This document is a Program of Requirements (POR) prepared by the Texas Juvenile Justice Department (TJJD) for a new facility designed to house violent and aggressive youth. The project involves constructing a 104-bed mental health facility with comprehensive infrastructure to address challenges in existing juvenile justice facilities, including staffing shortages and the need for specialized mental health treatment. The facility will be located in one of two potential sites: southeastern Dallas-Fort Worth area or northwestern Houston area, spanning approximately 30 acres. The new build aims to improve treatment outcomes by providing a secure, therapeutic environment with specialized spaces including a Regulation Safety Unit, education and vocational areas, recreational spaces, residential housing units, health infirmary, and support services.
The facility design emphasizes security, mental health intervention, and rehabilitative programming. Key design features include thirteen housing clusters with eight youths per unit, each with dedicated day rooms, dining areas, and support spaces. The project will incorporate advanced technological and architectural elements such as electronic access control, tamper-resistant fixtures, three-level lighting dimming, and spaces designed for intensive observation and behavioral intervention. The facility will include specialized areas like a multi-purpose Regulation Safety Unit for youth requiring intensive monitoring, education spaces with virtual reality and GED capabilities, and recreational areas with fitness trails and merit-based activity zones. The total estimated gross building area is 124,979 square feet, with a projected distribution across functional areas including administration, health services, education, residential housing, and building support services.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Texas Juvenile Justice Department New Build for Violent and Aggressive Youth
Program of Requirements
Final Document
12/16/2024
Distribution for CMAR and CxA Solicitations
1/31/25
Attachment F-2
TJJD New Build for Violent and Aggressive Youth POR
P a g e | 2
Intentionally Blank Page
P a g e | 3
TABLE OF CONTENTS
A.Executive Summary
A.1 Current TJJD Challenges
A.2 Project Purpose
A.3 Project Description and Scope
B.Facility Programming Process
C. Guiding Principles and Concepts
D.Building Occupancy
E.Design Parameters
E.1 Site Selection
E.2 Civil and Site Requirements
E.3 Architectural Design
E.4 Structural Design
E.5 Mechanical Systems
E.6 Electrical Systems
E.7 Plumbing Systems
E.8 Technology
F.Space Needs
F.1 Building Summary
F.2 Gatehouse and OIG Investigations
F.3 Parole Offices
F.4 Administration and Training
F.5 Public Areas
F.6 Regulation Safety Unit and Control Room
F.7 Education/Vocation/Recreation
F.8 Residential Food Services
F.9 Health Infirmary and Mental Health Providers
F.10 Residential Housing
F.11 Building Services
G. Space Criteria Sheets
P a g e | 4
Acknowledgements
Thanks and recognition to all of those that contributed to this planning process. This includes Executive
Leadership, vested stakeholders, and service line users groups. Any successful planning effort requires input from the diverse occupants and users of the facility to derive a holistic vision of the facility needs.
Kitchell Project Leaders Seth Ackland, Project Executive Cameron Glass, Director of Justice Katherine Kraai, Project Manager
Broaddus Planning Greg Hughes, Executive Manager Denise Davis, Facility Programmer Paul Chastant, Subject Matter Expert Jacque Judy, Cost Estimator
Contributors Chief Daniel Guajardo - OIG Deputy Chief Kevin Dubose - OIG Dr. Lepore – Medical Skylar Lott – Recreation Russell Biehle – Kitchen Tim Pickerill – Central Warehouse
TJJD Executive Committee Shandra Carter, Executive Director Sean Grove, Deputy Executive Director Rachel Gandy, Chief of Staff Emily Anderson, Deputy Executive Director - Finance and Support Operations Alan Michel, Director of Secure Facilities Evan Norton, Director of Integrated Treatment and Intervention Chris Ellison, Director of Training Daniel Guajardo, Chief Inspector General Zachary Valdez, Director of Construction
TJJD Support Staff Stormie Railsback
TFC Project Leaders William McKerall, Deputy Executive Director Amanda Cambre, Project Manager Jon Conant, Director, Real Estate Acquisition & Development
P a g e | 5
A. EXECUTIVE SUMMARY
P a g e | 6
A.1 Current TJJD Challenges The current TJJD state operated facilities are experiencing challenges ranging from outdated or inadequate facilities, demand peaks, and staff shortages. The most significant issue is recruiting and retaining existing staff to manage and operate facilities. Historically state juvenile justice facilities have been in rural, sparsely populated areas, with a small staffing market. These decisions to locate away from city centers have led to staffing shortages upwards of 50%, compromising facility operations and safety.
A.2 Project Purpose
To address staffing shortages and improve treatment outcomes, TJJD is building two new facilities. This facility will house 104 youth in a secure, therapeutic environment to improve the mental health the juvenile population.
A.3 Project Description and Scope This document details the needs of a new building for juveniles with mental health issues. The functional areas include:
• Security control areas at the gatehouse and Regulation Safety Unit;
• Administration and training for staff support;
• Juvenile support areas for public visitation, educational, vocational, recreational, health, food services, residential housing; and
• Building services for maintenance and warehousing needs.
