Amendment_2_-_47PC0319R0008.pdf
PDF 53 KB Posted
- Solicitation number
- 47PC0319R0008
About this file
Amendment 2 - 47PC0319R0008
View the file
Other files
Show all 25
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
2PQC
Winnie Eng, Senior Contracting Officer
Please see attached.
General Services Administration Public Buildings Service One World Trade Center, 55th Floor New York, NY 10007
General Services Administration Public Buildings Service One World Trade Center, 55th Floor New York, NY 10007
47PC0319R0008
1 4
08/23/2019
08/01/2019
U.S. VIRGIN ISLANDS HURRICANE RECOVERY PROJECT
ST. CROIX GSA-PBS, REGION 2
SOLICITATION NO. 47PC0319R0008
AMENDMENT NO. 2
Amendment No. 2 is hereby issued as follows:
1. To add the following option:
Option 4: Almeric L. Christian Federal Building and U.S. Courthouse - New Water Source and Domestic Water Filtration/Treatment Installation (Dwgs 2i-A000 to 2i-S410)
2. Remove and replace Page 3, CONTRACT PRICING FORM, on the SF1442 – 47PC0319R0008 with the attached CONTRACT PRICING FORM dated August 23, 2019.
3. To respond to the following RFI’s:
7. Please indicate if it is allowed a temporary office in the project.
Response: Space in the green area adjacent to the building can be made available for the contractor's trailer based on space availability.
8. What will be the limits of encroachment into the various rooms for delineating the construction area for the work necessary to perform removal and replacement of the windows?
Response: The drawings have a suggested staging plan for window replacement. The contractor is encouraged to follow it or propose a better alternative without affecting tenant operations.
9. Will the contractor be required to erect a full demising wall inside the occupied office space to segregate the work area from the occupied space?
Response: The drawings have a suggested staging plan for window replacement that includes temporary partitions. The contractor is encouraged to follow it or propose a better alternative without affecting tenant operations.
10. Can GSA provide a list of the available hours for the various tenant spaces (preferably by room No.)? If not, will the GSA pay a shift differential for any work that has to be done after normal working hours contained in the RFP?
Response: The contractor is to plan the work under the requirement to maintain the building be fully operational. Building operating hours are Monday thru Friday from 8:00AM to 5:00PM, excluding Federal Holidays. GSA will not pay a shift differential. Any work that might interrupt the tenants’ mission will have to be planned to be performed after hours (5:00PM to 8:00AM). The contractor should prepare their price proposal and plan the execution of work accordingly.
11. During construction there will be periods where the windows in an occupied space will need to be out overnight. Will the window opening be required to be secured each night?
Response: Yes; areas will need to be secured overnight and protected from the elements.
12. Are there test results for lead testing of paint on window frames, walls, mechanical equipment, etc. be made available prior to bid?
Response: There are no hazardous materials in the Almeric L. Christian Federal Building and U.S. Courthouse in St. Croix.
13. Are there asbestos testing results available for floor coverings, base molding, adhesives, ceiling tiles, etc. to be made available prior to bid?
Response: There are no hazardous materials in the Almeric L. Christian Federal Building and U.S. Courthouse in St. Croix.
14. Will there be an area made available to the contractor for staging materials prior to installation in the building?
Response: The space in the green area adjacent to the building can be made available for contractor's material storage based on space availability. Under no circumstances will the Government be responsible for material stored on-site or off-site.
15. Will there be a location on the site, or in the building to provide a temporary field office for supervisors of the work?
Response: The space in the green area adjacent to the building can be made available for the contractor's trailer based on space availability.
16. Will the RFP include a bid alternate for performing work after normal building operational hours?
Response: No; the contractor is to plan the work under the requirement to maintain the building be fully operational. Building operating hours are Monday thru Friday from 8:00AM to 5:00PM, excluding Federal Holidays. GSA will not pay a shift differential. Any work that might interrupt the tenants’ mission will have to be planned to be performed after hours (5:00PM to 8:00AM). The contractor should prepare their price proposal and plan the execution of work accordingly.
17. Please advise the disposition of all government equipment and material to be removed and/or replaced. Are they to be turned back to the government or are we to include proper disposal only?
Response: The contractor shall dispose of all equipment and material removed from the building unless otherwise specified in the drawings and specifications.
18. Will there be limitations on the type of work that can be done during working hours? If so what types of noises will not be permitted?
Response: Work that will interrupt building operations shall be planned outside of building operating hours, to include but not limited to noise and odor producing type of work.
19. If work needs to be halted during court sessions, how will the contractor be compensated for lost productivity and schedule due to interruptions.
Response: The contractor will plan the work around the requirement to keep the building fully operational. Additional time or compensation will not be considered at this time. Future requests will be evaluated on a case by case basis.
20. Please confirm proposal due date.
Response: The date and time for receipt of proposals remains unchanged.
21. Please confirm if an elderly home with healthcare services can be considered as an institutional building.
Response: Yes
22. The submission of more than 3 projects on Attachment A1 – Experience Summary Table, will harm our evaluation rating?
Response: The submission of more than 3 projects on the experience summary table will not harm the evaluation; however only the first 3 projects will be evaluated.
23. Please, clarify if the New Cistern installation is part of the project scope.
Response: Yes; this scope needs to be included in the proposal under Contract Option 4.
24. Please, clarify if the New Cistern is provided by the owner.
Response: The new cistern is to be provided by the contractor.
25. Design pressures can either be Ultimate or Allowable. (Ult x .6). The structural drawings do not indicate if the wind pressures are one or the other. This will be critical for the outcome and whether it needs steel inside the frames. Please ask the Structural engineer to clarify if the loads are Ultimate or Allowable. I looked at CD-2 and do not see clarification.
Response: Per Note #1 on 2-S003, component and cladding wind pressures are determined per ASCE 7-16. Accordingly, wind pressures determined per the referenced code are ultimate wind pressures.
26. Please consider a time extension for bid submission in order to be able to prepare a responsive proposal.
Response: The date and time for receipt of proposals remains unchanged.
The date and time for receipt of proposals remains unchanged.
END OF AMENDMENT NO. 2