortlist maximum of three (3) of the most highly qualified Offerors based on the offers in response to Phase 1 to proceed to Phase 2.
The GSA will publicly announce the names of the shortlisted firms on the SAM.gov website.
The Government has no intent to request revised proposals during Phase 1 of the solicitation. However, if the Government determines to consider revised proposals, then the procedures of FAR 15.306, Exchanges with offerors after receipt of proposals will be followed.
Phase 1 Evaluation Criteria:
The approach to selection of an Offeror for this procurement will be pursuant to the design-build approach in FAR 36.3 and GSAM
536.3. The purpose of Phase 1 (the Request for Qualifications or RFQ) is to select the most highly qualified offerors from Phase 1 to participate in Phase 2 (the Request for Proposals or RFP). The CO will select a maximum of three of the most highly qualified offerors to proceed to Phase 2. Phase 1 will consist of the following non-price/technical factors:
Non-Price/Technical Factors:
1. Technical Qualifications – Past Experience of the General Contractor and A-E Firm
1A: Past Experience of the General Contractor (15%)
1B: Past Experience of the A-E (15%)
2. Technical Qualifications – Past Performance of the General Contractor and A-E Firm
2A: Past Performance of the General Contractor (15%)
2B: Past Performance of the A-E (15%)
3. Approach to Design-Build (20%)
4. Lead Designer (20%)
Proposals will be evaluated in Phase 1 to determine which offerors will be shortlisted to submit proposals for Phase 2. At the conclusion of Phase 2, GSA intends to award a contract to a single Offeror for all design and all construction services pursuant to FAR
Best Value Selection Procedures (FAR Part 15).
VI.B. Evaluation of Phase 2 Proposals
The Government will award a contract resulting from this Solicitation to the responsible Offeror whose offer conforming to the
Solicitation will be most advantageous to the Government, Total Evaluated Price and other factors considered. During Phase 2, award of the contract under the solicitation will be based solely on the offers submitted in response to the Phase 2 evaluation factors and
Phase 2 of the solicitation (i.e. proposals submitted under Phase 1 will have no impact on the best value determination under Phase 2).
In addition to Total Evaluated Price, it is anticipated that at least the following four Phase 2 non-price factors, which are subject to change, will be used to evaluate offers. Additional non-price factors are anticipated to address provisions of the Inflation Reduction
Act (IRA) of 2022
Evaluation Factor 1: Design Concept (50%)
Evaluation Factor 2: Key Personnel (25%)
Evaluation Factor 3: Management Plan (15%)
Evaluation Factor 4: Project Labor Agreement (10%)
VI.C. Determination of Responsibility
In order to be considered responsible, an Offeror must demonstrate that it meets the requirements of FAR 9.104-1. The Contracting
Officer's determination of an Offeror's responsibility or non-responsibility may be based upon any information obtained by the
Contracting Officer and is independent of the evaluation of offers set forth herein.
VI.D. Price Analysis and Price Realism Analysis
1. The offeror’s cost or price for the work (design or construction) to complete the project that is described in the solicitation will be evaluated. Offerors with prices that are unreasonable, unrealistic, or unbalanced may be rejected as unacceptable and ineligible for award.
2. During Phase 2 of the solicitation, the Contracting Officer will use Price Analysis to analyze the Offeror’s proposal to ensure that the final agreed-to-price is fair and reasonable, realistic, and balanced. In performing Price Analysis, the Contracting
Officer may use, singly or in combination with others, the analytical techniques described in FAR 15.404-1, to ensure that the final price is fair and reasonable. The Contracting Officer may request the advice and assistance of other experts to ensure that the appropriate Price Analysis is performed.
3. In addition, during Phase 2 of the solicitation, the Contracting Officer will use Price Realism Analysis in conjunction with the evaluation of the offeror’s Management Plan an Offeror’s understanding of the requirements and to assess the risk inherent in an Offeror’s proposal. Accordingly, Offerors are advised that a business decision to submit significantly low pricing will be considered as reflecting on their understanding or the risk associated with their proposals. Price Realism Analysis will not be used for the purpose of determining the probable cost to the Government.
VI.E. Total Evaluated Price
Total Evaluated Price shall be calculated using the prices indicated in the Phase 2 Price Proposal.
