36E77620R0043.docx

DOCX document 99 KB Posted

Attached to
Y1GZ--Construct Replacement Warehouse Prescott VAMC (Minor Construction) Federal contract opportunity
Solicitation number
36E77620R0043
Issued by
Department of Veterans Affairs Headquarters

About this file

This document provides details for a federal solicitation seeking proposals to construct a replacement warehouse facility at the Northern Arizona VA Health Care System in Prescott, Arizona. The solicitation will be issued as a Request for Proposal evaluated under the Lowest Price Technically Acceptable procedure. It is a total Service-Disabled Veteran-Owned Small Business set-aside with a NAICS code of 236220 and size standard of $39.5 million. The period of performance is approximately 360 calendar days from notice to proceed. The project involves demolishing existing warehouse buildings from 1908 and constructing a new approximately 10,930 square foot conditioned storage warehouse with nearly 30,000 square feet of paved areas for loading and parking. Questions must be submitted in writing by August 20, 2020 and the solicitation will be issued on or around July 27, 2020.

View the file

Other files for this federal contract opportunity

Other files attached to Y1GZ--Construct Replacement Warehouse Prescott VAMC (Minor Construction), newest first.
File Type Posted
36E77620R0043 0006.docx DOCX document
Technical Questions Tracking Sheet - 09-14-2020.pdf PDF
Monitoring and Discovery Protocol.pdf PDF
1395.26_Revised Roof Slope Sketch.pdf PDF
Telecom Specs1.pdf PDF
36E77620R0043 0005.docx DOCX document
Technical Questions Tracking Sheet - 09-09-2020.pdf PDF
Construction Wage Rates - Yavapai - 08-21-2020.pdf PDF
10 26 00 Wall Protection.pdf PDF
Item 81 response_Fire-rated Ceiling Assembly Detail.pdf PDF
36E77620R0043 0004.docx DOCX document
Item 70 response_Drawing-Montage Commercial Classic.pdf PDF
07 43 00 Wall and Roof Panels.pdf PDF
Item 69 response_Drawing-Montage Commercial Classic Gate.pdf PDF
1395.26 Construct Replacement Warehouse_ASI 002 Narrative.pdf PDF
01 00 00 - General Requirements.pdf PDF
S05 - Technical Questions Tracking Sheet TO BE PUBLISHED 9-4.pdf PDF
36E77620R0043 0003.docx DOCX document
Reference C - Question 112 - 067 165-M-301 MECHANICAL SECTIONS AND ENLARGED.pdf PDF
Reference E - Question 113 - DIV 13 SPECIAL CONSTRUCTION.pdf PDF
Reference D - Question 113 - 026 165-SA-001 STRUCTURAL GENERAL NOTES.pdf PDF
Technical Questions Tracking Sheet 36E77620R0043.pdf PDF
36E77620R0043 0002.docx DOCX document
36E77620R0043 - SITE VISIT SIGN IN SHEET - 08-11-2020.pdf PDF
36E77620R0043 0001.docx DOCX document
Attachment 16 - Contractor Safety _ Env Record Form.docx DOCX document
Attachment 11 - S Drawings.pdf PDF
Attachment 12 - T Drawings.pdf PDF
Attachment 10 - P Drawings.pdf PDF
Attachment 15 - Construction Wage Rates - Yavapai - 06-05-2020.pdf PDF
Copy of Attachment 14 - Division Price Breakdown.xlsx XLSX spreadsheet
Attachment 7 - F Drawings.pdf PDF
Attachment 13 - Warehouse Building Soils Report.pdf PDF
Attachment 5 - C Drawings Part II.pdf PDF
Attachment 6 - E Drawings.pdf PDF
Attachment 1 - Volume 01 Specifications REV.pdf PDF
Attachment 9 - M Drawings.pdf PDF
Attachment 4 - A Drawings.pdf PDF
Attachment 3 - Volume 03 Specifications REV.pdf PDF
Attachment 8 - G Drawings.pdf PDF
Attachment 2 - Volume 02 Specifications.pdf PDF
Attachment 5 - C Drawings Part I.pdf PDF
Attachment 17 - Prescott Site Map.pdf PDF
Show all 43

