3c_Statement of Work.pdf

PDF 124 KB Posted

Attached to
Rental and maintenance of one 6,000-lb and one 12,000-lb LPG forklift
Solicitation number
75110PR270000099
Issued by
Not on record

About this file

This is a Statement of Work (SOW) for the rental and maintenance of industrial forklifts at the United States Coast Guard Training Center (TRACEN) Birmingham-Southern in Birmingham, Alabama.

The Contractor shall provide a seven-month commercial rental (December 1, 2026 through June 30, 2027) of two standard industrial counterbalanced forklifts: one 6,000-lb capacity unit and one 12,000-lb capacity unit. The contract is structured as a Firm-Fixed-Price (FFP) arrangement for equipment rental, mobilization, demobilization, operator familiarization and safety training, and maintenance services, with a separate Not-to-Exceed (NTE) Contract Line-Item Number (CLIN) for on-demand LPG fuel supply. Key deliverables include equipment delivery and commissioning with joint acceptance inspection; scheduled preventive maintenance at OEM-specified intervals performed either on-site via mobile service truck or off-site at no additional Government cost; unscheduled repairs and replacement of defective equipment within four business days of notification; initial basic operating and safety training within five business days of delivery, with up to one additional quarterly training session upon GTR request; on-demand LPG fuel replenishment within two business days of Government Technical Representative (GTR) request with zero spare cylinders or bulk fuel storage remaining on-site; and contract closeout and equipment demobilization within five business days after contract expiration. The Contractor must provide OEM Operator and Maintenance Manuals upon delivery, submit Preventive Maintenance and Repair Service Tickets within two business days of service completion, provide signed LPG Fuel Delivery Tickets with monthly invoices, submit Training Attendance Rosters and Training Completion Summaries within two business days after each training session, and notify the Contracting Officer and GTR when cumulative fuel billings reach 75 percent of the NTE CLIN ceiling. The place of performance is USCG TRACEN Birmingham-Southern, 900 Arkadelphia Road, Birmingham, AL 35204, with work generally performed between 0800 and 1700 Central Time, Monday through Friday, except Federal holidays. The Government will furnish designated outdoor/indoor parking and staging areas, an on-site training area, and restroom facilities for Contractor personnel.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK (SOW)

FOR

RENTAL AND MAINTENANCE OF 12,000-LB AND 6,000-LB FORKLIFTS AT

USCG TRACEN BIRMINGHAM-SOUTHERN

1.0 GENERAL

1.1 BACKGROUND

The United States Coast Guard (USCG), a component of the Department of Homeland Security

(DHS), operates USCG Training Center (TRACEN) Birmingham-Southern located at 900

Arkadelphia Road, Birmingham, Alabama 35204. Daily logistics, warehouse management, and training support operations at USCG TRACEN Birmingham-Southern require reliable material handling equipment to transport, load, and unload pallets, training aids, and heavy supplies across paved indoor and outdoor campus areas.

1.2 SCOPE

The Contractor shall provide a seven-month (7) commercial rental of one (1) 6,000-pound (lb) capacity standard industrial counterbalanced forklift and one (1) 12,000-lb capacity standard industrial counterbalanced forklift at USCG TRACEN Birmingham-Southern. The scope includes equipment delivery, commissioning, scheduled preventive maintenance, unscheduled repairs, replacement of defective or inoperable equipment within four (4) business days of notification, basic operating and safety training for USCG personnel (once shortly after equipment delivery and up to once per quarter thereafter upon request of the Government Technical

Representative (GTR)), on-site LPG fuel replenishment on an as-needed basis within two (2) business days of GTR request, and contract closeout demobilization.

Statement of Work supports a Firm-Fixed-Price (FFP) contract for equipment rental, mobilization, demobilization, operator familiarization and safety training, maintenance, and replacement services, with a separate Not-to-Exceed (NTE) Contract Line-Item Number (CLIN) for on-demand LPG fuel supply.

