This file package contains construction specifications and supporting documents for the City of Wichita's Street Improvements project for 21st Street North from Mosley Avenue to I-135 in Wichita, Kansas. The project includes reconstruction of the street to provide wider pavement and improved stormwater drainage, with an estimated total disturbed area of 3.10 acres and an anticipated project start date of March 1, 2023, and completion date of March 31, 2024. Key specifications address railroad coordination with Union Pacific Railroad (UPRR), including temporary sheet pile shoring installation, track and ground monitoring, potholing for utility location, and abandonment in place of an existing 8-inch water main. The documents contain detailed requirements for soil excavation and groundwater management, monitoring well capping procedures, and compliance with Kansas Department of Health and Environment (KDHE) regulations. A Notice of Intent (NOI) for stormwater discharge authorization was submitted on October 26, 2022, and authorized by KDHE on November 30, 2022, under Kansas Permit No. S-AR94-1800 and Federal Permit No. KSR121041, with authorization expiring July 31, 2027.

The project involves approximately 834 cubic yards of material excavation, with specific volumes allocated for pavement, storm sewer, water lines, sanitary sewer, and ITS conduit installations. Contractor responsibilities include developing and implementing a Track, Ground, and Shoring Monitoring Plan, preparing an ITS Utility Potholing Plan, and managing contaminated soils classified as Special Waste or Hazardous Waste in accordance with KDHE requirements. Payment is structured through multiple bid items including temporary sheet pile shoring measured by linear foot, pipe abandonment in place measured by linear foot, and lump-sum compensation for Railroad Coordination work that encompasses all contractor-prepared submittals, right-of-entry coordination, utility locating, monitoring, contingency response planning, and associated third-party charges including UPRR flagging and RailPros construction observation fees. The contractor must obtain a UPRR Right-of-Entry and all contractor-specific insurance, training, and access authorizations before entering railroad right-of-way, and Written Authorization to Proceed cannot be issued until execution of the City-UPRR agreement, acquisition of required utility easements, and UPRR approval of final plans and monitoring procedures.

View the file

Other files

File Type Posted
5-BPAttach03 Ks SWPPP 210455.pdf PDF
2-260273 Bid Table.pdf PDF
1-BP 472-2022-085792.pdf PDF
3-BPAttach02 NSF Agreement.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Effective: August 1, 2022 Notice of Intent (NOI) for Discharge of Stormwater Runoff from Construction Activites Page 1 of 4

NOTICE OF INTENT (NOI)

For Authorization to Discharge Stormwater Runoff from Construction Activities In accordance with the Kansas Water Pollution Control General Permit Under the National Pollutant Discharge Elimination System (NPDES)

Submission of this Notice of Intent constitutes notice that the party identified in Section I of this form requests authorization for coverage under the Kansas Water Pollution Control general permit, or KDHE issued successor permits, issued for stormwater runoff from construction activities in the State of Kansas. Becoming a permittee obligates the discharger to comply with the terms and conditions of the general permit. A complete request for Authorization for coverage under the general permit must be submitted or the request will not be processed. KDHE will notify owners or operators whose Notice of Intent (NOI) and supporting documentation for Authorization of stormwater runoff associated with construction activities are incomplete, deficient, or denied.

I. OWNER OR OPERATOR ADDRESS, BILLING, CONTACT & RECORDS LOCATION INFORMATION

Owner/Operator Shawn Mellies Mailing Address: 455 N Main St,7th Floor Company Name: City of Wichita City, State Zip: Wichita, KS 67202 Phone: (316) 268-4501 Email: smellies@wichita.gov

Contact Name: Shawn Mellies Mailing Address: 455 N Main St, 7th Floor Company Name: City of Wichita City, State Zip: Wichita, KS 67202 Phone: (316) 268-4501 E-mail: smellies@wichita.gov

PERMIT FEE BILLING INFORMATION

Billing Contact: Shawn Mellies, City of Wichita Billing Address: 455 N Main St, 7th Floor Wichita, KS 67202

Phone: (316) 268-4501 E-mail: smellies@wichita.gov

Address where records will be kept (if not on-site):

Records Address: 455 N Main St Wichita, KS 67202

II. SITE INFORMATION

Project Name: Street Improvements for 21st Street North from Mosley Avenue to I-135 Street Address: 1300 E. 21st St N.

Wichita, KS 67214 County: Sedgwick

Legal Site Description:

Qtr: S2 Qtr: SW Section: 04 Township: 27S Range: 01E

Decimal Degrees Latitude: 37.722500 Decimal Degrees Longitude: -97.321667

AUTHORIZED:Submission Received: 10/26/2022 Submission Number:

HPN-QG6T-7TT3C YES X NO

Reviewer: Is Authorization Conditional

YES NO X

(if yes, see Section V for conditions)

Larry Hook Are there any Considerations

YES NO X

(if yes, see Section V for considerationsAuthorized By:

Secretary, Kansas Department of Health and Environment KS Permit No.: S-AR94-1800

Issued: November 30,2022 Federal Permit No.: KSR121041

KEIMS Watermark KSR121041 v1.0

Approved Issued On:11/30/2022

Expires On:07/31/2027

Project Name: Street Improvements for 21st Street North from Mosley Avenue to I-135 Notice of Intent (NOI)

Effective: August 1, 2022 Notice of Intent (NOI) for Discharge of Stormwater Runoff from Construction Activites Page 2 of 4

B. Existing Conditions/Uses

1) Is any part of the project located on Indian Country Land?

No

2) If stormwater runoff drains to or through a Municipal Separate Storm sewer System (MS4): MS4 Name:

City of Wichita

3) Name of the first receiving water, stream, or lake E Fork Chisholm Creek, River Basin AR -

LOWER ARKANSAS

4) Are contaminated soils present on the site or is there groundwater contamination located within the site boundary?

