Specifications Addendum 1.pdf
PDF 108 KB Posted
- Attached to
- Y1AZ--RENOVATE CMOP WAREHOUSE
- Solicitation number
- 36S79724R0003
About this file
This document is a Federal Contract Opportunity for the renovation design and construction of the Hines, Great Lakes, Consolidated Mail Outpatient Pharmacy (CMOP) in Hines, Illinois. The Statement of Work (SOW) outlines the key objectives, which include: enclosing the CMOP swing space, replacing revolving doors with turnstiles and a smoke/fire curtain, installing exterior egress doors, and adding fire suppression to the walk-in refrigerator/freezer. The contract is an IDIQ valued at $VA770-17-P-1447, with Project Number 765-16-02. The period of performance is six months. Key requirements include demolition, construction, electrical, plumbing, fire safety, and HVAC work to meet NFPA and other codes/standards. Contractors must be qualified, follow all safety regulations, and coordinate closely with the Contracting Officer's Representative to minimize impacts to CMOP operations. Proposals are due August 27, 2024.
View the file
Other files
Show all 29
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
A/E Services – Warehouse Renovation Design 06-01-24 GL CMOP Hines, Illinois IDIQ# VA770-17-P-1447 | VA Project Number: 765-16-02 Submittal Date: August 27, 2024
00 01 10 - 1
SECTION 00 01 10
TABLE OF CONTENTS
SECTION NO DIVISION AND SECTION TITLES DATE
DIVISION 00 - SPECIAL SECTIONS
00 01 15 List of Drawing Sheets 05-20
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements 11-21
01 33 23 Shop Drawings, Product Data, and Samples 11-23
01 35 26 Safety Requirements 05-24
01 45 00 Quality Control 02-21
01 91 00 General Commissioning Requirements 04-22
DIVISION 02 – EXISTING CONDITIONS
02 41 19 Selective Demolition 08-17
DIVISIONS 03–05 NOT USED
DIVISION 06 – WOOD, PLASTICS AND COMPOSITES
06 10 00 Rough Carpentry 10-17
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 21 13 Thermal Insulation 01-21
07 84 00 Firestopping 01-21
DIVISION 08 - OPENINGS
08 11 13 Hollow Metal Doors and Frames 01-21
08 31 13 Access Doors and Frames 04-22
A/E Services – Warehouse Renovation Design 06-01-24
00 01 10 - 2
SECTION NO DIVISION AND SECTION TITLES DATE
08 33 00 Coiling Doors and Grilles 01-21
08 71 00 Door Hardware 03-24
08 80 00 Glazing 01-21
DIVISION 09 – FINISHES
09 22 16 Non-Structural Metal Framing 06-18
09 29 00 Gypsum Board 04-20
09 51 00 Acoustical Tile Ceilings 12-18
09 91 00 Painting 01-21
DIVISIONS 10–27 NOT USED
DIVISIONS 21 – 28
Refer to Drawings for Divisions 21 – 28 Specifications
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 31 13 Chain Link Fences and Gates 05-18
32 05 23 Cement and Concrete for Exterior Improvements 08-16
DIVISIONS 33–48 NOT USED
- - - E N D - - -
A/E Services – Warehouse Renovation Design 08-01-16
32 05 23 - 1
SECTION 32 05 23
CEMENT AND CONCRETE FOR EXTERIOR IMPROVEMENTS
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Subbase for concrete pavements.
2. Curbs.
3. Pedestrian Pavement: Walks, grade slabs, pedestrian crossings,
1.2 RELATED REQUIREMENTS
A. Field Testing: Section 01 45 29, TESTING LABORATORY SERVICES.
1.3 APPLICABLE PUBLICATIONS
A. Comply with references to extent specified in this section.
B. American Association of State Highway and Transportation Officials
(AASHTO):
1. M147-65-UL-04 - Materials for Aggregate and Soil-Aggregate Subbase, Base and Surface Courses.
2. M233-86 - Boiled Linseed Oil Mixture for Treatment of Portland
Cement Concrete.
C. American Concrete Institute (ACI):
1. 305R-10 - Guide to Hot Weather Concreting.
2. 306R-10 - Guide to Cold Weather Concreting.
D. American National Standards Institute (ANSI):
1. B101.3 - Wet DOCF of Common Hard Surface Floor Materials (Including
Action and Limit Thresholds for the Suitable Assessment of the
Measured Values).
