This document is an Addendum #2 for Request for Qualifications (RFQ) #0006148 issued by the Texas Facilities Commission (TFC) for Construction Materials Testing Services for Texas Juvenile Justice Department (TJJD) New Detention Facilities. The addendum modifies the original solicitation by updating the schedule of events, with the proposal submission deadline set for September 2, 2025, at 3:00 PM. Two mandatory pre-submittal conferences were held on August 19 and 20, 2025, with detailed attendee lists included. The addendum addresses a question about Attachment G accessibility and clarifies that it can be downloaded from Bonfire or the Electronic State Business Daily (ESBD).

The document includes specific clarifications about field testing requirements for various construction materials and systems, such as firestopping, infrared thermography, window testing, water penetration, and air barrier leakage testing. A key point of clarification is that the 23.7% Historically Underutilized Business (HUB) goal applies only to subcontracted firms, not to the prime contractor's own participation. The attendee lists reveal multiple engineering, testing, and consulting firms participated, with many being HUB-certified. The solicitation appears to be seeking comprehensive construction materials testing services for new detention facility construction, with a focus on diverse and qualified testing providers.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Chair Brian Bailey

Commissioners Eddy Betancourt Robert H. Clay JJ Isbell Daniel K. Signorelli C. Price Wagner Robert S. Wetmore

Executive Director Mike Novak

Mailing address:

P. O. Box 13047

Austin, TX 78711-3047

(512) 463-3446 www.tfc.texas.gov

ADDENDUM #2

DATE: 8/20/2025

REP #: 0006148

TITLE: CMT for TJJD New Detention Facilities PROPOSAL DEADLINE: 9/2/2025 at 3:00 PM

Addendum item #1: The proposal submission due date is changed to read as follows:

1. SCHEDULE OF EVENTS: TFC reserves the right to change the dates shown below.

EVENT DATE

Issue RFQ

8/05/2025

Mandatory Pre-Submittal Conference 8/19/2025 Tuesday, 10:00 AM

(OR)

Mandatory Pre-Submittal Conference 8/20/2025 Wednesday, 10:00 AM Deadline for Submission of Questions 8/26/2025 Deadline for Submission of Qualifications &

HSP

9/02/2025 Tuesday @ 3:00 PM

.2. Addendum item #2: The attendee lists to the 8/19/25 and 8/20/25 Pre-Submittal Conferences is attached to this addendum.

3. Addendum item #3: The following questions from potential Respondents were submitted for clarification.

# QUESTION ANSWER

1.

Attachment G seems to be protected or locked. Will TFC please upload an unlocked document for review?

Attachment G can either be downloaded from Bonfire or the ESBD. The link to view the solicitation on the ESBD is: ESBD

Texas Facilities Commission

Physical address: 1711 San Jacinto Blvd, Austin, Texas 78701 Planning and administering facilities in service to the State of Texas http://www.tfc.texas.gov/ https://www.txsmartbuy.gov/esbd/0006148

2.

Are you looking for field or laboratory versions of these tests?

Firestopping Field Testing (ASTM E2174) Infrared Thermography Inspections of Building Envelope and Roof Systems ASTM Window Chamber Testing Water Penetration Testing (AAMA 501.2) Whole Building Air Barrier Leakage Testing (ASTM E779)

See response to the specific tests referenced:

• Firestopping Field Testing (ASTM E2174)

This standard is specifically designed for field inspections of firestop systems after installation. Lab testing of firestopping (e.g., ASTM E814) exists, but that’s for pre-qualification of materials not in-situ validation.

• Infrared Thermography Inspections of Building Envelope and Roof Systems This inspection relies on real-time thermal imaging of the actual building to detect insulation gaps, air leaks, or moisture issues.

You can’t replicate site-specific conditions like solar loading or ambient temperature in a lab.

• ASTM Window Chamber Testing While similar test procedures are used in labs to qualify window systems before construction, E1105 is written for field application assessing how the installed systems perform under real conditions.

• Water Penetration Testing (AAMA 501.2) This is a diagnostic, in-situ hose test intended to evaluate how installed curtain walls or storefronts resist water leakage.

Lab alternatives exist (like AAMA 502/503 or ASTM E547), but 501.2 is strictly a field quality assurance method.

