ND-BAS_Upgrades_Phase_2_SOW_v2_03152019.pdf

PDF 89 KB Posted

Attached to
BUILDING AUTOMATION SYSTEM INTEGRATION FOR EIGHT FEDERAL BUILDINGS IN NORTH DAKOTA
Solicitation number
47PJ0019Q0044
Issued by

About this file

Statement of Work

View the file

Other files

File Type Posted
Minutes_Pre-Bid_6-6-19.pdf PDF
Notice_of_second_site_visit.pdf PDF
Notice_of_cancellation_of_site_visit.pdf PDF
Attachment_L_-_REQUEST_FOR_SBU_BUILDING_INFO.pdf PDF
Attachment_P_-_Existing_Controller_and_Object_Counts.pdf PDF
Attachment_B_-_Badging___Security_Requirements_5.31.2017.pdf PDF
Attachment_C_-_GSA_PBS_Telecommunications_Distribution_Design_Guide.pdf PDF
Attachment_J_-_ND-BAS_Upgrades_Pricing_Template.xlsx XLSX spreadsheet
Attachment_I_-_Object_Naming_Submittal_TEMPLATE-v2.xlsx XLSX spreadsheet
Attachment_N_-_GSA_R8_Smart_Building_Technology_Guide_v0_0_3.pdf PDF
Attachment_H_-_Device_Schedule_TEMPLATE-v2.xlsx XLSX spreadsheet
RFQ_ND_BAS_Phase_II.pdf PDF
Attachment_K_-_CMMS_Inventory_Uploader_Template.xlsx XLSX spreadsheet
Attachment_D_-_GSA_R8_BAS_Technology_Implementation_Guide.pdf PDF
Attachment_G_-_GSA_R8_BAS_Graphic_Format_Standard_v2_0_0_20140822.pdf PDF
Attachment_A_-_Universal_Scope_Requirements_v2.1_6.8.18.pdf PDF
Attachment_F_-_GSA_Data_Normalization_for_Building_Automation_Systems_v2.5.pdf PDF
Attachment_O_-_SCA_Wage_Determinations.pdf PDF
Attachment_E_-_GSA_R8_Open_Protocol_Implementation_Guide_-_BACnet_-_v1_0_0_FINAL.pdf PDF
Attachment_M_-_GSA_OFM_Standards_for_Installing_Network_Cabling_in_Electrical_Equipment.pdf PDF
Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1 | P a g e

CONSTRUCTION SCOPE OF WORK

U.S. GENERAL SERVICES ADMINISTRATION, ROCKY MOUNTAIN REGION 8

Date: 3/15/2019 Revision: 2

Section 1: Project Title North Dakota BAS Upgrades – Phase 2

Section 2: Project Location, Building Name, & Building Number BASE SCOPE Buildings:

ND0000AO Pembina Border Station, 10980 I-29, Pembina, ND ND0018 Pembina PO/CU, 112 W Stutsman St, Pembina, ND ND0008 Ronald N Davies FB, 102 N 4th St, Grand Forks, ND ND0002 FB, 304 E Broadway, Bismarck, ND ND0037 William L Guy FB/PO/CH, 220 E Rosser Ave, Bismarck, ND ND0046 FB/PO, 657 2nd Ave N, Fargo, ND ND0006-ND0047 Quentin C Burdick FB/CH, 655 1st Ave N, Fargo, ND

Section 3: Contact List

Contracting Officer (CO) Name: Angelica Cohen Email: angelica.cohen@gsa.gov Address:

Phone (O): 303-236-5362 Phone (C): 720-445-0803

ND Project Manager Name: Jesse Johnson Email: jesse.johnson@gsa.gov Address:

Phone (O):

Phone (C): (701) 557-9649

Regional Project Manager Name: Marty Findeisen Email: martin.findeisen@gsa.gov Address:

Phone (O): (312) 353-4560 Phone (C): (720) 576-6970

Regional BAS Name: Donovan Hanson Email: c.donovan.hanson@gsa.gov Address:

