4. 25Z5AB9 SOW Chiller Plant Controls.pdf
PDF 2 MB Posted
- Attached to
- Project 25Z5AB9 Upgrade Chiller Control - 15B51525Q00000001 Federal contract opportunity
- Solicitation number
- 15B51525Q00000001
About this file
This is a Statement of Work (SOW) for upgrading and retrofitting chiller controls at the Federal Bureau of Prisons (FBOP) Federal Correctional Institution (FCI) Texarkana. The project requires replacing or retrofitting the current Trane Building Control Unit, Summit software, and MP580 to enable communication with Niagara 4, including upgrading the FX 8000 for HTML 5 compatibility and viewing over a stand-alone network. The scope includes furnishing and installing a Dell Tower Workstation with Windows 11 Pro, 24" monitor, APC battery backup, and implementing a JCI System Controller with various components including expansion panels, supervisory controllers, and BACnet communication capabilities.
The work must be performed between 8:00 AM - 2:30 PM Monday through Friday at 4001 Leopard Drive, Texarkana, TX 75501. The contractor must provide all labor, materials, tools, permits, and equipment necessary for installation, testing, and staff training. Security requirements include a 4-hour orientation, contractor badges, and submission of security clearance documentation 14 days prior to work start. The site plan included shows the area of proposed work in the powerhouse building. Technical drawings show existing control systems to be replaced, including Schneider Electric frequency drive controllers and associated electrical components.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 3. NEW 25Z5AB9 Upgrade Chiller Control 15B51525Q00000001.pdf | ||
| Letter of Solicitation - Project 25Z5AB9 Upgrade Chiller Control.pdf | ||
| Pre Solicitation - Project 25Z5AB9 Upgrade Chiller Control.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FCI Texarkana
SOW
Approval
Project 25Z5AB9 - Upgrade Chiller
Control Sensitive But Unclassified
STATEMENT OF WORK
UPDATE CHILLER CONTROLS
FCI TEXARKANA
I. SPECIFICATIONS
A. INTRODUCTION
The Federal Bureau of Prisons (FBOP), Federal Corrections Institution (FCI) Texarkana intends to award to a responsible entity for the provision of updating/retrofitting the controls between the chiller and cooling tower at FCI Texarkana, located at 4001 Leopard Drive, Texarkana, Tx 75501.
Awarded contractor will be required to provide all labor, materials, tools, permits, and equipment, necessary to Replace/Retrofit the controls between the chiller and cooling tower. The current Trane Building Control Unit, Summit software, and MP580 must be replaced or retrofitted. The system needs to be able to communicate with Niagara 4. This requires the upgrading of the FX 8000 as it uses HTML 5 and viewing information over the stand-alone network. With IT Administrator approval Tridium Web can be allowed. We are also requesting a Dell computer with monitor to view chiller plant operation.
All equipment specified in this statement must be brand name or an equal product. Should your firm choose to submit an equal product, you must submit all technical specification of the equal product to be analyzed and a technical determination issued with acceptance/non-acceptance. The government retains the right to determine technical acceptance for all submitted equal products.
B. SCOPE OF WORK
1. Awarded Contractor shall be a reputable Chiller Plant Control Provider with proven experience in plant controls. The Contractor shall provide the Institution’s Contracting Officer and his Representative (COR) with such proof.
2. Service will comply with all Local, State, and Federal codes and safety requirements as well.
3. Installation: Removal of the existing controls, and installing of the new controls, start up, commissioning, and staff training.
4. Contractor shall perform job site clean-up and removal of all excess materials, debris, and old equipment associated with the project. Removal and disposal of all debris must be completed in accordance with all applicable Federal, State, and Local laws pertaining to such work.
5. Contractor shall haul away and dispose of the old equipment through an approved licensed scrap metal recycling entity within five (5) business days of its removal from the institution. Evidence of the appropriate recycled action shall be provided to the institution’s Contacting Officer.