Yes

On separate paper describe in detail the locations and concentrations of the contaminants.

5) Are there any contaminated soils that will be disturbed or any contaminated groundwater that will be pumped by the proposed construction activity?

No

6) Are there any surface water intakes for public drinking water supplies located within ½ mile of the site discharge points?

No

7) Are there any known historical or archeological sites present within the site boundary or any historic structures located within 1000 feet of the project site?

No

Note: Include documentation of project-specific coordination with the Kansas Historical Society in making this determination

8) Is any threatened or endangered species habitat located within the site boundary or in the receiving water body?

No

Note: Include documentation of project-specific coordination with the Kansas Department of Wildlife, Parks & Tourism in making this determination.

9) Will the project impact the line or grade of a stream or does it include dredge or fill of a potential jurisdictional water body or wetlands?

No

10) Are any Critical Water Quality Management Areas, Special Aquatic Life Use Waters, or Outstanding National Resource Waters located within ½ mile of the facility boundary?

No

C. Project Description

1) Project Description:

Reconstruction of 21st Street to provide wider pavement and improved storm water drainage.

Does this NOI include all proposed soil disturbing activities associated with the entire common plan of development? Yes

2) Anticipated project Start Date: March 1, 2023 and Completion Date: March 31, 2024

3) Estimated total area to be disturbed: 3.10 Acres

4) Total area of the site: 3.10 Acres

5) Do you plan to disturb ten or more acres that are within a common drainage area? No

KEIMS Watermark KSR121041 v1.0

Approved

Project Name: Street Improvements for 21st Street North from Mosley Avenue to I-135 Notice of Intent (NOI)

Effective: August 1, 2022 Notice of Intent (NOI) for Discharge of Stormwater Runoff from Construction Activites Page 3 of 4

E. Maps

Include an area map showing the outline of the construction site and the topographic features of the area at least one mile beyond the project site.

F. Erosion Control Plan and Best Management Practices

1) Provide a summary of the sequence of major soil disturbing activities including installation of the corresponding stormwater management and pollution control features.

1. Construct temporary construction entrance/exit.

2. Install silt fence and other BMPs around perimeter.

3. Perform Grading.

4. Water disturbed areas frequently to minimize dust.

5. Disturbed areas of the site where construction activity has ceased for more than 14 days shall be stabilized

6. Install BMPs at the locations of all grate inlets, curb inlets, and at the ends of all exposed storm sewer pipes

7. Carry out final grading and gravel and/or asphalt placement

8. Remove BMPs only after all paving is complete and exposed surfaces are stabilized. Exposed surfaces are stabilized when 75% vegetative cover has been established

9. Remove temporary construction entrance/exits.

2) Provide one or more site plans covering the anticipated soil disturbing activities showing the limits of disturbance, the existing and proposed elevation contours, the types and locations of erosion/sediment control measures and stormwater management/pollution control features during each phase of construction and the locations where stormwater runoff leaves the construction site.

3) Provide a description of the best management practices to be utilized to control erosion and the discharge of sediment and other pollutants in stormwater runoff throughout construction and the design calculations for each sediment basin including total drainage area and storage capacity below the elevation of the mass volume flow outlet device.

n/a

4) Provide the name and License or Certification Number of the engineer, geologist, architect, landscape architect, or Certified Professional in Erosion and Sediment Control (CPESC) under which the construction stormwater pollution prevention plan has been developed.

Kara Anderson 18596 Engineer Name License or Certification Number Profession or Field

III. ANNUAL FEES

The first year of the annual permit fee specified in K.A.R 28-16-56 et seq. as amended is currently $60.00 and can be paid through the KEIMS system at time of submittal. The fee must be paid before this NOI will be processed. An invoice for the annual permit fee will be sent to the contact person requesting a permit until such time as the permittee submits a Notice of Termination (NOT).

Failure to pay the annual fee timely may result in termination of the construction stormwater discharge Authorization.

IV. OWNER OR OPERATOR CERTIFICATIONS

I, the undersigned, certify that a Stormwater Pollution Prevention Plan (SWP2 Plan) will be or has been developed for the construction site described in this NOI and supporting documentation. I further certify that the plan will be implemented at the time construction begins, and, as required by the NPDES general permit for Stormwater Runoff from Construction Activity, will revise the SWP2 plan if necessary.

KEIMS Watermark KSR121041 v1.0

Approved

Project Name: Street Improvements for 21st Street North from Mosley Avenue to I-135 Notice of Intent (NOI)

Effective: August 1, 2022 Notice of Intent (NOI) for Discharge of Stormwater Runoff from Construction Activites Page 4 of 4

I understand that continued coverage under the NPDES general permit for Stormwater Runoff from Construction Activities is contingent upon maintaining eligibility as provided for in the requirements and conditions of the general permit, and paying the annual fee.

I certify under penalty of law that this document and all attachments were prepared under my direction or supervision in accordance with a system designed to assure that qualified personnel properly gather and evaluate the information submitted.

Based on my inquiry of the person or persons who manage the system, or those persons directly responsible for gathering the information, the information submitted is, to the best of my knowledge and belief, true, accurate, and complete. I am aware that there are significant penalties for submitting false information, including the possibility of fine and imprisonment.

Shawn Mellies 10/26/2022 2:19:18 PM Signature (owner or operator) Date

Official Title

V. CONDITIONS AND/OR CONSIDERATIONS OF APPROVAL

Conditions of Authorization - For Official Use Only:

When indicated, Conditions of Authorization are as follows:

NONE

Notes on Consideration – For Official Use Only:

NONE

KEIMS Watermark KSR121041 v1.0

Approved

UPRR COORDINATION

21ST STREET NORTH – MOSLEY TO I-135, PHASE 2 110-1

448-2021-002927

SECTION 110 - UPRR COORDINATION

PART 1 GENERAL

1.01 DESCRIPTION

A. This section establishes requirements for railroad coordination associated with the Line 5 Water Line Improvements and for utility locating and potholing required to support the approved ITS installation within and adjacent to Union Pacific Railroad (UPRR) right-of-way.

