Minutes_Pre-Bid_6-6-19.pdf

PDF 65 KB Posted

Attached to
BUILDING AUTOMATION SYSTEM INTEGRATION FOR EIGHT FEDERAL BUILDINGS IN NORTH DAKOTA
Solicitation number
47PJ0019Q0044
Issued by

About this file

Site visit meeting minutes with questions and answers

View the file

Other files

File Type Posted
Notice_of_second_site_visit.pdf PDF
Notice_of_cancellation_of_site_visit.pdf PDF
Attachment_L_-_REQUEST_FOR_SBU_BUILDING_INFO.pdf PDF
Attachment_P_-_Existing_Controller_and_Object_Counts.pdf PDF
Attachment_B_-_Badging___Security_Requirements_5.31.2017.pdf PDF
Attachment_C_-_GSA_PBS_Telecommunications_Distribution_Design_Guide.pdf PDF
Attachment_J_-_ND-BAS_Upgrades_Pricing_Template.xlsx XLSX spreadsheet
Attachment_I_-_Object_Naming_Submittal_TEMPLATE-v2.xlsx XLSX spreadsheet
Attachment_N_-_GSA_R8_Smart_Building_Technology_Guide_v0_0_3.pdf PDF
Attachment_H_-_Device_Schedule_TEMPLATE-v2.xlsx XLSX spreadsheet
RFQ_ND_BAS_Phase_II.pdf PDF
Attachment_K_-_CMMS_Inventory_Uploader_Template.xlsx XLSX spreadsheet
Attachment_D_-_GSA_R8_BAS_Technology_Implementation_Guide.pdf PDF
Attachment_G_-_GSA_R8_BAS_Graphic_Format_Standard_v2_0_0_20140822.pdf PDF
Attachment_A_-_Universal_Scope_Requirements_v2.1_6.8.18.pdf PDF
Attachment_F_-_GSA_Data_Normalization_for_Building_Automation_Systems_v2.5.pdf PDF
ND-BAS_Upgrades_Phase_2_SOW_v2_03152019.pdf PDF
Attachment_O_-_SCA_Wage_Determinations.pdf PDF
Attachment_E_-_GSA_R8_Open_Protocol_Implementation_Guide_-_BACnet_-_v1_0_0_FINAL.pdf PDF
Attachment_M_-_GSA_OFM_Standards_for_Installing_Network_Cabling_in_Electrical_Equipment.pdf PDF
Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DFC Building 44 Roof Replacement Design 1

Meeting Minutes

GSA Public Buildings Service www.gsa.gov

North Dakota BAS Upgrades Phase II

Project Name: North Dakota BAS Upgrades Phase II

Date: 6-6-2019

Location: GSA Building Office, Fargo, ND

Called by: Marty Findeisen

Minutes Prepared by: Marty Findeisen

These minutes reflect the author’s understanding of the discussion and the direction for future action by the attendees. If these minutes do not accurately reflect other parties’ understanding of the conversations held, please respond directly to the author within two days of receipt, via email. The minutes will stand as a record of the meeting unless corrections are received within this timeframe.

Attendees

Team Member Organization Marty Findeisen GSA

Dave Busching GSA

Felipe Jolles GSA (teleconference)

Mike Grush McKinstry

Lynn Johnston Energy Tech Systems

Rob Hermanson Energy Tech Systems

Dustin Johnson Wired Electric

Kevin Pectruszewski FedServ

Minutes – Information Sharing and Status Updates

1. Felipe Jolles, the Contracting Officer reviewed the project contract.

i. Solicitation close date: 6/17/2019.

ii. Page 13 evaluation criteria.

iii. Technical Evaluation due at same time as proposal

iv. Period of performance is 180 from award with completion by 12-31-2019.

v. All RFIs need to be sent to Felipe Jolles and Marty Findeisen.

vi. RFI period closes 6-12-2019.

2. Marty Findeisen reviewed the following:

i. HandlingSensitive but unclassified information (SBU).

ii. HSPD 12 security clearances

iii. Enterprise network (ENT) access requirements.

iv. RFIs

v. Marty’s role will be as Project Manager and will handle day to day project coordination.

2 Meeting Name

GSA Public Buildings Service www.gsa.gov Meeting Minutes Meeting Name

vi. Mike Grush will be technical support and is the author of the scope of work.

3. Mike Grush Reviewed the following scope items:

i. Bacnet requirements

ii. Schneider Struxureware software tools reside on the server.

iii. Object naming standards

iv. Alarms and Trends

v. Proposals section 6 check list to be followed, no exclusions.

vi. Bismarck and Fargo have point to point wireless devices that will be reviewed (used for meters).

vii. Submittals are due within 30 days (see SOW section 9).

4. Contractor questions/ facility tour

i. ETS asked about network drop cabling: The contractors are responsible for the network drop installation from ASP to Switch or twisted pair from BAS network to ASP.

ii. ETS asked about breaking the network trunk because of size and need for multiple ASPs. The contractor will ensure that the building is visible as much as is possible on either the INET or New

ASP systems. Disruptions of BAS visibility shall be minimized and shall be included in the Method of

Procedure (MOP) submittal.

5. Meeting adjourned

Minutes – Action Items and Follow Up

# Item Responsible Due