Phone (O):

Phone (C): (720) 498-2737

Regional MSI Name: Mike Grush Email: michael.grush@gsa.gov Address:

Phone (O):

Phone (C): (206) 963-5417

2 | P a g e

Section 4: Project Background & Project Description GSA buildings in North Dakota have an existing Building Automation System (BAS), the CSI I/Net system, that is obsolete. The objective of the North Dakota BAS Upgrade Project is to provide a new integration platform and upgrade pathway for the obsolete I/Net system. The new integration platform will enable users to configure, program, and manage the obsolete system while seamlessly integrating new modern BACnet devices as they are added to the platform. This will allow the obsolete system to be gradually and systematically replaced with new devices over time, while providing a single platform and user interface for all BAS devices.

Before submitting a proposal on the work specified herein, each bidder is strongly advised to conduct a site visit and/or review the existing BAS to familiarize themselves with all existing conditions, identify limitations, and field verify dimensions for use in submitting offer and completion of work. No extra compensation will be allowed because of the Contractor’s misunderstanding as to the amount of work involved or because of his/her lack of knowledge of any existing conditions.

Section 5: Project Objectives The contractor shall provide labor, materials, equipment and supervision necessary to perform:

1) Installation, configuration, and programming of new integration platform with integrated web server to integrate all existing CSI I/Net devices and control objects. (Should any existing I/Net devices be offline prior to integration, the contractor shall bring those issues to GSA’s attention so that corrective action can be taken and full integration can be achieved.) Integration platform shall be the Schneider Electric SmartStruxure Automation Server (AS-P) platform. Contractor shall be a licensed partner of Schneider Electric capable of providing direct manufacturer support for the products provided.

a. GSA has an existing installation of the Schneider Electric SmartStruxure Workstation software application on a GSA server. Access to this software shall be utilized to configure/program the AS-P once it has been connected to the GSA IT network. The contractor shall not under any circumstances connect any non-GFE device or computer to the GSA network without explicit instructions from GSA.

b. Upgraded system shall:

i. Conform to ASHRAE 135-2016 (BACnet); the device shall be native-BACnet.

ii. Be BTL-listed (BACnet Testing Laboratories).

iii. Use BACnet/IP protocol to communicate with Tridium Niagara enterprise server on the GSA IP Network

iv. Be approved for use on GSA IP network by GSA IT Security. The device shall be configured for security using the applicable IT hardening guide approved by GSA IT Security.

v. Integrate existing I/Net BAS devices, making all objects available to the BACnet internetwork. All existing

BAS control points (physical and virtual) shall be mapped to be discoverable using BACnet.

vi. Simultaneously support routing for BACnet MS/TP network(s) for transition of I/Net devices that are replaced with BACnet MS/TP devices.

vii. Be sized appropriately to provide a high-performance system with 25% spare capacity. See Existing

Controller & Object Counts.pdf for the number of existing devices and points per site.

viii. Support local GUI including dynamic inter-active custom graphical representations of all controlled equipment

(and equipment controlled by integrated devices).

c. Technical and Performance Requirements:

i. The BAS vendor is responsible for configuring IP and BACnet network configurations according to GSA OFM BAS instructions. GSA manages IP and BACnet network configurations.

ii. Any required computer or server hardware (i.e. PC, laptop) and peripherals (i.e. mouse, keyboard, monitor) and/or routing and switching equipment, used to provide GSA network connectivity, will be government furnished and provided by GSA. Exception is the AS specified in Section 5:1. The BAS vendor shall not include Government Furnished Equipment (GFE), as defined, in their proposal.

iii. Any contractor-provided hardware requiring access to the GSA network must be pre-approved for use by the GSA (PBS CIO). The Schneider Electric AS-P device with v1.9.3.24 firmware is already pre-approved by

GSA (PBS CIO).

iv. All BACnet objects that mirror I/Net objects shall support read functionality.

v. All new and integrated control points, equipment schedules, and trend logs shall be BACnet objects discoverable using any BACnet client. All BACnet objects shall be listed in an Object Naming Submittal spreadsheet (see Object Naming Submittal TEMPLATE-v1.xlsx) with GSA Object Naming Standard names for each object, and submitted to GSA OFM BAS for approval. Approval of object names shall be obtained from GSA prior to proceeding with implementation of the naming. GSA is not responsible for re-work resulting from using unapproved object naming.

