RFI log.pdf
PDF 104 KB Posted
- Attached to
- Replace Fire Main Construction Federal contract opportunity
- Solicitation number
- 47PF0024R0101
About this file
This document is a Request for Information (RFI) log for Solicitation No. 47PF0024R0101, titled "Replace Remaining Degraded Fire Water Supply Pipe" at the Anthony J. Celebrezze Federal Building.
The key details include:
- The project involves replacement of two underground fire mains, two underground utility vaults, two fire department connections, and associated 8-inch fire protection piping inside the building. It also includes excavation work, lead-based paint and asbestos remediation, and coordination with the city for sidewalk and road closure permits.
- The performance period is 180 days from award to substantial completion. This is a negotiated procurement set aside for Small Businesses under NAICS code 236220 with a $45 million standard.
- Offer due date is November 21, 2024 at 4:00pm EST. Offers are to be submitted electronically to the Contract Specialist.
- The RFI log addresses various questions related to the scope of work, site access, fire alarm system, wall/floor penetrations, maintenance of traffic, and potential contract modifications.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| RFI clarification 2.pdf | ||
| Amendment 01.pdf | ||
| Pre-Bid Meeting Sign-In Sheet.pdf | ||
| site visit agenda.pdf | ||
| RFP 47PF0024R0101.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR INFORMATION (RFI) LOG
Solicitation No: 47PF0024R0101
Project Title: Replace Remaining Degraded Fire Water Supply Pipe Location: Anthony J. Celebrezze Federal Building
Master No.
Submission Date
Doc. Ref.
(page, detail or paragraph number)
RFI / Clarification Response Date Closed
1 11/13/24 Is a 5 ft wide trench to run new line next to existing acceptable? Yes.
2 11/13/24
Will there be a designated area in garage for tools and material?
GSA expects at least half of the back wall will be cleared of cars for work but will clear all parking spots at once if possible. The cleared area of work along the back wall will be used to work and store materials. The area in front of the E. 6th St. backflow is a no parking zone for storage.
3 11/13/24 Is there any parking in garage for tool trucks?
The cleared area of work will contain space for tool trucks.
Individuals operating a vehicle in the garage will have to pass a background check and get a badge.
4 11/14/24 Who is the preferred fire alarm contractor for the building?
Existing subcontract for operations is Hatzel and Buehler. Subs that have been used are Hatzel and Buehler, Fire Tec, SA Comunale.
Programming work is proprietary and done by Simplex/JCI.
5 11/14/24 What is the make and model number of the fire alarm control box? Who "owns" the system? Is it something like JCI? Simplex/JCI - Simplex 4100U
6 11/14/24
Are any of the walls or floors that are being penetrated fire rated? It says to refer to architectural, but there is none.
There are no building floor penetrations on this project. Existing pipe penetrations are to be re-used if possible and rated equal to what is existing. All walls that are to be (potentially) penetrated are interior and exterior block walls located within the basement / parking garage.
7 11/14/24
Who is responsible for the creation of the maintenance of traffic plan and its implementation?
The general contractor is responsible for the planning, coordination, and implementation of any and all plans, permits, road & sidewalk closures, etc. as required by the city to maintain access and operation during construction. Access to the building must be maintained throughout construction. Proper signage and barriers must be installed to ensure continued access and safety of pedestrian and vehicle traffic in the area.
8 11/14/24 01 40 00 1.5 Do the Superintendent, SSHO and QC Manager need to be 3 separate individuals? No.
9 11/14/24 Can the period of performance be extended after award once the material/equipment lead times are confirmed due to current market conditions for the equipment for this project?
The period of performance starts at award. Time extensions will be a contract modification and will be considered on a case-by-case basis pending technical justification.
12 11/18/24 Drawings C004 & C005
Drawing C004 does not have the drain line crossed out (to be removed)? Please clarify that this section of drain line is to be replaced? (Drawing attached)
The intent for that being shown on the demolition plan is to show the limits of sawcut for when the 6” drain line (shown on sheet C005) is installed. There will be no drains removed, just trenching.
13 11/18/24 request for paint spec for the protective painting for the fire line
14 11/18/24 What is the road cross section of East 6th Street and Lakeside Avenue? Should we figure the replacement as asphalt over concrete or brick? This will affect pricing.
15 11/19/24 Are soil boring reports available? If not, it will be assumed that excavation will be clear of rocks and obstructions. Not available.