08_Department Of Energy - National Nuclear Security Administration Joint Cyber Facility Request for Information Log - RFI Log.pdf

PDF 180 KB Posted

Download PDF, 180 KB

Attached to
Department Of Energy - National Nuclear Security Administration Joint Cyber Facility Construction Solicitation
Solicitation number
47PB5427R0003
Issued by
Not on record

About this file

This is a Request for Information (RFI) Log for GSA solicitation 47PB5427R0003, documenting 143 total inquiries, of which 129 have been addressed, 8 are amended, and 6 are to be addressed in a forthcoming amendment.

The solicitation concerns a substantial federal construction project involving tenant improvements and core and shell work at a Department of Energy/NNSA facility. Key deliverables include renovation of approximately 21,784 usable square feet encompassing office space, data center infrastructure, secure spaces (SCIF), mechanical and electrical systems, raised access flooring, specialized security systems, radon testing, and commissioning. The project budget encompasses two funding sources: CLIN 0001 for Tenant Improvements (BA80) and CLIN 0002 for Shell Building (BA54), with the Government anticipating a single contract award encompassing both portions. The anticipated construction commencement is April 2027 with a 345-calendar-day substantial completion requirement and 60-calendar-day final completion period. Proposals were originally due December 7, 2026, but the Government extended the deadline to December 21, 2026, at 11:00 a.m. Mountain Time. Award was anticipated within 10 calendar days of proposal receipt. Required qualifications for the general contractor include three similar projects with minimum construction value of $10 million at award and minimum 15,000-square-foot footprint. All project personnel must be U.S. citizens with HSPD-12 Tier 1 credentialing. The Government has established a 20 percent small business participation objective. Significant technical topics addressed in the RFI responses include RF shielding requirements, SCIF construction procedures, long-lead equipment procurement, radon sampling protocols per ANSI/AARST MA-MFLB-2023 standards, independent testing for Acoustic and RF Performance verification, security system infrastructure, BIM/COBie execution requirements, and coordination with existing building systems including fire alarm (EST 4 panel tie-in), Building Automation System (Niagara/Siemens), and network relocation activities. The Government retained AECOM as Construction Manager as Advisor (CMa) and Commissioning Authority (CxA).

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REQUEST FOR INFORMATION (RFI) LOG

Solicitation No: 47PB5427R0003

TOTAL INQUIRIES ADDRESSED AMENDED

To Be Addressed in a Forthcoming Amendment

143 129 8 6

RFI ID Date Received Question Official Response Status

RFI-001 2026-11-12 Could you share the expected number of radon test locations and the anticipated testing window? It would help to know whether testing is expected in one round at closeout or in phases.

If the concrete slab foundation will be fully penetrated, radon sampling will be required with the following response:

GSA requires contractors to follow the sampling requirements, including testing locations, outlined in the ANSI/AARST MA-MFLB-2023 Protocol for Conducting Measurements of Radon and Radon Decay Products in Multifamily, School, Commercial and Mixed-Use Buildings. For non-residential ground-contact locations, one measurement shall be conducted in all ground-contact rooms, offices, and general use areas that are occupied or intended to be occupied with the exceptions noted in the Table 3.8 of the standard. For larger rooms, one detector shall be placed for every 2,000 SF. See Sections 3.3 and 3.5 of the standard. The test should only include the occupied project area and any other occupied areas affected by the project:

Website Link: https://standards.aarst.org/MA-MFLB-2023/index.html#zoom=z

Addressed

RFI-002 2026-11-18 Factor 1 requires a construction value of at least $10M at the time of award. Could a final contract value with modifications count toward the $10M?

No. As specified in Section II.D, Factor 1, the referenced project must have had a construction value of at least $10 million at the time of contract award. Subsequent contract modifications or increases in contract value do not satisfy this requirement.

Addressed

RFI-003 2026-11-18 Can a JV or teaming partner's project be used as one of the 3 Factor 1 projects? Yes. In accordance with Section II.D, Consideration of Joint Ventures and Teaming Arrangements, qualifying experience of individual joint venture members and eligible first-tier subcontractors may be considered toward the three-project submission requirement.

The three-project limitation applies collectively to the Offeror’s proposed team. Each submitted project must satisfy the applicable Factor 1 requirements.

Offerors relying on such experience shall identify the entity that performed the work, its role on the referenced project, and its proposed responsibilities under this contract. The Government will evaluate the relevance of that experience in relation to the entity’s proposed role and responsibilities, consistent with the solicitation and applicable SBA regulations.

Addressed

RFI-004 2026-11-18 Are all 5 Factor 1 criteria pass/fail, or are they scored for relevance? For example, would a project slightly under 15,000 SF be excluded or just rated lower?

Factor 1 is evaluated based on the extent to which submitted projects demonstrate similarity to the requirements of this acquisition, consistent with the Similar Project Definition and Standard for Evaluation identified in Section II.D.

The solicitation establishes that the standard is met when the Offeror submits three projects that each meet the definition of a Similar Project. The Government will assess the submitted projects in terms of size, scope, complexity, technical requirements, and construction execution challenges.

With respect to square footage, the solicitation specifies a comparable construction footprint “generally consisting of at least 15,000 square feet.” Accordingly, projects slightly below 15,000 square feet are not automatically excluded solely on that basis. The Government will evaluate the extent to which such projects demonstrate comparable size and overall similarity to the requirements of this acquisition.

Projects that do not fully demonstrate the characteristics of a Similar Project may receive less favorable consideration in the overall Factor 1 evaluation.