3 | P a g e

vi. Legacy system objects and new BACnet objects shall be capable of being displayed on the same graphic.

vii. All cabling in GSA buildings must be designed and installed in accordance with Chapter 16 (Building

Automation) Building Industrial Consulting Services International Inc., (BICSI) standards, for guidance on serial cables, and in conjunction with the GSA Telecommunications Distribution and Design Guide (TDDG), as it relates to Ethernet cabling. Provide all required cabling, conduit, and appurtenances as required to complete the project in compliance with GSA, State, and local standards. Cabling in mechanical, electrical, and unfinished areas shall be in conduit. Provide 120 VAC power where required. Include a NEMA-1 enclosure with key lock in any building where the AS-P(s) will be installed in a location that is not inside a locked IT closet. Enclosures shall have a 3” x 3” sticker of the official blue GSA logo to positively identify the enclosure as belonging to GSA. Devices mounted inside locked IT closets shall be identified with a 3” x 3” sticker of the official blue GSA logo. Coordinate with the local Building Manager and O&M contractor to determine a suitable installation location.

viii. Configuration and programming tools shall be provided and licensed to GSA, and installed on the AS-P platform and/or on a remote GSA server. Tools shall enable operators to view and modify configuration and programming of integrated I/Net system devices and new BACnet devices. (See Section 5:1.a. for existing tool software.)

ix. All new hardware and field level devices installed for the project shall not be limited in their ability to communicate with a specific brand or device.

2) Create a new web-based Graphical User Interface (GUI) conforming to GSA Region 8 Standards, and convert all control points, trend logs, equipment schedules, and alarms to standard BACnet objects. HTML5-based GUI for the facility shall be hosted on AS-P and be accessible over the GSA IP network from other facilities using any web browser. Permission to access the GSA network may be required.

3) Work shall include all hardware, wiring, programming, graphics, testing, and commissioning necessary to deliver a complete, functioning system at the conclusion of the project.

4) A new user account with full administrator privileges shall be created, and any generic and/or default user accounts shall be removed and/or disabled. GSA shall be provided with credentials for the administrator user account immediately upon connection to the GSA IP network.

5) Contractor shall configure alarms and email/SMS notification for critical equipment failure indicators and deviation from critical design parameters. Alarm events shall use BACnet Notification Classes and shall be routable using BACnet.

6) Contractor shall configure BACnet equipment schedules to replace all existing equipment schedules. Existing system schedules shall be removed.

7) Contractor shall create BACnet Trend Log objects for all physical points, active or effective setpoints, and mode points (Occ/Unocc, etc.). Existing system trending shall be removed.

8) Provide operator training to the Building Manager and/or GSA personnel identified by the Building Manager, and to the O&M contractor building operators. After final acceptance of the new system, web-based online operator training shall be provided by Contractor. Provide 8 hours of operator training covering topics including at minimum: Logging on and off; system navigation;

commanding & releasing points; configuring control points, schedules, trend logs, alarms, notifications, and user accounts;

navigating the help file(s), owner’s manual(s), user guide(s), and as-built data; system object, control logic, and graphics modification; system backup and restoration procedures; creating and displaying reports; trend data visualization;

troubleshooting procedures; and warranty service request procedures. Demonstrate these activities, and provide training materials that include step-by-step instructions to perform these functions. Training materials shall be provided electronically and shall be referenced during training. If any Option buildings are awarded, and additional 8-hour training session shall be provided.