Features that are unique to this facility include:
• Food delivery at the housing units rather than a central dining room;
• A Regulation Safety Unit designed to remove juveniles from the housing units for more intensive observation, address behavioral, or mental health crisis issues; and
• Recreational amenities tailored to the population with the objective to reduce conflicts, and provide more opportunities for merit-based activities.
SITE NEGOTIATIONS are in progress. Please focus on (2) Sites - One in SE DFW Area and One in NW Houston Area. Site usable area is approximately 30 Acres. The Selected AE firm will get all site information obtained to date including due diligence that is being done.
P a g e | 7
B. FACILITY PROGRAMMING PROCESS
P a g e | 8
A proven facility programming process was used to ensure that the facility's design aligns with operational needs, budget constraints, and stakeholder priorities.
1. INITIATION AND DATA GATHERING
The project began with validating the scope, confirming budget and schedule parameters, and forming the steering committee. Data gathering includes site visits to other facilities, stakeholder questionnaires, and interviews. Key data resources such as the TFC space guidelines informed the space programming.
2. ANALYSIS
The preliminary programming and space needs projections are based on the data gathered and stakeholder input, staff projections, and changes in programs. The analysis includes review of the pros and cons of recent juvenile justice facilities visited in Salt Lake City and San Diego. Key takeaways from these site visits was the integration of exterior space and dining areas into the housing units, ideas for incentive and recreational programs, and operational efficiencies such as the need for an integrated security access controls. With input from the steering committee, we developed the preliminary goals, facts, conceptual ideas and programmatic needs. This analysis was the foundation for the next phase of the project, the Visioning Synthesis.
P a g e | 9
3. VISIONING SYNTHESIS
Visioning synthesis is achieved through workshops where final goals are set, final conceptual ideas are generated, methods are developed to control the project scope and project priorities are established. This is the phase in the process for "critical thinking”. Using the information produced in the previous phases, and with a great deal of input from stakeholders, we start to ask “what if…” and “how about…” to generate project goals and concepts. At the same time, we will explore different options for shared or combined space, explore how space can be used more efficiently, and balance these against programmatic needs. It is the planning team’s responsibility to develop a space program that balances the budget with the stated needs.
4. PROJECT DEVELOPMENT
Next, Broaddus Planning’s approach to complex facility planning projects is to finalize the goals, concepts, facts and needs developed through the previous phases. Once the project direction is confirmed, we continue to evaluate the conceptual ideas that were generated during the workshops. We evaluated innovative concepts against practical constraints, such as budget and operational requirements. The culmination of this phase is the vetting of space requirements, the development of a detailed conceptual cost estimates and the finalization of guiding principles.
5. REFINEMENT AND DOCUMENTATION
Now, with a defined direction and a preferred conceptual direction, a draft facility program or “Basis of Design” document is developed for review and comment. The draft programming document has finalized goals, concepts, facts, needs, project schedule, room criteria, and conceptual relationship or work flow diagrams. The more detailed conceptual cost estimate is included for further review. Final comments are incorporated into the document and the final document is issued.
The process resulted in a detailed space program, guiding principles, a conceptual cost estimate, and a draft facility program document for review.
P a g e | 10
C. GUIDING PRINCIPLES AND CONCEPTS
P a g e | 11
The following guiding principles were developed during discussions with TJJD personnel.
Form
• The building will be organized around a central outdoor recreational area with access from the housing units
• A smaller courtyard for recreational space will be provided between housing units with access directly from the units to provide natural light and more recreational opportunities
• The building will primarily be one story, with administration offices located within the secure area, potentially on an upper level if required
• A campus layout can be considered for the mental health facility but must have full visibility to all areas of the secured compound
Function Site Organization
• Visitor parking and access to the building will not be visible from the youth occupied space to eliminate potential problems
• Vehicular circulation will be zoned for visitor access, staff access, and secured youth transportation
• Sally ports should not be visible from visitor parking areas or entrance into the facility for enhance security and maintain the facility's professional appearance
• Provide a separate road for deliveries outside of the secured area for easier access to the warehouse
Entry Organization
• A single building entry will be used for both staff and visitors
• A screening process will be used prior to entry into the secured area by staff and visitors
• Visitors will have very limited access to the facility to include the visitor lobby and visitation center only
Housing Unit Organization
• Sleeping rooms will be organized in thirteen housing units with a central day room
• Staff offices will be located off the day room with visibility to all spaces within the unit
• Preparation kitchen will be centralized with food service delivery to each housing unit
• A space for food serving, drug distribution, and staff breakroom will be adjacent to the youth dining area.
The space will have a distribution window; nurse will not have any other contact with youth; ideally, access to the this room will be from an access-controlled corridor separate from the main corridors used by youth.
• The dining area will be accessible from two different housing units and sized for 8 youths requiring two sittings
• Sleeping rooms will have detention grade bed, shelves, desk, and combo sink and toilet; toilets and sinks will be accessible from a shared chase outside of the housing units
• All access to the housing units will be electronically controlled
• A green space will be accessible from the day room to provide natural light and recreational opportunities
• Youth shower access will be monitored by staff and have shower curtains that are anti-ligature and visibility panels above and below a privacy panel for staff observation
P a g e | 12
Intake and Transport and Release Organization
• Transport will be into/from the facility through the Regulation Safety Unit through secured, interlocked doors at the sally ports
Economy
• Economy address issues relating to building maintenance, materials, efficiencies, etc.
