4-AE-Fee-Schedule 08 01 26.pdf

PDF 901 KB Posted

Attached to
Architectural Design Services
Solicitation number
DB27-012-RFSQ
Issued by
Salt Lake County, Utah

About this file

This document is the Division of Facilities and Construction Management (DFCM) Architectural/Engineer Fee Guidelines for the State of Utah, effective August 1, 2026. These guidelines serve as the basis for negotiating reasonable and fair compensation for architectural, engineering, and surveyor professional services on State of Utah projects. The guidelines establish that while professional services selection must follow the State Procurement Code based on qualifications, fees are negotiated after selection is made. The document provides standardized fee schedules for both architectural and engineering projects, categorized by complexity levels (Schedules A through E for architectural projects; Schedules A through C for engineering projects) and organized by construction budget ranges. Additionally, separate fee guidelines are provided for three Building Performance consultants typically hired by DFCM: Energy Engineers, Building Envelope Commissioning Agents, and Building System Commissioning Agents, with typical combined fees ranging from 0.5 to 2 percent of the project construction budget.

The fee schedules represent maximum allowable fees for basic services on typical projects and serve as negotiation frameworks rather than fixed rates. Basic services encompass standard design work including architectural, structural, civil, mechanical, and electrical engineering services, site planning, and construction administration for single-phase projects. Projects may warrant fee adjustments based on complexity, specialized consultant requirements, and unique scope characteristics, with consultant and scope complexity fees not to exceed 0.75 percent without DFCM director or deputy director authorization. Direct and reimbursable costs such as printing and travel are reimbursed at 105 percent of actual cost, with travel from the servicing office location to the project site within 100 miles included in the basic fee. Renovation projects include an additional fee modifier ranging from 0.50 to 1.00 percent depending on complexity level. DFCM Project Managers must employ these guidelines during fee negotiations, and any exceptions require written approval from the DFCM director or designee.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DIVISION OF FACILITIES AND CONSTRUCTION MANAGEMENT

ARCHITECTURAL/ENGINEER FEE GUIDELINES

EFFECTIVE DATE: AUGUST 1, 2026

**THESE ARE GUIDELINES, NOT A SCHEDULE**.

I. Purpose To provide a guideline for a reasonable A/E fee structure on State of Utah projects. These guidelines are provided as a basis for negotiation to ensure fair compensation while maintaining fiscal responsibility.

II. Background The State Procurement Code requires that professional services for architects, engineers, and surveyors be selected by one of the processes in the Procurement Code, but that the initial selection is based on qualifications and not the fee. Once the selection is made by a lawful process, the fee can be considered and negotiated.

To ensure that reasonable and consistent fees are paid for awarded work, this document shall serve as the primary guideline and the basis for negotiation for determining such fees. This policy updates earlier standards to provide additional clarity for all parties involved in the negotiation process.

III. Policy DFCM Project Managers shall employ this guideline for the negotiation of

Architectural/Engineering/HPBS Consultant Fees. Any exception to this guideline can only be obtained by written approval of the DFCM director or the director’s designee.

IV. Procedures A. The fee should be established using these guidelines as a basis for negotiation, keeping the specific project size and complexity in mind.

B. An individual project may require fee adjustments due to complexity inherent in the project type, the specialized nature of required consultant services, or the unique scope of the project.

C. The fee schedules represent the guideline for the maximum allowable fee for basic services on a typical project. Fees for consultant complexity and scope complexity are not fixed;

rather, the fee schedules serve as a basis for negotiation on a case-by-case basis.

Complexity of consultant services requires a separate fee proposal for each individual firm.

D. Basic Services include the design work that is customary on a typical project to take an established building program, site, and budget, and then develop the architectural design, engineer the building systems, producing construction documents, and perform construction administration for a single-phase project. Basic Services include the design services customary on every project such as architectural, structural, civil, mechanical, and electrical engineering services.