1.3 OBJECTIVE

Provide two (2) fully operational, maintained, and fueled industrial counterbalanced forklifts (one

6,000-lb capacity unit and one 12,000-lb capacity unit) for continuous Government use at USCG

TRACEN Birmingham-Southern throughout the seven month (7) rental period. Maintain operational readiness and operator safety through turn-key preventive maintenance, initial and quarterly basic operating and safety training, on-demand mobile LPG refueling within two (2) business days of GTR request, and equipment replacement within four (4) business days of breakdown notification. Support safe and uninterrupted material handling operations across the training center.

1.4 APPLICABLE DOCUMENTS

The Contractor shall comply with all applicable Federal, State, and local laws and regulations that pertain to the rental, operation, maintenance, and fueling of industrial forklifts and the handling of liquid propane gas.

2.0 SPECIFIC REQUIREMENTS/TASKS

The Contractor shall perform the following tasks. The Government will measure performance against the stated deliverables and timeframes. The Contractor is responsible for determining the means and methods of performance.

2.1 TASK ONE. FORKLIFT EQUIPMENT DELIVERY AND COMMISSIONING

The Contractor shall provide, deliver two (2) standard industrial counterbalanced forklifts at

USCG TRACEN Birmingham-Southern in accordance with the following requirements:

2.1.1 FORKLIFT (6,000-LB CAPACITY)

Provide one (1) standard counterbalanced industrial forklift with a minimum rated load capacity of 6,000 lbs at a 24-inch load center, powered by LPG, equipped with pneumatic or solid pneumatic tires for indoor and outdoor paved operations, a three-stage mast with a minimum

15-foot lift height, side-shift carriage, 48-inch pallet forks, Roll-Over Protective Structure / Falling

Object Protective Structure (ROPS/FOPS) overhead guard, seatbelt, backup alarm, strobe beacon, Light-Emitting Diode (LED) work lights, and a mounted Class ABC dry chemical fire extinguisher.

2.1.2 FORKLIFT (12,000-LB CAPACITY)

Provide one (1) medium standard counterbalanced industrial forklift with a minimum rated load capacity of 12,000 lbs at a 24-inch load center, powered by LPG, equipped with pneumatic or solid pneumatic tires for indoor and outdoor paved operations, a two-stage or three-stage mast with a minimum 12-foot lift height, side-shift carriage, minimum 48-inch pallet forks, ROPS/FOPS overhead guard, seatbelt, backup alarm, strobe beacon, LED work lights, and a mounted Class ABC dry chemical fire extinguisher.

2.1.3 OEM MANUALS AND LOAD CHARTS

Provide one (1) weather-resistant copy of the Original Equipment Manufacturer (OEM) Operator and Maintenance (O&M) Manual and a legible load capacity data plate mounted on each forklift upon delivery.

2.1.4 INITIAL ACCEPTANCE INSPECTION

Conduct a joint initial acceptance inspection and operational load verification with the GTR upon delivery, and provide a signed Pre-Delivery Inspection Report documenting baseline equipment condition, serial numbers, and initial hour-meter readings.

2.2 TASK TWO. SCHEDULED PREVENTIVE MAINTENANCE AND UNSCHEDULED

REPAIRS

The Contractor shall maintain both the 6,000-lb and 12,000-lb forklifts in safe operating condition throughout the Period of Performance in accordance with the following requirements:

2.2.1 PREVENTIVE MAINTENANCE INTERVALS

Perform scheduled preventive maintenance (PM) on both forklifts at the intervals specified by the OEM using a self-contained mobile service truck on-site at USCG TRACEN Birmingham-

Southern or by transporting the equipment off-site at no additional cost to the Government.

2.2.2 MAINTENANCE SCOPE AND CONSUMABLES

Provide labor, OEM replacement parts, filters, lubricants, tires, hydraulic hoses, lift chains, engine tuning to maintain Carbon Monoxide (CO) exhaust emissions within permissible exposure limits for indoor/outdoor operation, and consumables required to maintain both forklifts in operational condition throughout the Period of Performance.

