4. Cost Estimate Blank QUUG 25-1010.xlsx

XLSX spreadsheet 64 KB Posted

Attached to
Repair Roofs for Multiple Buildings at Moron Air Base, Spain
Solicitation number
FA557525B0016
Issued by

About this file

This file is an Independent Government Estimate (IGE) Construction Cost Estimate Breakdown for roof repair projects at Moron Air Base, Spain. The solicitation (FA557525B0016) covers repair work for three buildings (203, 415, and 1215) with a project budget between $500,000 and $1,000,000 and a 310-day performance period. The scope includes comprehensive roof renovation activities such as demolition, concrete and masonry work, waterproofing, safety equipment installation, mechanical and electrical system modifications, and restoration of solar panels, gutters, and related infrastructure.

Key dates include a pre-proposal conference/site visit on 6 August 2025, with questions due by 12 August 2025 and bids due by 29 August 2025 at 10:00 hours local time. The project is specifically restricted to local sources in Spain, with contractors required to be licensed and registered to conduct construction business in Spain. The Department of the Air Force (United States Air Forces in Europe - Air Forces Africa) is the sponsoring agency, and funding availability is not guaranteed, with the bid acceptance period extended through 31 December 2025. The estimate was prepared by KBR Services LLC and details work to be performed in euros, with a currency conversion rate of $1 to 0.9249 euros.

View the file

Other files

File Type Posted
Questions and Answers.pdf PDF
3. SOW (Spa) QUUG 25-1010.pdf PDF
Solicitation - FA557525B0016.pdf PDF
1. Drawings QUUG 25-1010.pdf PDF
2. SOW (Eng) QUUG 25-1010.pdf PDF
5. Schedule of Material Submittals QUUG 25-1010.xlsx XLSX spreadsheet

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Summary

CONSTRUCTION COST ESTIMATE BREAKDOWN
CONTRACTORADDRESS
MORÓN AIR BASE, SPAIN
CONTRACT FOR (Work to be performed)PROPOSED TOTAL CONTRACT PRICE
RPR Roofs, Multi - SUMMARY
PURCHASE REQUEST NUMBERPROJECT NUMBERWORK LOCATION
QUUG 25-1010MORÓN AIR BASE, SPAIN
UNITMATERIAL COSTLABOR COSTSOTHER
LINITEMOFDIRECTLINE
NO.MEAS.QUANTI.UNITTOTALMH/MDAV.RATTOTALCOSTSTOTAL
(1)(2)(3)(4)(5)(6)(7)(8)(9)(10)
SUMMARY
RESUMEN
CLIN 001 (BASE DID) Building 203
CLIN 001 (BASE BID) Edificio 203
CLIN 002 (Additive #1) Building 415
CLIN 002 (Additive#1) Edificio 415
CLIN 003 (Additive#2)Building 1215
CLIN 003 (Additive#2)Edificio 1215
GRAND TOTAL
GRAN TOTAL
TOTAL MATERIAL COSTS
TOTAL LABOR COSTS
TOTAL OTHER DIRECT COSTS
TOTAL DIRECT COSTS
OVERHEAD
SUBTOTAL
PROFIT
TOTAL PROJECT EUROS
$10.9249euros
TOTAL PROJECT US$

DATE: 27 MAY 2025

These costs and overhead and profit percentages will be applied in any possible future modifications

