Phase 1 Procurement pre-bid meeting minutes 2026 03 24.pdf
PDF 3 MB Posted
- Attached to
- IRS Martinsburg Enterprise Computing Center (ECC) Roof Replacement Project located in Kearneysville, WV
- Solicitation number
- 47PB5126R0019
About this file
This document is the Phase 1 Pre-Bid Conference & Site Walk Minutes for GSA Solicitation 47PB5126R0019, a roof replacement project for the IRS Martinsburg Electronic Computing Center. The project involves replacing approximately 190,000 square feet of roofing across four primary buildings (office and auditorium, data center, warehouse, and MEP addition). The scope includes replacement of ballasted protected membrane roofs (PMR), coping, flashing, expansion joints, skylights, and roofing accessories; lightning protection systems; rooftop unit structural cross bracing; EPDM awning roofs; an elevator overrun roof; installation of new fixed exterior access ladders; and a new fall protection system throughout the building perimeter. Options include reroofing the MEP addition, installing fixed exterior access ladders, and installing fall protection throughout the entire building perimeter. The period of performance is 12 months from Notice to Proceed to Substantial Completion.
The procurement is conducted under FAR Part 15 using a two-phase competitive negotiation process with one contract award. In Phase 1 (due by April 16, 2026, at 2:00 PM EST), offerors submit technical proposals evaluated on Prior Experience on Relevant Projects (40%), Project Management Plan and Approach (30%), and Past Performance on Relevant Projects (30%). The government will establish an advisory short-list ranking all Phase 1 offerors; this ranking does not prevent Phase 2 submission. Phase 2 includes price proposal evaluation, interviews, and best value trade-off analysis targeting early June for 100% construction documents issuance. Questions regarding Phase 1 must be submitted by March 30, 2026, via RFI to the Contracting Officer. This is a small business set-aside project. Work will be performed primarily on the building exterior with limited interior access; all personnel require HSPD-12 Tier 1 clearances and PIV cards, with minimum two business days' notice required for visitors. The facility is located on a secure government site.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
IRS Martinsburg Electronic Computing Center Roof Replacement Project Solicitation 47PB5126R0019 Phase 1 Pre-Bid Conference & Site Walk Minutes
Date: 3/24/2026 Time: 1:30 PM EST Location: IRS ECC Facility https://sam.gov/workspace/contract/opp/7d3f0028a32b4164bada841103677119/view
Attendance
Name Company
Jonathan Plotkin GSA
Emily Davis GSA
Jacob Yates WDP
Will Griffin WDP
Trevor Weilbach WDP
Jean Steele AECOM
Bill Weyers AECOM
Chris Bunting IRS
Jordan Owens AODRBTJV
Robin Smith Inland Construction & Engineering, Inc.
Jennifer Stone SAW Contracting, Inc.
Cody Smith Wolf Creek Contractors, LLC
Corey Strimer Wolf Creek Contractors, LLC
David Powell Progressive Roofing
Valentine Lentz RSSI Roofing Company
Joshua Houghton H2 Construction, Inc.
Taylor Hoeltje H2 Construction, Inc.
Joe Cotter Vertex Roofing
Alejandro Palma Capital Trades, LLC
Philip Smith Miami Wiipica https://sam.gov/workspace/contract/opp/7d3f0028a32b4164bada841103677119/view
Attendance (continued)
Name Company
Mike Strader Centimark
Augustus Strader Centimark
Brice Baker GBOSS
Dale Pasley Portico Services
Derek Buzzo Portico Services
Collin Fannin Ritz Construction, Inc.
Nick Ott Houck
Andy Anglia Houck
Cameron Wedgwood Competition Roofing, Inc.
Elijah LaPoint Modern Roofing
General Services Administration Office of Program and Project Management Capital Projects East Division www.gsa.gov
1. Agenda
1.1. Project Overview
1.2. Proposal Process
1.3. Key Milestones
1.4. Q&A
1.5. Site Visit
2. Project Partners/Introductions
2.1. General Services Administration
2.2. IRS
2.3. WDP (A/E)
2.4. AECOM (CMa/BECxP)
3. Project Scope The overall roof replacement is about 190,000 SF, including the 2011 MEP addition, across the four primary buildings (office and auditorium, data center (including link between them), warehouse, and MEP addition. In general, the existing roofs consist of ballasted protected membrane roofs (PMR) over structurally sloped concrete slabs.
There are also three small awning roofs, totaling roughly 1,300 SF, which consist of EPDM over structurally sloped metal decks, rather than PMR over concrete, and one elevator overrun roof consisting of modified bitumen. The scope of work generally involves the following:
● Replace existing PMR, coping, flashing, expansion joints, skylights, and other roofing accessories;
● Replace lightning protection systems;
● Replace existing rooftop unit structural cross bracing;
● Replace existing EPDM awning roofs;
● Replace existing elevator overrun roof;
● Install new fixed exterior access ladders; and
● Install new fall protection system throughout building perimeter.
4. Options and Allowances
4.1. Option 1
Include reroofing the MEP addition using the same BOD as in base scope.
4.2. Option 2
Install fixed exterior access ladders.
4.3. Option 3
Install fall protection throughout the entire building perimeter.