Addressed

RFI-005 2026-11-18 Please clarify the required 28-day compressive strength for new slab-on-grade concrete and trench restoration. The structural notes, trench detail, and Specification 03 30 00 indicate differing requirements of 4,000 PSI, 3,500 PSI, and 3,000 PSI.

In the event of a conflict between the noted requirements, the minimum 28-day compressive strength for new slab-on-grade concrete and trench restoration shall be 4,000 psi.

Addressed

RFI-006 2026-11-18 Please confirm who is responsible for providing and installing the Lithium-Ion Tamer Gas detection system. If EC needs to install it, please provide the required product specifications.

EC to provide Honeywell Li-Ion Tamer GEN 3 sensing system with Monitoring sensors, Reference sensors, and a controller/hub. Exact quantities of sensors to be confirmed with Honeywell.

Addressed

RFI-007 2026-11-18 Is the Contractor responsible for furnishing and installing the branding graphics and Signage shown in Graphics_Signage_CD-100IFC?

Yes, include furnishing and installing the branding graphics and signage shown, coordinated with the tenant for final content and approvals.

Addressed

RFI-008 2026-11-18 The construction drawings identify a telecommunications cable tray system, but the project specifications do not appear to include a dedicated cable tray specification section. Please confirm the technical product requirements.

TC to refer to the TC-0.02 for the product selection for the cable tray and accessories. Addressed

RFI-009 2026-11-18 Please confirm the required manufacturer, model, and installation configuration for power and telecommunications junction boxes within the raised-floor system. Additionally, please confirm whether the FSR FL- 500P floor box identified on the AV drawings applies exclusively to AV connections.

The drawings denote for power section: J-boxes shown on power plan are standard 4x4 boxes that will be utilized by furniture installer for furniture vendor provided furniture power system. Floor boxes in conference rooms are called out under note EP2. The drawing also denote all electrical pathways and telecom cabling required with AV cabling to be performed by the Tenant.

Yes, the FSR FL-500P floor box identified on the AV drawings applies exclusively to AV connections.

Addressed

TOTAL INQUIRIES ADDRESSED AMENDED

To Be Addressed in a Forthcoming Amendment

143 129 8 6

RFI ID Date Received Question Official Response Status

RFI-010 2026-11-19 What total IT KW output is the design for data center based on? 290 kW for main server racks, with an additional 4 kW for AV racks. Total kW is 294kW. Addressed

RFI-011 2026-11-19 You said that we will be reusing existing cooling infrastructure, does that include existing ductwork? If so, what ductwork would we be responsible for in the data center?

No. As shown in the contract documents, "Existing Air Handling Unit Schedule" equipment shown on M-0.3 is to be reused in conjunction with the dedicated chillers, cooling tower, etc.

Existing ductwork will be reused only where indicated on the contract drawings and where field conditions. All other existing duct is to be demolished as shown MD-1.0 and MD-1.1. The contractor is responsible for all new and modified ductwork, branches, and tie-ins as shown on M-1.0.

Addressed

RFI-012 2026-11-19 What heat elements would we be running to the office areas? The original data center required cooling only. Per the drawings, the contractor is to provide VAV boxes with integral electric reheat coils per VAV Box Schedule on M-0.3. Hot water piping will be ran to the VAV boxes serving the office areas. A hydronic hot water preheat coil is not required.

Addressed

RFI-013 2026-11-19 Can you confirm which telecom cabling, AV, and video wall work is GC scope and which is tenant-installed?

The drawings denote all electrical pathways and telecom cabling required with AV and Video wall cabling to be performed by the Tenant.

Refer to the Owner's AV integrator drawings, 06.2_5_Conference Rooms_GDIT AV Design_Rev 7_20261023 and 06.2 _4_Watch Floor_Planar Video Wall Design_20260806, for the scope of work expected from the GC's AV subcontractor. This scope includes, but is not limited to, AV racks, fiber patch panels, wall mounts, and table cubbies.

The drawings define the infrastructure, equipment, and installation responsibilities assigned to the GC's AV subcontractor and should be used for coordination and execution of the associated AV work.

Addressed

RFI-014 2026-11-19 Is the access control and intrusion detection integrator under the GC, or is DOE bringing its own security vendor? And who owns programming and the monitoring tie-in?

The tenant will contract directly with a security systems vendor that will furnish, install, program, test, and commission the security system devices identified as Owner-furnished/Owner-installed in the contract documents. The Contractor remains responsible for all security-related infrastructure identified in the drawings and specifications, including but not limited to conduits, boxes, pathways, supports, power, grounding, rough-ins, and coordination activities necessary to support the Owner's security vendor.

Addressed

RFI-015 2026-11-19 The price form puts Shell under BA54 and TI under an RWA. Is the RWA funded today? If it slips, would you award Shell only or hold the whole award?

Funding is presently available for both the Shell (BA54) and TI (BA80) portions of the project. The Government anticipates making a single contract award encompassing both portions of the work.

As provided in Section III.A, Availability of Funds, contract award remains subject to the availability of appropriated funds.

Should funding circumstances change, the Government will provide any necessary updates through the solicitation amendment process.

Addressed

RFI-016 2026-11-19 What's your target award date, and how long should we hold our price? With a firm fixed price and an April 2027 start, escalation is our biggest pricing risk.

Offers submitted in response to this solicitation shall remain valid for a minimum of 120 calendar days following the date established for receipt of proposals.

Offerors shall account for anticipated labor, material, equipment, and other cost escalation in their proposed firm-fixed-prices, considering the anticipated construction commencement date and the required period of performance.

Addressed

RFI-017 2026-11-19 Is Substantial Completion tied to DOE accrediting the space? If shielding or TEMPEST testing fails for reasons outside our work, how does that affect our schedule and liquidated damages?

