4-E. LIQUIDATED DAMAGES ACKNOWLEDGEMENT.pdf

PDF 805 KB Posted

Attached to
26B-009 NE 58TH AVE RESURFACE PROJECT, TIP080454 (FROM E HWY 326 TO NE 90TH STREET ROAD)
Solicitation number
26B-009
Issued by
Marion County, Florida

About this file

This is a Contractor Acknowledgment of Liquidated Damages form for Marion County, Florida, applicable to the NE 58th Avenue Resurface Project (TIP080454), a 3.09-mile reclaim and resurfacing project from E Highway 326 to NE 90th Street Road that includes roadway widening, pavement resurfacing, shoulder sodding, drainage modifications, driveway construction, and pavement marking installation. Contractors must submit a work schedule at or before the Pre-Construction Conference that complies with the contract timeline and includes tentative performance dates. Successful bidders must commence work within fifteen calendar days of the Notice to Proceed issuance, and the Notice to Proceed will not be issued until all required documents are received and approved by Marion County. No work is permitted during weekends, holidays, or outside established workday hours without forty-eight hours advance written approval from the County.

The contract time is measured in calendar days including County-observed holidays, with liquidated damages assessed at the rate specified in Section 8-10.2 of the FDOT Standard Specifications for Road and Bridge Construction FY 2024-2025 if the Final Completion deadline is not met. Project closeout requires completion of all work, punch list items, As-Built Surveys, final inspections with acceptance, reflectivity reports, Notice of NOI Termination, and final invoices. Time extensions or adjustments to the Final Completion date are only valid when issued in writing by Marion County Procurement Services Department as a Revised Notice to Proceed or Change Order. Acceptance of these liquidated damages terms is mandatory for bid responsiveness and completion of a successful submittal.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTRACTOR ACKNOWLEDGMENT OF LIQUIDATED DAMAGES

FOR CONSTRUCTION PROJECTS

On behalf of my firm, I acknowledge the County may assess liquidated damages in the event that this construction project is not completed within the timeframe established in this Invitation to Bid (ITB).

Liquidated damages may be assessed if the Final Completion deadline date is not met by the Contractor.

Adjustments or extensions to the Final Completion date is only acceptable when in writing, issued by the Marion County Procurement Services Department in the form of a Revised Notice to Proceed or Change Order.

The contract time for this project is ___ calendar days including County observed holidays. No work is permitted during any holidays, weekends, or outside the established workday time frame, unless approved by the County forty-eight (48) hours in advance, in writing. Failure to complete work within the contract time will cause the charge of Liquidated Damages against the Contractor at the rate as determined under Section 8-10.2 of the FDOT Standard Specifications for Road and Bridge Construction FY 2024-2025. At or BEFORE the Pre-Construction Conference, Contractors shall submit a schedule for performing the work. The schedule shall be within the contract time allotted for this project and shall include tentative dates of performance. The Notice to Proceed will not be issued until all required documents are received and approved by the County. Time shall begin upon issuance of a Notice to Proceed by the County. Successful bidder must start work on this project within fifteen

(15) calendar days after the Notice to Proceed date; failure to adhere to this timeline may cause the bid to be rejected.

Amount of Liquidated Damages: Reference Section 8-10.2 of the FDOT Standard Specifications for Road and Bridge Construction FY 2024-2025, for fee schedule.

Contractor shall Close Out the project on or before the Final Completion date. Close Out is defined as having all work complete, all Punch list items corrected, As-Built Survey submitted, Final Inspection complete (and accepted), Reflectivity Reports submitted, Notice of NOI Termination submitted, and Final Invoice submitted.

Failure to accept the terms listed herein will be cause to deem your submittal non-responsive; it is a requirement of a complete and successful bid.

Contractor/Firm Name Contractor’s Authorized Representative (Print or Type) (Print Name, Title)

Date Signature

This document must be completed and returned with your Submittal

File details come from the government source that posted it. Updated .