• Whole Building Air Barrier Leakage Testing

(ASTM E779)

This test uses blower door equipment to measure actual air leakage in the constructed building. It must be done in the field, with the structure sealed and HVAC systems turned off.

3.

If a prime firm is HUB and plans on using subcontractors, can the prime firm’s participation count towards the 23.7% goal?

No, the 23.7 % goal only applies to subcontracted firms only.

All other aspects of RFQ # 0006148 remain as is.

James Gonzalez, CTCD, CTCM TFC Procurement Department Phone: 512-936-0647 Email: james.gonzalez@tfc.texas.gov mailto:james.gonzalez@tfc.texas.gov

RECEIPT OF ADDENDUM #2 OF RFQ #0006148

IN YOUR SUBMITTAL THE RESPONDENT SHALL ACKNOWLEDGE RECEIPT OF THIS

ADDENDUM.

Respondent Signature Date

Printed Name Company Name

RFQ #0006148 Construction Materials Testing Services for TJJD New Detention Facilities Attendee List for

Pre-Submittal Conference for Tuesday, August 19, 2025

First Name Last Name Organization Email Phone Prime or Subcontractor Is your firm a HUB firm?

HUB

Eligibility

HUB

Gende Registration Time

Approval Status

Natasha Griffin Arias and Associates natasha.griffin@ariasinc.com 2106673495 Subcontractor Yes, my firm is a HUB firm. HI M 8/13/2025 13:58 approved Parth Thapa Arias and Associates pthapa@ariasinc.com 6825608981 Subcontractor Yes, my firm is a HUB firm. HI M 8/19/2025 9:58 approved Karl Crenwelge Arias and Associates karl.crenwelge@ariasinc.com 210.693.4672 Subcontractor Yes, my firm is a HUB firm. HI M 8/13/2025 8:17 approved Basil Abdulkareem Burgess Engineering & Testing basil.a@burgessengineer.com 405-790-0488 Prime Contractor No, my firm is not a HUB firm. 8/11/2025 15:39 approved RAFAEL CONTRERAS Earth Engineering, Inc. Rafaelc@eartheng.com 7136815311 Prime Contractor Yes, my firm is a HUB firm. HI F 8/18/2025 8:49 approved Derrick Mcgowen Earth Engineering, Inc. derrickm@eartheng.com 713-681-5311 Prime Contractor Yes, my firm is a HUB firm. HI F 8/18/2025 9:25 approved Jazmin Mendez Geotech Engineering and Testing jazmin@geotecheng.com 713-699-4000 Prime Contractor Yes, my firm is a HUB firm. 8/5/2025 9:02 approved AJ JACKSON Geotex Engineering ajackson@geotex-engineering.com 940-395-5330 Subcontractor Yes, my firm is a HUB firm. WO F 8/19/2025 9:54 approved Jordan Ferrell Gessner Engineering jferrell@gessnereng.com 9796808840 Subcontractor Yes, my firm is a HUB firm. WO F 8/13/2025 15:27 approved diana Brown HDB diana@hellodianabrown.com 7137252499 Subcontractor No, my firm is not a HUB firm. 8/14/2025 12:22 approved Tom Salmon Intertek thomas.salmon@intertek.com 872-583-6600 Subcontractor No, my firm is not a HUB firm. 8/11/2025 10:12 approved Reni Acosta Intertek-PSI reni.acosta@intertek.com 4693870612 Prime Contractor No, my firm is not a HUB firm. 8/10/2025 21:45 approved Theophilus Maku Jitaol Engineering theomaku@jitaolengineering.com 6823135910 Prime Contractor Yes, my firm is a HUB firm. BL M 8/13/2025 10:27 approved Jason Allen Raba Kistner, Inc. jallen@rkci.com 682-232-3228 Prime Contractor No, my firm is not a HUB firm. 8/6/2025 9:16 approved Badre Enam TBS Testing LLC badre@tbstesting.com 346-824-5545 Prime Contractor Yes, my firm is a HUB firm. AS M 8/18/2025 10:53 approved Christopher Auchter Terracon Consultants, Inc. christopher.auchter@terracon.com 7136908989 Prime Contractor No, my firm is not a HUB firm. 8/18/2025 10:36 approved Hollie O'Connor Terracon Consultants, Inc. hollie.oconnor@terracon.com 2814142693 Prime Contractor No, my firm is not a HUB firm. 8/19/2025 8:40 approved Travis Kilgore Thompson Engineering, Inc. tkilgore@thompsonengineering.com 4092049949 Prime Contractor No, my firm is not a HUB firm. 8/8/2025 21:14 approved Jimmy Si Thompson Engineering, Inc. jsi@thompsonengineering.com 5124667614 Prime Contractor No, my firm is not a HUB firm. 8/14/2025 9:47 approved