E. ASTM International (ASTM):
1. A615/A615M-16 - Deformed and Plain Carbon Steel Bars for Concrete
Reinforcement.
2. A996/A996M-15 - Rail-Steel and Axle-Steel Deformed Bars for Concrete
Reinforcement.
3. A1064/A1064M-16 - Carbon-Steel Wire and Welded Wire Reinforcement, Plain and Deformed, for Concrete.
4. C33/C33M-16 - Concrete Aggregates.
5. C94/C94M-16 - Ready Mixed Concrete.
6. C143/C143M-15a - Slump of Hydraulic Cement Concrete.
7. C150/C150M-16 - Portland Cement.
32 05 23 - 2
8. C171-16 - Sheet Materials for Curing Concrete.
9. C260/C260M-10a - Air Entraining Admixtures for Concrete.
10. C309-11 - Liquid Membrane Forming Compounds for Curing Concrete.
11. C494/C494M-15a - Chemical Admixtures for Concrete.
12. C618-15 - Coal Fly Ash and Raw or Calcined Natural Pozzolan for Use in Concrete.
13. C979/C979M-16 - Pigments for Integrally Colored Concrete.
14. C989/C989M-14 - Slag Cement for Use in Concrete and Mortars.
15. C1240-15 - Silica Fume Used in Cementitious Mixtures.
16. D1751-04(2013)e1 - Preformed Expansion Joint Filler for Concrete
Paving and Structural Construction (Nonextruding and Resilient
Bituminous Types).
17. D5893/D5893M-10 - Cold Applied, Single Component, Chemically Curing
Silicone Joint Sealant for Portland Cement Concrete Pavements.
18. D6690-15 - Joint and Crack Sealants, Hot Applied, for Concrete and
Asphalt Pavements.
1.4 PREINSTALLATION MEETINGS
A. Conduct preinstallation meeting at project site minimum 30 days before beginning Work of this section.
1. Required Participants:
a. Contracting Officer's Representative.
b. Inspection and Testing Agency.
c. Contractor.
d. Installer.
2. Meeting Agenda: Distribute agenda to participants minimum 3 days before meeting.
a. Installation schedule.
b. Installation sequence.
c. Preparatory work.
d. Protection before, during, and after installation.
e. Installation.
f. Terminations.
g. Transitions and connections to other work.
h. Inspecting and testing.
i. Other items affecting successful completion.
32 05 23 - 3
3. Document and distribute meeting minutes to participants to record decisions affecting installation.
1.5 SUBMITTALS
A. Submittal Procedures: Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.
B. Submittal Drawings:
1. Show size, configuration, and fabrication and installation details.
2. Show reinforcing.
3. Include jointing plan for concrete pavements, curbs and gutters.
C. Manufacturer's Literature and Data:
1. Description of each product.
2. Installation instructions.
D. Samples:
1. Exposed Aggregate Concrete Panel: 0.4 sq. m by 50 mm (4 sq. ft. by
2 inches) thick, 2 required, each color and finish.
2. Colored Concrete Panel: As specified in Section 09 06 00, SCHEDULE
FOR FINISHES, with mix data.
E. Test reports: Certify products comply with specifications.
1. Concrete materials.
2. Select subbase materials.
3. Field test reports.
F. Certificates: Certify products comply with specifications.
1. Expansion joint filler.
2. Reinforcement.
3. Curing materials.
4. Concrete protective coating.
G. Qualifications: Substantiate qualifications comply with specifications.
1. Installer // with project experience list //.
2. Land surveyor.
H. Concrete mix design.
I. Select subbase job-mix design.
J. Proposed hot and cold weather concreting methods.
K. Land surveyor's construction staking notes, before placing concrete.
1. Identify discrepancies between field conditions and Drawings.
1.6 QUALITY ASSURANCE
A. Installer Qualifications:
32 05 23 - 4
1. Regularly installs specified products.
2. Installed specified products with satisfactory service on five similar installations.
a. Project Experience List: Provide contact names and addresses for completed projects.
B. Land Surveyor: Professional land surveyor or engineer registered to provide land surveys in jurisdiction where project is located.
