This is a Special Provisions document for Contract No. 1 of the 2026 Roadway Project issued by Myerstown Borough, Pennsylvania. The project encompasses approximately 5,775 square yards of milling and 490 tons of bituminous wearing course, with work to be completed on or before October 1, 2026. Bids were accepted online through PennBID until Tuesday, March 31, 2026, at 2:00 PM, with questions accepted only until 12:00 PM on Friday, March 27, 2026. The contractor must notify the Municipality five working days prior to project start and is responsible for traffic control and safety devices in compliance with current MUTCD publications. The Municipality will inspect the completed project, and the contractor is responsible for any defects occurring within one year of application. Final Completion Certificate and Notice of Completion are required upon project conclusion.
Liquidated damages will be assessed at $250 per calendar day for any work not completed by the October 1, 2026 deadline. A certified check or bid bond equal to 10 percent of the total bid is required, with bonds to be issued by a surety licensed in Pennsylvania. The contract is subject to the Pennsylvania Prevailing Wage Act, Federal OSHA requirements, Pennsylvania Act 229 of 2002, the Pennsylvania One Call Act, the Pennsylvania Human Relations Act, noncollusion affidavit requirements, non-discrimination in employment/contract compliance regulations, and the Public Works Employment Verification Act. The Municipality reserves the right to award based on aggregate totals of like items, to limit work completed, to procure materials best suited to their requirements, and to reject any or all bids. Future contract awards will be based on the quality of work as determined by the Municipality.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(5-06)
Contract No. 1 SPECIAL PROVISIONS TO CONTRACT MS-944 (Attachment 1-A)
CONTAINS IMPORTANT INFORMATION FOR THE CONTRACTOR
The Prime Contractor and subcontractors must comply with all of the following provisions that are marked with an “X”
Traffic Control and Safety Devices to be provided by the Contractor (Maintenance and Protection of Traffic to comply with current MUTCD, Publication 212 and Publication 213.)
Delivery tickets for all materials.
CS-4171 Certificate of Compliance and/or TR-465 Daily Bituminous Mixture Certification required for all materials.
Notify the Municipality five working days prior to start of project.
Work to be completed on or before October 1, 2026. After October 1, 2026 liquidated damages apply at the rate of $250 per calendar day.
Roadway to be power broomed by (contractor municipality ) prior to start of project.
Excess material to be removed by (contractor municipality ).
Municipality to inspect project.
Need Bill of Lading for each shipment of bituminous material per Section 702.1(c) of Specifications 408.
Tack Coat required per Section 460, or 409 for superpave, of Specifications 408 and is incidental to paving item unless noted otherwise.
Prime Coat require per Section 461 of Specifications 408.
Bituminous Seal on all abutting pavement and curbs required.
Saw cut or Milled Paving Notch required and incidental to paving item unless noted otherwise.
Scratch/Leveling Courses to be placed at the discretion of appointed inspector(s).
Full width pavement with one pass required.
Municipality reserves the right to limit work completed.
Taper pavement the last 3 feet to curb.
For FOB Source bids, hauling distance will determine selection of bid award.
Municipality reserves the right to procure material which best suits their requirements after all bids and items are reviewed.
Incidental Preparation and clean up required. (Project Construction Materials) The municipality reserves the right to make an award on the basis of the aggregate total for all like items on which quotations are received.
Provide design, which meets Specifications Form 408 to the municipality 5 days prior to start of work.
Contractor is responsible for defects that occur within one year of applications.
Contractor is required to review proposed project with Municipality’s Representative prior to bidding.
Oil samples required from each distributor truck by contractor (1) quart: A.M. & P. M. and witnessed by municipality and retained by municipality. (Oil samples must be placed in an approved type container that is compatible with oil sample.)
At least three random stone samples to be taken by contractor on project site witnessed by municipality and retained by municipality.
Complete all testing in accordance with Specification Form 408 Section 409 except for superpave volumetric testing.
Notice to Proceed will be the date of Contract acceptance.
Final Completion Certificate & Notice of Completion required.
Future award of Contract will be based on quality of work as determined by the municipality.
Contractor notify all residents of pending work to be performed.
My signature signifies that I have read and understand the above special provisions to this contract, and by being authorized by this company to act as their authorized representative, and on their behalf hereby agree to adhere to any and all of the provisions pertaining to this contract.
CONTRACTOR’S REPRESENTATIVE DATE MUNICIPALITY’S REPRESENTATIVE DATE