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

36E77620R0043

1. SOLICITATION NUMBER

2. TYPE OF SOLICITATION

3. DATE ISSUED

PAGE OF PAGES

4. CONTRACT NUMBER

5. REQUISITION/PURCHASE REQUEST NUMBER

6. PROJECT NUMBER

7. ISSUED BY

CODE

8. ADDRESS OFFER TO

a. NAME

b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date) 12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

12b. CALENDAR DAYS

13. ADDITIONAL SOLICITATION REQUIREMENTS:

STANDARD FORM 1442 (REV. 8/2014)

STANDARD FORM 1442

Prescribed by GSA-FAR (48 CFR) 52.236-1(d)

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

SOLICITATION

SOLICITATION

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR INFORMATION

CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SEALED BID (IFB)

NEGOTIATED (RFP)

11. The Contractor shall begin performance within ____________ calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).

YES

NO

a.

Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.

b.

An offer guarantee is, is not required.

c.

All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d.

Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

36E77620R0043 X 07-30-2020 649-414 Y

PCAC

PCAC POST AWARD CO

Department of Veterans Affairs Program Contracting Activity Central 6150 Oak Tree Blvd, Suite 300 Independence

OH

44131 Y Jamahel Fayall Department of Veterans Affairs Program Contracting Activity Central 6150 Oak Tree Blvd, Suite 300 Independence

OH

44131 Jamahel Fayall 216-447-8300x49580 In accordance with 38 U.S.C. § 8127 (Public Law 109-461), this project is a competitive Service-Disabled Veteran- Owned Small Business (SDVOSB) Set-Aside.

Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish all tools, equipment, materials, labor, supervision and personnel to perform work for the "Construct Replacement Warehouse" Minor Construction project as required by the attached drawings and specifications.

The project is located at the:

Northern Arizona VA Health Care System - Prescott 500 Highway 89 North Prescott, AZ 86313

NAICS Code: 236220 ($39.5M) VAAR Magnitude of Construction: $5,000,000.00 to $10,000,000.00

10 (TEN)

X X 52.211-10 X

10 (TEN)

0 (ZERO)

02:00 PM

09-02-2020 X

90 (NINETY)

14. NAME AND ADDRESS OF OFFEROR

15. TELEPHONE NUMBER

16. REMITTANCE ADDRESS

CODE

FACILITY CODE

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

AMENDMENT

NUMBER

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE

21. ITEMS ACCEPTED:

22. AMOUNT

23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

ITEM

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c)( 41 U.S.C. 3304(a) (

26. ADMINISTERED BY

27. PAYMENT WILL BE MADE BY

PHONE:

FAX:

28. NEGOTIATED AGREEMENT

29. AWARD

Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.

shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER

TO SIGN

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE

BY

OFFER

AWARD

STANDARD FORM 1442 (REV. 8/2014) BACK

(Include ZIP Code) (Include area code) (Include only if different than Item 14.)

(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each) (Type or print) (4 copies unless otherwise specified) (Type or print) (Type or print) (Contractor is required to sign this document and return _______ copies to issuing office.)

(Contractor is not required to sign this document.)

(Must be fully completed by offeror) (To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

See Price Schedule

PCAC

Department of Veterans Affairs Program Contracting Activity Central 6150 Oak Tree Blvd, Suite 300 Independence

OH

44131

VAFSC

Department of Veterans Affairs Financial Services Center Invoices to be Submitted Electronically www.ob10.com/us/en/veterans-affairs/ e-Invoice Setup Info Phone 877-489-6135