C. Preconstruction Testing:
1. Engage independent testing laboratory to perform tests and submit reports.
a. Deliver samples to laboratory in number and quantity required for testing.
2. Concrete mix design.
3. Select subbase job-mix design. Report the following:
a. Material sources.
b. Gradation.
c. Plasticity index.
d. Liquid limit.
e. Laboratory compaction curves indicating maximum density at optimum moisture content.
1.7 DELIVERY
A. Deliver steel reinforcement to prevent damage.
B. Before installation, return or dispose of distorted or damaged steel reinforcement.
C. Bulk Products: Deliver bulk products away from buildings, utilities, pavement, and existing turf and planted areas. Maintain dry bulk product storage away from contaminants.
1.8 STORAGE AND HANDLING
A. Store products indoors in dry, weathertight facility.
B. Protect products from damage during handling and construction operations.
1.9 FIELD CONDITIONS
A. Hot Weather Concreting Procedures: ACI 305R.
B. Cold Weather Concreting Procedures: ACI 306R.
1. Use non-corrosive, non-chloride accelerator admixture.
32 05 23 - 5
2. Do not use calcium chloride, thiocyanates or admixtures containing more than 0.05 percent chloride ions.
1.10 WARRANTY
A. Construction Warranty: FAR clause 52.246-21, "Warranty of
Construction."
PART 2 - PRODUCTS
2.1 CONCRETE MATERIALS
A. Portland Cement: ASTM C150/C150M, Type I or II.
B. Pozzolans:
1. Fly Ash: ASTM C618, Class C or F including supplementary optional physical requirements.
2. Slag: ASTM C989/C989M; Grade 80.
3. Silica Fume: ASTM C1240.
C. Coarse Aggregate: ASTM C33/C33M; size 57 or 67to suit application .
D. Fine Aggregate: ASTM C33/C33M.
E. Mixing Water: Fresh, clean, and potable.
F. Air-Entraining Admixture: ASTM C260/C260M.
G. Chemical Admixtures: ASTM C494/C494M.
H. Reinforcing Steel: ASTM A615/A615M or ASTM A996/A996M, Grade 420 (60);
deformed.
I. Welded Wire Fabric: ASTM A1064/A1064M, deformed; Grade 385 (56);.
J. Expansion Joint Filler: ASTM D1751.
K. Sheet Materials for Curing Concrete: ASTM C171.
2.2 SELECT SUBBASE
A. Subbase: AASHTO M147;Grade A
1. Select granular material composed of sand, sand-gravel, crushed stone, crushed or granulated slag, with or without soil binder, or combinations of these materials.
32 05 23 - 6
SUBBASE GRADING REQUIREMENTS
Sieve Size Percentage Passing by Mass
Grades
(mm) (in) A B C D E F
50 2 100 100
25 1 75-95 100 100 100 100
9.5 3/8 30-65 40-75 50-85 60-100
4.47 No. 4 25-55 30-60 35-65 50-85 55-100 70-100
2.00 No. 10 15-40 20-45 25-50 40-70 40-100 55-100
0.425 No. 40 8-20 15-30 15-30 25-45 20-50 30-70
0.075 No. 200 2-8 5-20 5-15 5-20 6-20 8-25
B. Other Acceptable Gradations: Materials within three to five percent, plus or minus, of specified gradation, or as recommended by the geotechnical engineer and approved by the Contracting Officer's
Representative.
2.3 FORMS
A. Forms: Wood, plywood, metal, or other materials, approved by
Contracting Officer's Representative, of grade or type suitable to obtain type of finish specified.
1. Plywood: Exterior grade, free of defects and patches on contact surface.
2. Lumber: Sound, grade-marked, S4S stress graded softwood, minimum
50 mm (2 inches) thick, free from warp, twist, loose knots, splits, or other defects.
3. Form Coating: As recommended by Architect/Engineer.
B. Provide forms suitable in cross-section, depth, and strength to resist springing during depositing and consolidating concrete.
1. Do not use forms varying from straight line more than 3 mm in
3000 mm (1/8 inch in 10 feet), horizontally and vertically.