B. The work includes, but is not limited to, contractor-prepared railroad and permit-support submittals and information; right-of-entry coordination; utility locating and potholing; track, ground, and shoring monitoring; temporary sheet pile shoring installation; excavation;

water line construction and connection; abandonment in place of existing water line facilities; coordination with UPRR, RailPros, and railroad flagging personnel;

implementation of contingency measures; documentation; and restoration.

C. UPRR Application 2074390 and UPRR Project No. 0803432 apply to the Line 5 Water Line Work. The UPRR agreement, final UPRR approvals, and required Utility Easements associated with that work may remain pending when the Contract is advertised or awarded. UPRR Application 2073963 and UPRR Project No. 0803431 apply to the ITS installation and have been approved by UPRR. This section also establishes requirements for railroad coordination and existing-fiber verification required before directional drilling for the ITS installation.

1.02 REFERENCES

A. Contract Documents and Line 5 Water Line Improvement plans.

B. The fully executed agreement between the City of Wichita and UPRR, including all exhibits, conditions, insurance provisions, and construction requirements.

C. UPRR Guidelines for Track & Ground Monitoring.

D. UPRR & BNSF Guidelines for Temporary Shoring.

E. UPRR Guidelines for Abandonment of Subsurface Utility Structures.

F. UPRR Guidelines for 3rd Party Utility Potholing.

G. UPRR approval documents associated with Application 2073963 and Project No. 0803431.

H. UPRR Railroad Exhibit A applicable to the approved encroachment.

I. UPRR guideline documents are available from the Structures Design Guidelines page:

https://www.up.com/communities/public-projects/structures-design.

J. Comply with the versions of the referenced UPRR guidelines incorporated into the executed UPRR agreements, written UPRR approvals, or permits for Applications 2074390 and 2073963, as applicable. When no version is identified, use the version directed by UPRR for the applicable submittal or construction activity.

K. UPRR requirements issued or revised after the Bid Date that materially change the Work will be administered in accordance with the Contract's change provisions, except when the change results from a Contractor deviation, incomplete submittal, or noncompliance.

L. When a conflict or ambiguity exists among the Contract Documents, UPRR requirements, approved submittals, or field direction, stop the affected work and obtain written direction from the Engineer of Record before proceeding. Do not interpret a conflict in a manner that reduces railroad protection.

21ST STREET NORTH – MOSLEY TO I-135, PHASE 2 110-2

448-2021-002927

1.03 DEFINITIONS

A. Engineer of Record: MKEC Engineering, Inc. (MKEC), the professional engineering consultant responsible for the engineering design associated with the Work addressed by this section and for providing engineering services related to the applicable UPRR approvals and submittals.

B. Line 5 Water Line Work: All construction associated with the Line 5 Water Line Improvements, including preparatory work, shoring, excavation, monitoring, connection, abandonment, backfill, and restoration within or affecting UPRR right-of-way.

C. Railroad: Union Pacific Railroad.

D. RailPros: UPRR's designated construction-observation consultant for the Line 5 Water Line Work and other railroad work when required by UPRR.

E. Zone A: The railroad influence zone defined by the current UPRR guidelines and the approved Contract Documents.

F. Written Authorization to Proceed: Written notice issued by the Engineer of Record specifically releasing the Contractor to begin the Line 5 Water Line Work. A general Notice to Proceed for the Project is not authorization to begin the Line 5 Water Line Work.

1.04 CONDITIONS PRECEDENT AND WORK RESTRICTIONS

A. The City may award the Contract before all railroad approvals and required Utility Easements associated with the Line 5 Water Line Work have been obtained.

B. The Contractor shall not enter UPRR right-of-way for purposes of performing the Line 5 Water Line Work, install temporary shoring associated with the Line 5 Water Line Work, excavate for the Line 5 Water Line Work, or otherwise begin the Line 5 Water Line Work until the Engineer of Record issues Written Authorization to Proceed. Authorization will not be issued until each of the following has occurred:

1. The agreement between the City of Wichita and UPRR has been fully executed.

2. All Utility Easements required on adjacent properties west of UPRR right-of-way have been acquired and made available for construction.

3. UPRR has approved the final plans and the temporary sheet-pile shoring system designed by the Engineer of Record.

4. UPRR has accepted the Contractor's Track, Ground, and Shoring Monitoring Plan, including the Contingency and Emergency Response Plan.

5. UPRR has provided written approval for abandonment in place of the existing 8-inch water main, including any project-specific exception to or conditions concerning hazardous-material testing.

6. The Contractor has obtained all contractor-specific right-of-entry, insurance, training, access, flagging, RailPros observation, and other authorizations required by UPRR or the executed agreement.

C. Work associated with the approved ITS installation under UPRR Application 2073963 and UPRR Project No. 0803431 may proceed independently of the Line 5 Water Line Work, subject to the requirements and conditions of that approval. Before entering UPRR right-of-way to locate or expose existing utilities, the Contractor shall obtain a valid UPRR Right-of- Entry and all contractor-specific insurance, training, access, flagging, construction-observation, and other authorizations required by UPRR.

D. Preparation and review of submittals, scheduling, procurement, off-site fabrication, and other activities that do not require entry onto restricted property may proceed before the Line 5 Water Line Work is released.

21ST STREET NORTH – MOSLEY TO I-135, PHASE 2 110-3

448-2021-002927

E. The Contractor may proceed with other authorized Project work and shall sequence the work to account for the Line 5 Water Line Work restrictions. The City does not guarantee the date on which the Line 5 Water Line Work will be released.