877-353-9791 512-460-5429 Donald A. Marsh III

PCAC15L3-1697

Table of Contents

PART I - THE SCHEDULE1
SECTION A - SOLICITATION/CONTRACT FORM1
A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair)1
A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION, ALTERATION, OR REPAIR)– BACK2
PRICE SCHEDULE6
INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS7
1.1 PROPOSAL MATERIAL:7
1.2 BID GUARANTEE:7
1.3 PAYMENT & PERFORMANCE BONDS:7
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS8
2.2 REQUEST FOR PROPOSAL & BASIS FOR AWARD:8
2.3 SDVOSB SET-ASIDE:8
2.4 TECHNICAL QUESTIONS:8
2.5 AMENDMENTS:8
2.6 PREPARATION OF PROPOSALS:8
2.7 PROPOSAL REQUIREMENTS:8
2.9 DETERMINATION OF RESPONSIBILITY:13
2.10 VETS 4212:14
2.11 SYSTEM FOR AWARD MANAGEMENT (SAM):14
2.12 BACKGROUND INVESTIGATIONS AND SPECIAL AGREEMENT CHECKS:14
2.13 REVIEW REQUIRED REGISTRATION WITH CONTRACTOR PERFORMANCE ASSESSMENT SYSTEM (CPARS):14
2.14 REFERENCES TO VA ENGINEER, RESIDENT ENGINEER OR PROJECT MANAGER:15
2.15 52.216-1 TYPE OF CONTRACT (APR 1984)15
2.16 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014)15
2.17 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)15
2.18 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014)16
2.19 52.228-1 BID GUARANTEE (SEP 1996)17
2.20 52.233-2 SERVICE OF PROTEST (SEP 2006)18
2.21 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)19
2.22 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)19
2.23 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (OCT 2018)20
REPRESENTATIONS AND CERTIFICATIONS21
3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (MAR 2020)21
3.2 52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS AND VIDEO SURVEILLANCE SERVICES OR EQUIPMENT (DEC 2019)25
3.3 52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018)26
3.4 52.209-13 VIOLATION OF ARMS CONTROLS TREATIES OR AGREEMENTS—CERTIFICATION (JUL 2020)27
GENERAL CONDITIONS30
4.1 52.204-21 BASIC SAFEGUARDING OF COVERED CONTRACTOR INFORMATION SYSTEMS (JUN 2016)30
4.2 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)31
4.3 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (MAY 2020)32
4.4 52.223-2 AFFIRMATIVE PROCUREMENT OF BIOBASED PRODUCTS UNDER SERVICE AND CONSTRUCTION CONTRACTS (SEP 2013)35
4.5 52.223-9 ESTIMATE OF PERCENTAGE OF RECOVERED MATERIAL CONTENT FOR EPA-DESIGNATED ITEMS (MAY 2008)35
4.6 52.223-20 AEROSOLS (JUN 2016)36
4.7 52.223-21 FOAMS (JUN 2016)37
4.8 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (MAY 2014)37
4.9 52.228-5 INSURANCE—WORK ON A GOVERNMENT INSTALLATION (JAN 1997)40
4.10 SUPPLEMENTAL INSURANCE REQUIREMENTS41
4.11 52.236-4 PHYSICAL DATA (APR 1984)41
4.12 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)42
4.13 VAAR 852.203-70 COMMERCIAL ADVERTISING (MAY 2018)45
4.14 VAAR 852.219-10 VA NOTICE OF TOTAL SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESS SET-ASIDE (JUL 2019) (DEVIATION)45
4.15 VAAR 852.219-74 LIMITATIONS ON SUBCONTRACTING—MONITORING AND COMPLIANCE (JUL 2018)47
4.16 VAAR 852.223-71 SAFETY AND HEALTH (SEP 2019)48
4.17 VAAR 852.228-70 BOND PREMIUM ADJUSTMENT (JAN 2008)49
4.18 VAAR 852.228-72 ASSISTING SERVICE-DISABLED VETERAN-OWNED AND VETERAN-OWNED SMALL BUSINESSES IN OBTAINING BONDS (DEC 2009)49
4.19 VAAR 852.232-70 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (WITHOUT NAS– CPM) (NOV 2018)50
4.20 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2018)52
4.21 VAAR 852.236-71 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (APR 2019)54
4.22 VAAR 852.236-79 CONTRACTOR PRODUCTION REPORT (APR 2019)55
4.23 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 2019)55
4.24 VAAR 852.242-70 GOVERNMENT CONSTRUCTION CONTRACT ADMINISTRATION (APR 2019)55
4.25 VAAR 852.243-70 CONSTRUCTION CONTRACT CHANGES—SUPPLEMENT (SEP 2019)56
4.26 VAAR 852.270-1 REPRESENTATIVES OF CONTRACTING OFFICERS (JAN 2008)58
4.27 MANDATORY WRITTEN DISCLOSURES58
LIST OF ATTACHMENTS59