Time
• Time relates to project schedules
P a g e | 13
D. BUILDING OCCUPANCY
P a g e | 14
D. Building Occupancy
The building occupancy was determined through input from TJJD staff. The numbers for youth, staff and visitors are used to determine the need and size of spaces. Staffing will be in shifts, so discussions with TJJD staff resulted in requirements for space for each shift.
Youth Population The youth population for the New Build Mental Health facility is 104 divided into groups of eight in the housing units. This population will be transfers from existing TJJD facilities.
Staff Population The total staff is estimated at 404. The staff will fill shifts that cover the facility full time, seven days a week, 24-hours per day.
Visitors The number of visitors to the facility can vary depending on visitation days and times. A total of 30 visitors was used to calculate the area requirements of the visitation center. Additional visitors to the facility will be to the Administration, OIG, and Parole offices.
Notes: Staffing numbers were provided by the following individuals:
1. Gatehouse and OIG figures provided by OIG
2. Direct Care, Treatment Administration, Administration numbers provided by Deputy Executive Director -
Finance and Support Operations
3. Education/Vocation/Recreation figures provided by the Director of Secure Facilities
4. Food Service staff provided by Russell Biehle
5. Maintenance staff figures provided by Director of Construction
Staffing
Area Staff
Gatehouse OIG 8
OIG Investigations 7
Direct Care 284
Treatment Administration 13
Administration 31
Education/Vocational 21
(Core Teachers/Elective Teachers) 14
Recreation 8
Food Services 10
Maintenance 8
Total Staff 404
P a g e | 15
E. DESIGN PARAMETERS
P a g e | 18
E.2 Civil and Site Requirements
Site Investigations:
Since a site has not been determined for the proposed development it is difficult to access the site’s needs from a drainage, water quality, and flood plain perspective. Civil requirements will be subject to the site selected for this new building. Due diligence on the sites selected is being completed by a third party company. The studies should be consulted when developing the site. The construction cost estimate assumes a green field site with cut and fill balance and compactable soil.
Any improvements will need to adhere to the governing jurisdiction’s detention and water quality requirements.
Typically, increases to the existing impervious coverage of a site, may trigger detention requirements. Water quality may be a requirement due to the nature of program’s use. Once a site has been determined, further drainage, detention, and water quality analysis will be required in order to properly determine the program’s requirements.
Site Security
The building as envisioned will be the first line of security with a perimeter fence as the secondary line of security. The site will be zoned for site security with the visitor parking outside of the secured area. The secured area will start at the building entrance with a perimeter fence consistent with juvenile justice facilities and access gates for a loop road for deliveries and access to staff parking. The perimeter fencing will have sensors that monitor tampering tied to the control room in the gatehouse. The site will be secured with perimeter fencing and electronic gate access, with call button and card reader.
Vehicular Access
All driveway locations must comply with the governing jurisdiction’s driveway spacing and design requirements.
In addition, all driveway’s will need to meet minimum fire access requirements. A separate drive for staff/visitors and deliveries is recommend.
Pedestrian Access On-site pedestrian access will be from the parking areas to the central security controlled entry into the building. All staff and visitors will be required to enter through this entry.
Parking Requirements Parking numbers are based on the estimated number of staff and visitors; the number of spaces for ADA compliance and electric vehicles will need to be verified with the governing jurisdiction. Current numbers of spaces shown in the diagrams are 200 for staff and 50 for visitors.
Parking lot trees/landscape: islands to be located within certain distance within all parking spaces, with trees as required in parking lot islands. Size of the parking lot islands and distance of trees to parking spaces to be determined by jurisdiction requirements. If parking lot trees are not outlined in jurisdiction requirements, all parking spaces are to be located within 50’-0” of a tree.
Stormwater:
The due diligence reports will address the needs for stormwater requirements based on the jurisdiction of the site.
P a g e | 19
Floodplain The due diligence reports will address the needs for floodplain requirements based on the governing jurisdiction of the site.
Availability and Location of Utilities The selected site will have to have water and wastewater services. Specific capacities and tie in locations will be required to be verified during the site due diligence step in the development process. A comprehensive water and sewer study may be necessary to assess the existing water and/or sanitary sewer system and determine whether additional public improvements are necessary.
Platting and Zoning The proposed site must be properly entitled to allow the proposed use. The site must be considered a legal lot in order to be allowed to have water and wastewater services. This may be achieved either by being located within an approved subdivision or through some type of platting exemption process. All platting activities will be regulated by the governing jurisdiction in which the site is located in.
Landscape and Tree Selection
The landscape material and tree requirements shall comply with the area’s jurisdiction. The governing jurisdiction will determine the species and minimum caliper of trees, shrubs, and groundcover.
All existing trees on the selected site shall be surveyed and identified on plans. If tree removal is necessary, this mitigation shall meet the jurisdiction requirements.
Material is to be drought tolerant and low water requirements, prioritizing native species when possible.
Additionally, low maintenance design and plant species are desired by the client.