F. Written Authorization to Proceed does not waive any UPRR requirement or relieve the Contractor from obtaining required contractor-specific approvals.

1.05 RESPONSIBILITY

A. The Engineer of Record is responsible for the engineering design of the temporary sheet-pile shoring shown in the Contract Documents and for formal transmission of permit-related submittals to UPRR for the work addressed by this section. The approved shoring plans will be issued to the Contractor when available.

B. The Contractor is responsible for all construction means, methods, techniques, sequences, procedures, labor, materials, equipment, temporary works, safety, railroad coordination, right-of-entry requirements, utility locating and potholing, monitoring, documentation, and emergency response necessary to complete the Line 5 Water Line Work and the ITS-related railroad work required by this section.

C. The Contractor shall develop the Track, Ground, and Shoring Monitoring Plan, including the Contingency and Emergency Response Plan, based on its proposed equipment, staffing, sequence, means, and methods. The Contractor shall also provide construction-specific information requested by the Engineer of Record to complete or revise the temporary-shoring submittal.

D. The Engineer of Record may provide limited drafting or plan-sheet support for contractor-prepared information. Such assistance does not transfer responsibility for the technical content, completeness, feasibility, accuracy, or compliance of the Contractor's plans.

E. The Contractor shall review the Contract Documents and approved temporary shoring design for compatibility with its proposed construction methods, equipment, site access, and actual field conditions. Notify the Engineer of Record promptly of conflicts or conditions requiring clarification.

F. Approval, acceptance, review, comment, or drafting assistance by the City, Engineer of Record, UPRR, or RailPros does not relieve the Contractor of its construction responsibilities.

1.06 UPRR PERMIT SUBMITTALS

A. Submit the initial contractor-prepared permit-support package within 30 calendar days after the Project Notice to Proceed, unless an earlier date is established by the Engineer of Record. Provide complete information early enough to accommodate Engineer of Record and UPRR review and required resubmittals.

B. Required Contractor-Prepared Deliverables:

1. Track, Ground, and Shoring Monitoring Plan: Prepare a project-specific plan, including the Contingency and Emergency Response Plan, in accordance with the applicable UPRR Guidelines for Track & Ground Monitoring, the UPRR-approved shoring plans, and written UPRR comments. Include all certifications required by

UPRR.

2. Construction-Specific Shoring Information: Provide equipment, proposed methods, sequence, construction loads, staging, dimensions, and other information requested by the Engineer of Record to complete or revise the temporary-shoring plans and calculations prepared by the Engineer of Record.

3. Contractor-Proposed Deviations or Alternatives: Provide signed and sealed plans and calculations for any proposed deviation, substitution, or alternate shoring system. Documents shall be prepared by a professional engineer licensed in Kansas and experienced with railroad loading.

21ST STREET NORTH – MOSLEY TO I-135, PHASE 2 110-4

448-2021-002927

4. ITS Utility Potholing Plan: Prepare a project-specific potholing procedure and plan for locating the two existing fiber optic cables within UPRR right-of-way before directional drilling for the ITS installation. Include the proposed excavation and backfill methods, equipment, pothole locations and dimensions, track clearances, access and travel paths, equipment and material staging, excavation protection, emergency contingency provisions, and other information required by the UPRR Guidelines for 3rd Party Utility Potholing or written UPRR direction.

5. Right-of-Entry Documentation: Before entering UPRR right-of-way for Contractor-performed utility locating or potholing, provide evidence to the Engineer of Record that the required UPRR Right-of-Entry and contractor-specific access authorizations have been obtained.

6. Additional UPRR-Requested Information: Provide supporting calculations, procedures, drawings, or other information expressly required by the executed agreement, permit conditions, applicable UPRR guideline, or written UPRR direction.

C. Submission and Review:

1. Format and Delivery: Provide each deliverable to the Engineer of Record in the format required by the Engineer of Record or UPRR. Do not submit directly to UPRR unless authorized in writing by the Engineer of Record.

2. Formal Submission: The Engineer of Record will formally transmit permit-related submittals to UPRR under Applications 2074390 and 2073963, as applicable.

3. Contractor Responsibility: Engineer of Record review, drafting assistance, or formal transmission does not transfer responsibility for the technical content, completeness, feasibility, accuracy, or compliance of contractor-prepared information.

4. Resubmittals: Promptly revise and resubmit incomplete or rejected information.

Account for applicable UPRR review durations in the Project schedule. For potholing submittals and resubmittals, assume a minimum UPRR review duration of four weeks each unless otherwise directed by UPRR. Do not begin the affected work until required UPRR acceptance is received.

PART 2 MATERIALS

2.01 MONITORING EQUIPMENT

A. Provide monitoring instruments, survey equipment, targets, benchmarks, data-logging equipment, communications, power, and backup equipment capable of meeting the UPRR-accepted monitoring plan.

B. Calibrate, maintain, and replace monitoring equipment as required by the UPRR-accepted monitoring plan and manufacturer recommendations.

2.02 TEMPORARY SHEET PILE SHORING

A. Provide sheet piles, walers, bracing, connections, appurtenances, and other materials shown on the UPRR-approved shoring plans.

B. Do not substitute materials, sections, lengths, connection details, or bracing without prior written approval from the Engineer of Record and UPRR.

C. Provide installation equipment suited to the approved design, existing site and soil conditions, railroad clearance requirements, and vibration restrictions.

2.03 GROUT AND CONTROLLED LOW-STRENGTH MATERIAL

A. Provide pressure-grouting materials and contingency resources required by the accepted Contingency and Emergency Response Plan. Maintain required resources at the site during critical operations.

21ST STREET NORTH – MOSLEY TO I-135, PHASE 2 110-5

448-2021-002927

B. For the existing water main authorized by UPRR to be abandoned in place, provide controlled low-strength material (CLSM) conforming to the written UPRR authorization and applicable UPRR Guidelines for Abandonment of Subsurface Utility Structures. Submit the mix design to the Engineer of Record before placement and to UPRR only when specifically required.