PRICE SCHEDULE

CLIN 0001, GENERAL CONSTRUCTION: Work includes general construction, alterations, roads, walks, grading, drainage, necessary removal of existing structures and construction and certain other items for construction of a new Warehouse Facility, as identified by the construction drawings and specifications.

The period of performance is 360 calendar days after date of receipt of Notice to Proceed.

CLIN 0001: $__________________________________

CLIN 0002, ELECTRICAL WORK: Work includes all labor, material, equipment and supervision to perform the required electrical construction work on this project., as identified by the construction drawings and specifications.

The period of performance is 360 calendar days after date of receipt of Notice to Proceed.

CLIN 0002: $__________________________________

CLIN 0003, MECHANICAL WORK: Work includes all labor, material, equipment and supervision to perform the required Mechanical construction work on this project including., as identified by the construction drawings and specifications.

The period of performance is 360 calendar days after date of receipt of Notice to Proceed.

CLIN 0003: $__________________________________

TOTAL CLINS 0001, 0002 and 0003: $__________________________________

NOTICE

1. CLIN 0001, CLIN 0002 and CLIN 0003 contain all the work for this project.

2. Offerors must provide a lump sum price for CLIN 0001, CLIN 0002 and CLIN 0003. Failure to do so may render their proposal as nonresponsive.

3. Award will be made on the TOTAL of CLIN 0001, CLIN 0002 and CLIN 0003.

4. Pricing shall be submitted in whole dollar values. Please do not include pricing in cents.

5. Please ensure that in addition to submitting the Price Schedule, Attachment 14 - Division Price Breakdown is completed as part of your Volume II submission.

Page 1 of Page 1 of

INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS

1.1 PROPOSAL MATERIAL:

Proposal materials consisting of drawings, specifications, and contract forms are included and/or attached as part of this Request For Proposal. The VA will not provide printed copies of drawings or specifications. It is the responsibility of the offeror to obtain the proposal materials in a time and manner sufficient to respond to this solicitation by the specified due date.

1.2 BID GUARANTEE:

A Bid Guarantee, SF 24, is required in an amount not less than 20 percent of the proposal price but shall not exceed $3,000,000. Failure to furnish the required bid (proposal) guarantee in the proper form and amount, by the time set for receipt of proposals, may result in the rejection of the proposal. Copies of the SF 24 may be obtained from http://www.gsa.gov/portal/forms/type/TOP.

1.3 PAYMENT & PERFORMANCE BONDS:

The offeror to whom award is made will be required to furnish two bonds, a Payment Bond, SF 25A, and a Performance Bond, SF 25, each in the penal sum as noted in the General Conditions of the Solicitation. Copies of SFs 25 and 25A may be obtained from http://www.gsa.gov/portal/forms/type/TOP.

INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS

2.1 AVAILABILITY OF SOLICITATION DOCUMENTS:

All solicitation related documents will be published to Contract Opportunities at https://beta.sam.gov//.