9) After the new GUI is operational, punch lists have been completed, and operator training has been conducted:

a. demolish all existing CSI I/Net 7 workstations, modems, serial converters, and associated appurtenances.

b. Demolish all existing TAC Xenta 527 devices.

c. Ensure that network wiring is restored and functioning optimally, and that all devices are online.

d. Contractor shall remove and salvage for GSA, all removed equipment.

e. Create a complete system backup for each site suitable to completely restore the system on completely new hardware, should an AS-P fail. Provide these backup files to GSA electronically on the SmartStruxure Workstation server.

10) Building-Specific Scope Items (in addition to scope items described above):

a. ND0006-ND0047 Quentin C Burdick FB/CH, Fargo, ND:

i. Connect existing Advanced Metering System electric meter to existing GSA IP network switch

1. Install conduit and cabling required

2. Reconfigure meter IP to be compatible with local IP network (with GSA support)

ii. Integrate 32 existing BACnet devices, and incorporate them in the GUI for the site

b. ND0046 FB/PO, Fargo, ND:

4 | P a g e

i. Demolish point-to-point wireless IP link system components

c. ND0002 FB, Bismarck, ND:

i. Connect existing Advanced Metering System electric meter to existing GSA IP network switch

1. Install and support CAT6 patch cable (meter and IP switch are in the same room)

2. Reconfigure meter IP to be compatible with local IP network (with GSA support)

d. ND0037 William L Guy FB/PO/CH, Bismarck, ND:

i. Demolish point-to-point wireless IP link system components

Section 6: Proposal Pricing & Site Walk

1) Pre-proposal Site Visit Meeting:

a) The site visit shall consist of a meeting to review construction requirements followed by a walk-thru of the project site(s).

The meeting shall be attended by the contractor and GSA project personnel, and appropriate sub-contractors.

b) Review existing conditions of the project area including any field verification.

c) Review the solicitation/evaluation requirements.

d) Site visit appointments to be scheduled during proposal submission period. Dates and times to be determined.

2) Cost Proposal Requirements:

a) When submitting a proposal, provide a cost breakdown per building (including building number and building name) for each task into the following categories: Materials, Labor Hours, Labor Rates, Subcontractor’s Quotes, Overhead, Profit, and Total. Use the pricing template provided.

3) Cost Proposal Checklist:

a) System description

b) Generic network architecture diagram

c) Product Literature

a. Technical data sheets

b. BACnet PICS (Protocol Implementation Conformance Statement)

c. BTL Listing/BTL Certification

d. Listing of tools (hardware and software) required to configure and program the system and all provided devices

d) Approximate project timeline

e) Contractor & personnel qualifications

a. Company history and experience

b. Case studies of similar projects

c. References

d. OEM certifications and must be Schneider certified

e. Technician resumés and certifications

f) Exclusions & Assumptions

a. Note that all items in this Scope of Work are project requirements, and exclusion of any Scope item invalidates the proposal.

g) Completed pricing template (see Pricing Format TEMPLATE.xlsx)

h) Single Point of Contact (POC) for the project

Section 7: Period of Performance Once Award has been issued, the contractor has 180 calendar days to reach Completion of the project. The contractor must also promptly begin the badging process at the time of Award. Please allow a minimum of 30 days to complete the badging process; during this time the contractor shall conduct a kickoff meeting, submit a detailed project schedule, produce the technical design submittal, and begin executing the work. Final Acceptance shall be achieved when all project deliverables are complete and no known issues remain. Extensions may be granted for unforeseen conditions and other factors outside of the contractor’s control at the Contracting Officer’s discretion.

Materials and workmanship shall be covered under a full 2-year materials and labor warranty. Warranty shall be administered on-site, or, where feasible and effective, using remote access provided by GSA. Warranty repairs and/or corrections shall be made promptly.

Warranty shall not begin prior to Final Acceptance of the system.