2.04 SAFETY AND PROTECTIVE MATERIALS

A. Provide covers, guardrails, fencing, barriers, temporary lighting, warning devices, and other protective materials required by UPRR, FRA, OSHA, the UPRR-approved plans, and the accepted monitoring and contingency requirements.

B. Protect railroad ballast and subballast from contamination. Provide containment and cleanup materials suitable for the work.

PART 3 CONSTRUCTION REQUIREMENTS

3.01 PRECONSTRUCTION COORDINATION

A. Do not mobilize onto UPRR property or restricted adjacent property for the Line 5 Water Line Work before Written Authorization to Proceed and receipt of contractor-specific access authorization.

B. Schedule RailPros construction observation and UPRR flagging for all activities requiring those services. No work shall proceed when required observation or flagging personnel are absent.

C. Complete all Call Before You Dig requirements applicable to the work, including 811 notification, UPRR long-haul fiber locating, and Railroad signal line locating, before disturbing the ground. Do not begin potholing until existing utilities and Railroad signal lines have been marked as required by UPRR.

D. Obtain, verify, and post current emergency contact information at the work site. Brief each shift on railroad communication, train-approach, threshold, shutdown, and emergency procedures.

E. Railroad operations have priority. Comply immediately with instructions from UPRR, its flagman, RailPros, and the Engineer of Record concerning railroad safety and protection.

F. Upon the approach or passage of a train, stop work, clear personnel, and secure equipment as directed by UPRR, the UPRR flagging representative, RailPros, or the applicable railroad work rules.

3.02 WORK SEQUENCING

A. Sequence other Project work to account for the pending UPRR agreement, UPRR approvals, and Utility Easements associated with the Line 5 Water Line Work.

B. After Written Authorization to Proceed, coordinate the Line 5 Water Line Work schedule with railroad construction windows, flagging, RailPros observation, City operations, utility owners, adjacent property access, and the overall Project schedule.

C. Do not impair railroad operations, drainage, access, utilities, signals, communications, or support facilities.

3.03 ITS UTILITY POTHOLING AND EXISTING FIBER OPTIC VERIFICATION

A. UPRR Application 2073963 and associated UPRR Project No. 0803431 for the ITS installation have been approved by UPRR. Before directional drilling for the ITS conduit, positively locate the two existing fiber optic cables within UPRR right-of-way that run generally parallel to the tracks.

21ST STREET NORTH – MOSLEY TO I-135, PHASE 2 110-6

448-2021-002927

B. Before entering UPRR right-of-way for utility locating or potholing, obtain a valid UPRR Right-of-Entry and all required contractor-specific insurance, training, access, flagging, construction-observation, and other authorizations.

C. Perform utility locating and potholing in accordance with the UPRR Guidelines for 3rd Party Utility Potholing, the approved ITS application and plans, and written UPRR direction.

Complete required Call Before You Dig procedures and utility and Railroad signal line locates before potholing.

D. Use non-invasive locating methods before physical excavation as required by UPRR.

Locate potholes as far from the tracks as practical and comply with UPRR requirements for excavation methods, pothole size, track clearances, access, equipment placement, excavation protection, and backfill.

E. Provide UPRR flagging, RailPros or other UPRR-required construction observation, and track and ground monitoring when required. Maintain the materials and equipment required by the approved potholing procedure and emergency contingency requirements.

F. Do not begin directional drilling for the ITS conduit until the Contractor has positively located and documented the horizontal and vertical position of both existing fiber optic cables and provided the location information to the Engineer of Record.

G. Backfill and restore each pothole in accordance with the UPRR Guidelines for 3rd Party Utility Potholing and UPRR requirements. Protect the existing fiber optic facilities throughout the work and immediately report any damage or suspected damage.

3.04 TEMPORARY SHEET PILE SHORING

A. Temporary sheet pile shoring for Line 5 Water Line Work is being designed by the Engineer of Record and is subject to UPRR review and approval in accordance with the current UPRR & BNSF Guidelines for Temporary Shoring. Approved shoring plans will be provided when available.

B. Do not install any component of the shoring system affecting UPRR right-of-way until UPRR written approval has been received and the Engineer of Record has issued Written Authorization to Proceed.

C. Install, maintain, inspect, and remove the shoring system in strict conformance with the UPRR-approved plans and accepted monitoring and contingency requirements.

D. Install all required Zone A shoring before beginning excavation. Open excavation without an approved temporary shoring system is prohibited.

E. Maintain the excavation limits, track clearances, construction loads, bracing, staging, and sequence shown on the UPRR-approved plans. Verify controlling dimensions and clearances before excavation.

F. Contractor-proposed deviations, alternate shoring systems, or substitutions shall be prepared and sealed by a professional engineer licensed in Kansas and experienced with railroad loading. Submit through the Engineer of Record for review and UPRR approval.

Do not proceed with a deviation until written approval is received.

G. Monitor the shoring for movement throughout installation, excavation, water-line work, backfill, and removal. Immediately report movement exceeding approved limits.

H. The Contractor remains responsible for the safe execution and performance of shoring construction, even when the Engineer of Record provides the design.

3.05 TRACK, GROUND, AND SHORING MONITORING AND ACTION LEVELS

A. Implement the UPRR-accepted Track, Ground, and Shoring Monitoring Plan with qualified personnel under the direction of the Contractor's monitoring engineer.

21ST STREET NORTH – MOSLEY TO I-135, PHASE 2 110-7

448-2021-002927

B. Establish required baseline readings before construction enters Zone A. Begin, continue, and conclude monitoring at the times required by the accepted plan and applicable UPRR guidelines.