C. Provide flexible or curved forms for forming radii.
2.4 CONCRETE CURING MATERIALS
A. Concrete curing materials, conform to one of the following:
1. Burlap: Minimum 233 g/sq. m (7 ounces/sq. yd.) dry.
2. Sheet Materials for Curing Concrete: ASTM C171.
32 05 23 - 7
3. Curing Compound: ASTM C309, Type 1 clear; liquid membrane forming type, without paraffin or petroleum.
2.5 CONCRETE MIXES
A. Design concrete mixes according to ASTM C94/C94M, Option C.
B. Concrete Type: Non-air-entrained and Air-entrained . See Table I.
C. Maximum Slump: ASTM C143/C143M. See Table II.
TABLE II - MAXIMUM SLUMP
APPLICATION MAXIMUM SLUMP
Curb & Gutter 75 mm (3 inches)
Pedestrian Pavement 75 mm (3 inches)
Vehicular Pavement 50 mm (2 inches) Machine Finished
100 mm (4 inches) Hand Finished
Equipment Pad 75 to 100 mm (3 to 4 inches)
TABLE I - CONCRETE TYPES
Concrete
Type
Minimum 28 Day
Compressive
Strength f'c
MPa (psi)
Non-Air-Entrained Air-Entrained
Min. Cement kg/cu. m
(lbs./cu. yd.)
Max.
Water
Cement
Ratio
Min. Cement kg/cu. m
(lbs./cu. yd.)
Max.
Water
Cement
Ratio
A 35 (5000)1,3 375 (630) 0.45 385 (650) 0.40
B 30 (4000)1,3 325 (550) 0.55 340 (570) 0.50
C 25 (3000)1,3 280 (470) 0.65 290 (490) 0.55
D 25 (3000)1,2 300 (500) * 310 (520) *
Footnotes:
1. If trial mixes are used, achieve compressive strength 8.3 MPa (1,200 psi) in excess of f'c. For concrete strengths greater than 35 MPa (5,000 psi), achieve compressive strength 9.7 MPa (1,400 psi) in excess of f’c.
2. For Concrete Exposed to High Sulfate Content Soils: Maximum water cement ratio is 0.44.
3. Laboratory Determined according to ACI 211.1 for normal weight concrete.
32 05 23 - 8
2.6 ACCESSORIES
A. Equipment and Tools: Obtain Contracting Officer's Representative's, approval of equipment and tools needed for handling materials and performing work before work begins.
B. Maintain equipment and tools in satisfactory working condition.
C. Sealants:
1. Concrete Paving Expansion Joints: ASTM D5893/D5893M, Type SL, single component, self-leveling, silicone joint sealant.
2. Concrete Paving Joints: ASTM D6690, Type IV, hot-applied, single component joint sealant.
D. Concrete Protective Coating: AASHTO M233 linseed oil mixture.
PART 3 - EXECUTION
3.1 PREPARATION
A. Examine and verify substrate suitability for product installation.
B. Protect existing construction and completed work from damage.
C. Prepare, construct, and finish subgrade. See Section 31 20 00, EARTHWORK.
D. Maintain subgrade in smooth, compacted condition, in conformance with the required section and established grade until the succeeding operation has been accomplished.
3.2 SELECT SUBBASE
A. Placing:
1. Place subbase material on prepared subgrade in uniform layer to required contour and grades, and to maximum 200 mm (8 inches) loose depth.
2. When required compacted thickness exceeds 150 mm (6 inches), place subbase material in equal thickness layers.
3. When subbase elevation is 13 mm (1/2 inch) or more below required grade, excavate subbase minimum 75 mm (3 inches) deep. Place and compact subbase to required grade.
B. Compaction:
1. Perform compaction with approved hand or mechanical equipment well suited to the material being compacted.
2. Maintain subbase at optimum moisture content for compaction.
32 05 23 - 9
3. Compact each subbase layer to minimum 95 percent or 100 percent of maximum density as specified in Section 31 20 00, EARTHWORK.
C. Subbase Tolerances:
1. Variation from Indicated Grade: Maximum 9 mm (3/8 inch).
2. Variation from Indicated Thickness: Maximum 13 mm (1/2 inch).
D. Protection:
1. Protect subbase from damage until concrete is placed.
2. Reconstruct damaged subbase before placing concrete.
3.3 SETTING FORMS
A. Form Substrate:
1. Compact form substrate to uniformly support forms along entire length.
2. Correct substrate imperfections and variations by cutting, filling, and compacting.
B. Form Setting:
1. Set forms to indicated line and grade with tight joints. Rigidly brace forms preventing movement.
2. Remove forms when removal will not damage concrete and when required for finishing.
3. Clean and oil forms before each use.
4. Correct forms, when required, immediately before placing concrete.
C. Land Surveyor: Establish control, alignment, and grade for forms.
1. Notify Contracting Officer's Representative immediately when discrepancies exist between field conditions and drawings.