Substantial completion will be determined in accordance with the contractual construction and completion requirements and is not contingent solely upon issuance of DOE accreditation.

The Contractor remains responsible for satisfying all applicable contractual requirements, including required testing, inspections, and correction of nonconforming work. All independent testing is required for meeting substantial completion. Any discrepancies between the contractors independent testing and the governments testing remains the responsibility of the contractor for conformance to the contract requirements.

Should accreditation related testing identify deficiencies attributable to circumstances beyond the Contractor’s control and not resulting from nonconforming work, any associated schedule impacts, requests for time extensions, or applicability of liquidated damages will be evaluated in accordance with the terms and conditions of the contract. Any warranted contract adjustments will be addressed through the applicable contractual procedures.

Addressed

RFI-018 2026-11-19 Has the CTTA countermeasures review been completed on the IFC set? If new TEMPEST requirements come up after award, will GSA treat them as a change?

The CTTA countermeasures review has been completed on the IFC set. As directed by the AO, any new TEMPEST-driven requirements directed after award and not in the contract documents will be treated as changes via modification.

Addressed

RFI-019 2026-11-19 Who provides construction surveillance technicians and secure storage for SCIF materials, GSA or the contractor? Will any workers need US citizenship or clearances beyond HSPD-12?

NNSA will provide a Construction Site Security Manager for this project.

The designated secure storage is within the warehouse of the building per the Site Logistics Plan.

In accordance with the SOW, CSP, and project security requirements, all personnel assigned to the project must be U.S.

citizens and must successfully complete the HSPD-12 Tier 1 credentialing process. These requirements apply to all personnel regardless of anticipated duration on site. This will be further documented and included on the ROCAL List.

TOTAL INQUIRIES ADDRESSED AMENDED

To Be Addressed in a Forthcoming Amendment

143 129 8 6

RFI ID Date Received Question Official Response Status

RFI-020 2026-11-19 Where the design says an item is required only if the Accrediting Official directs it, should we carry it in base price, or will it be added by change?

If this inquiry pertains to the Owner's Project Requirements (OPR), the AO has clarified that the Contractor is required to perform independent testing to verify compliance with Acoustic Security Performance and RF Performance requirements.

Completion of all required independent testing is a prerequisite to Substantial Completion.

The Contractor remains responsible for ensuring that the completed work satisfies the applicable Contract requirements, including correcting deficiencies identified through independent testing or Government validation testing that are attributable to nonconforming work.

The OPR will be revised by solicitation amendment to remove language indicating that such testing is required only when directed by the Government.

Any additional requirements directed by the AO that are outside the scope of the Contract Documents will be evaluated and addressed in accordance with the applicable contractual changes procedures.

Amended

RFI-021 2026-11-19 Will the LNTP authorize ordering long-lead items like the UPS and secure door assemblies, and will GSA pay for stored materials before construction NTP?

Yes. The Government anticipates that the LNTP will authorize procurement of specifically identified and approved long-lead items, subject to completion of applicable submittal reviews and the express authorization provided in the LNTP. A designated caged area within the building is anticipated to be available for material staging.

In accordance with FAR 52.232-5 and GSAR 552.232-5, the Government may consider progress payments for materials delivered and stored on-site prior to issuance of the CNTP, provided the following conditions are satisfied:

Authorization: Procurement of the materials is expressly authorized under the LNTP.

Approved Submittals: Applicable material and equipment submittals have received the required Government approval.

Delivery and Inspection: Materials are delivered to the designated staging area, properly identified, segregated, protected, and available for Government inspection.

Title and Insurance: The Contractor provides satisfactory documentation establishing ownership of the materials and adequate insurance protection.

Payment Documentation: The Contractor submits the required supporting documentation, participates in the pre-invoice payment review process, and provides the required GSA Form 2419 certification.

Progress payments remain subject to the Contracting Officer’s review and approval in accordance with the contract requirements. Procurement undertaken outside the express authorization of the LNTP is at the Contractor’s risk.

Addressed

RFI-022 2026-11-19 Will finishing earlier than 345 days earn credit in the technical evaluation, or is schedule pass/fail? We understand the tenant wants occupancy as early as possible.

As provided in Factor 3 – Technical and Management Approach, the proposed project schedule will be evaluated as part of the overall technical assessment and is not strictly pass/fail.

The Government will evaluate the realism, feasibility, sequencing, coordination, and risk mitigation associated with the proposed schedule. While earlier completion may be considered within the overall assessment of the proposed approach, no separate evaluation credit or preference will be assigned solely for proposing completion earlier than the contractual requirement of 345 calendar days.

Offerors are encouraged to propose realistic and achievable schedules that demonstrate effective project execution while satisfying all applicable contract requirements.

Addressed

RFI-023 2026-11-19 What's the realistic EOD and badge turnaround in Region 8 right now, and can we start fingerprinting before LNTP? Since late badging gets no extension, we need to plan around it.

The HSPD-12 Tier 1 badging process typically takes 3 to 6 weeks from initial submission to badge pickup. Under ideal conditions—with no background issues, rejected forms, or scheduling delays—a contractor can receive their badge in 3 to 4 weeks. However, vendors should budget 6 to 8 weeks to account for regional enrollment backlogs and fitness review times.

Following Contract Award, the vendor initiates the process by submitting the Requesting Official Contractor Approval List (ROCAL) and an individual Contractor Information Worksheet (CIW) for each employee:

• Sponsorship (1–2 Weeks): The vendor submits the CIW to the COR/Requesting Official. The Office of Mission Assurance (OMA) enters the applicant into the system, triggering an automated USAccess scheduling email.