2.2.3 WASTE FLUID MANAGEMENT

Contain and remove waste oils, hydraulic fluids, spent filters, oily rags, and maintenance debris generated during on-site service visits from USCG TRACEN Birmingham-Southern prior to departing the installation on the same day in accordance with Section 4.15.

2.2.4 SERVICE TICKETS AND DOCUMENTATION

Record each preventive maintenance service, safety inspection, and repair action on a

Preventive Maintenance and Repair Service Ticket, and submit a copy of the ticket to the GTR via electronic mail within two (2) business days of service completion.

2.3 TASK THREE. DEFECTIVE OR INOPERABLE EQUIPMENT REPLACEMENT

The Contractor shall resolve equipment breakdowns and replace inoperable forklifts in accordance with the following requirements:

2.3.1 TROUBLESHOOTING AND REPAIR RESPONSE

Respond to GTR notifications of equipment defect, mechanical breakdown, or safety deficiency, and conduct on-site troubleshooting and repair at USCG TRACEN Birmingham-Southern.

2.3.2 REPLACEMENT EQUIPMENT DELIVERY

Provide, deliver, and offload a replacement forklift meeting the technical specifications of

Section 2.1.1 (for the 6,000-lb unit) or Section 2.1.2 (for the 12,000-lb unit) to USCG TRACEN

Birmingham-Southern within four (4) business days of GTR notification when a malfunctioning forklift cannot be repaired and returned to full operational status within four (4) business days of notification.

2.3.3 REMOVAL OF INOPERABLE EQUIPMENT

Remove the defective or inoperable forklift from USCG TRACEN Birmingham-Southern at no additional cost to the Government upon delivery of the replacement forklift.

2.4 TASK FOUR. ON-DEMAND LIQUID PROPANE GAS (LPG) FUEL SUPPLY (NOT-TO-

EXCEED CLIN)

The Contractor shall supply LPG fuel for both forklifts on an as-needed basis under the NTE

Fuel CLIN in accordance with the following requirements:

2.4.1 LPG FUEL REPLENISHMENT

Perform on-site LPG fuel replenishment at USCG TRACEN Birmingham-Southern during normal operating hours (0800 to 1700 Central Time, Monday through Friday) on an as-needed basis within two (2) business days of GTR request, by exchanging depleted LPG forklift cylinders mounted directly on the two forklifts with full cylinders, or by direct mobile refueling in compliance with all Federal and State regulations.

2.4.2 CYLINDER MANAGEMENT

Remove depleted or spare LPG cylinders from USCG TRACEN Birmingham-Southern upon completion of each refueling visit so that zero spare LPG cylinders or bulk fuel storage tanks remain stored on-site.

2.4.3 FUEL DELIVERY TICKETS

Track and document the quantity of LPG cylinders or gallons supplied during each delivery on an LPG Fuel Delivery Ticket, obtain GTR signature verification on the ticket upon delivery, and submit the signed tickets with the monthly invoice.

2.4.4 NTE CLIN MONITORING

Monitor cumulative fuel charges against the contract NTE Fuel CLIN ceiling, and notify the

Contracting Officer and GTR in writing when cumulative fuel billings reach 75 percent of the

NTE CLIN ceiling. The Government will reimburse only actual, verified quantities of fuel delivered at the contract unit rate up to the NTE ceiling.

2.5 TASK FIVE. BASIC OPERATING AND SAFETY TRAINING FOR USCG PERSONNEL

The Contractor shall conduct on-site basic operating and safety training for designated USCG personnel at USCG TRACEN Birmingham-Southern in accordance with the following requirements:

2.5.1 INITIAL TRAINING SESSION

Conduct one (1) initial on-site basic operating and safety training session for designated USCG personnel within five (5) business days following the delivery and commissioning of the two forklifts, scheduled in coordination with the GTR.