Trees are not recommended in outdoor areas used by the youth and must not hinder sight-lines at the perimeter of the building or from the gatehouse to visitor parking area.
Screening/Buffering
Screening and buffering will be defined by the governing jurisdiction. Screening may be required at detention ponds, adjacent land uses, loading docks, utilities, mechanical equipment, trash encloser, etc.
Screening of the parking lot may also be required.
Screening will be required at the Sallyport to ensure there is no visibility from the visitor parking area. The sallyport will be within the secured area.
Irrigation Requirements
All new planting areas to be irrigated and scheduled by a central controller. The controller will have multiple cycle start capacity and will be equipped with a rain and freeze sensor shut-off device. All sprinkler head spacing will be designed for head-to-head coverage and minimize overspray and runoff.
The following component will be utilized, unless directed otherwise by client/owner:
•Drip irrigation to be used in all shrub beds.
•Spray irrigation to be used for turf areas.
•Two bubblers to be used for each new tree.
•If irrigation is not required by jurisdiction and not desired by client, new plant material is to be temporarily
P a g e | 20 irrigated to establish and ensure success.
Site Lighting
Site lighting will be provided at staff and visitor parking lots and pathway lighting.
Site Recreation Amenities
Within the secured compound courtyard provide a walking trail with fitness stations, playing field and running track.
Other recreational amenities may include basketball and hand ball courts.
Site Furnishings
Site furnishings such as trash receptacles, bench, and/or tables may be considered for the interior courtyard if approved by the client.
P a g e | 21
E.3 Architectural Design
The selected Project A/E will be responsible for the project design as required for this project. This Program of
Requirements (POR) document is therefore intended to establish basic design criteria. This POR does not include all User requirements that may be identified in the project during the design process. Further, it is to be used in conjunction with the Texas Facilities Commission and the Texas Juvenile Justice Department requirements. The project team will review and become familiar with the criteria and design related data provided in this POR. The team shall make additional professional evaluations of design problems and issues related to this project, analyze the advantages and disadvantages of each, evaluate, and recommend solutions to issues during the design process. Adherence to the project schedule and budget as defined in this POR are fundamental parameters to achieve in the project implementation.
It is expected that the Project A/E will utilize sound architectural and engineering principles to establish the most functional, economical, and efficient use of space, materials, the site, and construction methods to provide the requested facilities and align with budget during the design phases. The current space program is consistent with the client requests. As the project is designed, a goal of the project will be to provide an efficient design that meets client needs with the potential to reduce the size of the facility.
Building Configuration
The Project A/E is charged with the responsibility of establishing the final building configuration, massing, and layout to achieve the design objectives provided within the POR. Position of the building and site elements need to achieve the access, security, and flow requirements for the site while taking into consideration site conditions.
The building has been envisioned as a single structure with a large interior courtyard for youth recreational purposes. The secured perimeter of the building would serve as the first line of security with a perimeter site fence as a secondary line of security. Other options for a campus layout for would be considered for the Mental
Health Youth facility. Clear sightlines to all areas of the secured area must be maintained.
The choice of building materials should be commiserate with a secured environment. To be considered, both interior and exterior, masonry construction with concrete tilt-up perimeter walls and masonry interior walls in the secured areas. The image of the facility should be less institutional and strive to meet an environment with ample natural light and calming color palette. Areas with hardened surfaces like the day room in the housing units, should have acoustical panels to reduce sound.
P a g e | 22
Building Security
Building security should meet juvenile justice regulations with a high security level.
Surveillance cameras will be mounted to the building to monitor the building perimeter and associated building approaches and site perimeter and security access gates. Surveillance cameras will be required to cover all areas of the interior of the building that is accessible by youth including but not limited to the visitation center, regulation safety unit, education and recreational areas, housing units, all youth sallyports, and main corridors.
E.4 Structural Design
The preference construction type is load bearing concrete masonry or tilt wall concrete for perimeter wall system with steel frame columns and roof structure.
Roof structure will need to provide positive slope and not allow ponding for potential leaks into building requiring a parapet to visually shield the roof. The housing units will not have roof penetrations, mechanical shall be provided from grade mounted units to a ceiling chase for distribution.
Foundation and slab will be designed for soil and load conditions to be determined during design.
P a g e | 23
E.5 Mechanical Systems
Heating, Ventilation and Air Condition Systems
The A/E shall provide completed design and engineering for permits, materials, installation, start-up, testing, adjusting, and balancing to achieve fully operational HVAC systems for a juvenile justice facility in Texas. The system design must meet the highest standards of quality, durability, and maintainability, suitable for a Class A, owner-occupied institutional facility, and must comply with the Texas Mechanical Code, International
Mechanical Code (IMC), Texas Department of Juvenile Justice Standards, and International Energy Conservation
Code (IECC).
The design must incorporate proven technologies and equipment, emphasizing energy efficiency, reliability, and safety. The project shall consider sustainable design principles to ensure energy conservation and environmental responsibility. The HVAC system must balance occupant comfort, ease of maintenance, and long-term system longevity while meeting the energy reduction requirements outlined in the project specifications.