• Enrollment (1–2 Weeks): The applicant attends an in-person USAccess appointment (subject to Region 8 site availability) for fingerprints, a photo, and verification of two valid I-9 IDs.

• eApp & Initial Fitness (1–2 Weeks): The applicant submits the SF-85 via eApp. OMA issues an initial fitness determination based on form reviews and favorable FBI fingerprint checks, without waiting for the full Tier 1 investigation to close.

• Card Pickup & Activation (1 Week): Once shipped, the applicant schedules a final credentialing site appointment to collect and activate the badge.

TOTAL INQUIRIES ADDRESSED AMENDED

To Be Addressed in a Forthcoming Amendment

143 129 8 6

RFI ID Date Received Question Official Response Status

RFI-024 2026-11-19 Regarding the existing data center: Who owns the downtime window, and who carries the risk if a unit fails after we move it?

The existing data center is no longer operational. What remains is a building demarcation room and adjacent suite network systems that must be relocated early in the project prior to full demolition activities. This work includes installation of electrical infrastructure serving a new building demarcation room, Alternate Point of Presence (APOP) rooms, and new rack and cable terminations in Suite 8110.

Coordination among the Contractor, GSA, NNSA, and the Network Provider (Lumen) will be required to execute this work.

Lumen will be responsible for installing new network circuits through Contractor-installed conduits and pull boxes and for furnishing and installing the fiber distribution panels serving the new building demarcation room and APOP locations.

Any required outage or cutover activities shall be coordinated among the Contractor, GSA, NNSA, and Lumen and incorporated into the Contractor's project schedule. For bidding purposes, Offerors should anticipate a phased migration effort that may require approximately two weeks for NNSA equipment relocation activities and installation of new network circuits by Lumen, followed by a planned cutover event that is anticipated to occur over a three-day weekend to minimize impacts to building tenants. Actual durations and sequencing will be determined through coordination among the parties during project execution.

Responsibility for damage to, or disruption of, active systems resulting from Contractor operations will be determined in accordance with the contract requirements and the specific circumstances causing the outage or failure.

Addressed

RFI-025 2026-11-19 Can GSA provide the hydrant flow test before bid? The sprinkler design depends on it, and we want to know who carries the risk if supply comes up short.

The hydrant flow test information is unavailable. The contractor will be required to conduct early in construction a water‑supply flow test to establish the basis of design and final acceptance testing to verify performance and compliance as noted in Specification 21 08 00 and Drawing FX00.

Addressed

RFI-026 2026-11-19 Can you share the O&M contractor's outage rates and current FPS escort rates before bid? We pay both directly, and we'd rather price real numbers than allowances.

The 2026 O&M and estimated 2027 FPS rates are in the SOW with further instructions; we will provide any updated rates when available.

For pricing future years, a 4% annual escalation rate may be assumed.

GSA O&M - 2026 Rates:

HVAC Tech is $75.82 ST / $91.80 OT Electrician $79.43 ST / $97.20 OT After-hours call-out: minimum of two hours.

Holidays and Sundays are billed at double the straight time hourly rate. Minimum two hours

FPS Escorts - ~2027 Rates:

Per FPS, the estimated $82.30 for 2027 may increase due to yearly department of labor wage determinations but the amount of increase is not known.

The rate remains the same for afterhours, holiday, with no set minimum amount of hours required.

Addressed

RFI-027 2026-11-19 If tenant-furnished items like the video wall or watch floor furniture arrive late, will GSA adjust our completion date? They sit on our critical path.

The Contractor is responsible for coordinating and maintaining the construction schedule, including activities associated with the delivery and installation of tenant-furnished items. Continuous coordination among the Contractor, GSA, and tenant representatives is required throughout construction to facilitate timely delivery and installation.

The Contractor shall promptly communicate any anticipated schedule deviations or coordination issues that may affect the delivery or installation of tenant-furnished items and identify appropriate mitigation measures.

Should delays attributable to the Government impact the project’s critical path and contract completion, any requests for schedule adjustments will be evaluated in accordance with the terms and conditions of the contract. Any warranted adjustments will be addressed through the applicable contractual procedures.

Addressed

RFI-028 2026-11-19 For Past Experience and Past Performance, will a major subcontractor's projects count the same as the prime's? If not, how are they weighted?

As provided in Section II.D, Consideration of Joint Ventures and Teaming Arrangements, the Government may consider the experience and past performance of qualifying first-tier subcontractors or team members in evaluating Factors 1 and 2.

Such experience and past performance will be evaluated based on its relevance to the contract requirements, the subcontractor’s role on the referenced projects, and the extent to which that experience aligns with its proposed responsibilities under this contract.

The Government will place greater emphasis on experience and past performance directly attributable to the entity proposed to perform the relevant work. No predetermined numerical weighting is assigned to prime contractor versus subcontractor experience or past performance.

For Factor 1, submitted projects must satisfy the applicable solicitation requirements, including the provisions governing qualifying first-tier subcontractor experience. The three-project submission limit applies collectively to the proposed team.

TOTAL INQUIRIES ADDRESSED AMENDED

To Be Addressed in a Forthcoming Amendment

143 129 8 6

RFI ID Date Received Question Official Response Status

RFI-029 2026-11-19 Can one person fill two key roles, like QC Manager and safety, on a project this size? And can the Superintendent be a subcontractor's employee?

Offerors shall propose personnel and staffing arrangements sufficient to fulfill all applicable contract requirements, including those identified under Factor 4 – Key Personnel Qualifications.

