This document contains special provisions for a Florida County resurfacing project on NE 58th Avenue, a 3.09-mile roadway improvement initiative. The scope of work includes reclaiming and widening the existing roadway, constructing driveway and side street aprons, removing and adding cross drains and end treatments, installing and restriping pavement markings, and sodding shoulders. The total contract duration is 180 calendar days, including approximately 21 days from substantial completion to project closeout, with county-observed holidays excluded from work authorization unless approved 48 hours in advance. The successful bidder must submit a detailed schedule at the Pre-Construction Conference and commence work within 15 calendar days of receiving the Notice to Proceed. The contractor is responsible for ongoing mowing, ensuring proper drainage through culvert cleaning and outlet swale grading, maintaining existing stormwater drainage patterns, preventing ponding at side road aprons, resetting survey monuments, and providing as-built documentation.
Liquidated damages will be assessed at daily rates based on the original contract amount, ranging from $904 per day for contracts under $299,999 to $10,224 plus 0.00005 of any amount over $40 million for contracts of $40 million and above. The contractor will not receive allowances for increases in liquid asphalt costs. Additional sod requirements beyond the specified quantity for the Roadside Sod pay item will be considered incidental to the Earthwork pay item. All erosion control, water pollution prevention and abatement measures, and associated materials are included within the contractor's obligations and costs.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
OCE SPECIAL PROVISIONS
1. SCOPE OF WORK: CONTRACTOR is to complete a lowest bid technically acceptable resurfacing project for NE 58TH AVE, from E HWY 326 to NE 90TH ST RD. Generally, the work includes:
1.1 Reclaiming and widening the existing roadway
1.2 Constructing driveway and side street aprons
1.3 Removing/adding cross drain and end treatments
1.4 Installing/restriping pavement markings
1.5 Sodding shoulders
2. Contract Time, Schedule and Liquidated Damages: The total contract time for this project is 180 calendar days (including approximately 21 days from substantial completion to project closeout), including COUNTY observed holidays. No work is permitted during COUNTY holidays unless it is approved by the COUNTY, forty-eight (48) hours in advance. Failure to achieve Final Completion within the allotted contract time will cause the charge of liquidated damages against the CONTRACTOR at the daily rate established in this provision. At the Pre-Construction Conference, CONTRACTOR shall submit a schedule for performing the work. The schedule shall be within the contract time allotted for this project and shall include tentative dates of performance. The Notice to Proceed will not be issued until all required documentation is received by the COUNTY. The successful bidder shall start work on this project within 15 calendar days after a Notice to Proceed.
FY2025-26 FDOT Specifications Book 8-10.2 Amount of Liquidated Damages: Applicable liquidated damages are the amounts established in the following schedule:
Amount of Liquidated Damages: Applicable liquidated damages are the amounts established in the following schedule:
Original Contract Amount Daily Charge Per Calendar Day $299,999 and under .......................................................$904 $300,000 but less than $2,000,000............................. $1,685 $2,000,000 but less than $5,000,000...........................$2,667 $5,000,000 but less than $10,000,000.........................$3,813 $10,000,000 but less than $20,000,000.......................$5,021 $20,000,000 but less than $40,000,000.......................$7,442 $40,000,000 and over .............. $10,224 plus 0.00005 of any amount over $40 million (Round to nearest whole dollar)
3. Asphalt Adjustment: There will not be allowances for an increase to the cost of liquid asphalt.
4. Any additional sod required above the total quantity listed for the “Roadside Sod” pay item will be considered incidental to the “Earthwork” pay item.
5. CONTRACTOR shall continue to mow the contract area until the completion of the contract.
6. CONTRACTOR shall ensure that all culverts are cleaned and outlet swales are graded and sodded to allow for the drainage of run-off. This work and all materials required shall be inclusive of “Prevention, Control, and Abatement of Erosion and Water Pollution”.
7. CONTRACTOR shall ensure that the existing stormwater drainage patterns are maintained.
8. CONTRACTOR to ensure that ponding does not occur at side road aprons. Adjust asphalt thickness and/or grade shoulders to ensure that water drains off the roadway.
9. CONTRACTOR shall re-set survey monuments existing within the roadway.
10. As-Builts are required, and should show survey monuments as being re-set.