5 | P a g e

Section 8: Universal Scope Requirements

• ALL of the requirements in this section are MANDATORY for ALL GSA projects

• See the attached Universal Scope Requirements document for the full details outlining each item

• Failure to comply with any and all of the requirements will result in the project not being accepted as complete

REQUIREMENTS for ALL Projects (Construction, Design & Design/Build)

a) Safety and Health Program:

a. Contractor Responsibility: The contractor shall assume full responsibility and liability for compliance with applicable code, standards and regulations pertaining to the health and safety of personnel during execution of the work, and shall hold the Government harmless for any action on the contractor’s part, or that of the contractor’s employees or subcontractors, that results in illness, injury or death.

b. References: In addition to publications referenced in the Construction Contract Clauses, the following Code of Federal Regulations (CFR), publications apply to conduct of the work (see Typical Project Document References below). State and local safety and health regulations that apply are not cited herein. Current editions at the date of the agreement apply. The more stringent requirements apply.

b) Asbestos Containing Materials. To comply with federal and state regulations as well as GSA policy, an asbestos pre-alteration assessment is required for all construction projects as outlined in Section B of the Universal Scope Requirements.

c) Lead Containing Paint / Lead Based Paint

d) Accessibility

e) Green Purchasing

f) Construction Indoor Air Quality (IAQ) Management Plan

g) Construction Waste Diversion

REQUIREMENTS for ALL projects IF APPLICABLE (Remove if not needed AFTER consulting with OFM and/or other appropriate groups)

h) GSA IT Network (todd.tangye@gsa.gov)

i) Building Automation Systems (BAS) (c.donovan.hanson@gsa.gov)

j) Advanced Metering System (james.shull@gsa.gov)

Typical Project Document References

a) PBS-P100, Facilities Standards for the Public Buildings Services (https://www.gsa.gov/portal/category/21048), current at the time of the award, including all applicable standards, criteria, and guides listed therein. The Design Stage submissions shall comply with PBS-P100 Appendix-A, unless otherwise, indicated in this Statement of Work.

b) GSA Order PBS 3490.1, Management of Sensitive but Unclassified (SBU) building information.

c) National Fire Protection Association (NFPA) 70E Electrical Safety Requirements Manual, EM 385-1-1, current edition.

d) 29 CFR, Part 1910: Occupational Safety and Health Administration (OSHA) General Industry and Health Standards.

e) 29 CFR, Part 1926: “Safety and Health Regulations for Construction”

f) 40 CFR 260, “Hazardous Waste Management System”

g) 40 CFR 261, “Identification and Listing of Hazardous Waste”

h) Federal Standard: Fed Std. 313A, Material Safety Data Sheets, Preparation and the Submission of.

Rebates

The Contractor shall pursue any and all utility rebate and incentive programs and any government grant or incentive programs at the local, state, and federal level. Contractor is responsible for researching, submitting, and ensuring collection of all applicable rebates. Rebate opportunities must be explored for all elements of the project including but not limited to resource-saving equipment, materials, design & services (Commissioning/Recommissioning and other strategies & processes). Submit all rebate checks to:

General Services Administration Attn: Ron Burnett 1961 Stout Street Suite 01-107 Denver, CO 80294 https://www.gsa.gov/portal/category/21048 https://maps.google.com/?q=1961+Stout+StreetSuite+01&entry=gmail&source=g https://maps.google.com/?q=1961+Stout+StreetSuite+01&entry=gmail&source=g

6 | P a g e

For assistance with the rebate process please contact Doug Baughman, Regional Rebate Coordinator doug.baughman@gsa.gov (303) 941-1306

Codes and Standards

a) All contractual references – documents, codes, and standards – shall be used to measure compliance of the design completion and implementation with contractual expectations. All services shall be conducted in accordance with the documents listed below. The applicable version of each document shall be the version current at the time of award of this contract. In the event of a conflict between the requirements stated in these documents and requirements provided elsewhere in this Statement of Work, the requirements in the Statement of Work shall prevail.

b) Any conflicts or ambiguities within or among the referenced standards and criteria documents, or any deviations from requirements contained in the standards and criteria documents, shall be reported to GSA’s Contracting Officer in writing, for determination as to applicability.