Typically, there are also three additional consultants hired by DFCM to ensure the State’s

Building Performance standards are met: Energy Engineer (EnE), Building Envelope

Commissioning Agent (BECxA), and a Building System Commissioning Agent (CxA).

E. Basic Services for site on an Architectural Project shall be limited to the following: site planning including layout of site features, building position, preliminary grading, location of

Page 1/7DFCM A/E FEE GUIDELINES paving for walkways, driveways and parking, basic landscaping, and fencing locations. Also included are the normal connections required to service the building such as water, drainage, and sanitary systems, if applicable.

F. Renovation complexity modifier for renovation is intended for capital development projects only. The fee guideline for the consultants applies to all applicable capital development projects including renovations.

G. Not included in the basic services are amounts to cover direct and reimbursable costs such as printing and travel. These costs are reimbursed at 105% of actual cost; travel will be determined in accordance with state travel guidelines. Travel from the servicing office location to the site less than 100 miles is included in the basic fee.

H. The following process provides the guideline for calculating the initial fee proposal:

• Categorization: Determine if the project is Architectural or Engineering.

• Classification: Identify the appropriate complexity based on building type.

• Calculation: Locate the basic fee percentage using the proper budget range and complexity. Multiply the construction budget by this percentage to establish the fee guideline.

• Total Fee: The total fee is then determined by combining the basic fee with the negotiated fees for consultant complexity and scope complexity. These negotiated fees may not exceed 0.75% without DFCM director/deputy director authorization. These schedules are intended for development projects and provide the definitive basis for negotiation between the State and the selected firm.

I. Basic services will vary from project to project. For example, projects that don’t require a complete A/E team or projects that require a specific discipline to take on a higher percentage of the work would necessitate a revision of the percentage allocation.

J. The Building Performance consultants are hired directly by the building owner, often

DFCM, but occasionally another state agency such as a college or university. Typical total fee for the three consultants will equal between 0.5 – 2% of the project’s construction budget.

K. DFCM may elect to post a maximum allowable fee when soliciting for a project. When a maximum fee is posted any questions or concerns need to be addressed during the question period of the solicitation. If the fee is not adjusted by addendum, it is to be considered accepted.

Page 2/7DFCM A/E FEE GUIDELINES

SCHEDULE OF ARCHITECTURAL PROJECT COMPLEXITY

Schedule -A Schedule - B Schedule - C Schedule -D Schedule - E

Considerably less than average Complexity

Less than Average Complexity

Average Complexity More than average

Complexity Considerably more than average Complexity

Warehouses Student Housing Classroom Buildings Complex Classroom Bldgs. Scientific Research

Parking Structures Office Buildings General Teaching Spaces Libraries Medical Research

Garages Complex Parking

Structures Clinics Dining Facilities Engineering Research

Farm Structures Liquor Stores Gymnasia Theaters - no stage Hospitals

Residential Housing Visitor Centers Armories Arenas Museums

Capital Improvement Roofing Projects

Shop & Maintenance Facilities

Nursing Homes Auditoriums - no stage Mental Health Facilities

Tenant Improvement Projects

Care Facilities Medical Schools Prison Facilities

Athletic/Fitness Cntr. Specialty Schools Stadiums

Mixed-Use Housing Physically Disadvantaged Emergency Ops Center

Public Safety Admin. Adult or Youth Detention Fish Hatcheries

Laundry Court Facilities Veterinarian Facilities

Capital Improvement Projects

Performing Arts Auditorium - w/Stage

Elementary School Medical Clinics Theater - w/Stage

Skilled Nursing

Data Facilities

Recreation Facilities

Teaching Labs

Middle/Junior High

High School

Complexity of Scope Complexity of Consultant not included in the complexity of building type

Schedule Acceleration Historical Renovation Performance Consultants FF&E Design Branding

