4. Schedule of Material Submittals.xlsx

XLSX spreadsheet 38 KB Posted

Attached to
Demolish Surplus Military Family Housing Units
Solicitation number
FA557525B0017
Issued by

About this file

The file is a Schedule of Material Submittals for Project QUUG 24-1003, which involves demolishing surplus military family housing units at Moron Air Base in Spain. The document outlines 30 specific material submittals that the contractor must provide during different stages of the project, with submission deadlines tied to contract start or specific project milestones. Required submittals include a warranty letter, construction schedules, work plans, quality control plans, environmental protection plans, demolition plans, waste management documentation, and technical submittals related to concrete, backfill materials, landscaping, and utility infrastructure.

The associated federal contract opportunity is a solicitation (FA557625B0017) by the Department of the Air Force, United States Air Forces in Europe - Air Forces Africa, with a project value between $250,000 and $500,000 and a projected performance period of 190 days. The solicitation is specifically restricted to local sources in Spain, with a pre-proposal conference on 6 August 2025 and bid submissions due by 10:00 hours local time on 1 September 2025. Notably, the government advises that funds are not currently available, and the bid acceptance period should remain valid through 31 December 2025, with the government reserving the right to cancel the solicitation at any time.

View the file

Other files

File Type Posted
Solicitation - FA557525B0017.pdf PDF
2. Concept Drawings.pdf PDF
5. Blank Cost Estimate Breakdown.xlsx XLSX spreadsheet
7. EFGS, May 2014.pdf PDF
8. Statement of Work (Eng).pdf PDF
1a. Especificaciones Tecnicas.pdf PDF
1b. Technical Specifications.pdf PDF
6. INRMP.pdf PDF
9. Statement of Work (Spa).pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Material Submittals Schedule

SCHEDULE OF MATERIAL SUBMITTALSPROJECT NUMBER
QUUG 24-1003PROJECT TITLE

DEMO SURPLUS MFH UNITS MULTI

SOLICITATION / CONTRACT NO.

(To be completed by Project Engineer)(To be completed by Contract Administrator)
NUMBER OF COPIES REQUIRED
LINE NUMBERITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTALCERTIFICATION OF COMPLIANCESHOP DRAWINGSSAMPLESCOLOR SELECTIONMANUFACTURER'S RECOMMENDATIONMANUFACTURER'S WARRANTYCATALOG DATAOPERATING INSTRUCTIONSSCHEDULES, LISTINGS, REPORTS, PLANSTECHNICAL DATATEST REPORTSFIELD REPORTSREQUIRED SUBMISSION DATE

fergusog: Enter the due date from the Contractor (MM/DD/YY)

DATE RECEIVED IN CONTRACTING

fergusog: Enter the date received from the Contractor. (MM/DD/YY)

DATE TO CIVIL ENGINEERING

fergusog: Enter the date submittal was given to CE for review. (MM/DD/YY)

RETURN SUSPENSE DATE

fergusog: Enter the date the submittal is due back from CE

(MM/DD/YY)

SUBMITTAL NUMBERS

fergusog: Enter the Submittal Number

DATE CONTRACTOR NOTIFIED CONTRACTOR RESUBMITTAL

fergusog: Enter Resubmittal Number

FINAL APPROVAL

fergusog: Enter the submittal final approval date

(MM/DD/YY)

REMARKS

fergusog: Enter any comments pertaining to the submittal

APPROVED

fergusog: Enter date the Contractor was notified of submittal approval

(MM/DD/YY)

fergusog: Enter Resubmittal Number

DISAPPROVED

fergusog: Enter date the Contractor was notified of submittal disapproval

(MM/DD/YY)

fergusog: Enter the submittal final approval date

(MM/DD/YY)

fergusog: Enter any comments pertaining to the submittal

SECTION 01 11 01
01Warranty letter1Acceptance +15
02Construction Schedule1Contract Start +7BCE to review and approve.
03Progress Schedule1Contract Start +10
04Work Plan1Contract Start +7
05Mobility Plan1Contract Start +15
06Project Sign1Contract Start +15
07Quality Control Plan1Contract Start +15
08Environmental Protection Plan1Contract Start +15
09DD Form 13541Pre-Final Inspection -15RP needs to complete the form within 10 days after BOD
10Waste & construction debris management1Final Inspection-15
11As-Built drawings1Final Inspection -15
12Spatial Data1As-Built Drawings Approval +10Spatial data should be based on the approved As-Built drawings.
13Key Staff1Contract Start+15
14Health and safety Plan1Contract Start+15
SECTION 01 11 02
15Work Phasing Plan1Work Commencement -15
16Utilities shut off Plan1Work Commencement -15
17Salvage plan1Contract Start +15
18Operation & Maintenance (O&M) Manuals1Pre-Final Inspection -15Shops to review and provide inputs as applicable.
19Final Testing (when required)1Pre-Final Inspection -15
SECTION 02 41 16
20Program and schedule of the works1
21Demolition plan1
22Management and disposal plan of the waste1
23Manager of waste from demolition and construction1
24Authorized dump or treatment and recovery plant1
25Delivery and disposal certicate of waste1
SECTION 03 30 00.00 20
Concrete batch plant1
Concrete Control Test Program1
Results of the Concrete Control Tests1
Assembly of ironworks1
Polypropylene fiber1
SECTION 31 23 00.00 20
26Backfill material1
27SECTION 32 92 19
28Seed1
29Fertilizer1
30Topsoil1
SECTION 32 93 00
1Time Restrictions and Planting Conditions1
2Dates and locations for each type of planting1
3Local/Regional Materials1
4Peat1
5Composted Derivatives1
6Organic Mulch Materials1
7Gypsum1
8Mulch1
9Ground Stakes1
10Fertilizer1
11Staking Material1
12Antidesiccants1
13Topsoil Composition Tests1
14Percolation Test1
15Nursery Certifications1
SECTION 33 82 00
16Conduit and Accessories1
17Type A1 Manhole1
18Type D-400 Manhole Cover1

&"Arial,Bold"&8Schedule of Material Submittals, Feb 05 (SAF/AQCP) Page &P of &N