VI.F. Non-Price Factors
EVALUATION FACTOR 1: TECHNICAL QUALIFICATIONS – PAST EXPERIENCE OF THE GENERAL
CONTRACTOR AND A-E FIRM
Applicable to Subfactors 1A and 1B: For small business concerns using capabilities, past performance, and experience of first-tier subcontractors:
The Government will consider the capabilities, past performance, and experience of each first-tier subcontractor in accordance with the regulations promulgated by the Small Business Administration in 13 CFR § 125.2(g), which states that –
When an offer of a small business prime contractor includes a proposed team of small business contractors and specifically identifies the first-tier subcontractor(s) in the proposal, the head of the agency must consider the capabilities, past performance, and experience of each first tier subcontractor that is part of the team as the capabilities, past performance, and experience of the small business prime contractor if the capabilities, past performance, and experience of the small business prime does not independently demonstrate capabilities and past performance necessary for award.
SUBFACTOR 1A: PAST EXPERIENCE OF THE GENERAL CONTRACTOR (15%)
Description:
This evaluation subfactor considers the extent of the past experience of the Offeror’s proposed General Contractor of the
Offeror’s design-build (DB) team. For purposes of this evaluation factor, the term General Contractor is defined as an individual, firm, partnership, corporation, association, or other legal entity permitted by law to and whose main responsibility is for the construction, improvement or renovation of a project under contract. The Offeror should submit at least one SP completed by the General Contractor.
For this evaluation subfactor, Similar Project (SP) means a project that meets all of the following: (Changed via Amendment 0002)
• Construction was substantially completed within 15 years prior to the submission deadline for Phase 1 proposals;
• Construction of a commercial building that as at least 15,000 gross square feet;
• Construction included the construction of site utilities, storm drainage, grading, roads, and security; and
• Construction contract cost at award was greater than or equal to $25 million.
Additional favorable consideration may be given to the extent any of the following are demonstrated beyond the one
(1) SP performed by the General Contractor: (Changed via Amendment 0002)
• Two or more SPs are received for the General Contractor.
• The SP was completed in Climate Zone 7 or Climate Zone 8 as defined in Solicitation Attachment 03 –
ASHRAE - Climatic Data for Building Design Standards.
• Construction was delivered using the design-build (D-B) or Integrated Project Delivery (IPD) methods.
For purposes of this evaluation factor, IPD is defined as the execution of a multiparty agreement in which the owner or developer contracted with a single Offeror to provide all, or substantially all, of the design and construction services for that project.
Submittal Requirement:
Each Offeror shall provide sufficient documentation in order to demonstrate the extent of the Offeror’s past experience for at one (1), but no more than three (3) SPs total completed by the General Contractor. The submission for each project is limited to a maximum of four (4) pages.
SUBFACTOR 1B: PAST EXPERIENCE OF THE A/E FIRM (15%)
This evaluation subfactor considers the extent of the past experience of the Offeror’s proposed A/E Firm of the Offeror’s design-build (DB) team. For purposes of this evaluation factor, the term A/E Firm is defined as an individual, firm, partnership, corporation, association, or other legal entity permitted by law to practice the profession of architecture and engineering that will have responsibility for developing complete, detailed design and construction documents. The Offeror should submit at least one SP performed by the A/E Firm.
For this evaluation subfactor, Similar Project (SP) means a project that meets all of the following: (Changed via Amendment 0002)
• Construction was substantially completed within 15 years prior to the submission deadline for Phase 1 proposals;
• Construction of a commercial building that as at least 15,000 gross square feet;
• Construction included the construction of site utilities, storm drainage, grading, roads, and security; and
• Construction contract cost at award was greater than or equal to $25 million.
Additional favorable consideration may be given to the extent any of the following are demonstrated beyond the one
(1) SP performed by the A/E Firm: (Changed via Amendment 0004)
• Two or more SPs are received for the A/E Firm.
• The SP was completed in Climate Zone 7 or Climate Zone 8 as defined in Solicitation Attachment 03 –
ASHRAE - Climatic Data for Building Design Standards.
• Construction was delivered using the design-build (D-B) or Integrated Project Delivery (IPD) methods.
For purposes of this evaluation factor, IPD is defined as the execution of a multiparty agreement in which the owner or developer contracted with a single Offeror to provide all, or substantially all, of the design and construction services for that project.
Each Offeror shall provide sufficient documentation in order to demonstrate the extent of the Offeror’s past experience for at one (1), but no more than three (3) SPs total completed by the A/E Firm. The submission for each project is limited to a maximum of four (4) pages.