Seismic Upgrade LEED Certification

Complex Engineering Surveys Third Party Cost

Consultant

Complex Site Conditions Travel Geotechnical Surveys Acoustical Consultant

Photo-realistic Rendering Programming Specialty Consultants Traffic Consultant

Additional Energy Measures Master Planning Feasibility Study

Lab Consultants Third Party Schedule

Consultant

IT/AV Complex Landscape Kitchen Consultant

Consultant complexity and scope complexity classifications are intended for Development projects only. When a portion of the project scope exceeds the base building complexity classification, that specific scope may be isolated and used as a basis for negotiation to justify the inclusion of specialty consultants or additional fees. Any fee adjustments related to mixed-complexity scope are subject to final review and approval by DFCM.

Page 3/7DFCM A/E FEE GUIDELINES

STATE OF UTAH

ARCHITECTURAL PROJECT DESIGN FEE

GUIDELINE

**Complexity modifier for renovation is intended for Capital Development Projects only.

Construction Budget Schedule A Schedule B Schedule C Schedule D Schedule E $49,999 and below 9.90% 10.49% 11.09% 11.68% 12.38% $50,000 to $99,999 9.41% 10.00% 10.59% 11.19% 11.88% $100,000 to $149,999 9.11% 9.70% 10.30% 10.89% 11.58% $150,000 to $199,999 8.81% 9.41% 10.00% 10.59% 11.29% $200,000 to $299,999 8.51% 9.11% 9.70% 10.30% 10.99% $300,000 to $499,999 8.22% 8.81% 9.41% 10.00% 10.69% $500,000 to $749,999 7.92% 8.51% 9.11% 9.70% 10.40% $750,000 to $999,999 7.62% 8.22% 8.81% 9.41% 10.10% $1,000,000 to $1,499,999 7.33% 7.92% 8.51% 9.11% 9.80% $1,500,000 to $1,999,999 7.03% 7.62% 8.22% 8.81% 9.50% $2,000,000 to $2,999,999 6.73% 7.33% 7.92% 8.51% 9.21% $3,000,000 to $3,999,999 6.53% 7.13% 7.72% 8.32% 9.01% $4,000,000 to $4,999,999 6.34% 6.93% 7.52% 8.12% 8.81% $5,000,000 to $7,999,999 6.14% 6.73% 7.33% 7.92% 8.61% $8,000,000 to $11,999,999 5.94% 6.53% 7.13% 7.72% 8.42% $12,000,000 to $14,999,999 5.64% 6.14% 6.63% 7.13% 7.62% $15,000,000 to $19,999,999 5.45% 5.94% 6.44% 6.93% 7.43% $20,000,000 to $24,999,999 5.25% 5.74% 6.24% 6.73% 7.23% $25,000,000 to $29,999,999 5.15% 5.64% 6.14% 6.63% 7.13% $30,000,000 to $34,999,999 5.05% 5.54% 6.04% 6.53% 7.03% $35,000,000 to $39,999,999 4.95% 5.45% 5.94% 6.44% 6.93% $40,000,000 to $49,999,999 4.80% 5.30% 5.79% 6.29% 6.78% $50,000,000 to $99,999,999 4.50% 5.00% 5.60% 6.10% 6.60% $100,000,000 to $149,999,999 4.20% 4.70% 5.35% 5.85% 6.35% $150,000,000 to $199,999,999 3.95% 4.45% 5.15% 5.65% 6.15% $200,000,000 to $249,999,999 3.70% 4.20% 4.95% 5.45% 5.95% $250,000,000 to $299,999,999 3.50% 4.00% 4.80% 5.30% 5.80% $300,000,000 to $399,999,999 3.30% 3.80% 4.65% 5.15% 5.65% $400,000,000 to $499,999,999 2.95% 3.45% 4.45% 4.95% 5.45% $500,000,000 and above Negotiated Negotiated Negotiated Negotiated Negotiated For renovation projects add to percentage above for the portion that is renovation 0.50% 0.65% 0.75% 0.85% 1.00%

Page 4/7DFCM A/E FEE GUIDELINES

SYSTEMS COMMISSIONING FEE

GUIDELINE

** This fee included employing analytics on the BAS for the project and 1-2 years of continuous commissioning by the CxA.