An individual proposed to perform multiple roles must possess the required qualifications and demonstrate the ability to effectively fulfill the responsibilities of each assigned position without compromising project management, quality control, safety, or construction oversight. Any such arrangement must comply with the applicable contract specifications and personnel requirements.

The solicitation does not expressly require the proposed Construction Superintendent to be a direct employee of the prime contractor. However, the prime contractor remains responsible for overall contract performance, including construction supervision, coordination, quality, and safety. The proposed Superintendent must satisfy all applicable qualifications and demonstrate sufficient authority and availability to fulfill the position’s responsibilities.

All proposed staffing arrangements will be evaluated in accordance with the solicitation requirements.

Addressed

RFI-030 2026-11-19 If the prime is a small business, does our self-performed work count toward the 20% small business goal, and is a subcontracting plan still required?

Yes. For purposes of Factor 5 – Small Business Participation Plan, work self-performed by an eligible small business prime contractor may be counted toward the Government’s 20% small business participation objective.

All offerors, regardless of business size, are required to submit a Small Business Participation Plan addressing the requirements of Factor 5.

The Small Business Participation Plan is separate from the formal Small Business Subcontracting Plan required under FAR 52.219-9. Small business prime contractors are not required to submit a FAR 52.219-9 subcontracting plan. An apparent successful offeror that is an other-than-small business must submit an acceptable subcontracting plan prior to award, when applicable.

Addressed

RFI-031 2026-11-19 If AECOM's countersignature isn't back by December 7, will a copy signed by us, with proof we sent it to AECOM, be accepted?

If this question pertains to the Proprietary Information Agreement with AECOM, offerors are responsible for coordinating execution of the agreement with AECOM. Agreements that substantially conform to the GSA provided sample are not anticipated to experience significant delays in obtaining AECOM's countersignature. Agreements containing additional or modified provisions may require further review by AECOM’s legal counsel.

If AECOM’s countersignature has not been received by the proposal submission deadline, the Government will accept an offeror-signed agreement accompanied by documentation demonstrating its submission to AECOM for execution.

However, a fully executed agreement, including AECOM’s countersignature, must be provided prior to contract award.

RFI-032 2026-11-19 The Agreement lists general liability, auto, and workers' comp. Do you also require builder's risk or pollution coverage, and can the $5 million GL limit be met with an umbrella?

In accordance with Section III.F, Insurance Requirements, of the Agreement, the Contractor shall maintain the insurance coverage and minimum limits specified therein. Builder’s risk and pollution liability insurance are not separately required under Section III.F, unless otherwise required by the applicable contract documents.

The $5,000,000 per-occurrence commercial general liability requirement may be satisfied through a combination of primary commercial general liability and umbrella or excess liability insurance, provided the combined coverage meets the required limits, scope of coverage, and all applicable contractual requirements, including FAR 52.228-5 and GSAR 552.228- 5.

Addressed

RFI-033 2026-11-19 The Volume 1 Table of Contents lists Sections 09 65 00 – Resilient Flooring and 09 65 13 – Resilient Base and Accessories. However, neither section is included in the specification manual dated 10/23/2026.

Please issue both missing specification sections. These sections govern RF-01, RF-02, RF-03, BA-01 through BA-08, and FT-01 through FT-03.

These sections were inadvertently omitted from the 10/23/2026 issuance. Spec section 09 65 00 and 09 65 13 to be provided.

To Be Addressed in a Forthcoming Amendment

RFI-034 2026-11-19 Carpet Tile vs. Raised Access Floor Panels: Specification 09 69 00, Section 2.3.A.2, requires raised access floor panels with alignment pins for field-installed carpet tile. However, carpet types CP-01, CP-02, and CP-03 are identified as 18" x 36" tiles on drawing AN-5.3.

Please confirm whether panels without alignment pins are acceptable with an adhesive or tab installation system, or whether the carpet tile dimensions need to be revised.

Carpet tile dimensions will not be revised. Spec section 09 69 00 will be updated to remove this requirement. To Be Addressed in a Forthcoming Amendment

RFI-035 2026-11-19 Raised Access Flooring Extents: Please identify which rooms and areas are to receive raised access flooring and which areas will remain on concrete slab.

Drawing AN-5.3 includes the note "coordinate with access flooring module" for every RF and CP finish designation; however, the architectural plans do not identify the limits of the raised access flooring.

Sheet A-0.0 shows the extent of RAF removal and sheet A-1.0 notes the height and locations of the RAF "RAISED ACCESS FLOORING". Additionally all partition details note the demising requirements for all partitions within the scope of work.

TOTAL INQUIRIES ADDRESSED AMENDED

To Be Addressed in a Forthcoming Amendment

143 129 8 6

RFI ID Date Received Question Official Response Status

RFI-036 2026-11-19 Plywood Underlayment Requirements: Architectural drawing A-4.0, Keynote 401, requires 1/4" plywood under all resilient flooring.

Please clarify:

• Does this requirement apply to concrete slab, raised access floor panels, or both?

• What plywood grade is required, and what fastening method is acceptable?

• How does plywood installation comply with Specification 09 69 00, Section 2.3.C.1.d, which requires each access floor panel to remain removable?

1. The 1/4-inch plywood underlayment requirement applies only over raised access floor (RAF) panels where resilient flooring is installed. It does not apply over concrete slab. Sheet note 401 shall be disregarded for: Reception 01.000 via amended A-4.0.

2. Use 1/4" APA Rated Underlayment, Exposure 1, sanded face, for a smooth and durable surface. The contractor shall confirm with manufacture on acceptable fasteing methods applied to the concrete filled raised access floor panels which should be mechanical or fasteners or compatible adhesive.