All work shall be performed in accordance with Division 23 of the CSI MasterFormat, covering all aspects of
HVAC systems, and must be compliant with local and state regulations to ensure optimal system performance for the unique needs of a juvenile justice facility in Texas.
IT/ Radio Room HVAC Systems
A self-contained, redundant HVAC system is required for the IT/radio rooms. This system should be sized for heat load, and be as compact as possible. Effort should be made to locate units above ceiling or outside of actual
IT/radio room spaces. No condensation lines should be run above the equipment spaces. Systems shall be designed in accordance with current applicable codes, standards and authorities having jurisdiction. All materials and workmanship to be first class as required for a complete HVAC system. Ventilation system should be designed to meet heat loads. Passive system may not meet the need for air circulation.
Life Cycle Cost Analysis
The engineer shall provide a Life Cycle Cost Analysis of the proposed systems.
Local HVAC or Central Energy Plant
The A/E team will determine the most economical system while considering maintenance, access to the system without entering the secured area, replacement of systems and life-cycle costs, and the availability of parts. The systems would include roof-top units, ground-mounted units or a central plant.
Systems will be sized appropriately to serve their intended zones within individual buildings (i.e. housing units, offices, control rooms, etc.). Each building shall have specialized conditioned air distribution systems. The housing units may have multiple units, which serve the sleeping areas, day room, offices, dining room, and group rooms. General exhaust fans will be sized for serving all spaces requiring air to be exhausted to the outside by code.
P a g e | 24
The Medical Infirmary will have both negative and positive pressure rooms. The dental and infirmary areas should isolated from each other having their own independent systems.
An energy management control system comprised of intelligent control panels connected via a communications network shall be provided for the mechanical equipment control serving this building. The system is to be set up to be controlled with laptop access and a desktop computer station in the Facility Services building’s
Maintenance Office.
Air Distribution
Ductwork shall be mounted above the ceiling and shall be compatible with the structural design of the interior space. Main trunk duct runs shall be rigid. No ductwork shall be accessible to youths. The ducts shall be designed as low pressure galvanized ductwork in accordance with the current editions of the SMACNA Low Pressure Duct
Construction Standards and ASHRAE Handbooks refer to specification Division 23. Provide duct material, gages, reinforcing, and sealing for required operating pressures. Exhaust ducts from showers and other wet areas shall be aluminum and sloped back towards the area served. All grilles in ductwork and in exhaust systems in youth areas shall be durable and flush-mounted to provide for anti-ligature grills.
HVAC Zoning
Provide separate zone controls for housing areas, conference rooms, health care spaces, waiting rooms and all other areas as required by code. Heating zones shall be determined based on exposure and amount of calculated heat loss.
Temperature Control /Energy Managements System
The building automation system shall be capable of providing information for maintenance, scheduling, and troubleshooting and be capable of controlling and managing the sequence and operation of the mechanical systems. A complete digital control system shall provide temperature controls, hours of operation, VAV and CAV box control, damper control and operational management for all HVAC systems such as air handlers, split system air conditioning units, and exhaust systems.
All connected mechanical systems must be non-proprietary communication programming language and be fully integrated into the BAC/BMS system for all functional aspects of the process as well as diagnostics and trending.
Points or aspects to be trended will be programmed and commissioned before occupancy.
P a g e | 25
E.6 Electrical Systems
The A/E shall provide complete design and engineering documents to obtain permits, provide installation, start-up, testing, adjusting and prepare facilities for commissioning for complete and operational electrical systems in compliance with applicable codes.-Also, incorporate sustainable design that demonstrates energy efficiency, reduces lighting power density for illumination, and provides opportunities for alternative sustainable power and/or reducing electrical demand on the public power grid.
The engineer shall provide detailed calculations for all systems the equipment and systems in order to confirm equipment and systems final sizes, capacity, and ratings. Provide electrical energy calculations that demonstrate performance that are more efficient than the median comparable benchmarked facility types using Energy Star
Portfolio Manager or other database for determining energy intensity for juvenile justice facilities.
Emergency Power
A dedicated emergency generator powered by natural gas or diesel engine Generator Set (GENSET) shall be provided for emergency operations of the facility. GENSET shall be pad-mounted in a location outside the secure perimeter and shall be located such that future additional generators and tanks may be added. The location for generator and ATS’s shall be sized at no less than 300% for future growth. A weatherproof and sound attenuated (65 db) enclosure shall be provided.
The generator should be sized to provide for continuous operation of all services for 100% of the facility for a minimum of 72 hours. Load for generator and ATSs shall be sized at no less than 125% of the total connected load plus 25% future / spare capacity. If a diesel engine generator set is provided, a skid-mounted fuel oil tank will be required.
Provide emergency power feeder from the generator breaker via Automatic Transfer Switches (ATS) for priority and emergency power to the facility emergency and priority distribution switchboards located in the main electrical room.
The A/E shall be responsible for coordinating with the local air quality management district to address all requirements needed for permits for installation, testing, and operation of the generator. Provide generator load calculation to coordinate with the fire pumps and showing the generator is sufficiently sized to start the fire pumps under emergency power conditions. Fire pumps shall be hard-wired directly to the emergency bus and generator load calculations shall be furnished to support worst case startup condition of the fire pump.