2.2 REQUEST FOR PROPOSAL & BASIS FOR AWARD:

This is a Request For Proposal (RFP) in accordance with FAR Part 15. Award will be made to the offeror whose proposal represents the “best value” to the Government utilizing the Lowest Price Technically Acceptable (LPTA) method of evaluation. The Technical submissions for Factor 1 and 2 shall be included in Volume I (Technical)) and the submittal for Price shall be included in Volume II (Price). In order to be eligible for award, a rating of acceptable must be achieved for the two (2) Technical evaluation factors: Project Work Plan and Metal Insulated Panels. Additionally, all proposals shall include Volume III (Administrative Information) as detailed in section 2.5 (B)(4). A responsibility determination will be made in accordance with FAR 9.1, Responsible Prospective Contractors. All proposals shall be subject to evaluation by a team of Government personnel. The Government reserves the right to award without discussions based upon the initial evaluation of the proposals.

2.3 SDVOSB SET-ASIDE:

This procurement is 100% set-aside for Service-Disabled Veteran-Owned Small Business concerns. Offers received from other than Service-Disabled Veteran-Owned Small Business concerns will not be considered. All Service-Disabled Veteran-Owned Small Businesses must be listed as verified by the VA’s Center for Veterans Enterprises (CVE) (http://www.vetbiz.gov). Offerors must be verified by CVE and visible in the Vendor Information Pages (VIP) database at TIME OF SUBMISSION OF OFFERS AND TIME OF AWARD. Failure to be BOTH visible and verified at the time of proposal submission and award will result in the offeror’s proposal being deemed unacceptable and ineligible for award.

2.4 TECHNICAL QUESTIONS:

Questions of a technical nature must be provided in writing and shall be submitted by the prospective offerors to Jamahel Fayall. Questions shall be submitted only via e-mail to: jamahel.fayall@va.gov. The subject line must read: Construct Replacement Warehouse – Technical Questions. Oral questions of a technical nature are not acceptable. THE CUT-OFF DATE AND TIME FOR RECEIPT OF QUESTIONS IS August 20, 2020 at 2:00 PM (ET). Any questions submitted after the cut off date may not be answered.

2.5 AMENDMENTS:

Amendments to this solicitation will be posted at Contract Opportunities at https://beta.sam.gov//. Paper copies of the amendments will NOT be individually mailed. No other notification of amendments will be provided. Potential Offerors are advised that they are responsible for obtaining and acknowledging any amendments to the solicitation. Failure to acknowledge an amendment may result in your proposal being considered unacceptable.

2.6 PREPARATION OF PROPOSALS:

The Government will not pay for any costs incurred in preparation and submission of proposals.

2.7 PROPOSAL REQUIREMENTS:

A. General:

a. Proposals shall be based on solicitation document issued for RFP number 36E77620R0043. Proposals will be in the format stipulated in this document.

b. Proposals shall be received on or before the date and time specified in Block 13 of the SF 1442. There will be no public opening of the proposals.

c. Submit proposals via email to:

a. Jamahel.fayall@va.gov

b. Emails are limited to five (5) MB.

d. Submit the original of the Bid Guarantee by mail to:

a. US Postal Service Deliveries:

Jamahel Fayall Veterans Health Administration Program Contracting Activity Central (VHA-PCAC) 6150 Oaktree Blvd., Suite 300 Independence, OH 44131

b. Commercial Delivery Services / Hand Carry (Monday- Friday, 8:00 AM to 4:30 PM (ET)) Jamahel Fayall Veterans Health Administration Program Contracting Activity Central (VHA-PCAC) 6150 Oaktree Blvd., Suite 300 Independence, OH 44131

c. Failure to furnish the required bid guarantee in the proper form and amount, by the time specified in Block 13 of SF 1442, may result in rejection of the proposal. SEE FAR Provision 52.228-1, Bid Guarantee, of this Solicitation.