Workstation
1. Furnish and install one (1) Dell Tower Workstation
• Windows 11 Pro
• Microsoft Office
2. Furnish and install one (1) Dell 24” Monitor
3. Furnish and install one (1) APC 1500 UPS Battery Backup
4. ProSupport 36 Month
APPROVED 11/21/2024 SCRO
• Web based access of the control system
• Equipment Graphics
• Time Scheduling
• Setpoint Scheduling
• Alarm routing
JCI System Controller
1. Furnish and install one (1) PA0000001FH0 Expansion Panel 16x20
2. Furnish and install one (1) FX-SC9BASE-0 Supervisory Controller
3. Furnish and install one (1) FX-SC8CL005 5 Device License
4. Provide Initial SMA-8005 36 month SW Maintenance
5. Furnish and install one (1) HEP Connectivity Module
6. Furnish and install one (1) Netgear 5-port switch
7. Generate Equipment Graphics
• Chiller Plant Chillwater System
• Chiller Plant Condenser Water System
• Chiller 1 & 2 Monitoring and Control
8. Provide (2) hours customer on-site training
9. Program and start-up Chiller Plant Controller
10. Furnish and install one (1) F4-CGM09090-0H Fully programmable controller w/ integral display, BACnet MS/TP.
11. Furnish and install two (2) FX-XPM Expansion Input/output Modules
12. Utilize existing panel
13. Utilize existing field devices and wiring
14. Furnish and install BACnet Communication trunk
15. Program and start up
Chiller 1 & 2
1. Furnish and install daisy chained BACnet Communication trunk from Daikin Chillers to Chiller Plant Control Panel and System Control Panel
2. Set up BACnet Communication protocol
C. QUALITY ASSURANCE/INSTALLATION REQUIREMENTS
Equipment/Work Specifications
• Fully-customized, real-time graphical user interface (GUI)
• Non-proprietary “open protocol” platform
• Non-proprietary software upgrades
• Non-proprietary device licenses
• Provides freedom and flexibility to choose what service company you select
• Scalability allows for ease of future expansion
• Communication in multiple protocol languages
All installers/technicians shall be qualified and certified by the manufacturer to install, test, and certify the new retro fit control system. Such certification must be verified in writing by the manufacturer and submitted to the COR seven (7) days before the project starts.
All seismic zone requirements, environmental compliance, Life Safety, NFPA, ADA-ABA, and Federal, State and Local codes and regulations will be considered during all phases of this project.
Services and materials provided by the contractor will adhere to and shall be consistent with the most current industry standards, the Underwriters Laboratories (UL) and the General and the National Electric Code (NEC).
It is the contractor’s responsibility to obtain permitting, should it be required. Copies of all permits must be submitted to the COR upon receipt from local agency.
D. UTILITIES
The FBOP will provide water, use of restrooms and minimal electricity service (120V) for small hand power tools including battery chargers. The contractor will provide all other equipment, supplies and materials needed to complete this project.
E. TESTING AND ACCEPTANCE
The Contractor shall notify the COR two (2) days prior to the final system testing and certification so that arrangements can be made to have BOP required staff available to observe testing. A complete plan detailing test procedures must be submitted to the Contracting officers representative (COR) in advance for final check out and testing of the complete system.
F. HOUSEKEEPING AND MATERIAL DISPOSAL
The contractor awarded the contract will be responsible to ensure the premises are kept clean and free from accumulations of waste materials and rubbish at all times. The contractor will remove all debris, scrap, and rubbish from the work area daily. Surplus materials and all equipment shall be promptly removed from the site upon completion of the work. The Contractor shall be responsible to remove all debris and waste materials from the job site at FCI Everywhere upon conclusion and acceptance of the project. These items must be disposed of in accordance with all Federal, State, and local laws. If required the Contractor is also responsible to conduct all structural repairs, patch walls, paint, repair ceiling etc., associated Replace/Retrofit the controls between the chiller and cooling tower.
G. SUBMITTALS & TRAINING
Submittals:
1. The contractor shall provide written submittals to the COR describing recommended equipment within (15) days from receiving the Notice to proceed for approval.
2. All security clearance paperwork/documentation shall be submitted to the COR a minimum of (14) working day prior to the start of work (see below).
3. The Contractor shall provide to the COR three (3) copies of the Safety Data Sheets (SDS) on all materials and substances that may be used during the course of the project. In the event the material is not approved by the Safety Manager, it shall be the responsibility of the Contractor to locate and procure an alternative product.
4. For security and safety purposes, forty-eight (48) hour advance notice in writing, prior to disruption to the system must be given to the Contracting Officer and COR.