Section 9: Submittals

1) Technical design submittals shall be submitted within 30 calendar days of NTP.

2) Contractor shall submit a Method of Procedures (MOP) to the GSA Delivery Project Manager (PM) for approval prior to commencement of work. At a minimum, the MOP shall include:

a) Brief narrative describing method of accomplishment, construction techniques, etc.

b) Project schedule (to include critical path, major milestones, long lead time items, mob & de-mob, inspection dates, substantial completion, and final acceptance)

c) Service/Utility Outages (if necessary)

d) Phasing schedule (if necessary)

e) Any building infrastructure/BAS equipment that may be impacted

3) All new equipment and anything requiring a preventative maintenance plan shall be inputted into Maximo upload template (see attached CMMS Inventory Uploader Template.xlsx)

4) Manufacturer's specifications, instructions and material specification sheets in original form

5) Submittal register/ log for all products specified to establish a standard of quality to include. Submittal register response by the government shall be (21) calendar days or less.

a) For pricing purposes please assume zero hard copies of submittals and one electronic copy to be transmitted to the project team (with additional electronic copies provided upon request). Distribution list including final quantities will be finalized after receipt of the submittal log/ register by GSA project manager.

6) If product samples are not submitted in a timely fashion, any delays caused by the contractor will not warrant a time extension.

After completion of all work, the Contractor shall submit to the project manager the manufacturer's specifications, instructions and material specification sheets in original form. Additionally, the Contractor shall submit all inventory changes (removals, additions, upgrades, etc., and new condition codes) to the COR.

7) Submittal response by the government shall be (21) calendar days or less.

8) Submittal Checklist:

a) System description

b) Project-specific network architecture diagram (riser diagram)

c) Control diagrams

d) Device Schedule (see Device Schedule TEMPLATE-v2.xlsx)

e) Maximo NCMMS Upload Template (see Maximo Upload Template)

f) Product Literature

i. Technical data sheets

ii. All applicable technical manuals (startup, programming, networking, etc.)

iii. Owner’s manuals (O&M manuals)

iv. Installation, Operation, & Maintenance manuals (IOM manuals)

v. OEM guides, manuals, and technical documentation

vi. BACnet PICS

vii. BTL-Listing/BTL Certification

g) Object Naming Submittal (see Object Naming Submittal TEMPLATE-v1.xlsx)

h) Method of Procedure

i. Work plan

ii. Safety plan

iii. Coordination plan

i) Operator training guide mailto:doug.baughman@gsa.gov tel:(303)%20941-1306 tel:(303)%20941-1306

7 | P a g e

j) Project Schedule

k) RFI requesting IP and BACnet network configuration information

Section 10: General Requirements

1) Contractor Use of the Premises

a) During the period of the project, the contractor will have physical access to the site only during business hours of 8:00 am to 4:30 pm, Monday through Friday excluding federal holidays. All site work shall be coordinated with the Project Manager and property manager(s). No on-site work shall be performed outside these hours or on holidays unless otherwise directed by the property manager. The contractor will need to coordinate with the property manager to arrange access to the parking lot. The contractor shall make every effort to cause a minimum of damage to federal property. Any damage caused will be repaired at the contractor’s expense.

2) Progress Meetings

a) The contractor shall schedule bi-weekly meetings (once every two weeks) with the GSA. The contractor shall keep meeting minutes and distribute copies at the following meetings. The meeting agenda will include the following as a minimum: Approval of previous meeting, review of work progress, field observations, problems and decisions, identification of problems which impede planned progress, review of submittals schedule and status of submittals, maintenance of progress schedules, planned progress during the succeeding work period.

b) 24 hour notice is required before start any work to announce the contractor arrival to the Port of Entry Officers.

c) The buildings are fully occupied and shall remain so throughout the performance of the contract. Approval of a schedule of work shall be required prior to starting construction. Any work requiring outages shall be coordinated with the property manager and occupants two weeks in advance, detailing the work to be accomplished during the outage.