&"Times New Roman,Regular"Page &P of &N

IGE 203

CONSTRUCTION COST ESTIMATE BREAKDOWN
CONTRACTORADDRESS
MORÓN AIR BASE, SPAIN
CONTRACT FOR (Work to be performed)PROPOSED TOTAL CONTRACT PRICE
RPR Roof Bldg 203
PURCHASE REQUEST NUMBERPROJECT NUMBERWORK LOCATION
QUUG 25-1010MORÓN AIR BASE, SPAIN
UNITMATERIAL COSTLABOR COSTSOTHER
LINITEMOFDIRECTLINE
NO.MEAS.QUANTI.UNITTOTALMH/MDAV.RATTOTALCOSTSTOTAL
(1)(2)(3)(4)(5)(6)(7)(8)(9)(10)
ARCHITECTURAL REPAIR WORKS
TRABAJOS DE REPARACIÓN DE ARQUITECTURA
Demolition Works
Trabajos de demolición
1Install protective scaffolding platform above the entrance doors
Instalar plataforma de protección andamiada sobre puertasEa
2Demolish existing roof with all its elements
Demoler la cubierta existente con todos sus elementosSm
3Separate, load and transport the waste to authorized dump
Separar, cargar y transportar residuos a vertedero autorizadoJOB
4Disasembly fall arresting system for its further reinstallation.
Desmontaje el sistema anticaidas para su posterior instalacion.JOB
Total Demolition Works
Total Trabajos de demolición
Concrete and Masonry Works
Trabajos de hormigón y albañilería
5Construct concrete block for solar panels
Construir bloques hormigón para anclaje paneles solaresEa
6Install slope formation with concrete lightweight
Realizar formación de pendiente con horm. aligeradoSm
7Install PVC sleeve on roof for pipes and conduits
Instalar pasatubos de PVC para pasos de tuberias y cablesEa
Total Concrete and Masonry Works
Total Trabajos de Hormigón y albañilería
Roof Work and Waterproofing Operations
Trabajos de cubierta e impermeabilización
8Install flashings for drip edge on the roof perimeter
Instalar remates de goterón en el perimetro de cubiertaLm
9Install polyester fiber synthetic felt fleece layer
Instalar lamina antipunzonante de poliester sintéticoSM
10Install waterproof membrane and special elements
Instalar lamina impermeabilizante y elementos especiales.SM
11Install filtering tiles on entire roof surface
Instalar losas filtrantes en la totalidad de la cubiertaSM
12Install gutters and downspots.
Instalar canalones y bajantes.Lm
Total Roof Work and Waterproofing Operations
Total trabajos de cubierta e impermeabilización
Safety and Protection Equipments
Equipos de protección y seguridad
13Install dismantled fall arresting system.
Instalar sistema anticaidas desmontado.Ea
Total Safety and Protection Equipments
Total Equipos de protección y seguridad
Metal Works
Trabajos de metalistería
14Install steel brackets to support floodligths
Instalar soportes metalicos para proyectores.Ea
Metal Works
Trabajos de metalistería
Finish Works
Trabajos de Acabados
15Prepare, prime and paint metal surfaces
Preparar, imprimir y pintar superficies metalicasSm
16Prepare, prime and paint wall surfaces
Preparar, imprimir y pintar superficies de albañileríaSm
Total Finish Works
Toital Trabajos de Acabados
ARCHITECTURAL WORK SUMMARY
RESUMEN TRABAJOS DE ARQUITECTURA
Demolition Works
Trabajos de demolición
Concrete and Masonry Works
Trabajos de Hormigón y Albañilería
Roof Work and Waterproofing Operations
Trabajos de cubierta e impermeabilización
Safety and Protection Equipments
Equipos de protección y Seguridad
Metal Workss
Trabajops de Metalistería
Finish Works
Trabajos de Acabados
TOTAL ARCHITECTURAL WORK
TOTAL TRABAJOS DE ARQUITECTURA
MECHANICAL WORKS
TRABAJOS DE OBRA MECÁNICA
17Empty the water panels, disconnect water pipes & install caps
Vaciar paneles de agua, desconectar lineas y tapar entradasJOB
18Uninstall solar panels & custody during execution
Desintalar paneles solares y custodiar durante la obraJOB
19Provide & install new water lines from tank to the panels
Proveer e instalar nuevas lineas de agua tanque-panelesJOB
20Install solar panels, charge tanks and lines and check functions
Installar paneles solares, cargar lineas y tanques y probarJOB
21Unistall HVAC equipment and install it once construction works are finished.
Desinstalar equipos de AA/CC e instalar una vez terminados los trabajos de construccion.JOB
22Demolish ventilation oulets and bolier chimney.
Demoler salidas de ventilación y Chimenea de calefacción.JOB
MECHANICAL WORKS
TRABAJOS DE OBRA MECÁNICA
ELECTRICAL WORKS
TRABAJOS DE OBRA ELECTRICA
23Disconnet and remove electrical conduit to solar panels and HVAC equipment.
Desconectar y desmontar conductos electricos a paneles solares y equipamiento de AA/CC.JOB
24Provide new electrical line for solar panels sensors
Proveer nueva linea electrica para sensor de paneles solaresJOB
25Unistall existing exterior luminaires and install new ones once construcction works are finished.
Desinstalar luminarias exteriores existentes e instalar otras nuevas una vez hayan terminado las obras de construcción.JOB
26Remove TV antenas and its further reinstall on side façade.
Desmontar antenas de televisión y posterior reinstalación en fachada lateral.JOB
27Remove wires and utilities on roof underused.
Desmontaje de cables e instalaciones de la cubierta sin uso.JOB
28Install on sides electrical conduits and juntcion boxes for exterior lighting and communitations.
Instalar en laterales conductos electricos y caja de registro para iluminacion exterior y comunicaciones.JOB
29Provide new electrical lines for ligthing system to the electrical panel.
Instalar nuevas lineas para el sistema de iluminación desde en cuadros de distribucion.JOB
TOTAL ELECTRICAL WORKS
TOTAL TRABAJOS DE OBRA ELECTRICA
WORK SUMMARY
RESUMEN TRABAJOS
TOTAL ARCHITECTURAL WORK
TOTAL TRABAJOS DE ARQUITECTURA
MECHANICAL WORKS
TRABAJOS DE OBRA MECÁNICA
ELECTRICAL WORKS
TRABAJOS DE OBRA ELECTRICA
TOTAL
TOTAL
TOTAL MATERIAL COSTS
TOTAL LABOR COSTS
TOTAL OTHER DIRECT COSTS
TOTAL DIRECT COSTS
OVERHEAD
SUBTOTAL
PROFIT
TOTAL PROJECT EUROS
$10.9249euros
TOTAL PROJECT US$