3. When the plywood is installed for the resilient flooring, the access floor panel is not expected to be removable. This supersedes the specifications section indicating this.

Amended

RFI-037 2026-11-19 RF Floor Membrane Installation: Specification 13 49 15, Part 3, requires installation of the RF membrane over the floor construction.

Please clarify:

•What substrate will receive the finished flooring (concrete slab, RF membrane, topping, or raised access floor)?

•What flooring adhesive is approved for installation over the RF membrane?

•How are transition strips to be fastened? Specification 09 68 13, Section 3.3.F, requires anchors at 6" on center, while Specification 01 35 56 prohibits unapproved RF penetrations.

•Please provide an approved installation detail addressing these requirements.

Refer to the drawings for the extent of RF Shielding on floor representing 18" overlapped across the perimeter and at steel columns G-005 (Floor) and G-006 (Ceiling).

Addressed

RFI-038 2026-11-19 CP-01A and CP-03A Carpet Identification: Drawing AN-5.3 identifies CP-01A and CP-03A as carpet tile but lists the size as "Broadloom 12'."

Please confirm whether these finishes are intended to be broadloom carpet in accordance with Specification 09 68 16.

Additionally:

•Specify the stair nosing manufacturer, product, and finish for CP-03A stair treads and risers.

•Confirm whether carpet cushion is required. Specification 09 68 16, Section 1.10.C, references a cushion warranty but does not identify a cushion product.

The "A" designation is broadloom located at the ramps for CP-01A and CP-03A.

The schedule on AN-5.3 will be updated to remove the designation as carpet tile and changed to broadloom.

Amended

RFI-039 2026-11-19 Resinous Flooring and PT-12 Coating: Specification 09 67 23 identifies a broadcast epoxy flooring system at the removed equipment pad. However, drawing AN-5.3 identifies PT-12 as Sherwin-Williams Armorseal 8100 paint at Storage Room 01.039, and drawing A-4.1, Keynote 408, calls for PT-12 at demolition areas.

Please clarify:

• The intended flooring/coating system.

• All locations where each system is required.

• Which subcontractor trade package is responsible for this work.

The PT-12 Sherwin-Williams Armorseal 8100 paint at Storage Room 01.039 on drawing A-4.1, Keynote 408 should be used. Addressed

RFI-040 2026-11-19 Base Profile Requirements: Architectural drawing A-4.0, Note 10, identifies straight base BA-01 as typical. Drawing AN-5.3 indicates straight base at carpet areas and cove base at resilient flooring areas. Drawing A-4.2 illustrates both conditions.

Please confirm that drawing A-4.2 governs the base profile requirements.

A-4.2 governs the base profile requirements. Refer to A-4.2 for all bases. Addressed

RFI-041 2026-11-19 Flooring Attic Stock Requirements: Please provide the required attic stock quantities for RF-01, RF-02, RF-03, broadloom carpet, and associated base materials. These quantities are not currently identified in the specifications.

Provide attic stock equal to 10% for the following: RF-01, RF-02, RF-03, broadloom carpet, associated base materials, CS- 05, and CS-06.

Addressed

RFI-042 2026-11-19 Security Systems Procurement and Manufacturer Requirements: Is GSA contracting directly with a security systems contractor for this project?

If not, please clarify whether this is an open-specification project or whether GSA/NNSA requires specific security system manufacturers.

The tenant will contract directly with a security systems vendor that will furnish, install, program, test, and commission the security system devices identified as Owner-furnished/Owner-installed in the contract documents. The Contractor remains responsible for all security-related infrastructure identified in the drawings and specifications, including but not limited to conduits, boxes, pathways, supports, power, grounding, rough-ins, and coordination activities necessary to support the Owner's security vendor.

Addressed

RFI-043 2026-11-19 Security Contractor Scope of Work: Has it been determined whether the project scope is limited to conduit and rough-in installation, with GSA/NNSA contracting directly with a separate security contractor for the security systems?

Please clarify the intended division of responsibility before subcontractor pricing is finalized

The tenant will contract directly with a security systems vendor that will furnish, install, program, test, and commission the security system devices identified as Owner-furnished/Owner-installed in the contract documents. The Contractor remains responsible for all security-related infrastructure identified in the drawings and specifications, including but not limited to conduits, boxes, pathways, supports, power, grounding, rough-ins, and coordination activities necessary to support the Owner's security vendor.

TOTAL INQUIRIES ADDRESSED AMENDED

To Be Addressed in a Forthcoming Amendment

143 129 8 6

RFI ID Date Received Question Official Response Status

RFI-044 2026-11-19 Existing Security Cabling: Existing security cables appear to serve security doors on the southwest side of Building 810. These cables run through the new DMARC location, enter from the south side, and terminate in the existing IDF closet.

Please clarify how GSA wants the GC to handle and protect these existing security cables during construction, particularly where the existing pathway will be impacted by demolition and new construction.

No known security system cabling serving the southwest side of Building 810 has been identified. If existing conditions are discovered that could impact other tenants, security systems, or building operations, the GC shall maintain service continuity, provide temporary protection and rerouting as required, and coordinate with the Government security team and GSA Access Control personnel to implement an approved contingency plan. Security and access control systems shall remain operational at all times. Existing cable pathways are currently unknown; however, the Government is coordinating with the access control team to determine whether record drawings are available. If existing security cabling is identified that conflicts with the work, required mitigation measures will be evaluated and addressed in accordance with the contract requirements.