Omar Casas Texas Facilities Commission omar.casas@tfc.texas.gov 512-463-1861 Amanda Cambre Texas Facilities Commission - FDC Amanda.cambre@tfc.texas.com 7378024862 David Delgado Texas Facilities Commission - HUB david.delgado@tfc.texas.gov 512-463-1853 Cameron Glass Kitchell cglass@kitchell.com 5099988128 Carmen Gust Kitchell cgust@kitchell.com 512-920-0891 David Hoffmann Kitchell dhoffmann@kitchell.com 9794176852

RFQ #0006148 Construction Materials Testing Services for TJJD New Detention Facilities Attendee List for

Pre-Submittal Conference for Wednesday, August 20, 2025

First Name Last Name Organization Email Phone Prime or Subcontractor? Is your firm a HUB firm?

HUB

Eligibility

HUB

Gender Registration Time

Approval Status

Tina Morris Alliance Geotechnical Group, Inc. tmorris@aggengr.com 972-444-8889 Prime Contractor No, my firm is not a HUB firm. 8/7/2025 10:35 approved Karl Crenwelge Arias & Associates, Inc. karl.crenwelge@ariasinc.com 210.392.8168 Subcontractor Yes, my firm is a HUB firm. HI M 8/13/2025 8:18 approved Savanna Hardin Arias & Associates, Inc. savanna.hardin@ariasinc.com 208-313-3648 Subcontractor Yes, my firm is a HUB firm. HI M 8/13/2025 10:28 approved Vanessa Rivera Arias & Associates, Inc. vanessa.rivera@ariasinc.com 210-427-4905 Subcontractor Yes, my firm is a HUB firm. HI M 8/15/2025 16:09 approved Brenda Benitez ATSER, LP bbenitez@atser.com 281-999-9961 Prime Contractor Yes, my firm is a HUB firm. HI M 8/6/2025 16:18 approved Gerry Davila ATSER, LP gdavila@atser.com 713-259-2410 Prime Contractor Yes, my firm is a HUB firm. HI M 8/6/2025 14:53 approved Mark Madera ATSER, LP mmadera@atser.com 281-999-9961 Prime Contractor Yes, my firm is a HUB firm. HI M 8/6/2025 14:56 approved Veronica Dorlus ATSER, LP vdorlus@atser.com 281-999-9961 Prime Contractor Yes, my firm is a HUB firm. HI M 8/6/2025 14:51 approved Zowy Ramirez ATSER, LP zramirez@atser.com 281-999-9961 Prime Contractor Yes, my firm is a HUB firm. HI M 8/8/2025 11:33 approved LeAnn Belcher Braun Intertec Corporation lbelcher@braunintertec.com 214-566-1703 Prime Contractor No, my firm is not a HUB firm. 8/14/2025 9:53 approved Abigail Alford Certerra, Rone Engineering aalford@roneengineers.com 9727680717 Prime Contractor No, my firm is not a HUB firm. 8/8/2025 15:38 approved Alexandros Sioutis Certerra, Rone Engineering asioutis@roneengineers.com 5126985518 Prime Contractor No, my firm is not a HUB firm. 8/8/2025 11:29 approved Juanita Shihadeh Earth Engineering Inc. juanitas@eartheng.com 7135917256 Prime Contractor Yes, my firm is a HUB firm. HI F 8/19/2025 9:04 approved Stephanie Dogan Earth Engineering Inc. stephanied@eartheng.com 8326065466 Prime Contractor Yes, my firm is a HUB firm. HI F 8/19/2025 9:05 approved Caleb Loggins ECS Southwest, LLP cloggins@ecslimited.com 9729784693 Prime Contractor No, my firm is not a HUB firm. 8/19/2025 10:45 approved Blake Gieg Fenagh Inc. bgieg@fenaghengineering.com 512-595-7678 Prime Contractor No, my firm is not a HUB firm. 8/20/2025 9:05 approved