EVALUATION FACTOR 2: TECHNICAL QUALIFICATIONS – PAST PERFORMANCE OF THE GENERAL
CONTRACTOR AND THE A-E FIRM
Applicable to Subfactors 2A and 2B: For Small Business Concerns using past performance as participating member/partner of a
Joint Venture
In accordance with the following conditions, which appear in 15 U.S.C. § 644(e)(5), the Government will consider for the past performance factor only, giving due consideration to the information provided under (B)(ii) below, the past performance of the Joint Venture as the past performance of the participating joint venture small business concern member
(whether or not the other participating joint venture is a small business concern) –
A. Allowing the small business concern to elect to use the past performance of the joint venture if the small business concern has no relevant past performance of its own; and
B. Requiring the small business concern, when making an election under subparagraph (A) –
(i) To identify to the Contracting Officer the joint venture of which the small business concern was a member; and
(ii) To inform the Contracting Officer what duties and responsibilities the small business concern carried out as part of the joint venture.
The term “relevant past performance” means past performance for “SP(s)” as defined in Factor 1. So long as the definition of
“SP(s)” is otherwise met, the Government will consider relevant past performance of the offeror as the prime contractor more favorably than relevant past performance of the offeror as a member of the joint venture prime contractor.
In addition to the “SP(s)” submitted in response to Factor 1, Past Experience of the GC and A-E firm, the Government will consider for the Past Performance factor the past performance of the joint venture as the past performance of the offeror only if the offeror has no relevant past performance of its own. The Government will not consider the experience of the joint venture as the experience of the offeror for Factor 1, Past Experience of the GC and A-E Firm.
Applicable to Subfactors 2A and 2B: For small business concerns using capabilities, past performance, and experience of first-tier subcontractors
The Government will consider the capabilities, past performance, and experience of each first-tier subcontractor in accordance with the regulations promulgated by the Small Business Administration in 13 CFR § 125.2(g), which states that –
When an offer of a small business prime contractor includes a proposed team of small business contractors and specifically identifies the first-tier subcontractor(s) in the proposal, the head of the agency must consider the capabilities, past performance, and experience of each first tier subcontractor that is part of the team as the capabilities, past performance, and experience of the small business prime contractor if the capabilities, past performance, and experience of the small business prime does not independently demonstrate capabilities and past performance necessary for award.
Subfactor 2A: PAST PERFORMANCE OF THE GENERAL CONTRACTOR (15%)
This subfactor considers the past performance of the offeror’s proposed General Contractor on SPs submitted by the Offeror under Evaluation Subfactor 1A. and any other SPs that the Government becomes aware of. Past Performance will be evaluated to determine the probability that the Offeror will successfully perform the project identified in the Request for
Qualifications (RFQ) based on demonstrated past performance on SPs. (Changed via Amendment 0004)
Additional favorable consideration may be given to the extent of the following:
• Each Past Performance Questionnaire has an overall rating of better than average.
For each Offeror reference, the Offeror shall complete Section 1 and then distribute the Past Performance Questionnaire
(Solicitation Attachment 04 for GCs, Solicitation Attachment 05 for A-Es), including Section 1, to each Reference for completion. The References shall email the completed Past Performance Questionnaire to Rhonda Widick, Contracting Officer at rhonda.widick@gsa.gov or Christie VandenDries, Contract Specialist at christie.vandendries@gsa.gov not later than 10:00 AM Mountain Time, July 27, 2023. The email subject line should contain the solicitation number and the name of the offeror. Completed questionnaires submitted by the Offeror proposal will not be accepted. While the Government may elect to consider data from any source, the burden of providing detailed, current, accurate, and complete past performance information by the deadline for initial submissions rests with the Offeror and its evaluator/reference. GSA may also contact and question the past performance references directly.
(Changed via Amendment 0001)
Subfactor 2B: PAST PERFORMANCE OF THE A-E (15%)
This subfactor considers the past performance of the offeror’s proposed A/E Firm on SPs submitted by the Offeror under
Evaluation Subfactor 1B. and any other SPs that the Government becomes aware of. Past Performance will be evaluated to determine the probability that the Offeror will successfully perform the project identified in the Request for Qualifications
(RFQ) based on demonstrated past performance on SPs.
Additional favorable consideration may be given to the extent of the following:
• Each Past Performance Questionnaire has an overall rating of better than average.