3) Equipment The contractor shall provide all equipment associated with the entire project, operate in a safe manner and adhere to all OSHA and GSA standards.

4) Equipment and Material Storage The contractor shall provide and store all equipment, the materials specified above, and any other materials required completing the project. The materials are required to be kept clean and dry throughout the duration of the project.

Contractor to coordinate with building manager for location of storage sheds.

5) Sanitary Facilities Provide and maintain temporary toilet facilities in accordance with State Health Department and GSA requirements.

6) Electricity, Water, and Gas GSA will pay for electricity, water, and gas during the course of this project. The contractor is responsible for making connections to the existing systems. Temporary electrical work shall meet the requirements of NFPA 70-1996 (NEC), Article

305. When temporary connections are removed, restore existing utility services to their original condition.

7) Contractor’s Field Office The contractor may provide an office for their own use. Size, location, and construction shall be subject to approval.

8) Fire Watch Contractor shall be responsible for providing fire watch if required per attached GSA fire watch guidelines.

9) Fire Alarm Impairment and Hot Work When a fire suppression or alarm system impairment is required, contractor shall provide written outage request to GSA for approval in advance of impairing any systems. Contractor shall be responsible for having a GSA approved NICET certified fire alarm contractor perform all system impairments. During fire alarm/suppression impairments or hot work procedures, contractor shall provide a fire watch per the GSA Regional Fire Watch Guidelines.

10) Protection of Public The building site will continue to be used by tenants. The contractor shall fence, barricade, or otherwise block off the immediate work area to prevent unauthorized entry. The contractor shall illuminate barricades and obstructions at night and maintain safe building access and egress for tenants.

11) Housekeeping The project site shall be kept in a neat, orderly, and safe condition at all times. The contractor shall provide enough containers for collecting construction debris and construction materials to be recycled. The contractor shall wet down dry materials and rubbish to prevent blowing dust and keep volatile wastes in covered containers.

8 | P a g e

12) Transportation and Deliveries The contractor shall arrange deliveries of materials in accordance with construction schedules; coordinate with COR to avoid conflict with other tenants and other work conditions at the site. Contractor must make GSA PM & CO aware of any lead times that may affect the project schedule.

13) Cleaning Before scheduling the final inspection, the Contractor shall accomplish six items: (1) Remove all tools, equipment, surplus material, and rubbish; (2) Restore or refinish, to original condition, surfaces that are damaged due to the work of this contract; (3) Remove grease, dirt, stains, foreign materials, and labels from finished surfaces; (4) Thoroughly clean building interiors; (5) Pickup all construction debris from the site; and (6) At time of final inspection, project shall be thoroughly cleaned and ready for use.

14) Disruptive Work All painting, staining, or other activity which may cause noxious or undesirable fumes and/ or any noisy work that may be disruptive to the tenants/ public must be performed after normal working hours. The use of paint or stain that does not generate odors is preferred and may be required if the space will be occupied the following day with prior written approval from GSA.

Section 11: Badging & Security

1) Contractor is responsible to follow GSA’s security and badging requirements as detailed in the attached Badging & Security Requirements (Vendor Fitness Determination Training Manual).

2) US Access shared enrollment centers can be found at fedidcard.gov. Travel distances to the nearest center should be accounted for during the badging process.

Section 12: Payments

1) Information regarding payment requests and payment is in the solicitation/ contract. Please contact the CO if you have any questions regarding payments.

2) The contractor shall provide progress billing per building for the project following the project pricing format indicated in Section

6:2.a. of this document.