2.5.2 QUARTERLY TRAINING SESSIONS

Conduct up to one (1) additional on-site basic operating and safety training sessions at the request of the GTR, scheduled within ten (10) business days of each GTR request.

2.5.3 TRAINING CURRICULUM

Instruct trainees on both the 6,000-lb and 12,000-lb forklifts during each session, covering equipment controls, instrumentation, daily pre-operation inspection checklists, rated load capacity data plates, load stability and center-of-gravity principles, mast and side-shift operation, LPG fuel cylinder safety, indoor Carbon Monoxide ventilation precautions, and emergency shutdown procedures.

2.5.4 TRAINING DOCUMENTATION

Provide a signed Training Attendance Roster and Training Completion Summary to the GTR within two (2) business days after each completed training session, documenting the training date, instructor name, topics covered, and names of USCG personnel in attendance.

2.6 TASK SIX. CONTRACT CLOSEOUT AND EQUIPMENT DEMOBILIZATION

The Contractor shall demobilize and remove both forklifts upon contract completion in accordance with the following requirements:

2.6.1 EQUIPMENT REMOVAL

Remove and transport both forklifts from USCG TRACEN Birmingham-Southern within five (5) business days after contract expiration using self-contained transport equipment without using

Government lifting equipment or loading docks.

3.0 CONTRACTOR PERSONNEL

3.1 QUALIFIED PERSONNEL

The Contractor shall provide qualified personnel to perform all requirements specified in this

SOW.

3.2 CONTINUITY OF SUPPORT

The Contractor shall ensure that the services required under this SOW (equipment delivery, preventive maintenance, unscheduled repairs, equipment replacement, LPG fueling, and training) are performed within the stated timeframes. If a scheduled service visit cannot be completed as planned, the Contractor shall provide e-mail notification to the GTR as soon as practicable and shall complete the required service at the earliest opportunity.

3.3 KEY PERSONNEL

This requirement involves intermittent equipment delivery, maintenance, training, and fueling visits rather than continuous on-site staffing. No Contractor personnel are designated as Key.

3.4 EMPLOYEE IDENTIFICATION

3.4.1 FACILITY ACCESS

Contractor personnel do not require logical access to Government information systems or unescorted access to secure Government facilities. Common Access Cards (CAC) will not be issued. If temporary physical access to a Government facility is required for delivery, maintenance, training, or fueling, Contractor personnel shall comply with all local installation visitor control procedures, submit to standard security screening, and be escorted by

Government personnel as required by local policy.

3.4.2 IDENTIFICATION REQUIREMENTS

Contractor personnel shall clearly always identify themselves as contractors. This includes wearing visible corporate identification badges while at Government facilities, identifying themselves as contractors during telephone conversations and in meetings, and including a contractor designation (e.g., “[Contractor Company Name]”) in all email signatures and electronic communications.

3.5 EMPLOYEE CONDUCT

Contractor employees shall comply with all applicable Government regulations, policies and procedures (e.g., fire, safety, sanitation, environmental protection, security, and “off limits” areas) when visiting or working at Government facilities. The Contractor shall ensure Contractor employees always present a professional appearance and that their conduct does not reflect discredit on the United States or the Department of Homeland Security.

3.6 REMOVING EMPLOYEES FOR MISCONDUCT OR SECURITY REASONS

The Government may, at its sole discretion (via the Contracting Officer), direct the Contractor to remove any Contractor employee from DHS facilities for misconduct or security reasons.

Removal does not relieve the Contractor of the responsibility to continue providing the services required under the contract. The Contracting Officer will provide the Contractor with a written explanation to support any request to remove an employee.

4.0 OTHER APPLICABLE CONDITIONS

4.1 SECURITY

All work under this SOW is UNCLASSIFIED. Contractor access to classified information is not currently required under this SOW. The Contractor shall coordinate installation access with the

Government Technical Representative (GTR).