2. Correct discrepancies greater than 25 mm (1 inch) before placing concrete.
D. Form Tolerances:
1. Variation from Indicated Line: Maximum 6 mm (1/4 inch).
2. Variation from Indicated Grade: Maximum 3 mm in 3000 mm (1/8 inch in
10 feet).
3.4 PLACING REINFORCEMENT
A. Keep reinforcement clean from contamination preventing concrete bond.
B. Install reinforcement shown on drawings.
C. Support and securely tie reinforcing steel to prevent displacement during concrete placement.
32 05 23 - 10
D. Obtain Contracting Officer's Representative's reinforcement placement approval before placing concrete.
3.5 JOINTS - GENERAL
A. Place joints, where shown on approved submittal Drawings.
1. Conform to details shown.
2. Install joints perpendicular to finished concrete surface.
B. Make joints straight and continuous from edge to edge of pavement.
3.6 CONSTRUCTION JOINTS
A. Locate longitudinal and transverse construction joints between slabs of vehicular pavement as shown on approved submittal Drawings.
B. Place transverse construction joints of type shown, where indicated, and whenever concrete placement is suspended for more than 30 minutes.
C. Provide butt-type joint with dowels in curb and gutter at planned joint locations.
D. Provide keyed joints with tie bars when joint occurs in middle third of planned curb and gutter joint interval.
3.7 CONTRACTION JOINTS
A. Tool or cut joints to width, depth, and radius edge shown on drawings using grooving tool, jointer, or saw.
B. Construct joints in curbs and gutters by inserting 3 mm (1/8 inch) steel plates conforming to curb and gutter cross sections.
1. Keep plates in place until concrete can hold its shape.
C. Finish joint edges with edging tool.
D. Score pedestrian pavement with grooving tool or jointer.
3.8 EXPANSION JOINTS
A. Form expansion joints with expansion joint filler of thickness shown on drawings.
1. Locate joints around perimeter of structures and features abutting site work concrete.
2. Create complete, uniform separation between structure and site work concrete.
B. Extend expansion joint material full depth of concrete with top edge of joint filler below finished concrete surface where sealant is indicated on Drawings.
C. Cut and shape material matching cross section.
32 05 23 - 11
D. Anchor with approved devices to prevent displacing during placing and finishing operations.
E. Round joint edges with edging tool.
3.9 PLACING CONCRETE - GENERAL
A. Preparation before Placing Concrete:
1. Obtain Contracting Officer's Representative approval.
2. Remove debris and other foreign material.
3. Uniformly moisten substrate, without standing water.
B. Convey concrete from mixer to final location without segregation or loss of ingredients. Deposit concrete to minimize handling.
C. During placement, consolidate concrete by spading or vibrating to minimize voids, honeycomb, and rock pockets.
1. Vibrate concrete against forms and along joints.
2. Avoid excess vibration and handling causing segregation.
D. Place concrete continuously between joints without bulkheads.
E. Install construction joint in concrete placement suspended for more than 30 minutes.
F. Replace concrete with cracks, chips, bird baths, and other defects to nearest joints, approved by Contracting Officer's Representative.
3.10 PLACING CONCRETE FOR CURB AND GUTTER, PEDESTRIAN PAVEMENT, AND
EQUIPMENT PADS
A. Place concrete in one layer conforming to cross section shown on
Drawings after consolidating and finishing.