Section 13: Substantial Completion & Final Inspection

1) When project, or designated portion of project is complete, request a final inspection. Upon receipt of request that project is substantially complete, the Contracting Officer will proceed with the inspection within ten days of receipt of request or will advise the contractor of items that prevent the project from being designated substantially complete.

2) As-built design drawings and field training for Operations and Maintenance (O&M) personnel shall be provided at completion of project. Maintain one complete set of contract drawings. Clearly mark changes, deletions, and additions to show actual construction conditions. Show additions in red, deletions in green, and special instructions in blue print. Provide to GSA within timeframe negotiated at time of award.

3) Closeout Checklist:

a. Technical design as-built document detailing the final configuration of the system, including all product literature required in technical design submittal

i. Provide link on GUI to this document

b. Warranty information

c. All required manuals & guides

i. Provide links on GUI to these documents

d. Completed Maximo NCMMS form

e. Owner/operator training & training guide

i. Provide link on GUI to training guide document

f. All documents stored in electronic format on Workstation server

g. All backups stored on Workstation server http://fedidcard.gov/

9 | P a g e

Section 14: Attachments

1) Attachment A - Universal Scope Requirements_v2.1_6.8.18

2) Attachment B - Badging _ Security Requirements_5.31.2017

3) Attachment C - GSA Telecommunications Distribution Design Guide.pdf

4) Attachment D - GSA BAS Technology Implementation Guide.pdf

5) Attachment E - GSA Open Protocol Implementation Guide – BACnet – v1.pdf

6) Attachment F - GSA Data Normalization for Building Automation Systems v2.5.pdf

7) Attachment G - GSA R8 BAS Graphic Format Standard v2.pdf

8) Attachment H - Device Schedule TEMPLATE-v2.xlsx

9) Attachment I - Object Naming Submittal TEMPLATE-v2.xlsx

10) Attachment J - Pricing Format TEMPLATE.xlsx

11) Attachment K - CMMS Inventory Uploader Template.xlsx

12) Attachment L - REQUEST FOR SBU BUILDING INFO.pdf

13) Attachment M - GSA OFM Standards for Installing Network Cabling in Electrical Equipment.pdf

14) Attachment N - GSA R8 Smart Building Technology Guide v0_0_3

15) Attachment O – SCA Wage Determinations.pdf

16) Attachment P - Existing Controller & Object Counts.pdf

ALL of the requirements in this section are MANDATORY for ALL GSA projects
See the attached Universal Scope Requirements document for the full details outlining each item
Failure to comply with any and all of the requirements will result in the project not being accepted as complete
REQUIREMENTS for ALL Projects (Construction, Design & Design/Build)
REQUIREMENTS for ALL projects IF APPLICABLE (Remove if not needed AFTER consulting with OFM and/or other appropriate groups)
Typical Project Document References
Rebates
Codes and Standards
1) Contractor Use of the Premises
a) During the period of the project, the contractor will have physical access to the site only during business hours of 8:00 am to 4:30 pm, Monday through Friday excluding federal holidays. All site work shall be coordinated with the Project Manager ...
2) Progress Meetings
3) Equipment
4) Equipment and Material Storage
5) Sanitary Facilities
6) Electricity, Water, and Gas
7) Contractor’s Field Office
8) Fire Watch
10) Protection of Public
11) Housekeeping
12) Transportation and Deliveries
13) Cleaning
14) Disruptive Work
2) As-built design drawings and field training for Operations and Maintenance (O&M) personnel shall be provided at completion of project. Maintain one complete set of contract drawings. Clearly mark changes, deletions, and additions to show actual co...
3) Closeout Checklist:
a. Technical design as-built document detailing the final configuration of the system, including all product literature required in technical design submittal
i. Provide link on GUI to this document
b. Warranty information
c. All required manuals & guides
i. Provide links on GUI to these documents
d. Completed Maximo NCMMS form
e. Owner/operator training & training guide
i. Provide link on GUI to training guide document
f. All documents stored in electronic format on Workstation server
g. All backups stored on Workstation server