4.2 PERIOD OF PERFORMANCE

The period of performance for this contract is December 1, 2026 thru June 30, 2027

4.3 PLACE OF PERFORMANCE

The primary place of performance will be United States Coast Guard Training Center (TRACEN)

Birmingham-Southern, 900 Arkadelphia Road, Birmingham, AL 35204.

4.4 HOURS OF OPERATION

Contractor employees generally perform all work between the hours of 0800 and 1700 Central

Time, Monday through Friday (except for Federal holidays). However, there may be occasions when Contractor employees shall be required to work other than normal business hours, including weekends and holidays, to fulfill requirements under this SOW.

4.5 GENERAL REPORT REQUIREMENTS

The Contractor shall provide all written reports in electronic format with read/write capability using applications that are compatible with DHS workstations (Microsoft Office Applications).

4.6 PROTECTION OF INFORMATION

Contractor access to Privacy Act information or proprietary information beyond standard equipment manuals is not required under this SOW.

4.7 ENVIRONMENTAL COMPLIANCE

The Contractor shall contain and remove all waste oils, hydraulic fluids, spent filters, oily rags, and maintenance debris generated during on-site service visits from the installation on the same day. The Contractor shall leave no residual materials on-site and shall comply with all applicable

Federal, State, and local environmental regulations.

5.0 GOVERNMENT FURNISHED RESOURCES

The Government will provide designated outdoor/indoor parking and staging areas for the two rental forklifts, an on-site area for conducting basic operating and safety training, and access to on-site restroom facilities for Contractor personnel performing delivery, training, maintenance, and refueling visits at USCG TRACEN Birmingham-Southern.

6.0 CONTRACTOR FURNISHED PROPERTY

The Contractor shall furnish all facilities, materials, equipment and services necessary to fulfill the requirements of this contract, except for the Government Furnished Resources specified in

SOW 5.0.

7.0 GOVERNMENT ACCEPTANCE PERIOD

The GTR will review deliverables prior to acceptance and provide the Contractor with an e-mail that provides documented reasons for non-acceptance. If the deliverable is acceptable, the GTR will send an e-mail to the Contractor notifying it that the deliverable has been accepted.

7.1 Deliverable Review and Rejection

The GTR will have the right to reject or require correction of any deficiencies found in the deliverables that are contrary to the requirements of this SOW. In the event of a rejected deliverable, the Contractor will be notified in writing by the GTR of the specific reasons for rejection. The Contractor shall correct the rejected deliverable and return it per delivery instructions within the timeframe agreed with the GTR.

7.2 Review Timeframes

Unless otherwise specified in the Deliverables table or agreed in writing, the GTR will have five

(5) business days to review deliverables and provide comments. The Contractor shall have five

(5) business days to make corrections and redeliver.

8.0 DELIVERABLES

The Contractor shall consider items in BOLD as having mandatory due dates. All deliverables shall be submitted to the GTR unless otherwise noted.

ITEM SOW REF DELIVERABLE / EVENT DUE BY DISTRIBUTION

3 2.1.5 OEM Operator and Maintenance Manuals (one per forklift) Upon delivery GTR

4 2.2.4 Preventive Maintenance and Repair Service Ticket

Within 2 business days of service completion GTR

5 2.3.2 Replacement forklift (if required) Within 4 business days of GTR notification GTR

6 2.4.3 LPG Fuel Delivery Ticket (signed) With monthly invoice GTR

7 2.4.4 NTE CLIN 75% notification When cumulative fuel billings reach 75% of NTE ceiling

Contracting Officer and

GTR

8 2.5.1 Initial basic operating and safety training session

Within 5 business days after delivery and commissioning

GTR

9 2.5.2 Training sessions (up to 1) Within 10 business days of each GTR request GTR

10 2.5.4 Training Attendance Roster and Training Completion Summary

Within 2 business days after each training session GTR

11 2.6.1 Equipment demobilization and removal Within 5 business days after contract expiration GTR

File details come from the government source that posted it. Updated .