C. Monitor the track, ground, and shoring at the locations, frequencies, and durations specified in the accepted plan.

D. Maintain the field logs, electronic records, and reports required by the accepted plan. Make current records available to the Engineer of Record, City, UPRR, and RailPros upon request.

E. Immediately notify the required contacts of any threshold or shutdown value, ground loss, unusual movement, equipment failure, or other unsafe condition.

F. When a threshold or shutdown value established in the accepted plan is reached, suspend or stop the affected work and implement the required response in accordance with that plan and UPRR direction.

G. Do not resume suspended or stopped work until authorized by the Engineer of Record and UPRR or its authorized representative.

3.06 CONTINGENCY RESPONSE

A. Implement the accepted Contingency and Emergency Response Plan when required by monitoring results, ground loss, an unsafe condition, or UPRR direction.

B. Maintain the materials, equipment, qualified personnel, and specialty subcontractors identified in the accepted plan at the site and ready for immediate use during critical operations.

C. Follow the accepted communication and notification procedures. Railroad safety decisions and authorization to resume work remain with UPRR or its authorized representative.

D. Document the condition, monitoring data, notifications, directions, corrective actions, verification, and authorization to resume.

3.07 CONTINUOUS OPERATIONS WITHIN ZONE A

A. After installation of the sheet-pile shoring or other Line 5 Water Line construction begins within Zone A, progress the Line 5 Water Line Work continuously 24 hours per day, 7 days per week until the water-line connection, abandonment in place, backfill, shoring, and ground are in a condition accepted by UPRR for discontinuation of continuous operations.

B. Provide multiple shifts, supervision, monitoring personnel, lighting, communications, materials, fuel, spare parts, backup equipment, and contingency resources necessary to maintain continuous operations.

C. Coordinate shift changes so monitoring, construction observation, flagging, emergency contacts, and responsibility are continuously maintained.

D. Do not leave an excavation or incomplete installation unattended unless it has been secured in accordance with the approved plans and UPRR has authorized suspension of continuous operations.

3.08 EXCAVATION AND RAILROAD PROTECTION

A. Perform excavation only within the limits and sequence shown on the UPRR-approved plans.

B. Cover, guard, or otherwise protect excavations, holes, and trenches in accordance with the UPRR-approved plans, applicable UPRR guidelines, and OSHA and FRA requirements.

C. Provide temporary lighting when required to identify hazards to train crews and railroad personnel. Direct lighting so it does not interfere with railroad operations.

21ST STREET NORTH – MOSLEY TO I-135, PHASE 2 110-8

448-2021-002927

D. Control groundwater, surface water, drilling fluids, spoil, and ground loss. Do not contaminate or undermine railroad ballast, subballast, embankment, drainage facilities, utilities, signals, or communications.

E. Remove excavated soil and waste from UPRR right-of-way and dispose of it in accordance with applicable requirements, unless the approved plans expressly allow another disposition.

F. Immediately report damage or suspected damage to railroad track, ballast, signal equipment, utilities, structures, drainage, or other facilities.

3.09 WATER LINE INSTALLATION AND CONNECTION

A. Construct the Line 5 Water Line Improvements in accordance with the approved Contract Documents, executed UPRR agreement, UPRR approvals, and accepted contractor-prepared permit submittals.

B. After Written Authorization to Proceed and before making the water-line connection or beginning abandonment, expose and verify the location, elevation, size, material, and condition of the existing water line as necessary to complete the work. Perform verification in accordance with the UPRR-approved plans and applicable access, observation, flagging, and monitoring requirements. Protect the existing water line until the approved connection and abandonment sequence is complete.

C. Perform the work in the presence of RailPros and UPRR flagging personnel when required.

Provide access for construction observation and promptly correct nonconforming work.

D. Coordinate shutdowns, service interruptions, testing, disinfection, connection, and restoration with the City and affected parties.

3.10 EXISTING WATER-LINE ABANDONMENT

A. Base the Contract Price, schedule, and construction sequence on abandonment in place of the existing 8-inch water main crossing UPRR right-of-way. Fill the abandoned main with CLSM in accordance with the UPRR-approved plans, written UPRR authorization, and applicable UPRR requirements.

B. The City and Engineer of Record are requesting written UPRR authorization for abandonment in place and a project-specific exception to the hazardous-material testing requirements. Written Authorization to Proceed will not be issued until UPRR has approved abandonment in place of the existing water main and resolved associated testing requirements.

C. Plan the continuous Zone A operation so no hazardous-material testing or UPRR abandonment-in-place approval hold point occurs after sheet-pile installation or other continuous Line 5 Water Line Work begins.

D. Do not uncover, sample, or abandon the existing water main before Written Authorization to Proceed and before required shoring, monitoring, RailPros observation, and UPRR flagging are in place.

E. If UPRR does not approve abandonment in place as contemplated by the Contract Documents, or imposes additional testing or other requirements after the Bid Date that materially affect the Work, do not proceed with the affected work until the Engineer of Record provides written direction. Resulting changes will be administered in accordance with the Contract's change provisions.

F. Completely fill the water main authorized to remain in place, verify that no voids remain, and document the limits, method, quantity of fill, placement, and verification.

21ST STREET NORTH – MOSLEY TO I-135, PHASE 2 110-9

448-2021-002927

3.11 RECORDS, AS-BUILTS, AND RESTORATION

A. Maintain daily construction reports identifying work performed, staffing, equipment, RailPros and flagging attendance, train movements affecting the work, monitoring results, communications, inspections, incidents, and corrective actions.

B. Provide final monitoring logs, survey data, reports, CLSM and grout placement records, observation reports, photographs, written releases, and other documentation required by the approved plans or UPRR.

C. Survey and document the final location and elevation of the installed Line 5 Water Line facilities, abandoned facilities, shoring left in place when approved, and other features required for record drawings.