STATE OF UTAH

ENVELOPE COMMISSIONING FEE

GUIDELINE

* The minimum fee for the BECxA on these projects will be $15k. If the percentage on the chart = less than $15k, $15k should be used on the CBE.

STATE OF UTAH

ENERGY ENGINEERING & BUILDING

SIMULATION FEE GUIDELINE

Construction Budget Schedule A Schedule B Schedule C Schedule D Schedule E** $19,999,999 and below 0.50% 0.75% 1.00% 1.25% 1.50%

$20,000,000 to $29,999,999 0.35% 0.59% 0.81% 1.03% 1.25%

$30,000,000 to $39,999,999 0.34% 0.56% 0.75% 0.94% 1.14%

$40,000,000 to $49,999,999 0.31% 0.52% 0.68% 0.85% 1.01%

$50,000,000 to $99,999,999 0.30% 0.49% 0.62% 0.76% 0.90%

$100,000,000 to $249,999,999 0.28% 0.46% 0.57% 0.67% 0.78% $250,000,000 to $499,999,999 0.27% 0.43% 0.51% 0.59% 0.67%

$500,000,000 and above Negotiated Negotiated Negotiated Negotiated Negotiated

Construction Budget Schedule A Schedule B* Schedule C Schedule D Schedule E $19,999,999 and below 10-20K 0.18% 0.23% 0.23% 0.25%

$20,000,000 to $29,999,999 10-20K 0.17% 0.20% 0.20% 0.24%

$30,000,000 to $39,999,999 10-20K 0.16% 0.19% 0.19% 0.23%

$40,000,000 to $49,999,999 10-20K 0.15% 0.17% 0.17% 0.22%

$50,000,000 to $99,999,999 Negotiated 0.14% 0.16% 0.16% 0.21%

$100,000,000 to $249,999,999 Negotiated 0.12% 0.14% 0.14% 0.20%

$250,000,000 to $499,999,999 Negotiated 0.10% 0.13% 0.13% 0.18%

$500,000,000 and above Negotiated Negotiated Negotiated Negotiated Negotiated

Construction Budget Schedule A Schedule B Schedule C Schedule D Schedule E $19,999,999 and below 5-10K 8-15K 0.10% 0.15% 0.22%

$20,000,000 to $29,999,999 5-10K 8-15K 0.09% 0.13% 0.19% $30,000,000 to $39,999,999 5-10K 8-15K 0.07% 0.11% 0.16% $40,000,000 to $49,999,999 5-10K 8-15K 0.06% 0.09% 0.13% $50,000,000 to $99,999,999 Negotiated Negotiated 0.05% 0.07% 0.09%

$100,000,000 to $249,999,999 Negotiated Negotiated 0.03% 0.05% 0.06% $250,000,000 to $499,999,999 Negotiated Negotiated 0.02% 0.03% 0.03%

$500,000,000 and above Negotiated Negotiated Negotiated Negotiated Negotiated

Page 5/7DFCM A/E FEE GUIDELINES

SCHEDULE OF ENGINEERING PROJECT COMPLEXITY

Schedule -A Schedule – B Schedule – C Below Average

Complexity Average

Complexity Above Average

Complexity Average Retaining Walls and Foundations

Average Parks, Marinas and Rec Areas Average Roads and Streets

Average Storm Drain & Sewage Collection Small Dams

Small Bridges Roofing Seismic Upgrade

Water Wells Water Tanks Pump Station

Lift Station

Complex Retaining Walls and Foundations Complex Parks, Marinas and Rec Areas

Complex Roads and Streets Complex Storm Drain & Sewage Collection

Large or Complex Small Dams Asymmetric Bridges

Airport with Complex terminal Facilities Capital Improvement Projects **

Sewage & Water Treatment Facilities * Average Telecom Facilities

Electrical & Data Transmission * Solid Waste Disposal

Average Acoustical Design Air Pollution Abatement, Control and Testing

Water Reservoirs Utility Tunnel

Unusual Foundations with Complex Soils Complex Acoustical Design

Complex Mechanical and Electrical Controls * Storm Drain & Sewers – Heavily Urbanized Area