The existing building demarcation room will require relocation early in the project, prior to demolition activities. This work includes installing electrical infrastructure for a new building demarcation room, Alternate Point of Presence (APOP) rooms, and a new equipment rack with cable terminations in Suite 8110. Coordination among NNSA, GSA, the Network Provider (Lumen), and the Contractor will be required to execute this work. The network provider (Lumen) will be responsible for installing new network circuits through Contractor-installed conduits and pull boxes and for furnishing and installing fiber distribution panels within the demarcation room and APOP locations.

Addressed

RFI-045 2026-11-19 Waveguide Schedule and Requirements: The specifications indicate that all penetrations through SCIF walls require waveguides.

Please provide a waveguide schedule identifying:

•Required sizes.

•Quantities.

•Locations.

•Applicable penetration requirements.

Additionally, per Note 5 of the project narrative, please clarify whether waveguides are required when ductwork exits the SCIF above the mezzanine and subsequently re-enters the SCIF. This configuration would potentially double the required waveguides and increase system static pressure.

EP-1.0 identifies the currently known secure-space penetration locations. All penetrations through RF-shielded assemblies shall comply with the requirements of the contract documents and applicable ICD/ICS-705 requirements. Additional penetration details required for coordination will be addressed by amendment if necessary.

A waveguide schedule will not be additionally provided.

Any penetrations from the mezzanine will require a waveguide, noting that waveguides are only required for the secure spaces and not the unsecured mezzanine spaces (i.e. Mechanical/Electrical rooms).

Addressed

RFI-046 2026-11-19 Sound Attenuator Schedule: The specifications require sound attenuators at all penetrations through sound-rated walls.

Please provide a schedule identifying the required locations, sizes, quantities, and specifications for these sound attenuators. Vendors require this information to provide accurate pricing.

The sizes and quantities are dictated by the ductwork into those sound rated walls per M-0.2/Detail 3 and the respective M-1.0.

The sound attenuators were identified to be required by the accreditation team with the following example provided by the CTTA: https://ddsacoustical.com/products/hvac-acoustic-silencers#features We will work to provide the performance specifications for these attenuators but the example can be used as the basis of design for biding.

Addressed

RFI-047 2026-11-19 Hydronic Hot Water Coil: The mechanical specifications indicate that a new hydronic hot water coil will be installed to heat outside air before it enters the return air of the units. However, this heating water coil cannot be located on the mechanical drawings.

Please confirm whether this coil is required and, if so, provide the applicable mechanical details and specifications.

This specifcation was not updated to clarify what is reflected in the drawings. Per the drawings, the contractor is to provide VAV boxes with integral electric reheat coils per VAV Box Schedule on M-0.3. A hydronic hot water preheat coil is not required.

Addressed

RFI-048 2026-11-19 SCIF Wall Penetration Coordination: Mechanical drawing M-1.0, Detail M10, appears to show a penetration through a SCIF wall. However, this penetration is not identified on electrical/penetration drawing EP-1.0.

Please revise drawing EP-1.0 to identify all required penetrations, including those associated with the mezzanine.

The M-1.0, Detail M10, is not a penetration through the mezzanine. It is a wall penetration above the finished ceiling. Addressed

RFI-049 2026-11-19 Existing AHU Demolition and Removal: Can the existing air handling unit scheduled for demolition be cut up and removed within the mechanical room, or are there restrictions on demolition and removal methods?

Segmenting and removal within the mechanical room is acceptable, subject to compliance with contract safety requirements and protection of existing facilities. The Contractor shall submit its demolition and rigging plan for review.

Addressed

RFI-050 2026-11-19 Isolation Dampers for Air Distribution Redundancy: Project narrative Note 7 indicates that isolation dampers are to be added for air distribution redundancy.

Please identify the required isolation damper locations and provide the applicable mechanical drawings or details.

Refer to Typical Supply Branch Duct Detail on sheet M-0.1. Addressed

RFI-051 2026-11-19 Motor Starters and VFD Requirements: Please clarify whether motor starters and/or variable frequency drives (VFDs) are required for any new or existing mechanical equipment.

If required, please identify the applicable equipment and clarify the associated electrical and mechanical scope.

Fans specified have Vari-green motors, in which case just a starter would be required from the mechanical contractor. If a different fan is provided without a variable speed motor, a VFD would be required.

Addressed

RFI-052 2026-11-19 Ebtron Airflow Sensor: Please identify the required Ebtron airflow sensor manufacturer, model, and configuration for the project.

Airflow sensor to be GTx-116e-P or equal. Sensor density to be selected by Ebtron for duct dimensions and installation conditions.

Addressed

RFI-053 2026-11-19 Supply Duct and VAV Elevation at Watch Area: Please provide an elevation view showing the intended routing and arrangement of the supply ductwork and VAV boxes serving the Watch Area.

We will issue an enlarged plan and elevation/section for the Watch Area. To Be Addressed in a Forthcoming Amendment

TOTAL INQUIRIES ADDRESSED AMENDED

To Be Addressed in a Forthcoming Amendment

143 129 8 6

RFI ID Date Received Question Official Response Status

RFI-054 2026-11-19 Transfer Duct Insulation Thickness:

1). A duct insulation table would be useful, example in narrative (page 31)the duct after VAV's would be 1" but in spec 1 1/2"also in mechanical room all existing duct is wrapped while in new duct in the spec states that the return to be lined and supply to be wrapped.

2). In narrative page (34), it shows transfer duct at secure site with man bars, are these required in addition to waveguides? Again, a waveguide schedule and locations of them would be very helpful both for bidding and pricing from vendors.

1. Only supply air ductwork or ductwork, or an outside air duct shall have 2" external insulation. Refer to spec section 230713.2.1.

2. There shall be no manbars. Refer to the penetration plan for waveguide locations. On narrative page 34, the statement indicates that the "waveguides negate the need for the man bars".

