4. Blank Cost Estimate.xlsx

XLSX spreadsheet 27 KB Posted

Attached to
Repair Base Supply Enclosure & Windows, B402 Federal contract opportunity
Solicitation number
FA557525B0015
Issued by
Department of the Air Force United States Air Forces in Europe - Air Forces Africa

About this file

The document is an Independent Government Estimate (IGE) Cost Estimate Breakdown for a construction project at Moron Air Base, Spain. The project involves repairing and renovating the Base Supply Enclosure & Windows (Building 402), with specific work including window removal, installation of new windows, masonry work, and painting. The cost estimate details demolition tasks such as removing existing windows, A/C units, and metal panels, followed by architectural work like installing galvanized steel flashing, aluminum subframes, anodized aluminum windows, and surface repairs.

The associated federal contract opportunity (Solicitation Number FA557525B0015) is specifically for local Spanish contractors, with a project value between $25,000 and $100,000. Key dates include a pre-proposal conference/site visit on 30 July 2025, a question submission deadline of 6 August 2025, and bid submission deadline of 14 August 2025 at 10:00 hours local time. The solicitation emphasizes using Spanish materials, labor, and equipment, and is issued by the Department of the Air Force United States Air Forces in Europe - Air Forces Africa. Notably, funds are not currently available, and the government reserves the right to cancel the solicitation.

View the file

Other files for this federal contract opportunity

Other files attached to Repair Base Supply Enclosure & Windows, B402, newest first.
File Type Posted
Questions and Answers_QUUG 25-1009.pdf PDF
1. Drawings.pdf PDF
5. Schedule of Material Submittals.xlsx XLSX spreadsheet
2. Specifications (Eng).pdf PDF
3. Specifications (Spa).pdf PDF
Solicitation - FA557525B0015.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

IGE 25-1009

CONSTRUCTION COST ESTIMATE BREAKDOWN
CONTRACTORADDRESS
MORÓN AIR BASE, SPAIN
CONTRACT FOR (Work to be performed)PROPOSED TOTAL CONTRACT PRICE
RPR Base Supply Enclosure & Windows0.00 €$0.00
PURCHASE REQUEST NUMBERPROJECT NUMBERWORK LOCATION
QUUG 25-1009MORÓN AIR BASE, SPAIN
UNITMATERIAL COSTLABOR COSTSOTHER
LINITEMOFDIRECTLINE
NO.MEAS.QUANTI.UNITTOTALMH/MDAV.RATTOTALCOSTSTOTAL
(1)(2)(3)(4)(5)(6)(7)(8)(9)(10)
TRABAJOS DE DEMOLICIÓN

TRABAJOS DE DEMOLICIÓN

1Install polyethylene screen and catways for building protection.
Instalar pantalla de polietileno y pasarelas para proteger edificio existente.JOB
2Removal of existing windows and subframes
Desmontar ventanas existentes y premarcosEA
3Disconnect and remove wndows A/C unit and delivery to the Gov.
Desconectar y desmontar equipos de A/C de ventana y entregar al Govierno.EA
4Removal of metal and wood panel from the Com. room windows.
Desmontar paneles metálicos y de madera de las ventanas del cuarto de comunicaciones.JOB
5Cut masonry trim from window openings as indicated.
Cortar recercados de ventanas como se indica.JOB
6Reduce the thickness of the window drip sills.
Reducir el espesor de los alfeízares de ventana.JOB
7Separate, select and treat the material from demolition.
Separar, seleccionar y tratar el material procedente de la demolición.JOB
8Load, transport and delivery the waste material from demolition to authorized dump or recycle plant.
Cargar, transportar y enviar el material procedente de la demolición a vertedero autorizado o planta de reciclaje.JOB
STANDARD DEMOLITION WORKS TOTAL

TOTAL TRABAJOS DE DEMOLICIÓN ESTÁNDAR

ARCHITECTURAL WORKS

OBRA DE ARQUITECTURA

9Install galvanized steel flashing below the window drip sills.
Instalar remate de acero galvanizado bajo los alfeízares de ventana.EA
10Close the joint panel-sill with sealant and metal flashing.
Cerrar la junta panel-alfeízar con sellante y remate metálico.EA
11Repair window lintel, sill and notch and install aluminum subframe
Reparar dintel, alfeízar y mochetas de Ventana e instalar premarco .EA
12Install 2 cm thick synthetic resin window drip sill
Instalar alfeízar sintético de ventana de 2 cm de espesor.EA
13Install turn & tilt anodized aluminum window
Instalar ventana oscilobatiente de aluminio anodizado.EA
14Close window opening to match the surronded area
Cerrar hueco de ventana hasta igualar la superficie de alrededor.EA
15Seal window and flashing joints
Sellar ventanas y juntas de remateríaEA
16Paint the comnplete walls of interior surface affected by humidity
Pintar superf completa de paredes interiores afectada humedad.SM
17Paint all the exterior surface of the southern façade
Pintar toda la superficie de la fachada sur.Ea
ARCHITECTURAL WORKS TOTAL

TOTAL TRABAJOS DE ARQUITECTURA

WORK SUMMARY

RESUMEN TRABAJOS

DEMOLITION WORKS

TRABAJOS DE DEMOLICION

ARCHITECTURAL WORKS

OBRA DE ARQUITECTURA

GRAND TOTAL

GRAN TOTAL

TOTAL MATERIAL COSTS

TOTAL LABOR COSTS

TOTAL OTHER DIRECT COSTS

TOTAL DIRECT COSTS
FIRM NAME:
OVERHEAD

SUBTOTAL

PROFIT

TOTAL PROJECT EUROS
$10.9249euros
TOTAL PROJECT US$

DATE: FIRM NAME:

These costs and overhead and profit percentages will be applied in any possible future modifications

&"Times New Roman,Regular"CONSTRUCTION COST BREAKDOWN &"Times New Roman,Bold"F &"Times New Roman,Regular"Page &P of &N

File details come from the government source that posted it. Updated .