An emergency power plug shall be provided integral to the emergency power circuit to plug in a portable emergency generator for maintenance and/or power interruption event of the main generator fails.. A dedicated
UPS system shall be provided, sized to support all equipment in the Central Control for a minimum of 8 hours.
UPS location shall be accessible for life cycle replacement with dedicated HVAC and double door access.
A power monitoring annunciator panel shall be provided at the Central Control Room to indicate building normal and emergency power status, fuel level, and report building energy use. The annunciator shall sound a distinct chime to indicate faulty operation.
P a g e | 26
Electrical Distribution
A electrical distribution system, including all components, transformers, equipment, devices, fixtures, conduit, and cabling will be supplied for the project. Additionally, a fire alarm system will be installed, incorporating all components, equipment, devices, and wiring within conduit. This system must be fully integrated with a front-end control system, ensuring seamless communication with the programmed fire system control. The installation must comply with the manufacturer's specified version and licensing requirements to guarantee compatibility and proper functionality of the fire alarm system.
Low Voltage
The Fiber Optic and low voltage copper backbone for the facility Telecommunications, Communications and I.T.
Systems shall be terminated into the communications rooms and distributed to individual outlets in each space requiring services.
IT Wiring & Distribution
Provided complete system that includes all equipment, for installation, commissioning, training, and equipment warranty. The scope of the electrical work is to include OSP copper and fiber connectivity from the IT Hub, horizontal backbone provisions for communications, and other low voltage systems. Provisions include pathways and cable trays for copper and fiber cabling to be pulled, also empty conduits, junction boxes and outlet boxes for system wiring specified, designed and engineered by low-voltage systems consultants. Provisions are also to include all line-voltage power supplies and connections for the low-voltage systems equipment to the building power distribution and low voltage grounding system. Pathways and cable trays shall be designed in a manner that allows them to be expanded and connected to pathways in future facility buildouts.
Site Electrical Services
Provide BACNET smart metering capability for monitoring actual electricity use compared to the energy model predicted design demand. Typical for HVAC and lighting metering points including lighting panels, power distribution boards, motor control centers metering points to the building automation system.
Lighting
The building's lighting system shall be designed to meet the sustainable design for lighting and lighting controls including the latest State of Texas energy requirements. The A/E shall provide lighting energy connected load calculations including Lighting Power Density (LPD) and illumination photo metrics to demonstrate best sustainable design, lighting technologies, and energy conservation.
Provide alternative methods or technologies regarding exterior lighting and CCTV coordination, such as use of night vision technology, motion sensors, infrared low light level cameras, and full cutoff type fixtures in order to maximize night security surveillance while at the same time minimizing night sky illumination pollution.
P a g e | 27
Receptacles
In non-detention areas, one general purpose receptacle shall be provided per 8-10 linear feet of wall. In detention areas, one general purpose receptacle shall be provided per 40 linear feet of wall. Code minimum required 20 amp rated outlets shall be provided in all areas. Provide receptacles on rooftops and near mechanical equipment as required by code.
Provide additional receptacles for IT/radio services equipment cabinets. Receptacles shall include emergency source and non-emergency source power and an on-line type Static Uninterruptible Power Supply.
All hot conductors to convenience outlets located at youth rooms and pathways shall be remote controlled by a programmable lighting control panel with LAN based control by interactive touch screen display at the Central
Control Room.
Essential Electrical System
The facility shall have Essential Electrical System as required by current editions of CEC-and NFPA codes. Per the
CEC the Essential Electrical System shall be comprised of Emergency System and Equipment System. Emergency system shall include two branches, Life Safety Branch and Critical Branch. Provide three automatic transfer switches, one for each branch (life safety and critical) and one for equipment system. Loads shall be segregated as follows:
• Emergency System Life Safety Branch: Lighting, receptacles and equipment listed in CEC, egress path lighting and exit signs, fire alarm and life safety systems, fire water pumping equipment, alarm and alerting systems, communications systems, generator battery chargers for battery-powered lighting and receptacles, elevator cab lighting, control, communications and signal systems., All controlled doors, All security systems and electronics
• Emergency Critical Branch: Task illumination, fixed equipment, selected receptacles and special power circuits serving secure electronics and communications areas and functions including media room, staff offices, security control stations, intake/booking/releasing rooms, and fire life safety.
• Equipment System: Equipment, selected receptacles and special power circuits and functions per CEC.
Provide surge protection on the radio electrical panel/panels for both emergency and non-emergency power. Provide automatic transfer switches with a bypass isolation switch, for essential electrical system loads transfer to the standby emergency power source upon utility power failure. The automatic transfer switches (ATS’s) shall be located in the building main electrical room.
Lighting General
Sustainable design, including energy efficiency, shall be a prime consideration for all lighting applications consistent with security and operational requirements. Lamp and fixture types shall be selected to result in the highest efficiency consistent with the application. Daylighting shall be used where practical. Lighting controls shall switch off and/or dim the lighting where daylighting is available in staff offices and public areas.
Lighting in IT/radio rooms shall be placed so as to not interfere with rack placement, cable entrances, or ladder rack.