DATE: 27 may 2025 FIRM NAME: KBR SERVICES LLC SUCURSAL EN ESPAÑA

TITLE: ARCHITECT
BY: ALBERTO MENENDEZ PASAGALI
These costs and overhead and profit percentages will be applied in any possible future modifications

&"Times New Roman,Regular"INDEPENDENT GOVERNMENT ESTIMATE &"Times New Roman,Bold"FOR OFFICIAL USE ONLY &"Times New Roman,Regular"Page &P of &N

IGE 415

CONSTRUCTION COST ESTIMATE BREAKDOWN
CONTRACTORADDRESS
MORÓN AIR BASE, SPAIN
CONTRACT FOR (Work to be performed)PROPOSED TOTAL CONTRACT PRICE
RPR Roof Bldg 415
PURCHASE REQUEST NUMBERPROJECT NUMBERWORK LOCATION
QUUG 25-1010MORÓN AIR BASE, SPAIN
UNITMATERIAL COSTLABOR COSTSOTHER
LINITEMOFDIRECTLINE
NO.MEAS.QUANTI.UNITTOTALMH/MDAV.RATTOTALCOSTSTOTAL
(1)(2)(3)(4)(5)(6)(7)(8)(9)(10)
ARCHITECTURAL REPAIR WORKS
TRABAJOS DE REPARACIÓN DE ARQUITECTURA
Demolition Works
Trabajos de demolición
1Install protective scaffolding platform above the entrance doors
Instalar plataforma de protección andamiada sobre puertasEa
2Demolish existing roof with all its elements
Demoler la cubierta existente con todos sus elementosSm
3Separate, load and transport the waste to authorized dump
Separar, cargar y transportar residuos a vertedero autorizadoJOB
4Disasembly fall arresting system for its further reinstallation.
Desmontaje el sistema anticaidas para su posterior instalacion.JOB
Total Demolition Works
Total Trabajos de demolición
Concrete and Masonry Works
Trabajos de hormigón y albañilería
5Expand of conduits for exahust and fall arresting system brackets
Recrecido de conductos para extractores y soportacion para el sistema anticaidas.JOB
6Install slope formation with concrete lightweight
Realizar formación de pendiente con horm. aligeradoSm
Total Concrete and Masonry Works
Total Trabajos de Hormigón y albañilería
Roof Work and Waterproofing Operations
Trabajos de cubierta e impermeabilización
7Install flashings for drip edge on the roof perimeter
Instalar remates de goterón en el perimetro de cubiertaLm
8Install polyester fiber synthetic felt fleece layer
Instalar lamina antipunzonante de poliester sintéticoSM
9Install waterproof membrane and special elements
Instalar lamina impermeabilizante y elementos especiales.SM
10Install filtering tiles on entire roof surface
Instalar losas filtrantes en la totalidad de la cubiertaSM
11Install gutters and downspots.
Instalar canalones y bajantes.Lm
Total Roof Work and Waterproofing Operations
Total trabajos de cubierta e impermeabilización
Safety and Protection Equipments
Equipos de protección y seguridad
12Install dismantled fall arresting system.
Instalar sistema anticaidas desmontado.Ea
Total Safety and Protection Equipments
Total Equipos de protección y seguridad
Finish Works
Trabajos de Acabados
13Prepare, prime and paint metal surfaces
Preparar, imprimir y pintar superficies metalicasSm
14Prepare, prime and paint wall surfaces
Preparar, imprimir y pintar superficies de albañileríaSm
Total Finish Works
Toital Trabajos de Acabados
ARCHITECTURAL WORK SUMMARY
RESUMEN TRABAJOS DE ARQUITECTURA
Demolition Works
Trabajos de demolición
Concrete and Masonry Works
Trabajos de Hormigón y Albañilería
Roof Work and Waterproofing Operations
Trabajos de cubierta e impermeabilización
Safety and Protection Equipments
Equipos de protección y Seguridad
Finish Works
Trabajos de Acabados
TOTAL ARCHITECTURAL WORK
TOTAL TRABAJOS DE ARQUITECTURA
MECHANICAL WORKS
TRABAJOS DE OBRA MECÁNICA
15Dismantle the extractors for later installation and adapt the connection once the masonry work on the roof has been completed.
Desmontar los extractores para su porterior instalacion y adaptar la conexion una vez que los trabajos de albañileria hayan terminado.JOB
MECHANICAL WORKS
TRABAJOS DE OBRA MECÁNICA
ELECTRICAL WORKS
TRABAJOS DE OBRA ELECTRICA
16Remove air terminals and ground line for further reinstall.
Desmontaje de puntas de captacion y linea de tierras para su porterior reinstalacion.JOB
17Remove wires and utilities on roof underused.
Desmontaje de cables e instalaciones de la cubierta sin uso.JOB
TOTAL ELECTRICAL WORKS
TOTAL TRABAJOS DE OBRA ELECTRICA
WORK SUMMARY
RESUMEN TRABAJOS
TOTAL ARCHITECTURAL WORK
TOTAL TRABAJOS DE ARQUITECTURA
MECHANICAL WORKS
TRABAJOS DE OBRA MECÁNICA
ELECTRICAL WORKS
TRABAJOS DE OBRA ELECTRICA
TOTAL
TOTAL
TOTAL MATERIAL COSTS
TOTAL LABOR COSTS
TOTAL OTHER DIRECT COSTS
TOTAL DIRECT COSTS
OVERHEAD
SUBTOTAL
PROFIT
TOTAL PROJECT EUROS
$10.9249euros
TOTAL PROJECT US$