Complex Large Dams Extremely Complex Bridges

Complex Sewage & Water Treatment Facilities * Complex Telecom Facilities *

Complex Utility Tunnels

Complexity of Scope Complexity of Consultant Commissioning Programming Site Surveys

Schedule Acceleration Master Planning Geotechnical Surveys Complex Site Conditions Feasibility Studies Arc/Fault Current Study

Observation and Inspection Specialty Consultants Seismic Upgrade

These are examples of additional services that are not included in the complexity of schedules A-C. These services will be negotiated singularly and shall require a separate fee proposal. Complexity of consultant and complexity of scope is intended for Development projects only.

*These types of projects would need systems commissioning (CxA).

**These projects could potentially need either systems or building envelope commissioning services depending on the project.

Page 6/7DFCM A/E FEE GUIDELINES

ENGINEERING PROJECT DESIGN FEE SCHEDULE

Construction Budget Schedule A Schedule B Schedule C $49,999 and below 11.88% 12.87% 13.86% $50,000 to $99,999 10.89% 11.88% 12.87%

$100,000 to $149,999 10.40% 11.39% 12.38% $150,000 to $199,999 9.90% 10.89% 11.88% $200,000 to $299,999 9.41% 10.40% 11.39% $300,000 to $499,999 8.91% 9.90% 10.89% $500,000 to $749,999 8.42% 8.91% 9.60% $750,000 to $999,999 7.92% 8.42% 9.11%

$1,000,000 to $1,499,999 7.52% 8.02% 8.71% $1,500,000 to $1,999,999 7.13% 7.62% 8.32% $2,000,000 to $2,999,999 6.93% 7.43% 8.12% $3,000,000 to $3,999,999 6.73% 7.23% 7.92% $4,000,000 to $4,999,999 6.53% 7.03% 7.72% $5,000,000 to $6,999,999 6.34% 6.83% 7.52%

$7,000,000 to $11,999,999 6.14% 6.63% 7.33% $12,000,000 to $14,999,999 5.94% 6.44% 7.13% $15,000,000 to $19,999,999 5.94% 6.44% 7.13% $20,000,000 to $24,999,999 5.84% 6.34% 7.03% $25,000,000 to $29,999,999 5.84% 6.34% 7.03% $30,000,000 to $34,999,999 5.74% 6.24% 6.93% $35,000,000 to $39,999,999 5.74% 6.24% 6.93% $40,000,000 to $49,999,999 5.50% 6.00% 6.75% $50,000,000 to $99,999,999 5.25% 5.75% 6.50%

$100,000,000 to $149,999,999 5.00% 5.50% 6.25% $150,000,000 to $199,999,999 4.70% 5.20% 5.95% $200,000,000 to $249,999,999 4.40% 4.90% 5.65% $250,000,000 to $299,999,999 4.10% 4.60% 5.35% $300,000,000 to $399,999,999 3.80% 4.30% 5.05% $400,000,000 to $499,999,999 3.50% 4.00% 4.75%

$500,000,000 and above Negotiated Negotiated Negotiated

Page 7/7DFCM A/E FEE GUIDELINES

DIVISION OF FACILITIES AND CONSTRUCTION MANAGEMENT
ARCHITECTURAL/ENGINEER FEE GUIDELINES
I. Purpose
II. Background
III. Policy
IV. Procedures
SCHEDULE OF ARCHITECTURAL PROJECT COMPLEXITY
SCHEDULE OF ENGINEERING PROJECT COMPLEXITY

File details come from the government source that posted it. Updated .