5. Provide complete narrative descriptions of all system operations.
6. The contractor shall provide one complete set hardcopy D-size drawings of the entire system, an electronic version of all the plans in Computer Aided Design (CAD) format (2007 edition or later) and in PDF format in disc/s upon completion of the project.
7. The contractor shall provide an Installation Certification of the completed and tested systems that contains an affidavit signed by the contractor and manufacturer’s representative, notarized, certifying that the complete systems meet the contract requirements and is fully operational per the manufacturer's recommendations.
8. Any deviations from this Statement of Work will be considered a Change Order Request and must be authorized through the institution’s Contracting Officer prior to the implementation of the requested change.
9. It is the Contractor’s responsibility to repair and/or replace any Government property damaged by contractors/subcontractors employees. Damage will be corrected and restored to previous condition at no cost to the Government.
10. It shall be the Contractor’s responsibility for obtaining all measurements and data requirements to comply with manufacturer’s installation recommendations. All installations must be in accordance with product manufacture’s recommendations.
Training:
Upon completion of the installation, testing, and acceptance by the Government, the contractor shall provide the COR a complete hardcopy printout of the system programming including schematics and ladder logic diagram, along with CD- ROM disk copies of the program. CD-ROM disks shall include all manufacturers’ software necessary to perform maintenance and adds. The contractor shall provide operation/maintenance manuals for each piece of equipment/system installed. One copy of any required licensed software and associated manuals shall also be supplied to the institution.
The contractor shall furnish manufacturer’s factory-certified training and provide system certification for two (2) Bureau of Prisons employees, thus enabling them to maintain and repair all equipment and systems. Training shall include operations and maintenance of the control system.
II. CONTRACTOR SECURITY/WORKING REGULATIONS
A. Work Hours:
Work Hours for the contractor are 8:00 AM – 2:30 PM, Monday - Friday, excluding weekends and federal holidays. Any work required to be completed at any other time than noted above must be requested in writing to the COR five (5) working days prior to the start of the work and must be approved by the Warden. In the event of any equipment being replaced that would result in downtime of the normal orderly running of the institution, alternate work hours may be authorized in accordance with the time frame stated above.
Access to the site will be available during normal working hours except during emergencies. It shall be the responsibility of the Contractor to familiarize himself, his employees, and his subcontractors of the working hours and conditions in the correctional facility, as working hours may not constitute a full eight-hour work day. The Government assumes no responsibility to the Contractor nor to any of his subcontractors for shorter hours due to institutional emergencies or entry and/or exit of workers necessitated by normal institution routines.
Contractors should plan for a minimal amount of time accrued for security considerations, i.e., check-in screening, delay due to inmate movements, institution lock-down, institution emergencies, etc. In the event of an institution emergency, the Contractor will be instructed to secure all work, secure and stow all tools, equipment and materials, and the Contractor will be escorted out of the institution. Work will resume once the institution emergency passes.
(1) Daily staff escort will be provided during the performance period of this contract allowing for continuous work in one area.
B. Delivery of Materials:
All construction materials/equipment required for work on this project is required to be processed by the Contractor and coordinated with the institution COR for temporary storage.
Any related deliveries which are directly shipped to the contractor can be received between the hours of 8:00 a.m. to 2:30 p.m., Monday through Friday, excluding Federal Holidays. At no point will a Bureau of Prisons (BOP) staff member receive or sign for a delivery if the contractor or his representative is not present to verify and accept the delivery.
Under no circumstances will FCI Texarkana or its staff be responsible for the acceptance of any Contractor or company deliveries. The contractor shall be responsible for providing their own means of loading and unloading contractor material or equipment.
The contractor shall not use the institution entry/driveway for the loading, unloading, or storage of any materials and equipment. The contractor will not impede/block the driveway at any time during or after the work shift.
C. Storage of Materials and Equipment:
All materials/tools shall be stored in a designated area mutually agreed upon between the COR and the contractor. The storage area will be a secure lockable gang box or similar, size to be determined by the contractor and the COR. If required, the contractor shall provide a securable, single point access storage container, such as a Job or Gang Box that will be left in the agreed upon storage area for the duration of the project. Size of the storage container will be determined by the contractor and the COR. The container will be secured using a padlock protocol with two locks to secure it. One shall be a contractor lock and the other lock provided by the institution. If necessary, a heavy duty chain provided by the contractor may be used to facilitate the locking requirement. All materials and equipment stored within the container will be maintained in a safe an orderly fashion
All tools will be inventoried prior to entering the institution and will be inventoried back in to ensure accurate accountability when exiting the institution at the end of each work day.