D. Restore UPRR right-of-way and adjacent property to the condition required by the approved plans, executed agreements, and property documents. Obtain acceptance before demobilization.

PART 4 MEASUREMENT AND PAYMENT

4.01 MEASUREMENT

A. Line 5 Water Line Improvements will be measured in accordance with the applicable water line and paving bid items included in the Proposal.

B. Temporary sheet pile shoring will be measured by the linear foot under the “Pile, Shoring” bid item.

C. Temporary safety handrail on top of the temporary sheet pile shoring will be measured by the linear foot under the “Handrail, Railroad” bid item.

D. Abandonment in place of the existing 8-inch water main within UPRR right-of-way will be measured by the linear foot under the “Pipe Abandon in Place, RR-ROW” bid item.

E. All other Contractor work required by this section will be measured on a lump-sum basis under the “RR Coordination” bid item.

4.02 PAYMENT

A. Payment for Line 5 Water Line Improvements will be made under the applicable water line and paving bid items identified in the Proposal.

B. Payment for temporary sheet pile shoring will be made at the Contract unit price per linear foot under the “Pile, Shoring” bid item.

C. Payment for temporary safety handrail will be made at the Contract unit price per linear foot under the “Handrail, Railroad” bid item.

D. Payment for abandonment in place of the existing 8-inch water main within UPRR right-of-way will be made at the Contract unit price per linear foot under the “Pipe Abandon in Place, RR-ROW” bid item. Payment shall constitute full compensation for filling the existing water main with CLSM, required materials, equipment, labor, placement, verification, documentation, and all other work necessary to complete the abandonment in place in accordance with the Contract Documents and UPRR requirements.

E. Payment for “RR Coordination” will be made on a lump-sum basis. This item shall constitute full compensation for all Contractor responsibilities and work required by this section that are not specifically included in the applicable water line, paving, “Pile, Shoring”, “Pipe Abandon in Place, RR-ROW” or “Handrail, Railroad” bid items. The “RR Coordination” bid item includes, but is not limited to, contractor-prepared railroad and permit-support submittals; Right-of-Entry requirements and coordination; ITS utility locating and potholing; excavation, exposure, identification, documentation, backfill, and restoration associated with potholing; required professional engineering services; construction-specific shoring information; track, ground, and shoring monitoring; contingency and emergency-

21ST STREET NORTH – MOSLEY TO I-135, PHASE 2 110-10

448-2021-002927 response planning and implementation; railroad coordination; scheduling; reporting;

recordkeeping; and responses or resubmittals attributable to Contractor-prepared information.

F. The “RR Coordination” bid item includes all costs associated with UPRR flagging, RailPros construction observation, UPRR and RailPros review fees, Right-of-Entry fees, and other third-party railroad charges required to complete the Work. No separate measurement or payment will be made for these costs.

G. UPRR requirements issued or revised after the Bid Date that materially change the Work will be administered in accordance with the Contract's change provisions, except when the change results from a Contractor deviation, incomplete submittal, or noncompliance.

END OF SECTION 110

MONITORING WELL CAPPING

21ST STREET NORTH – MOSLEY TO I-135, PHASE 2 205-1

472-2022-085792

SECTION 205 – MONITORING WELL CAPPING

PART 1 GENERAL

1.01 DESCRIPTION

A. Plug the types of wells as shown in the Contract Documents.

1.02 BID ITEMS

A. Monitoring Well Capped

PART 2 MATERIALS

A. Provide grouts for plugging wells that comply with these requirements:

1. Neat cement grout: a mixture of 94 pounds (1 sack) of portland cement and 5 to 6 gallons of water.

2. Cement grout: a mixture of 94 pounds (1 sack) of Portland cement, an equal quantity of fine sand (by weight), and 5 to 6 gallons of water.

3. Bentonite clay grout: a mixture of a commercial sodium bentonite clay and water.

a. Use high solids sodium bentonite clay. Mix the grout according to the manufacturer’s recommendations such that its weight is not less than 9.4 pounds per gallon of mixture. Use agents to increase the weight of the mixture according to the manufacturer’s recommendations.

b. Use sodium bentonite pellets or tablets, or granular sodium bentonite that complies with K.A.R. 28-30-2(k)(3).

c. Do not use sodium bentonite products that contain low solids.

d. Or other products that meet or exceed the K.A.R. 28-30-7 requirements.

PART 3 CONSTRUCTION REQUIREMENTS

A. Plugging Ground Water Monitoring Wells. Before plugging any water well, notify and comply with all regulations set by the Kansas Department of Health and Environment (KDHE). The Contractor / subcontractor plugging the water well(s) shall be a KDHE Licensed Water Well Contractor. Plug all wells according to K.A.R. 28-30-7 and any other applicable regulatory requirements. Perform all plugging procedures under the supervision of KDHE. The final plugging record (Form WWC-5P) shall be accepted and approved in writing by KDHE.

B. Advance Notice. Before plugging any well, the Contractor shall give City of Wichita Environmental Services a minimum of 48 hours advanced notice.

PART 4 MEASUREMENT AND PAYMENT

A. The Engineer will measure each plugged well.

B. Payment for “Monitoring Well Capped” at the contract unit prices is full compensation for the specified work.

END OF SECTION 205

\\vren XVei.i, 28-30-7 the basement floor shall be considered ground level.

(p) Ml drilling waters used during the con struction or reconstruction of any water well shall be initially cisinfected by’ mixing with the water enough sodium Inpochlorite to produce at least 100 milligrams per liter, mg/i, of available chlorine.

(q) Natural organic or nutrient producing ma terial shall not be used during the construction, reconstruction, or treatment of a well unless it is thoroughly’ flushed from the well and the ground water aquifer or aquifers before the well is coin pleted. Natural organic or nutrient producing ma terial shall not be added to a grout mix used to grout the well’s annular space.

(r) Pump mounting.