B. Proposal Format:

a. All sections of the Offerors proposals will be evaluated independently; therefore, the Offeror shall submit the proposal in three (3) Volumes: Volume I Technical, Volume II Price and Volume III Administrative Information. In order that the Volume I Technical Factors may be evaluated strictly on the merit of the material submitted, the contractor shall include NO price information in Volume I. Offeror shall separate Volumes I, II and III. Each volume must be labeled with the Offeror's organization, business address, and VA Solicitation Number. The volumes shall be submitted in electronic format as searchable PDF documents. The proposal, in its entirety, shall not exceed three (3) emails (one email for each volume) of 5MB each. Include page numbers and the company name in the header or footer of each page.

b. Volume I: Offerors shall format the two (2) evaluation factors for Volume I Technical as listed below. The specific evaluation criteria and methodology for Volume I is contained in Sections B(c) and (d) and Section D.

a. The offer, including title page, preface, Project Work Plan and Metal Insulated Panels shall not exceed a total of THIRTY (30) pages.

b. The Volume I submission shall be submitted utilizing the standard (8.5 X 11 inch) paper. The background color of each page of the submission shall be white or ivory only. Excess pages will not be evaluated.

c. Failure to submit in the format required and clearly address the two (2) Technical factors may result in this offer being rated unacceptable.

c. Volume I, Factor 1 Project Work Plan (Technical): Offerors must write a detailed narrative explanation of their project work plan (step-by-step, detailed description of the contractor’s plan from beginning to end). Simply restating the requirements (copying and pasting from the solicitation) is not considered to be a demonstration of understanding of the project. The proposed project work plan should be inclusive of a quality control plan, an understanding of the maximum allowable noise levels for different phases of the work, a safety plan, an archeological monitoring plan, a Storm Water Pollution Prevention Plan and a traffic control plan. The Offerors must show that they have analyzed the requirements and demonstrate the extent to which they understand the requirements across the body of the proposal.

The following items will need to be demonstrated at a minimum in the project work plan:

1. How to minimize the disruption to traffic to Building 112 (Laundry), Building 111 (Boiler Plant) and Building 110 (Pest Control).

2. Provide a narrative demonstrating knowledge of archeological monitoring requirements for this project.

3. Discuss Coordination, scheduling and approval of each phase of the work with the site prior to the start of the next phase

4. Work plans shall be prepared in detail to facilitate VA review and approval of proposed utility or road shutdowns during the project.

5. Identify possible project challenges and risks, and how they will be mitigated.

d. Volume I, Factor 2 Metal Insulated Panels (Technical): In a narrative, provide details of how common issues, such as thermal barrier seals and electrical conduit or pipe supports are anchored in a MIPs walled building envelope high bay warehouse. Key areas that need to be addressed are as follows:

1. Provide a technical narrative explaining the process of efficiently constructing a MIPs walled warehouse, and;

2. Discuss challenges specific to MIPs construction.

e. Volume II, Factor 3, Price: Offerors shall format the Volume II Price proposal as listed below.

a. Offerors shall complete the price schedule in part A of this solicitation.

b. Offerors shall ensure the Signed Standard Form (SF) 1442 is provided. Offerors shall acknowledge receiving amendments by filling out section 19 of the SF 1442.

c. The Offeror’s signature on the SF 1442 must be a hand signature and not an electronic signature.

d. The Offeror shall submit their price information on the price schedule provided in this Solicitation. The Offeror shall submit a bid guarantee as stipulated in the solicitation. The prices shall be Firm Fixed Price.

e. In addition to the pricing schedule, Offerors shall submit a complete breakdown of the Division Pricing for CLIN 0001, 0002 and 0003 on Attachment 14 – Division Price Breakdown. The Division Pricing will also be used to determine price reasonableness. The Government also reserves the right to use this breakdown of Division Pricing as part of discussions during the competitive range, if they are required.

f. Volume III Administrative Information: Offerors shall include the following in Volume III. All of the below information must be provided.

(a) Representations & Certifications: The offeror shall provide their Representations and Certifications or their response to FAR 52.204-8 (2) (i) or (ii) Annual Representations and Certifications.

(b) Information Regarding Responsibility Matters: Offeror shall provide their response to FAR 52.209-7 (b) Information Regarding Responsibility Matters.