Materials cannot be stored at a height that would create a fall hazard. All tools will be inventoried prior to entering the Institution. At the start of each workday all tools will be inventoried out on a daily tool inventory sheet and at the end of the workday all tools will be inventoried back in to ensure accurate accountability of all tools at the end of each workday.
All contractor owned extension cords that will be used during the project, regardless of length, shall be in good condition with no broken outer Insulation. Extension cords are considered a “high risk” tool having a Federal Bureau of Prisons’ tool classification of Double A. All contractor owned extension cords used for this project will be required to exit the institution at the end of every workday for the duration of the project.
All contractor owned ladders approved for use within the institution, regardless of the size, shall be stored in a pre-determined area and secured to a stationary fixture with a heavy link chain and lock which would prevent removal.
D. Security Clearance/Contractor Badges:
The contractor shall provide the COR with all the necessary security clearance documents for all contractors and subcontractor employees accessing the institution and be security cleared for badging within 14 days of receiving the Notice to Proceed, as stated above. Security clearance documents will only be accepted from the prime contractor. If submitted by a sub-contractor, they will be rejected. It is the prime contractor’s responsibility to review security clearance submissions to ensure they are complete.
All contractors and their construction staff awarded the project will be required to attend a four (4) hour orientation and security procedures training. The contractors and any subcontract staff are required to attend. This training must be accomplished prior to any contract or subcontract employee being granted access to federal property to start work.
In the event a contractor or subcontractor employee cannot pass the security clearance process, it will be the contractor’s responsibility to provide another candidate. By law the BOP cannot, and will not, release any information to the contractor concerning the nature of why a contractors or subcontractor employee was not able to pass the security clearance process.
All contractors/subcontractors working at FCI Texarkana will be issued and required to wear a picture ID/contractor badge provided by the institution. For security reasons, the badge will be worn in a visible manner as directed by the
COR.
All contractors and subcontractor employees will provide a check list of all employees on site each day to the COR, verifying the number of workers on site each day and that all workers are approved to be on site.
E. Safety and Personal Protective Equipment:
All contractors and employees shall have and wear the required personal protective equipment (PPE) prescribed by industry standards at all times while on the job site. It is the responsibility of the contractor to provide all PPE equipment. All ladders regardless of the size shall be stored, and secured to a stationary fixture with a chain and lock in a predetermined area, in a way that they cannot be removed. If ladders are required, immediately consult with the COR to ensure that he or she can make timely notification to appropriate institution staff. All extension cords regardless of length shall be in good condition with no broken outer insulation and will be secured in a locked construction gang box. Should a system require Lock-out/Tag-out, the system will be required to have both Contractor and FCI Texarkana locks on the isolation point to prevent shock. All Lock-out/Tag-out procedures will be in compliance with the institution Lock-out program.
F. Other Considerations
1. Contractor technicians will NOT be allowed to bring cell phones, cameras or two way pagers into the Institution. Use of such devices however, may be used on institution exterior grounds. FCI Texarkana Reserves the right to restrict their use at any time if deemed a security threat or risk.
2. The Facilities Department at FCI Texarkana maintains a digital camera that will be utilized by FCI Facility Staff to document the project work. The Contractor may request copies of the digital photos for their record keeping.
3. All deviations from this Statement of Work must be approved in writing by the Contracting Officer and COR.
END STATEMENT OF WORK
N
63 58
232221
16 17
North 33° 22' 34.5" West 94° 5' 22.8"
COORDINATES
46 - STAFF HOUSING
52 - TRAILER STAGING AREA
49 - UNICOR STORAGE
55 - TOWER 1
54 - GARDEN
50 - SALVAGE YARD
48 - V.T. SHOPS
47 - V.T. CLASSROOM
53 - FARM IMPLEMENT SHED
51 - UNICOR CARDBOARD STO.
45 - FEDERAL PRISON CAMP
61 - LANDSCAPE OFFICE
64 - F/S FREEZERS
63 - GREENHOUSES
59 - TOWER 5
58 - TOWER 4
57 - TOWER 3
65 - WEIGHT AREA
62 - MEDICAL/COMMISSARY
60 - K-UNIT / ABOVE FOOD SERV.
