3MD0395 Post Award Schedule.pdf

PDF 12 KB Posted

Attached to
Lease of Office Space within Region 3. Request for Lease Proposals (RLP) #25REG03 - Office Space
Solicitation number
3MD0395
Issued by

About this file

This document is the Post-Award Schedule for the Lease of Office Space within Region 3 solicitation. It details the timeline for the project after the lease has been awarded, including the design kick-off meeting, submission of design intent drawings and construction documents, TI price proposal, construction kick-off, construction completion, final inspections, and punchlist completion. The related federal contract opportunity is for the lease of 4,690 - 4,925 ABOA square feet of office space in La Plata, Maryland for a 10-year term with a 5-year firm period. The solicitation is being conducted through the Automated Advanced Acquisition Program (AAAP) by the General Services Administration's Public Buildings Service in Region 3.

View the file

Other files

File Type Posted
3MD0395 AAAP Advertisement.pdf PDF
3MD0395 La Plata MD DA Boundary.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AAAP POST-AWARD SCHEDULE, PAGE 1 OF 1 PSA VERSION - REV (10/22)

AAAP Project Specific Advertisement (PSA) Attachment: Post-Award Schedule

This attachment details the post-award schedule for this project. It hereby replaces the Attachment referenced in section

1.05 of the RLP (R100) and should be used when reviewing section 4.01 of the Lease (L100).

The below post-award schedule commences within 5 working days of lease award. The time frames below apply to the management of the design and construction process, concluding at the date of acceptance for the space.

Activity Working Days

Design Kick-Off Meeting with Lessor, GSA, & Agency 10 days after lease award

Lessor-Provided Design Intent Drawings 20 Days

Lessor Preparation and Submission of Construction Documents 15 Days

Lessor Preparation and Submission of the TI and BSAC Price Proposal

20 Days

TI Negotiations Completed 50 days

Construction Kick Off Meeting 10 days

Lessor Completes Construction of TIs and Completion of Other Required Construction Work

60 days

Final Inspections/Government Acceptance 10 Days

Punchlist Completed 10 Days