Diana Brown HDB diana@hellodianabrown.com 7137252499 Subcontractor No, my firm is not a HUB firm. 8/12/2025 15:22 approved Tom Salmon Intertek thomas.salmon@intertek.com 9725836600 Prime Contractor No, my firm is not a HUB firm. 8/11/2025 10:13 approved Stephen Rohrer Intertek PSI stephen.Rohrer@intertek.com 713-927-4280 Prime Contractor No, my firm is not a HUB firm. 8/5/2025 10:16 approved Reni Acosta Intertek-PSI reni.acosta@intertek.com 4693870612 Prime Contractor No, my firm is not a HUB firm. 8/10/2025 21:45 approved Theophilus Maku Jitaol Engineering theomaku@jitaolengineering.com 6823135910 Prime Contractor Yes, my firm is a HUB firm. BL M 8/13/2025 10:28 approved Kelly Daniel Kleinfelder, Inc kdaniel@kleinfelder.com 512.491.4627 Subcontractor No, my firm is not a HUB firm. 8/19/2025 15:41 approved Danielle McKillion Kleinfelder, Inc dmckillion@kleinfelder.com 303-297-5726 Subcontractor No, my firm is not a HUB firm. 8/19/2025 11:29 approved Auriya Penny PSI Auriya.Penny@Intertek.com 4077099202 Prime Contractor No, my firm is not a HUB firm. 8/5/2025 16:29 approved Joanna Armstrong Raba Kistner, Inc. jarmstrong@rkci.com 8068811181 Prime Contractor No, my firm is not a HUB firm. 8/5/2025 7:00 approved Badre Enam TBS Testing badre@tbstesting.com 3468245545 Prime Contractor Yes, my firm is a HUB firm. AS M 8/19/2025 13:04 approved Tanvir Hossain TBS Testing tanvir@tbstesting.com 6154986649 Prime Contractor Yes, my firm is a HUB firm. AS M 8/13/2025 15:48 approved Christopher Auchter Terracon Consultants, Inc. christopher.auchter@terracon.com 7136908989 Prime Contractor No, my firm is not a HUB firm. 8/15/2025 9:38 approved Hollie O'Connor Terracon Consultants, Inc. hollie.oconnor@terracon.com 713-690-8989 Prime Contractor No, my firm is not a HUB firm. 8/15/2025 9:21 approved Kyle Kilgore Thompson Engineering, Inc. Kkilgore@thompsonengineering.com 8322605342 Prime Contractor No, my firm is not a HUB firm. 8/8/2025 21:15 approved Brian Bushong UES bbushong@teamues.com 7132590632 Prime Contractor No, my firm is not a HUB firm. 8/19/2025 11:00 approved Hannah McAdams UES hmcadams@teamues.com 972-620-8911 Prime Contractor No, my firm is not a HUB firm. 8/13/2025 16:42 approved Amber Widner Woyt International, LLC amber@woytintl.com 2817058640 Subcontractor Yes, my firm is a HUB firm. WO F 8/6/2025 14:27 approved

Amanda Cambre TFC amanda.cambre@tfc.texas.gov 7378024852 Kevin Mathis TFC Kevin.mathis@tfc.texas.gov 5124631771 Shonte Gordon TFC - HUB shonte.gordon@tfc.texas.gov 5123059269 Cameron Glass Kitchell cglass@kitchell.com 5099988128 Carmen Gust Kitchell cgust@kitchell.com 512-920-0891 David Hoffmann Kitchell dhoffmann@kitchell.com 979-417-6852

Page 1 if 1

0006148 Addendum #2 Draft 1.0
Email: james.gonzalez@tfc.texas.gov
00006148 Pre-Submittal Conference Attendee List for 8-18-25
registration_87158638150_2025_0
00006148 Pre-Submittal Conference Attendee List for 8-19-25
registration_85437817400_2025_0

File details come from the government source that posted it. Updated .