4.4. Allowances
Concrete repair details beyond standard substrate preparation for waterproofing.
General Services Administration Office of Program and Project Management
4.5. Changes between 95% and 100% CD package
Options 1, 2, and 3 will be combined into the base scope. Several concrete repair details and a schedule showing quantities will be provided; concrete repairs should be priced on a unit cost basis. An add alternate to replace HRA roofing with spray-applied polyurea roofing (including a spec and sample details) will be included.
5. Period of Performance
● 12 months from Notice to Proceed (NTP) to Substantial Completion. This includes all pre-mobilization badging requirements.
6. Work Conditions/Site Requirements
● The work will generally be performed on the exterior of the building. Contractors shall limit their presence inside the building to the maximum extent feasible.
Internal building access will be required for a very limited scope; however, site superintendents and other responsible parties are expected to perform internal walks throughout open access locations to assess interior conditions during construction. Vehicles that require security searches (large trucks, deliveries, sanitation disposal, etc.) are limited to M-F, 7A-3P, excluding federal holidays.
Site egress outside of those times is allowed.
● The building is located on a secure site. HSPD-12 Tier 1 clearances and PIV cards will be required for all personnel involved with the project. Minimum 2 business days of notice are required for all visitors to the facility throughout the construction duration.
7. Procurement Process
7.1. Phase 1
● This procurement is being conducted under FAR Part 15 (GSA Class Deviation RFO-2025-15) using a two phase selection process.
● One contract will be awarded using competitive negotiation.
● In Phase 1, the Government will evaluate all technical proposals and establish an "advisory short-list" that ranks all Phase 1 Offerors. Phase 1 Offerors will be notified of their ranking by the Government; however, this ranking does not impact Offerors’ ability to submit a proposal for Phase 2.
7.2. Phase 2
● In Phase 2, GSA will evaluate all price proposals, conduct interviews, and perform a best value trade-off analysis in accordance with FAR 15.103-1 and 15.2 (GSA Class Deviation RFO-2025-15).
● All responsible sources may submit a Phase 1 and Phase 2 proposal.
Phase 1 Offerors may choose not to submit Phase 2 proposals based on their rankings determined by the Government.
● If the Contracting Officer determines that the number of proposals exceeds the number at which an efficient competition can be conducted, General Services Administration Office of Program and Project Management the Contracting Officer may limit the number of proposals to the greatest number that will permit an efficient competition among the most highly rated proposals, in accordance with FAR 15.204-1(b) (GSA Class Deviation RFO-2025-15).
8. Questions/RFI Process (Phase 1)
● Any questions requiring a formal answer today must be submitted in writing using the RFI submission form.
● Submit all questions regarding Phase 1 to the Contracting Officer via email to ching.hung@gsa.gov (cc jonathan.plotkin@gsa.gov and emily.m.davis@gsa.gov) on or before March 30, 2026 using the Request For Information (RFI) submission form issued as part of the solicitation attachments.
● All responses provided by GSA will be posted to SAM.GOV as an Amendment to the Solicitation. We will attempt to expedite our responses as quickly as possible.
9. Receipt of Offers (Phase 1)
● Proposals must be sent to the Contracting Officer via email to ching.hung@gsa.gov by April 16, 2026, no later than 2:00 PM EST.
● Offerors must submit their proposal on time to be considered. No late proposals will be accepted.
10. Evaluation of Offers (Phase 1) The following non-price factors shall be used to evaluate offers:
● Factor 1 – Prior Experience on Relevant Projects(40%)
● Factor 2 – Project Management Plan and Approach (30%)
● Factor 3 – Past Performance on Relevant Projects (30%)
Non-Price Factors, when combined, are significantly more important than Total Evaluated Price.
11. Price Proposals (Phase 2)
● Price Proposals are not being submitted as part of Phase 1. Only Technical proposals will be evaluated in Phase 1. Pricing will be submitted in Phase 2.
● A pricing sheet that will need to be used by offerors and the 100% CDs and SOW will be provided via Amendment in Phase 2.
12. Method of Award
● GSA will award a contract to the Offeror whose proposal is considered to be the best value to the Government with respect to technical merit and price.
13. Q&A (Note that all responses are informal and RFIs should be submitted for any official questions. Responses indicated in italics)
● Timeline? Phase 1 is targeted for 1-1.5 months. Target Phase 2 drawings issuance early June
● Will there be another pre-proposal visit prior to Phase 2? There is currently no
General Services Administration Office of Program and Project Management Capital Projects East Division www.gsa.gov mailto:ching.hung@gsa.gov mailto:jonathan.plotkin@gsa.gov mailto:emily.m.davis@gsa.gov mailto:ching.hung@gsa.gov scheduled site visit prior to phase 2. If there is a need, please RFI this.
● Is this a small business set aside? Yes
● Picture requirements for this site visit? Per Chris Bunting (IRS), please do not take photos while onsite. If a photo is needed, please request Chris to take the photo. Requested photos are attached to these minutes.
● Will minutes be distributed? Yes
● Bond requirements? Reference the solicitation
Office of Program and Project Management
Office of Program and Project Management
Office of Program and Project Management
Office of Program and Project Management
Office of Program and Project Management
Office of Program and Project Management
Office of Program and Project Management