DATE: 27 may 2025 FIRM NAME: KBR SERVICES LLC SUCURSAL EN ESPAÑA

TITLE: ARCHITECT
BY: ALBERTO MENENDEZ PASAGALI
These costs and overhead and profit percentages will be applied in any possible future modifications

&"Times New Roman,Regular"INDEPENDENT GOVERNMENT ESTIMATE &"Times New Roman,Bold"FOR OFFICIAL USE ONLY &"Times New Roman,Regular"Page &P of &N

IGE 1215

CONSTRUCTION COST ESTIMATE BREAKDOWN
CONTRACTORADDRESS
MORÓN AIR BASE, SPAIN
CONTRACT FOR (Work to be performed)PROPOSED TOTAL CONTRACT PRICE
RPR Roof Bldg 1215
PURCHASE REQUEST NUMBERPROJECT NUMBERWORK LOCATION
QUUG 25-1010MORÓN AIR BASE, SPAIN
UNITMATERIAL COSTLABOR COSTSOTHER
LINITEMOFDIRECTLINE
NO.MEAS.QUANTI.UNITTOTALMH/MDAV.RATTOTALCOSTSTOTAL
(1)(2)(3)(4)(5)(6)(7)(8)(9)(10)
ARCHITECTURAL REPAIR WORKS
TRABAJOS DE REPARACIÓN DE ARQUITECTURA
Demolition Works
Trabajos de demolición
1Install protective scaffolding platform above the entrance doors
Instalar plataforma de protección andamiada sobre puertasEa
2Demolish existing roof with all its elements
Demoler la cubierta existente con todos sus elementosSm
3Demolish small brick wall and covering at construction joint.
Demoler murete de junta de construccion y cubricion.JOB
4Separate, load and transport the waste to authorized dump
Separar, cargar y transportar residuos a vertedero autorizadoJOB
5Disasembly if any, fall arresting system for its further reinstallation.
Desmontaje si fuera necesario, el sistema anticaidas para su posterior instalacion.JOB
Total Demolition Works
Total Trabajos de demolición
Concrete and Masonry Works
Trabajos de hormigón y albañilería
6Construct concrete block for solar panels
Construir bloques hormigón para anclaje paneles solaresEa
7Install slope formation with concrete lightweight
Realizar formación de pendiente con horm. aligeradoSm
8Install PVC sleeve on roof for pipes and conduits
Instalar pasatubos de PVC para pasos de tuberias y cablesEa
9Increase if needed, concrete blocks and reiforcement for an appropiate finished of roof sustem element around it.
Recdrecer si fuera necesario, los bloques de hormigon y sus armaduras para un remate adecuado de los elementos de cubierta a su alrededor.Ea
Total Concrete and Masonry Works
Total Trabajos de Hormigón y albañilería
Roof Work and Waterproofing Operations
Trabajos de cubierta e impermeabilización
10Install flashings for drip edge on the roof perimeter
Instalar remates de goterón en el perimetro de cubiertaLm
11Install polyester fiber synthetic felt fleece layer
Instalar lamina antipunzonante de poliester sintéticoSM
12Install waterproof membrane and special elements
Instalar lamina impermeabilizante y elementos especiales.SM
13Install filtering tiles on entire roof surface
Instalar losas filtrantes en la totalidad de la cubiertaSM
14Install gutters and downspots.
Instalar canalones y bajantes.Lm
Total Roof Work and Waterproofing Operations