66 - DRUG TREATMENT BLDG.
56 - TOWER 2
24 - POWERHOUSE
23 - RECREATION FIELD
33 - NEW POWERHOUSE
31 - CONSTRUCTION 1 OFFICE
27 - FUEL STORAGE TANKS
26 - GAS MANIFOLD SHELTER
32 - RADIO TOWER
29 - GREENHOUSE
25 - OUTSIDE PLUMBING SHOP
1 - ADMINISTRATION BLDG.
2 - COURT YARD
6 - WEST UNIT
5 - LAUNDRY
4 - STOREROOM
10 - UNICOR
8 - REAR GATE
9 - REAR GATE OFFICE
7 - SOUTHWEST UNIT
11 - COMMISSARY
3 - FOOD SERVICE
42 - FIREARMS CLASSROOM
41 - TRAINING BUILDING
40 - COMMAND CENTER
36 - UNICOR WAREHOUSE
39 - H.R.M. OFFICE
38 - MAIL ROOM
37 - ARMORY
35 - GARAGE
43 - FIRING RANGE
44 - PARKING AREA
16 - HOSPITAL
14 - EAST UNIT
20 - CHAPEL
19 - MECHANICAL SERVICES
18 - V.T. WELDING SHOP
17 - EDUCATION COMPLEX
15 - MODULAR UNIT
13 - CENTRAL UNIT
21 - GYMNASIUM
22 - RECREATION YARD OFFICE
12 - METAL DETECTOR BLDG. 34 - GROUND WATER TANK
30 - FOOD SERVICE WAREHOUSE
GRAPHIC SCALE IN FEET
FCI TEXARKANA
INSTITUTION SITE PLAN
E
O
BU
NEW MEXICO
R
A
E D
L
TEXAS LA
OKLAHOMA
O
ER UA
ARKANSAS
PR
IS
F
M
F
TR
AP
D E
FTNE O
UJ S
C T I E
N
AREA OF PROPOSED WORK
FCI / FPC TEXARKANA
4001 LEOPARD DRIVE
TEXARKANA, TEXAS 75501
SCRO
SCRO
SOUTH CENTRAL REGION
BUILDING INDEX
FCI TEXARKANA
67 - RECYCLE STORAGE BLDG.
68 - FCI CREDIT UNION
28 - LANDSCAPE SHOP
REVISIONS
ACAD Number:
Sheet number:
of: 3
Date Drawn:
02/05/2024
Checked By:
D. Osborn
Drawn By:
H. McMillan
M.W.O. Number:
B&F PROJECT NUMBER:
UREAU OF
L
TR
E
AP
D
D F E
ERA
OFTN
R
I
TI
EM JUS
B P
CE
O N S
S
H. McMillan, Engineering Tech
PREPARED BY
Fe de ra l C or re ct io na l I ns tit ut io n
- T ex ar ka na
Fe de ra l C or re ct io na l I ns tit ut io n R
EC
O
R D
D R
A W
IN
G
S
DRAWING TITLE
ELEVATED
WATER
TOWER
N/A
N/A
A-1
LOCATION PLAN
SCALE: USE GRAPHIC SCALE UpgradeChillerControl.DWG
APPROVED 11/21/2024 SCRO
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text Federal Bureau of Prisons
AutoCAD SHX Text United States Department of Justice
AutoCAD SHX Text 4001 Leopard Drive
AutoCAD SHX Text Texarkana, TX 75501
REVISIONS
ACAD Number:
Sheet number:
of: 3
Date Drawn:
11/20/2024
Checked By:
Drawn By:
H. McMillan
M.W.O. Number:
B&F PROJECT NUMBER:
UREAU OF
L
TR
E
AP
D
D F E
ERA
OFTN
R I
TI
EM JUS
B P
CE
O N S
S
H. McMillan, Engineering Tech
PREPARED BY
Fe de ra l C or re ct io na l I ns tit ut io n
- T ex ar ka na
Fe de ra l C or re ct io na l I ns tit ut io n R
EC
O
R D
D R
A W
IN
G
S
DRAWING TITLE
UPGRADE CHILLER CONTROL
N/A
25Z5AB9
D. Osborn
A-2
EXISTING CONTROL TO BE REPLACED
NOT TO SCALE
APPROVED 11/21/2024 SCRO
AutoCAD SHX Text Federal Bureau of Prisons
AutoCAD SHX Text United States Department of Justice
AutoCAD SHX Text 4001 Leopard Dr