(1) All pumps installed directly’ over the well casing shall be so installed that an airtight and wa— tertight seal is made between the top of the well casing and the gear or pump head. pump foun dation or pump stand.

(2) W’hen the pump is not mounted directly’ over the well casing and the pump column pipe or pump suction pipe emerges from the top of the well casing. a sanitary well seal shall be installed between the pump column pipe or pump suction pipe and the well casing. An ththglit and water tight seal shall be provided for the cable conduit when submersible pumps are used.

(5) Cunstruction of sand point or well point wa ter wells. Sand point or well point water wells shall be constructed by drilling or boring a pilot hole to a minimum depth of three feet below ground sur face. The pilot hole shall be a minimum of three inches greater in diameter than the drive pipe or blank casing if the casing method is used. Sand point wells shall only be completed by using the casing method or the drive pipe method as de scribed in paragraphs (1) and (2) below or other methods as described in paragraph (3) below.

Sand point wells constructed prior to the effective date of this regulation shall not be required to meet these requirements. All sand point wells that are replaced. constructed, reconstructed or plugged after the effective date of this regulatim shall meet these regulations.

(1) Casing method. Approved. durable, water tight well casing shall be set from a mininuim of three feet below the ground surface to at least one foot above the ground surface. The casing shall be sealed between the casing and the pilot hole with approved grouting material from the bottom of the casing to ground surface. The drive pipe shall be considered the pump drop pipe. For under ground discharge completions, a ‘f’ joint shall be used. The drive pipe shall be capped with a solid cap at the “T” joint when the casing method is used. An approved sanitan’ well seal and a well vent shall be installed on the top of the well casing in accordance with K.A.R. 28-30-6 (0 and (k).

(2) Drive pipe method. Sand point wells may’ be installed without a casing for above ground dis charge completions only’. In such completions, the drive pipe shall terminate at least one foot above finished ground level. The annular space betxveen the drive pipe and the pilot hole shall be sealed with approved grouting material from the bottom of the pilot hole to ground surface. The top of the drive pipe shall be sealed airtight and watertight with a solid cap of the same material as the drive pipe. A well vent shall not be required for the drive pipe niethod.

(.3) Other methods. Other methods may’ be spedficall approved by the department on a case-by-case basis by using the appeal procedure in cluded in K.A.R. 28-30-9.

(4) Abandonment of sand point wells. Upon abandonment of a sand point well, the contractor or landowner shall either pull the drive pipe or leave it in place. If the drive pipe is left in place, the sand point well shall be plugged from the bot tom of the well to three feet below the ground surface with approved grouting material, The drive pipe well shall be cut off three feet below the ground surface and the remaining three foot deep hole shall be backfilled with surface soil.

If the drive pipe is completely pulled, the re maining hole shall be plugged with approved grouting material from the bottom of the remain ing hole to three feet below the ground surface.

The hole shall be backfilled with surface soil from 3 feet to ground surface. (Authorized by K.S.A.

1991 Supp. 82a-i205; impleuienting K.S.A. 82a- 1202, K.S.A. 1991 Supp. 82a-1205; effective, E 74-34, July 2, 1974; modified, L. 1975, ch. 481, May 1, 1975; amended May 1, 1980; amended May 1, 1983; amended May 1, 1987; amended June 21, 1993.)

28-30-7. Plugging of abandoned wells, cased and uncased test holes. (a) All water wells abandoned by the landowner on or after July 1, 1979, and all water wells that were abandoned prior to July 1, 1979 which pose a threat to groundwater supplies, shall be plugged or caused

28-30-7 KANSAS DEPT. OF HEALTH AND ENVIRONMENT

to be plugged by the landowner. In all cases, the landowner shall perform the following as mini mum requirements for plugging abandoned wells.

(1) The casing shall be cut off three feet below ground surface and removed.

(2) MI wells shall be plugged from bottom to top using volumes of material equaling at least the inside volume of the well.

(3) Plugging top of well:

(A) For cased wells a grout plug shall be placed from six to three feet below ground surface.

(B) For dug wells, the lining material shall be removed to at least five feet below ground surface, and then sealed at five feet with a minimum of six inches of concrete or other materials approved by the department. Compacted surface silts anrl clay’s shall be placed over the concrete seal to ground surface.

(4) Any’ groundwater displaced upward inside the well casing riuring the plugging operation shall be removed before additional plugging materials are added.

(5) From three feet below ground level to ground level, the plugged well shall be covered with compacted surface silts or clay’s.

(6) Compacted clays or grout shall be used to plug all wells from the static water level to six feet below surface.

(7) All sand and gravel used in plugging aban doned domestic or public water supply wells shall be chlorinated prior to placement into a well,

(b) Abandoned wells formerly producing groundwater from an unconfined aquifer shall be plugged in accordance with the foregoing and in addition shall have washed sand, and gravel or other material approved by the department placed from the bottom of the well to the static water level,

(e) Abandoned wells, fonnerly producing groundwater from confined and unconfined aq uifers or in confined aquifers only, shall be plugged according to K.A.R. 28-30-7(a) and by us ing one of the following additional procedures:

(1) The entire well column shall be filled with grout, or other material approved by’ the depart ment, by use of a grout tremie pipe.

(2) A 10 foot grout plug shall be placed oppo site the iinpen’ious formation or confining layer above each confined aquifer or aquifers by’ use of a grout treinie pipe; and

(A) The space between plugs shall be filled with clays. silts. sand and gravel or grout and shall be placed inside the well so as to prevent hndging.

(B) A grout plug at least 20 feet in length shall be placed with a grout pipe so at least 10 feet of the plug extends below the base of the well casing anrl at least 10 feet of the plug extends upwarrl inside the bottom of the well casing.

(C) A grout plug at least 10 feet in length shall be placed from at least 13 feet below ground level to the top of the cut…