B. Deposit concrete near joints without disturbing joints. Do not place concrete directly onto joint assemblies.
C. Strike concrete surface to proper section ready for consolidation.
D. Consolidate concrete // by tamping and spading or with approved mechanical finishing equipment .
E. Finish concrete surface with wood or metal float.
F. Construct concrete pads and pavements with sufficient slope to drain, preventing standing water.
3.11 PLACING CONCRETE FOR VEHICULAR PAVEMENT
A. Deposit concrete as close as possible to its final position.
B. Place concrete continuously between construction joints without cold joints.
32 05 23 - 12
C. Strike and consolidate concrete with finishing machine, vibrating screed, or by hand-finishing.
D. Finish concrete surface to elevation and crown shown on drawings.
E. Deposit concrete near joints without disturbing joints. Do not place concrete directly onto joint assemblies.
F. Obtain Contracting Officer's Representative's approval before placing adjacent lanes.
3.12 FORM REMOVAL
A. Keep forms in place minimum 12 hours after concrete placement. Remove forms without damaging concrete.
B. Do not use bars or heavy tools against concrete to remove forms. Repair damage concrete found after form removal.
3.13 CONCRETE FINISHING - GENERAL
A. Follow operation sequence below, unless otherwise indicated on
Drawings:
1. Consolidating, floating, striking, troweling, texturing, and joint edging.
B. Use edging tool with 6 mm (1/4 inch) radius, unless otherwise shown on
Drawings.
C. Keep finishing equipment and tools clean and suitable for use.
3.14 CONCRETE FINISHING - PEDESTRIAN PAVEMENT
A. Walks, Grade Slabs
1. Finish concrete surfaces with metal float, troweled smooth, and finished with a broom moistened with clear water.
2. Finish slab edges and formed transverse joints with edger.
3. Broom surfaces transverse to traffic direction.
a. Use brooming to eliminate flat surface produced by edger.
b. Produce uniform corrugations, maximum 1.5 mm (1/16 inch) deep profile.
4. Provide surface uniform in color and free of surface blemishes, form marks, and tool marks.
5. Paving Tolerances:
a. Variation from Indicated Plane: Maximum 5 mm in 3000 mm (3/16 inch in 10 feet).
b. Variation from Indicated Thickness: Maximum 6 mm (1/4 inch).
32 05 23 - 13
6. Replace paving within joint boundary when paving exceeds specified tolerances.
B. Step Treads, Risers and Sidewalls: Finish as specified for pedestrian pavement, except as follows:
1. Remove riser forms sequentially, starting with top riser.
2. Rub riser face with wood or concrete rubbing block and water. Remove blemishes, form marks, and tool marks. Use outside edger to round nosing; use inside edger to finish bottom of riser.
3. Apply uniform brush finish to treads, risers, and sidewall.
a. Apply stiff brush finish to treads to provide slip resistant surface complying with ANSI B101.3.
4. Step Tolerance:
a. Variation from Indicated Plane: Maximum 5 mm in 3000 mm (3/16 inch in 10 feet).
3.15 CONCRETE FINISHING - VEHICULAR PAVEMENT
A. Align finish surfaces where new and existing pavements abut.
B. Longitudinally float pavement surface to profile and grade indicated on drawings.
C. Straighten surface removing irregularities and maintaining specified tolerances while concrete is plastic.
D. Finish pavement edges and joints with edging tool.
E. Broom finish concrete surface after bleed water dissipates and before concrete hardens.
1. Broom surface transverse to traffic direction.
a. Use brooming to eliminate flat surface produced by edger.
b. Produce uniform corrugations, maximum 3 mm (1/8 inch) deep profile.
F. Pavement Tolerances:
1. Variation from Indicated Plane: Maximum 6 mm in 3000 mm (1/4 inch in
10 feet) tested parallel and perpendicular to traffic direction at maximum 1500 mm (5 feet) intervals.
2. Variation from Indicated Thickness: Maximum 6 mm (1/4 inch).
G. Replace paving within joint boundary when paving exceeds specified tolerances.
3.16 CONCRETE FINISHING - CURBS AND GUTTERS
A. Round edges of gutter and top of curb with edging tool.
32 05 23 - 14
B. Gutter and Curb Top:
1. Float surfaces and finish with smooth wood or metal float until true to grade and section and uniform color.
2. Finish surfaces, while still plastic, longitudinally with bristle brush.
C. Curb Face:
1. Remove curb form and immediately rub curb face with wood or concrete rubbing block removing blemishes, form marks, and tool marks and providing uniform color.
2. Brush curb face, while still plastic, matching gutter and curb top.
D. Curb and Gutter Tolerances: Except at grade changes or curves.
1. Variation from Indicated Plane and Grade:
a. Gutter: Maximum 3 mm in 3000 mm (1/8 inch in 10 feet).
b. Curb Top and Face: Maximum 6 mm in 3000 mm (1/4 inch in
10 feet).