(c) Violation of Arms Controls Treaties or Agreements: Offeror shall provide their response to FAR 52.209-13 (b) (1) or (2) Violation of Arms Controls Treaties or Agreements.

(d) Representation Regarding Certain Telecommunications and Video Surveillance Services or Equipment: Offeror shall provide their response to FAR 52.204-24 (d) Representation.

(e) Post Award Small Business Program Representations: Offeror shall provide their response to FAR 52.219-28 items (h)(1), (h)(6), and (h)(7).

(f) Experience Modification Rate: The Offeror shall include the Safety or Environmental Violations and Experience Modification Rating Information, including filling out ATTACHMENT 16.

1. All Offerors shall submit information pertaining to their past Safety and Environmental record. The information must contain a certification that the Offeror has no more than three (3) serious, or one (1) repeat or one (1) willful OSHA or any EPA violation(s) in the past three years. If such certification cannot be made, an Offeror shall explain why and submit as much information as possible regarding the circumstances of its past safety and environmental record, including the number of EPA violations and/or the number of serious, repeat, and/or willful OSHA violations, along with a detailed description of those violations.

2. All Offerors shall submit information regarding their current Experience Modification Rate (EMR). This information shall be obtained from the Offeror’s insurance carrier and be furnished on the insurance carrier’s letterhead. If an Offeror’s EMR is above 1.0, Offeror must submit a written explanation of the EMR from its insurance carrier furnished on the insurance carrier’s letterhead, describing the reasons for the elevated EMR and the anticipated date the EMR may be reduced to 1.0 or below.

3. Self-insured contractors or other contractors that cannot provide their EMR rating on insurance letterhead must obtain a rating from the National Council on Compensation Insurance, Inc. (NCCI) by completing/submitting form ERM-6 and providing the rating on letterhead from NCCI. Note: Self-insured contractors or other contractors that cannot provide EMR rating on insurance letterhead from the states or territories of CA, DE, MI, NJ, ND, OH, PA, WA, WY, and PR shall obtain their EMR rating from their state run worker’s compensation insurance rating bureau.

4. If the NCCI cannot issue an EMR because the Offeror lacks insurance history, Offeror shall submit a letter indicating so from its insurance carrier furnished on the insurance carrier’s letterhead, and include a letter from the NCCI indicating that is has assigned Offeror a Unity Rating of 1.0.

5. The above information, along with other information obtained from Government systems, such as the OSHA and EPA online inspection history databases, will be used to make an initial Determination of Responsibility.

6. This requirement is applicable to all subcontracting tiers, and prospective prime contractors are responsible for determining the responsibility of their prospective subcontractors.

*If the EMR rating for the subcontracting tiers cannot be provided at time of proposal submission, the prime contractor shall acknowledge this and provide as a submittal with the insurance and bonding requirements.

7. Failure to provide the ATTACHMENT 16 containing the above information, may result in a determination that an Offeror is not responsible and therefore ineligible for award.

C. Final Proposal Revisions

a. The Government reserves the right to award without discussions based upon the initial evaluation of the proposals.

b. If determined to be necessary, proposal revisions will be requested. The CO will identify those Offerors, whose proposals are within the competitive range, considering the selection criteria identified in this section. Discussions will be conducted with those Offerors falling within the competitive range, after which proposal revisions will be requested. Proposal revisions will be submitted as detailed above, except as noted below and will be due at a time and place to be determined.

c. Offerors submitting proposal revisions will not be requested to re-submit any documents which are unchanged from their initial proposals. They should provide necessary changes to individual paragraphs, as briefly as possible, together with a table of contents, which clarifies where within the initial proposal the additional information or changed documents would be placed. Proposal revisions shall include a completed SF 1442 that acknowledges receiving all amendments, by number. A new bid bond shall be submitted only if the final proposal revisions Offeror’s price proposal is greater than its initial price proposal.

*Note this section only applies if discussions are conducted.