Lighting in areas of youth assembly, i.e., dayrooms, kitchens, secure corridors, etc., shall be equipped with
P a g e | 28 battery powered, instant on, emergency lighting systems that shall provide not less than three foot-candles lighting average throughout the space. Sleeping room lighting shall be controllable in either daylight mode or night mode, but not both at the same time and switchable for each sleeping room by lighting control panel at the Central Control Room.
Sleeping room Lighting Systems: The minimum lighting level for these areas shall be in conformance with code requirements.
All lighting locations and mounting methods must coordinate with CCTV Camera performance at the Central
Control Room.
Area lighting in non-secure areas shall be provided with lighting controls to meet the State of Texas energy efficiency standards including ultrasonic type occupancy sensors, programmable clock control time switches, photoelectric switches, lighting contactors. Where practical, daylighting and controls shall be provided for energy efficiency. Occupancy sensors shall be provided in the open office spaces, support rooms, storage, etc.
Lighting control for youth accessible areas shall be accomplished in conformance with the correction standards.
In general lighting these areas shall be controlled at the officer stations or control rooms responsible for managing and supervising the area. These controls may be on the security system touch screen. To prevent tampering and unauthorized access to devices, detention-grade fixtures should be used throughout the facility.
The mounting height of these fixtures will vary based on their location. In sleeping rooms, the goal is to have higher ceilings, ideally around 9 to 10 feet if feasible. In dayroom areas, where ceiling heights are significantly higher, the fixtures will be installed out of reach to enhance security and minimize the risk of tampering. Lighting in the dayroom and sleeping rooms should be dimmable to three levels.
Ceiling mounted lighting fixtures and lighting control devices shall not be installed above fixed tables and desks.
Coordinate furniture layout and reflected ceiling plans to allow for maintenance access to ceiling mounted fixtures.
Open office spaces shall utilize multi-wire circuitry and switched in such a way as to take advantage of day lighting opportunities. Stair lighting, exit lights, and egress lighting shall be non-switched. Wall box type occupancy sensors with dual level multi-circuit switching shall be provided for private offices. Provide complete building interior and exterior lighting control through the Building Management System.
Wall-type manual dimmers for selected area lighting include conference rooms, control rooms and office areas.
Maximum security lighting fixtures: Maximum security lighting fixtures shall be provided in holding sleeping rooms, dayrooms, corridors and similar areas on the floors with holding.
Emergency/Egress Lighting
Provide un-switched night lighting, connected to the emergency system life safety branch in all spaces. Egress lighting fixtures shall be provided with integral emergency battery backup.
Exit signs shall be provided where required by code. Exit signs shall not be provided in youth accessible areas as permitted by code. Exit signs shall be edge lit; self-powered, LED type, and connected to the emergency system life safety branch. Exit signs shall be provided with integral emergency battery backup. Coordinate face color of
P a g e | 29 exit sign with the Texas State Fire Marshal. Provide specialty lighting as indicated. Provide necessary calculations to ensure that proper lighting levels are being obtained. The minimum maintained lighting level shall be in accordance with code requirements.
Exterior Lighting
Wall mount exterior lighting fixture shall be separate circuit controlled by security personnel at the Central
Control Room. Typical for pole mounted exterior lighting. Lighting locations and fixture design shall coordinate with CCTV camera location requirements. Wall mounted fixtures must be flush mount or preferably the fixtures should be located on the roof. Provide both photoelectric and astronomical time control.
All exterior lighting shall be designed to avoid discomfort and minimize glare with respect to staff in control and observation areas and avoid illumination spill onto adjacent properties. Full cut-off fixtures shall be provided in accordance with the Texas State adopted code. Provide a photometric drawing showing illumination levels in foot candles, and also lighting power density in watts per square foot for all exterior lighting areas.
All exterior light fixtures must be located with the cooperation and mutual agreement of the CCTV camera contractor and camera locations, electrical contractor ensure maximum visibility and camera clarity.
P a g e | 30
E.7 Plumbing Systems
Provide and install all plumbing systems in accordance with applicable codes, standards, regulations and authorities having jurisdiction, and in accordance with current engineering practices, refer to listing in this section. All materials and workmanship to be premium materials and master plumbing standards to safe, reliable, and efficient systems, as required for a complete plumbing system.
Each utility service shall be site metered. Waste water flows, both grey and black, shall be metered by building and site. Monitoring shall be remote and recorded within the Facilities Services maintenance areas.
Provide design, engineering, installation, permits, testing, start-up and balancing for pressurization and leak detection to obtain a complete plumbing system for the building. Submit complete calculations, equipment selection charts and complete documentation prior to commencement of the work. Contract document drawings and design guidelines shall indicate locations of all fixtures, drains, equipment, etc. Check all documents and confirm the plumbing design to all conditions shown and called out in the documents.
Valves shall be installed on cold water, hot water, and hot water return circulating mains so that sections of the mains may be shut off without disturbing the services to other parts of the building (each housing unit sleeping room and youth restrooms, at minimum). In addition, a valve shall be provided on the connection to the main supply to the building and on the inlets and outlets of all mechanical equipment requiring water connections.
