This document summarizes a solicitation for architect-engineer services and a related federal contract opportunity. The General Services Administration is seeking design and construction services for a major modernization project at the Silvio V. Mollo Federal Building in New York, New York. The project involves building temporary swing space at the nearby Jacobs K. Javits Federal Building, fully renovating the Mollo building while it is empty, and relocating tenants to the completed swing space. Interested firms must submit qualifications by November 19, 2019 to be considered for the design contract, which is expected to be awarded in mid-July 2020. The estimated construction costs are $41 million for the swing space and $185 million for the Mollo renovation. Primary client agencies are the U.S. Attorney's Office, U.S. Marshals Service, and GSA. The selected architect-engineer firm will be responsible for design through construction administration for all three project phases.
AE Contract Pre-Submittal Meeting Presentation
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Silvio V. Mollo
Major Modernization Project
AE Contract Pre-Submittal Meeting
October 24, 2019
Silvio V. Mollo Federal Building, New York, NY
Building Statistics
•Year Built – 1975
•USF – 100,041 / 160,280 GSF
•Vacant USF – 0
•Tenants
•U.S. Attorneys Office, Southern District of New York (USAO)
•U.S. Marshals (USMS)
Overall Project Schedule
• Design: FY2020 – FY2022
• Construction: FY2022 – FY2025
Lower Manhattan Government Center
Near other Historic Designated Buildings
Pedestrian Only, Law Enforcement Controlled area
NYC Zoning Designation: C6-1
Silvio Mollo Bldg
◦ Built as part of MCC construction in 1974
◦ Not considered significant for historic designation per NYSHPO and GSA
Building Systems at the end of their useful life
Degraded Space Quality Jeopardizing Customer Mission and Quality of Life / Need to modernize
Life Safety & Code Deficiencies
Exterior Envelope Problems
Existing Structural Issues
Security Vulnerabilities
Extent of problems too great to correct with customer in the building
View of Entrance Bridge and Existing Security Screening Building
View of Old Substation between Mollo & MCC
Mollo Typical Floor
Mollo Structure Frame
Javits Typical Swing Space Floor
Project Phasing
• Phase I: USAO relocate to swing space at 26 Federal
Plaza, NY NY, (37th and
38th floors.)
• Phase II: Renovate Mollo FB
(while empty)
• Phase III: Relocate portion of
USAO from Lease to Javits
Swing Space following completion of Phase II
Project Scope & Phasing
Background
• Program based upon GSA
Feasibility Study dated Aug 10, 2017 by Perkins Eastman (30 alternatives considered)
Preparatory Work
• GSA relocate existing tenants from Javits 37th & 38th floors between now and March 2021.
• Design Architect / Engineer
•Full & Open Brooks Act (Design Excellence Procedures) •Designer for both Swing Space and Mollo R&A
• Construction Manager (Agent) •Region 2 CM IDIQ contract •CMa for both Swing Space and Mollo R&A
• Javits Swing Space General Contractor •Full & Open Design-Bid-Build
• Mollo R&A General Contractor •CMc Competitive Procurement
ECCA Javits Swing Space -- $41M (FY2020)
ECCA Mollo R&A--------- $185M (FY2022)
◦ (Includes $1M Art in Architecture)
AE Contract
◦ Stage I Submissions Due 11/19/2019
◦ GSA Issue Shortlist 1/16/2020
◦ Second round AE interviews 1/17/2020 to 2/13/2020
◦ Select AE by 3/26/2020
◦ Award AE contract by mid-July 2020
◦ Complete Design for Swing Space by June 2021
◦ Complete design for Mollo R&A by May 2022
AE will need to Design Phases I, II & III simultaneously
Phase I Design will need to also satisfy Phase III requirements with minimum space alterations required
Houses: USAO (functions currently in Mollo)
(86,000 GSF)
Scope Includes:
Demo and abate existing asbestos fireproofing / Replace with new fireproofing
Renovate and build out swing space for the USAO on two floors of the Javits Federal Building.
Houses:
◦ USAO, USMS & GSA BMO: (160,000 GSF)
Renovation and upgrade of the Silvio Mollo Federal building including demo and removal of all hazardous material, old systems and finishes
Upgrade building structure
Removal / replacement of the exterior facades and roof
New HVAC, electrical, elevator, life safety and other systems
Tenant fit-out buildout new space
Repairs to the existing bridges linking Mollo to other buildings
Construction of a new entrance and screening pavilion.
Houses:
◦ USAO staff relocating from Leased Space
◦ Small changes required to house USAO staff relocating from Leased Space
GSA P-100 (2018 version) and GSA P-120
US Attorney Facilities Standards (June 2014)
USMS Design Standards
DOJ & USMS Program of Requirements
LEED Gold (Interiors) – Javits Swing Space
LEED Gold (Ver 4) – Mollo R&A
Sustainability and Energy Efficiency Stds (EPAC 2005 & EISA 2007, Guiding Principles, Federal Floodplain Mgnt etc…)
Other GSA Requirements
Design Excellence, BIM, COBie, gBUILD, ePM, HSPD-12, GSA Pricing Policy, AiA, GSA IT Security, ISC Design Criteria etc…
ESPC Contract constraints at Javits
Mollo
◦ Building Envelop, Structural & Security Improvements
◦ Central HVAC plant which supplies MCC is located within Mollo. (Will need to replace aging systems while continuing to support MCC)
◦ Logistic challenges associated with building in Lower Manhattan on a congested Federal & City Law Enforcement controlled site
Javits
◦ Aging building in need of major modernization
◦ Connecting to existing HVAC systems
◦ 37th & 38th floor contain asbestos which will need to be abated
◦ Many other projects on-going simultaneously with our project
◦ Procurement Support Phases I, II & III
◦ Construction Support Phases I, II & III
◦ Interior Design Services Phases I, II & III (Customer Reimbursable)
◦ IT & Security System Design Services Phases I, II & III (Customer Reimbursable)
◦ Construction Closeout Services, Phases I, II & III
Region 2 Core Project Team
Ken Chin – PMD Director / Sponsor
Kevin Bunker – PM
Colby Janisch – COR
Jordana Covrigaru – CO
Lisa Zalar – Contract Specialist
Jana Gross – Bldg Mgr Mollo
Cat Lenis – Bldg Mgr Javits
Jessica Karkat – Asset Mgr Mollo
Mimi Chi – Asset Mgr Javits
Region 2 Supporting Project Team
Arkady Okun – Fire Protection
Cindy Badalato – Industrial Hygenist
Maria Guida – USAO Account Exec
David Anthone – Historic Preservation
Malina Moore – Fine Arts Officer
Thomas Burke – NEPA / Environmental
Tony Overton – Manhattan Svc Ctr Dir
Scott Fletcher – Lower Manhattan FO Dir
Barbara Peyton – Javits FO Dir
Vincent Scalcione – Portfolio Dir
David Wells – Portfolio Cap Pgm Branch
Michael Weippert Cap Pgm Branch
Central Office Team
Pam Howe R2 Liaison
File details come from the government source that posted it. Updated .