National Aeronautics and Space Administration (NASA) Engineering and Mission Operations Facility (EMO) N278 at the Ames Research Center in Moffett Field, CA.
Solicitation number
47PD0224R0081
Issued by

About this file

This document is a pre-proposal conference presentation for a NASA Engineering and Mission Operations (EMO) Facility Design-Build project at the Ames Research Center in Moffett Field, CA.

The procurement will be a two-phase design-build process solicited through the GSA Design Excellence Program. In Phase 1, offerors will be evaluated on prior experience, design-build approach, and lead designer qualifications. Up to three offerors will be shortlisted to submit proposals in Phase 2, which will be evaluated on design concept, key personnel, management plan, and small business utilization. Unsuccessful Phase 2 offerors will receive a stipend up to $70,000. The estimated total design/build cost is $33-43 million. The project scope includes demolition of existing facilities and construction of a new 30,292 GSF EMO building to consolidate key program functions and support NASA's goal of a "walkable campus" with sustainable, modern, and flexible workspaces. The solicitation will require a project labor agreement. The Phase 1 proposal is due on November 22, 2024.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

October 18, 2024 NASA Ames Research Center Engineering & Mission Operations (EMO) Facility N278 Pre-Proposal Conference Design / Build - Phase I

GSA Public Buildings Service

Introductions Overviews Project Location Project Scope Procurement Timeline & Deadlines Questions & Answers Today’s Agenda

GSA - Design-Build Contract Holder Jared Price, Project Manager Ray Porter, Contracting Officer Shane O’Brien, Contract Specialist Thomas Sincavage, Project Engineer Brian Muller, Project Executive Yomi Adewale, Regional Architect

Introductions - Government Representatives NASA - Client / Building Owner Karen Chan-hui, Project Manager Brian Fillenwarth, Deputy PM Jason Ritter, Project Executive Craig Myhre, Building End User Representative

Introductions - Contractor Representatives AECOM - Construction Management as Advisor (CMa) & Commissioning Authority (CXa) Services Matt Drabic, Project Manager Dana Marinzel, Architect Mark Chase, Construction Project Manager

NASA Ames Research Center Mountain View, California

NASA Ames is a leader in conducting world-class research and development in aeronautics, exploration technology and science aligned with the center’s core capabilities.

NASA Project Location

NASA Ames Research Center

NASA Ames is a secured, gated campus for 3,200+ employees.

Project Site is at the southwest intersection of Warner Road and Mark Avenue

NASA Ames Research Center - Campus Project Site

Main Entrance & Visitor Control

NASA Ames Research Center - Site View

Project site location and existing buildings to be demolished

Project Site Test Fit

NASA Ames Research Center - Project Site

Project Site

Demolition Services:

Two Existing Buildings: Motor Pool (N251) and Machine Shop (N216) Two Existing Fuel Pumps and related underground fuel tanks Requires demolition and environmental closure of fuel tank

NASA EMO Project Scope Overview

Design and Construction Services for a new NASA Engineering and Mission Operations Building (EMO) facility N278 Consolidate key program functions like offices, meeting space, technical labs, support spaces and conference spaces 30,292 gross square feet minimum of mixed use space Workspaces for 67 personnel Technical spaces include flexible, adaptable, versatile and convertible laboratories and cleanrooms

NASA EMO Project Scope Overview - continued

Design and Construction Services for a new NASA Engineering and Mission Operations Building (EMO) facility N278 Support NASA Master Plan for a ‘walkable campus,’ reduce the footprint and O&M costs while providing a healthy, safe, efficient, modern, flexible and sustainable workplace Outdoor gathering, meeting, and spill-out spaces for N278 that engage with the future greenway Designed to achieve USGBC LEED Gold and SITES Silver Project will be delivered under the GSA design excellence program

NASA EMO Project Scope Overview - continued

Purpose Provide a clear understanding of procurement information, process, and proposal submission requirements Word of Caution Base your proposals on the Solicitation and Amendments to the Solicitation as issued. Nothing said at this conference can be interpreted as a modification to the solicitation unless it is issued as a formal amendment.

Overview of Procurement

Solicitation #: 47PD0224R0081 NAICS 236220, Commercial and Institutional Building Construction Full and Open Competition Firm Fixed Price SAM.gov Link:

https://sam.gov/opp/cbc8f209f5914f50a3e451c63acb98ad/view

Solicitation Information

No amendments have been issued to date All amendments must be acknowledged with your phase 1 submission An amendment will be issued after this conference which will include the presentation and attendance sheet

Amendments

Qualification proposals will be evaluated in Phase 1 to determine which offerors will submit proposals for Phase 2.

In Phase 1, GSA will select a shortlist of the most highly qualified offerors and request that those offerors submit Phase 2 proposals.

A maximum of three (3) firms will be selected to submit Phase 2 proposals Only those selected offerors are authorized to submit Phase 2 proposals Those offerors not selected for participation in Phase 2 will be notified in accordance with FAR 15.503(a) A stipend will be paid to the offerors participating in Phase 2

Two-Phase Design-Build (FAR 36.3)

Phase 1 Evaluation Factors:

Prior Experience and Past Performance (60%) Approach to Design Build Methodology (20%) Philosophy and Design-Build Intent Management Process Design Excellence Stipend Lead Designer Qualifications (20%) Portfolio of their projects

Phase 1 - Request for Qualifications

Non Price Factors Design Concept (50%) Key Personnel (25%) Management Plan (15%) Small Business Utilization (10%) Non-Price Factors, when combined, are significantly more important to Total Evaluated Price.

A detailed phase 2 solicitation will be issued to the shortlisted firms A project labor agreement will be required

Proposal Overview - Phase 2

Sept 9th, 2024:Presolicitation Posted to SAM.gov
Oct 8th, 2024:Phase 1 Solicitation Posted to SAM.gov
Oct 25th, 2024:Request for Information (RFIs) Due
Nov 22nd, 2024:Phase 1 Proposal Due Date
Jan 2025:Shortlist Offerors Notified/Phase 2

Solicitation Issued

Timeline and Deadlines

Questions & Answers

Thank you for joining and for your interest in this project.

image1.png image7.png image3.png image6.png image5.png image4.png

File details come from the government source that posted it. Updated .