AutoCAD SHX Text Texarkana, TX 75501
UpgradeChillerControl.DWG
N525150495347644865456236686654545429316358185923222119292830615727263432252443589561015111312146036521445537447391617384043434241202917North 33° 22' 34.5"West 94° 5' 22.8"COORDINATES46 - STAFF HOUSING52 - TRAILER STAGING AREA49 - UNICOR STORAGE55 - TOWER 154 - GARDEN50 - SALVAGE YARD48 - V.T. SHOPS47 - V.T. CLASSROOM53 - FARM IMPLEMENT SHED51 - UNICOR CARDBOARD STO.45 - FEDERAL PRISON CAMP61 - LANDSCAPE OFFICE64 - F/S FREEZERS63 - GREENHOUSES59 - TOWER 558 - TOWER 457 - TOWER 365 - WEIGHT AREA62 - MEDICAL/COMMISSARY60 - K-UNIT / ABOVE FOOD SERV.66 - DRUG TREATMENT BLDG.56 - TOWER 224 - POWERHOUSE23 - RECREATION FIELD33 - NEW POWERHOUSE31 - CONSTRUCTION 1 OFFICE27 - FUEL STORAGE TANKS26 - GAS MANIFOLD SHELTER32 - RADIO TOWER29 - GREENHOUSE25 - OUTSIDE PLUMBING SHOP 1 - ADMINISTRATION BLDG. 2 - COURT YARD 6 - WEST UNIT 5 - LAUNDRY 4 - STOREROOM10 - UNICOR 8 - REAR GATE 9 - REAR GATE OFFICE 7 - SOUTHWEST UNIT11 - COMMISSARY 3 - FOOD SERVICE42 - FIREARMS CLASSROOM41 - TRAINING BUILDING40 - COMMAND CENTER36 - UNICOR WAREHOUSE39 - H.R.M. OFFICE38 - MAIL ROOM37 - ARMORY35 - GARAGE43 - FIRING RANGE44 - PARKING AREA16 - HOSPITAL14 - EAST UNIT20 - CHAPEL19 - MECHANICAL SERVICES18 - V.T. WELDING SHOP17 - EDUCATION COMPLEX15 - MODULAR UNIT13 - CENTRAL UNIT21 - GYMNASIUM22 - RECREATION YARD OFFICE12 - METAL DETECTOR BLDG.34 - GROUND WATER TANK30 - FOOD SERVICE WAREHOUSEGRAPHIC SCALE IN FEETFCI TEXARKANAINSTITUTION SITE PLANEOBUNEW MEXICORAEDLTEXASLAOKLAHOMAOERUAARKANSASPRISFMFTRAPDEFTNEOUJSCTIENAREA OF PROPOSED WORKFCI / FPC TEXARKANA4001 LEOPARD DRIVETEXARKANA, TEXAS 75501SCROSCROSOUTH CENTRAL REGIONBUILDING INDEXFCI TEXARKANA67 - RECYCLE STORAGE BLDG.672968 - FCI CREDIT UNION4628 - LANDSCAPE SHOP33
REVISIONS
ACAD Number:
Sheet number:
of: 3
Date Drawn:
11/20/2024
Checked By:
Drawn By:
H. McMillan
M.W.O. Number:
B&F PROJECT NUMBER:
UREAU OF
L
TR
E
AP
D
D F E
ERA
OFTN
R I
TI
EM JUS
B P
CE
O N S
S
H. McMillan, Engineering Tech
PREPARED BY
Fe de ra l C or re ct io na l I ns tit ut io n
- T ex ar ka na
Fe de ra l C or re ct io na l I ns tit ut io n R
EC
O
R D
D R
A W
IN
G
S
DRAWING TITLE
UPGRADE CHILLER CONTROL
N/A
25Z5AB9
D. Osborn
A-3
EXISTING CONTROL TO BE REPLACED
NOT TO SCALE
APPROVED 11/21/2024 SCRO
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text Federal Bureau of Prisons
AutoCAD SHX Text United States Department of Justice
AutoCAD SHX Text 4001 Leopard Dr
AutoCAD SHX Text Texarkana, TX 75501
UpgradeChillerControl.DWG
Blank Page
File details come from the government source that posted it. Updated .