3MD0395 Post Award Schedule.pdf
PDF 12 KB Posted
- Attached to
- Lease of Office Space within Region 3. Request for Lease Proposals (RLP) #25REG03 - Office Space
- Solicitation number
- 3MD0395
About this file
This document is the Post-Award Schedule for the Lease of Office Space within Region 3 solicitation. It details the timeline for the project after the lease has been awarded, including the design kick-off meeting, submission of design intent drawings and construction documents, TI price proposal, construction kick-off, construction completion, final inspections, and punchlist completion. The related federal contract opportunity is for the lease of 4,690 - 4,925 ABOA square feet of office space in La Plata, Maryland for a 10-year term with a 5-year firm period. The solicitation is being conducted through the Automated Advanced Acquisition Program (AAAP) by the General Services Administration's Public Buildings Service in Region 3.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 3MD0395 AAAP Advertisement.pdf | ||
| 3MD0395 La Plata MD DA Boundary.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AAAP POST-AWARD SCHEDULE, PAGE 1 OF 1 PSA VERSION - REV (10/22)
AAAP Project Specific Advertisement (PSA) Attachment: Post-Award Schedule
This attachment details the post-award schedule for this project. It hereby replaces the Attachment referenced in section
1.05 of the RLP (R100) and should be used when reviewing section 4.01 of the Lease (L100).
The below post-award schedule commences within 5 working days of lease award. The time frames below apply to the management of the design and construction process, concluding at the date of acceptance for the space.
Activity Working Days
Design Kick-Off Meeting with Lessor, GSA, & Agency 10 days after lease award
Lessor-Provided Design Intent Drawings 20 Days
Lessor Preparation and Submission of Construction Documents 15 Days
Lessor Preparation and Submission of the TI and BSAC Price Proposal
20 Days
TI Negotiations Completed 50 days
Construction Kick Off Meeting 10 days
Lessor Completes Construction of TIs and Completion of Other Required Construction Work
60 days
Final Inspections/Government Acceptance 10 Days
Punchlist Completed 10 Days