E. Replace curbs and gutters within joint boundary when curbs and gutters exceed specified tolerances.
F. Correct depressions causing standing water.
3.17 CONCRETE FINISHING - EQUIPMENT PADS
A. Strike pad surface to elevation shown on Drawings.
B. Provide smooth, dense float finish, free from depressions or irregularities.
C. Finish pad edges with edger.
D. After removing forms, rub pad edge faces with wood or concrete rubbing block, removing blemishes, form marks, and tool marks and providing uniform color.
E. Pad Tolerances:
1. Variation from Indicated Plane: Maximum 3 mm in 3000 mm (1/8 inch in
10 feet).
2. Variation from Indicated Elevation: Maximum 6 mm (1/4 inch).
3. Variation from Indicated Thickness: Maximum 6 mm (1/4 inch).
F. Replace pads when pads exceed specified tolerances.
3.18 SPECIAL FINISHES (NOT USED)
3.19 CONCRETE CURING
A. Concrete Protection:
1. Protect unhardened concrete from rain and flowing water.
32 05 23 - 15
2. Provide sufficient curing and protection materials available and ready for use before concrete placement begins.
3. Protect concrete to prevent pavement cracking from ambient temperature changes during curing period.
a. Replace pavement damaged by curing method allowing concrete cracking.
b. Employ another curing method as directed by Contracting
Officer's Representative.
B. Cure concrete for minimum 7 days by one of the following methods appropriate to weather conditions preventing moisture loss and rapid temperature change:
1. Burlap Mat: Provide minimum two layers kept saturated with water during curing period. Overlap Mats at least 150 mm (6 inches).
2. Sheet Materials:
a. Wet exposed concrete surface with fine water spray and cover with sheet materials.
b. Overlap sheets minimum 300 mm (12 inches).
c. Securely anchor sheet materials preventing displacement.
3. Curing Compound:
a. Protect joints indicated to receive sealants preventing contamination from curing compound.
b. Insert moistened paper or fiber rope into joint or cover joint with waterproof paper.
c. Apply curing compound before concrete dries.
d. Apply curing compound in two coats at right angles to each other.
e. Application Rate: Maximum 5 sq. m/L (200 sq. ft./gallon), both coats.
f. Immediately reapply curing compound to surfaces damaged during curing period.
3.20 CONCRETE PROTECTIVE COATING
A. Apply protective coating of linseed oil mixture to exposed-to-view concrete surfaces, drainage structures, and features that project through, into, or against concrete exterior improvements to protect the concrete against deicing materials.
32 05 23 - 16
B. Complete backfilling and curing operation before applying protective coating.
C. Dry and thoroughly clean concrete before each application.
D. Apply two coats, with maximum coverage of 11 sq. m/L (50 sq.
yds./gal.); first coat, and maximum 16 sq. m/L (70 sq. yds./gal.);
second coat, except apply commercially prepared mixture according to manufacturer's instructions.
E. Protect coated surfaces from vehicular and pedestrian traffic until dry.
F. Do not heat protective coating, and do not expose protective coating to open flame, sparks, or fire adjacent to open containers or applicators.
Do not apply material at temperatures lower than 10 degrees C
(50 degrees F).
3.21 FIELD QUALITY CONTROL
A. Field Tests: Performed by testing laboratory specified in Section
01 45 29, TESTING LABORATORY SERVICES.
1. Compaction.
a. Pavement subgrade.
b. Curb, gutter, and sidewalk.
2. Concrete:
a. Delivery samples.
b. Field samples.
3. Slip Resistance: Steps and pedestrian paving.
3.22 CLEANING
A. After completing curing:
1. Remove burlap and sheet curing materials.
2. Sweep concrete clean, removing foreign matter from the joints.
3. Seal joints as specified.
3.23 PROTECTION
A. Protect exterior improvements from traffic and construction operations.
1. Prohibit traffic on paving for minimum seven days after placement, or longer as directed by Contracting Officer's Representative.
B. Remove protective materials immediately before acceptance.
C. Repair damage.
1. Replace concrete containing excessive cracking, fractures, spalling, and other defects within joint boundary, when directed by
32 05 23 - 17
Contracting Officer's Representative, and at no additional cost to the Government.
- - - E N D - - -