Addressed

RFI-055 2026-11-19 Gripple Support System for Square Ductwork: The specifications indicate that Gripple supports are acceptable for round ductwork.

Please clarify whether Gripple supports may also be used for smaller square ductwork located outside the mechanical room.

This is acceptable for smaller square ductwork outside the mechanical room when installed per manufacturer recommendations and SMACNA requirements and within weight/deflection/seismic limits.

Addressed

RFI-056 2026-11-19 Ductwork Pressure Testing Requirements: Please identify which ductwork areas require pressure testing and specify the required percentage or extent of ductwork to be tested.

Please also clarify the applicable testing standards and acceptance criteria.

The supply air ductwork shall be tested to upstream of the VAV boxes. Exhaust air duct systems shall be tested. 25% of the total installed ductwork shall be tested. Refer to spec section 230593.3.10 for testing standards and acceptance criteria.

Addressed

RFI-057 2026-11-19 Exhaust Fan Demolition and Concrete Pads: Please clarify whether the existing concrete pads are to be removed as part of the exhaust fan demolition or whether they are to remain in place. The existing exhaust fans shall be carefully removed and relocated to the designated caged storage area within the building’s warehouse, nearest the loading dock, for subsequent GSA property reporting and disposition. Off-site transportation or disposal of the exhaust fans is not required under the base contract.

The Contractor shall provide all labor, equipment, rigging, handling, transportation, protection, and coordination necessary to safely remove and relocate the exhaust fans. The equipment shall be handled and stored in a manner that preserves its condition for subsequent Government evaluation and disposition. Removal and transportation activities shall be performed in a manner that protects existing floors, walls, doors, and other building components from damage, except for demolition expressly required by the Contract Documents.

Any additional Government-directed relocation, transportation, or disposal services outside the established contract scope will be addressed in accordance with the applicable contract changes provisions.

The existing concrete equipment pads supporting the exhaust fans shall be demolished in accordance with Drawing A-0.1, Keynote 11.

Addressed

RFI-058 2026-11-19 Exhaust Fan Removal and Disposition: Please clarify the following requirements for the existing exhaust fans being removed:

•Where are the removed exhaust fans to be delivered or stored?

•What are the approximate weights of the existing fans?

•Are there any specific handling, transportation, or disposal requirements?

The existing exhaust fans shall be carefully removed and relocated to the designated caged storage area within the building’s warehouse, nearest the loading dock, for subsequent Government property reporting and disposition. Off-site transportation or disposal of the exhaust fans is not required under the base contract.

The existing exhaust fans are identified as Twin City Fans, Model BAE-SWSI-542, with an estimated weight of approximately 3,600 to 4,400 pounds per fan (Estimate: Bare Fan (Class I or II Arr. 3): 2,400 – 2,950 lbs., Structural Channel Sub-Base & Yellow Belt Guard: 400 – 550 lbs., Motor & V-Belt Drive (est. 40–60 HP): 650 – 900 lbs.). These weights are estimates only. The Contractor shall verify actual equipment weights, dimensions, access constraints, and rigging requirements prior to removal.

The Contractor shall provide all labor, equipment, rigging, handling, transportation, protection, and coordination necessary to safely remove and relocate the exhaust fans to the designated storage area. Removal and transportation activities shall be performed in a manner that protects the existing building, equipment, and surrounding facilities from damage, except for demolition expressly required by the Contract Documents.

The exhaust fans shall be handled and stored in a manner that reasonably preserves their condition for subsequent Government evaluation and disposition.

Any additional Government-directed relocation, transportation, or disposal services outside the requirements described above will be addressed in accordance with the applicable contract changes provisions.

Addressed

RFI-059 2026-11-19 Exhaust Fan Roof Penetration and Roof Restoration: Following removal of the existing exhaust fans, please clarify the required treatment of the remaining roof openings.

Specifically:

•Is roof patching required?

•Is a new roof curb required?

•Are metal caps acceptable for covering the existing penetration openings?

•Please provide the required roof restoration detail and weatherproofing requirements.

Please define the required penetration interface process, including the coordination, submittal, review, approval, and installation procedures for penetrations through SCIF and other controlled construction assemblies.

The exhaust fans do not penetrate the roof, therefore not requiring any roof patching, roof curb, metal caps, or restoration.

The 3 exhaust fans are pulling air from the prior data center ceiling through duct work and exhausting out into the warehouse.

TOTAL INQUIRIES ADDRESSED AMENDED

To Be Addressed in a Forthcoming Amendment

143 129 8 6

RFI ID Date Received Question Official Response Status

RFI-060 2026-11-19 BIM Modeling Requirements: Can BIM modeling be completed at the end of the project to reflect the final as-built conditions, or is ongoing coordination modeling required throughout construction?

Please clarify the required BIM deliverables and submission schedule.

Based on the cited sections, ongoing 3D coordination modeling and clash detection are not required, as traditional 2D coordination governs. However, BIM/COBie execution cannot be deferred entirely until closeout and must begin pre-construction to fulfill mandatory upfront approvals (BEP, IDP, and live Kickoff Demonstration prior to payment) and phased BIM and COBie milestone submittals (60% Fiscally Complete, Beneficial Occupancy, and Fiscal Completion). Refer to 1_GSA BIM with CDX & COBie National Standard page 24 of 56 for Construction Phase Submission Matrix.

The "0.6.4_1a_BIM Submission QC Checklist_v2025.1" and "0.6.4_2a_GSA, CDX, and COBie Data Standard_v2025.1" is being added via amendment.

Amended

RFI-061…