Where plausible, valves service for housing units shall be located outside the secured area with a desire for access to be located outside the building. A shut-off valve shall be on each branch connection off the main serving more than one fixture. Valves shall also be provided at the base of all risers, at every toilet core and at each sleeping room in the chase.
Normally open valves with single pole electronic closure control shall be installed at each housing unit and treatment unit’s service entry and controlled from the Central Control Center. The valve shall be redundantly supported as part of the emergency power & emergency electrical services.
Water piping shall not be installed in or under the building slab except for trap primer lines. All plumbing piping for the youth sleeping rooms or housing units is to be routed through the plumbing chases that are located on the interior walls of the sleeping rooms or common restroom areas and within a chase accessible by maintenance personnel. No exposed pipe shall be placed within reach of the youths. Water, waste, cleanout, or condensation lines shall not be routed over the IT/radio rooms.
Sanitary Waste and Vent Systems
Coordinate invert elevation data with site work. Waste mains shall be located outside the building slab. Only vents, traps and vertical drops shall be located on the building’s interior. All interior service lines in housing units must be easily accessible. Each toilet room shall have a minimum of one drain. All floor drains shall be fitted with trap primers, except in showers. Floor drains shall be located to provide effective drainage for fixture overflow in youth sleeping rooms, but drains will not be allowed in sleeping rooms. Cleanouts from youth sleeping rooms to be equipped with flush excluder pin valve, mounted on the cover that protrudes into the flow of to catch any
P a g e | 31 solids that might be flushed down the sleeping room toilets.
Provide a waste macerator at the end run of the waste line and after the two-way building cleanout just before waste enters the sewer system. The macerator shall be accessible to cleaning and maintenance. The macerator shall be equal to the Auger Monster or Muffin Monster System. A grease trap interceptor shall be provided at the kitchen with outside clean-out prior to connection to the waste macerator.
Domestic Cold Water System
Water shall be distributed through mains, risers, and branches to plumbing fixtures and equipment. Mains shall be located outside the building slab.
Water piping shall not be placed in concrete fills or structural slabs, in transformer vaults, or over electrical switchboards, switchgear, computer/communication rooms, the main control room or above elevator equipment or similarly sensitive areas. Cold water pipes over ceilings shall be insulated against condensation.
Domestic Hot Water System
Hot water shall be generated in the most energy efficient and plausible manner. The contractor shall consider solar and alternative reclaim processes for domestic hot water generation. The domestic water heating equipment shall be automatically controlled and shall have sufficient capacity to deliver the following temperatures at all times:
a.Hand washing and food prep 140 F b.Youth sinks and showers 105 F c.Booster at Dishwashing 180 F
Natural Fuel Gas System
Natural gas shall be extended from a central main stub installed under agreement with utility provider. Natural gas shall be piped as required to support all gas fired systems. Actuated gas shutoff valve shall be provided and located at building gas entry. Shutoff shall be protected from accidental activation by protective fencing, enclosure, and bollards. Maximum interior design pressure of gas piping shall be 1/4 psi at 7” W.C. Provide approved pressure reducer valves where required with venting to the exterior. Connect natural gas piping to
HVAC equipment, and other equipment as required and/or as called for in design guidelines, or specifications.
All gas piping shall be designed in accordance with the latest edition of NFPA or ANSI Standard, refer to the specifications, Installation of Gas Appliances and Gas Piping and the governing Plumbing Code.
A back-up generator will be required. During design, the decision should be made to have a gas powered or diesel powered generator.
Plumbing Fixtures
Staff and public water closets shall be vitreous china siphon jet wall hung, 1.6 GPF water conserving automatic with sensors, 120 volt flush meter type. Staff and public urinals shall be vitreous china, wall hung siphon jet, 1.0
GPF water conserving automatic with sensors, 120 volt flush meter type. Staff showers shall include thermostatic
P a g e | 32 mixing valves, with 2.5 GPM flow restrictors in head.
Staff and public lavatories shall be vitreous china and provided with 0.5 GPM flow restrictors using automatic with sensors, 120 volt, metered faucets. Staff and public drinking fountains shall have an integral chiller unit and bottle filling capabilities.
Housing unit fixtures shall be stainless steel with white powder coating, manually controlled with an adjustable electronically controlled metering flush shut-off to prevent flooding from vandalism/abuse. The sinks in sleeping areas shall have a dual purpose bubbler for hand washing and drinking and be anti-ligature. Mouth guards are not required. A combo unit may be required depending on space constraints. Appropriate fixtures will be provided for ADA compliance. Youth grab bars and towel racks shall be anti-ligature.
Showers shall be stainless steel anti-ligature, modular construction.
Storm Water Drainage Systems
Roof drain piping shall be designed with no interior drains, ensuring that all drainage is directed to exterior downspouts. These downspouts will be strategically located outside youth areas and positioned to prevent access by the public. The roof overflow piping system must be designed to eliminate any exposed piping that could be used to gain access to the roof. All piping and downspouts must be fully concealed and secure to maintain facility safety and security.
Medical Gas System
Provide medical gas system consisting of vacuum and air for bedside of infirmary bed, and one dental chair.
Noise And Vibration Control
All piping and equipment subject to vibration and noise shall be isolated from the building…