Total trabajos de cubierta e impermeabilización
Safety and Protection Equipments
Equipos de protección y seguridad
15Install dismantled fall arresting system.
Instalar sistema anticaidas desmontado.Ea
Total Safety and Protection Equipments
Total Equipos de protección y seguridad
Finish Works
Trabajos de Acabados
16Prepare, prime and paint wall surfaces
Preparar, imprimir y pintar superficies de albañileríaSm
Total Finish Works
Toital Trabajos de Acabados
ARCHITECTURAL WORK SUMMARY
RESUMEN TRABAJOS DE ARQUITECTURA
Demolition Works
Trabajos de demolición
Concrete and Masonry Works
Trabajos de Hormigón y Albañilería
Roof Work and Waterproofing Operations
Trabajos de cubierta e impermeabilización
Safety and Protection Equipments
Equipos de protección y Seguridad
Finish Works
Trabajos de Acabados
TOTAL ARCHITECTURAL WORK
TOTAL TRABAJOS DE ARQUITECTURA
MECHANICAL WORKS
TRABAJOS DE OBRA MECÁNICA
17Empty the water panels, disconnect water pipes & install caps
Vaciar paneles de agua, desconectar lineas y tapar entradasJOB
18Uninstall solar panels & custody during execution
Desintalar paneles solares y custodiar durante la obraJOB
19Provide & install new water lines from tank to the panels
Proveer e instalar nuevas lineas de agua tanque-panelesJOB
20Install solar panels, charge tanks and lines and check functions
Installar paneles solares, cargar lineas y tanques y probarJOB
21Dismantle the extractors for later installation and adapt the connection once the masonry work on the roof has been completed.
Desmontar los extractores para su porterior instalacion y adaptar la conexion una vez que los trabajos de albañileria hayan terminado.JOB
MECHANICAL WORKS
TRABAJOS DE OBRA MECÁNICA
ELECTRICAL WORKS
TRABAJOS DE OBRA ELECTRICA
22Provide new electrical line for solar panels sensors
Proveer nueva linea electrica para sensor de paneles solaresJOB
23Remove TV antenas and its further reinstall on side façade.
Desmontar antenas de televisión y posterior reinstalacion en fachada lateral.JOB
24Remove wires and utilities on roof underused.
Desmontaje de cables e instalaciones de la cubierta sin uso.JOB
TOTAL ELECTRICAL WORKS
TOTAL TRABAJOS DE OBRA ELECTRICA
WORK SUMMARY
RESUMEN TRABAJOS
TOTAL ARCHITECTURAL WORK
TOTAL TRABAJOS DE ARQUITECTURA
MECHANICAL WORKS
TRABAJOS DE OBRA MECÁNICA
ELECTRICAL WORKS
TRABAJOS DE OBRA ELECTRICA
TOTAL
TOTAL
TOTAL MATERIAL COSTS
TOTAL LABOR COSTS
TOTAL OTHER DIRECT COSTS
TOTAL DIRECT COSTS
OVERHEAD
SUBTOTAL
PROFIT
TOTAL PROJECT EUROS
$10.9249euros
TOTAL PROJECT US$
DATE: 27 may 2025FIRM NAME: KBR SERVICES LLC SUCURSAL EN ESPAÑA
TITLE: ARCHITECT
BY: ALBERTO MENENDEZ PASAGALI
These costs and overhead and profit percentages will be applied in any possible future modifications

&"Times New Roman,Regular"INDEPENDENT GOVERNMENT ESTIMATE &"Times New Roman,Bold"FOR OFFICIAL USE ONLY &"Times New Roman,Regular"Page &P of &N