For each Offeror reference, the Offeror shall complete Section 1 and then distribute the Past Performance Questionnaire
(Solicitation Attachment 04 for GCs, Solicitation Attachment 05 for A-Es), including Section 1, to each Reference for completion. The References shall email the completed Past Performance Questionnaire to Rhonda Widick, Contracting Officer at rhonda.widick@gsa.gov or Christie VandenDries, Contract Specialist at christie.vandendries@gsa.gov not later than 10:00 AM Mountain Time, July 27, 2023. The email subject line should contain the solicitation number and the name of the offeror. Completed questionnaires submitted by the Offeror proposal will not be accepted. While the Government may elect to consider data from any source, the burden of providing detailed, current, accurate, and complete past performance information by the deadline for initial submissions rests with the Offeror and its evaluator/reference. GSA may also contact and question the past performance references directly.
EVALUATION FACTOR 3: APPROACH TO DESIGN BUILD (20%)
This factor considers the Offeror’s approach to design build (DB) to satisfy the Government’s objectives, including realization of DE, considering A and B below. For purposes of this evaluation factor, “Design Excellence” refers to GSA’s
DE Program which seeks a holistic approach (incorporating expertise in many areas, including but not limited to;
architecture, engineering, urban design, interior design, sustainability, and construction) that delivers value by producing high-quality, high-performance facilities on budget and on time. DE further seeks to commission our nation’s most talented constructors, designers, and artists to design and construct federal buildings of outstanding quality and value. These projects are to demonstrate the value of integrated design that balances aesthetics, cost, functionality, constructability, reliability;
creating environmentally superior workplaces for federal employees; and giving contemporary form and meaning to our democratic values.
Submittal Requirement:
Each Offeror is to submit a written narrative (not to exceed 10 pages) concerning its approach to the DB process for the project described in the solicitation. The narrative should discuss each of the following set forth below, in the context of DE.
The narrative should address each of the following:
A. Design Philosophy and Intent: The Offeror’s approach to achieving a superior and integrated design related to the project described in the solicitation, considering factors such as:
• Architecture
• Building performance
• Ease of Maintenance
B. Design-Build Process: The Offeror’s overall approach to design-build in the following areas:
• Quality
• Cost
• Schedule
EVALUATION FACTOR 4: LEAD DESIGNER (20%)
This factor considers (based on the elements 1-5 below) the likelihood of the Offeror’s proposed Lead Designer (LD), based on the LD’s portfolio of projects as LD, of achieving Design Excellence on the project described in the solicitation.
For purposes of this evaluation factor, the term “Lead Designer” means an individual or team of designers who will have the primary responsibility to develop the concept and the project design.
For purposes of this evaluation factor, “Design Excellence” has the same meaning as stated in Evaluation Factor 3.
The Offeror’s proposed LD, based on the LD’s portfolio of projects as LD, should have at least an adequate likelihood of achieving DE on the projects described in the solicitation.
Additional favorable consideration may be given to the extent of the following:
• Projects in the portfolio were delivered using the design-build delivery method;
• The proposed Lead Designer and the Offeror worked on the same project in the portfolio of projects submitted for the LD; and
• The projects in the portfolio:
o Include one or more SPs under Factor 1, o LEED Certifications, and o Awards for superior design
Each Offeror should submit the information requested below. The following are not subfactors; rather, they are elements the
Government will consider when evaluating the Offeror’s proposal.
Submit a portfolio of projects representative of the Lead Designer’s ability to provide Design Excellence as the Lead
Designer (LD). Address the Lead Designer’s participation/role for each project.
1. If the LD is an individual, submit a portfolio of up to three (3) projects completed in the last 15 years prior to the issuance of the solicitation. Each project submission is limited to a maximum of five (5) pages.
2. If the LD is a team, submit a portfolio of up to two (2) projects the lead designer(s) on the team completed as the LD in the last 15 years, prior to the issuance of the solicitation. Each project submission is limited to a maximum of five
(5) pages.
3. Each project should include a narrative that addresses the design approach with salient features and discuss how the client’s program, functional, image, mission, economic, schedule, and operational objectives were satisfied by the overall design/planning solution. Include tangible evidence such as certificates, awards, or peer recognition demonstrating Design Excellence.
4. In addition to the page limits for each project submitted for 1 and 2 above, each offeror should include o One of the following for each project
▪ a representative floor plan,
▪ a site plan,
▪ a rendered 3-D model,
▪ a building section, or
▪ other appropriate drawing o Two single side pages of photographs
5. Identify and describe areas of responsibility and commitment to each project.