This document is an Exhibit B - Method of Compensation for the Alligator Alley Statue Environmental Educational Project, issued by the Florida Department of Transportation (FDOT). The project involves the design, fabrication, delivery, and installation of an environmental education statue, with a total Lump Sum Amount of $65,000. The project is divided into three deliverables: Deliverable I - Design within 30 days of the Notice to Proceed (20% of the Lump Sum), Deliverable II - Fabrication, Production, and Furnishment within 300 calendar days of the Department's approval (30% of the Lump Sum), and Deliverable III - Delivery and Installation within 30 days of the Department's approval (50% of the Lump Sum). Failure to meet the timelines for each deliverable will result in financial consequences, with reductions of 5% for Deliverable I and II, and 10% for Deliverable III.
The document also outlines the progress payment process, requiring the vendor to submit invoices for each completed deliverable. The vendor is required to provide MBE/DBE utilization information with each invoice. The Department will provide written authorization for each task, and any tangible personal property purchased will become the property of the Department upon completion of the services.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DOT-ITB-23-4009-CO
EXHIBIT B – METHOD OF COMPENSATION
B - 1 of 4
State of Florida Department of Transportation
EXHIBIT B – METHOD OF COMPENSATION
(SAMPLE)
FOR
ALLIGATOR ALLEY STATUE ENVIRONMENTAL
EDUCATIONAL PROJECT
FINANCIAL PROJECT NUMBER: 437934-2-53-01
http://www.fdot.gov/
B - 2 of 4
1.0 PURPOSE:
This Exhibit defines the limits and method of compensation to be made to the Vendor for the services set forth in Exhibit "A" and the method by which payments shall be made.
2.0 COMPENSATION:
For the satisfactory performance of services detailed in Exhibit "A", the Vendor shall be paid up to a Lump Sum Amount of $ 65,000.00. The Lump Sum Amount consists of the following Progress payments:
Deliverable Time Frame Progress payments
Deliverable I, Design
Within 30 days of issuance of the Notice to Proceed.
20% of Lump Sum amount
Deliverable II, Fabrication of Molds, Production, and Furnishment
Within 300 calendar days of the Department’s written approval of the design renderings and schedule.
30% of Lump Sum amount
Deliverable III, Delivery, and Installation of Statue
Unless otherwise authorized by the Department in writing, within 30 days of the Department’s written approval of the design drawings/sketches.
50% of Lump Sum amount
The Lump Sum Amount for each includes all related costs including but not limited to the costs of final production, freight, and installation.
B - 3 of 4
3.0 PROGRESS PAYMENTS:
The Vendor shall submit an invoice (3 copies) upon completion of each Deliverable in a format acceptable to the Department. Payment shall be made to the Vendor for the satisfactory completion of each Deliverable as approved by the Department.
Invoices shall be submitted to:
Florida Department of Transportation Office of Planning and Environmental Management 3400 West Commercial Boulevard Fort Lauderdale, Florida 33309
The Vendor has certified that ____% MBE/DBE utilization would be achieved for this contract. If MBE utilization was certified by the Vendor, an MBE payment certification form shall be submitted with each invoice to verify the MBE utilization.
If DBE utilization was certified, DBE payments are to be input each month at the following link: https://www.fdot.gov/equalopportunity/eoc.shtm
New users reporting DBE payments will need to contact FDOT at EOOHelp@dot.state.fl.us to get a EOC user ID and password to access the application.
4.0 AUTHORIZATIONS:
The Department will provide written authorization for each course, task, project.
The Vendor shall not provide services until receipt of the written authorization.
5.0 TANGIBLE PERSONAL PROPERTY:
This Agreement includes the purchase of Tangible Personal Property, as defined in Section 273.02 Florida Statutes, which will be acquired in accordance with Rule 60A-1.017, Florida Administrative Code. Such property is identified below and will become the property of the Department upon purchase. Upon receipt of the property, the Consultant will provide the Department a copy of the purchase invoice and serial number, will affix Department inventory control labels, will accommodate physical inventories required by the Department and transfer control of the property to the Department upon completion of services.
https://www.fdot.gov/equalopportunity/eoc.shtm mailto:EOOHelp@dot.state.fl.us
B - 4 of 4
6.0 FINANCIAL CONSEQUENSES:
Failure to meet Deliverable I within the allotted timeframe will result in reduction of 5% of the compensation amount for Deliverable I.
Failure to meet Deliverable II within the allotted timeframe will result in a reduction of 5% of the compensation amount for Deliverable II.
Failure to meet Deliverable III within the allotted timeframe will result in a reduction of 10% of the compensation amount for Deliverable III.
**END OF EXHIBIT B – METHOD OF COMPENSATION**
FINANCIAL PROJECT NUMBER: 437934-2-53-01