D. Evaluation Methodology – Evaluation Factors To receive consideration for award, a rating of ACCEPTABLE must be achieved for both Factor 1 and Factor 2.

Volume I, Factor 1 Project Work Plan (Technical) The work plan narrative will be reviewed to determine if the plan is ACCEPTABLE or UNACCEPTABLE. Acceptable is defined as the Offeror met all of the minimum requirements identified in the solicitation for the work plan. Unacceptable is defined as the offeror failed to meet all of the minimum requirements as identified in the solicitation for the work plan. The minimum requirements for the work plan are as follows:

1. Acceptable traffic control plan;

2. Acceptable archaeological monitoring plan;

3. Discussed coordination and scheduling with logical work review points for the VA COR to inspect the work prior to acceptance.

4. Proposed acceptable Storm Water Pollution Prevention Plan.

5. Identified risks and recommended solutions in case the risks are realized.

Volume I, Factor 2 Metal Insulated Panels (Technical) Metal Insulated Panels Methods will be reviewed to determine if what provided is ACCEPTABLE or UNACCEPTABLE. Acceptable is defined as the Offeror met all of the minimum requirements identified in the solicitation for MIPs construction for a high bay warehouse. Unacceptable is defined as the offeror failed to meet all of the minimum requirements as identified in the solicitation for MIPs construction. The minimum requirements for MIPs construction are as follows:

1. Provided technical approach for the MIPs walls, anchor points, adjoining roof and thermal seals listed in the drawings and specifications, and;

2. Discussed specific challenges and solutions to the use of MIPs construction.

Volume II, Factor 3 Price The total evaluated price will be determined by the Offeror's price for CLIN 0001 and CLIN 0002. The Offeror who provides the lowest price will be determined to be the lowest priced Offeror.

Please note: If none of the offerors are within the available funding limitation, the VA reserves the right to enter into discussions with those offerors who are determined to be within the competitive range, if a competitive range is determined in the interest of the VA, otherwise discussions will be with all offerors.

If the Offeror communicates in its proposal any qualifications, exceptions, exclusions, or conditions to the proposed prices in the Offerors proposal documents, the Contracting Officer may reject the proposal and exclude the Offeror from further discussions.

2.8 USE OF ADVISORS:

Contractors are advised that VA contractor personnel may assist the Government during the Government’s evaluation of Proposals. The persons shall be authorized access to only those portions of the proposal and discussions that are necessary to enable them to provide specific technical advice on specialized matters or on particular problems. These individuals will be required to protect the confidentiality of any specifically identified trade secrets and/or privileged or confidential commercial or financial information obtained as a result of their participation in this evaluation. They shall be expressly prohibited from scoring, ranking or recommending the selection of an Offeror.

2.9 DETERMINATION OF RESPONSIBILITY:

A Determination of Responsibility will be conducted for the apparent successful offer prior to award of the project. The contracting officer will determine if the successful offeror is responsible using the general standards of responsibility for this procurement. Past performance will be evaluated as part of the general responsibility determination. In accordance with Procurement Policy Memorandum 2013-03, past performance evaluations may be conducted using information obtained from CPARS and any other sources deemed appropriate by the CO. Other sources may include, but are not limited to, inquiries of owner representatives, Federal Awardee Performance and Integrity Information System (FAPIIS), Electronic Subcontract Reporting System (eSRS), and any other known sources. NOTE: Any information received by the Government that would cause for a negative Determination of Responsibility may make the Offeror ineligible for award.

2.10 VETS 4212:

Title 38, USC Section 4212(d), codified at 41 CFR Section 61-300, requires that federal contractors report, at least annually, the number and category of veterans who are within their workforce. Submission of the VETS-4212 reporting information can be done electronically at: http://www.dol.gov/vets/vets4212.htm. Award cannot be made unless the awardee has filed their VETS-4212 report. Therefore, all Offerors are encouraged to file every year. The Contracting Officer may request a copy of the email confirmation of receipt notification, prior to awarding the project.

2.11 SYSTEM FOR AWARD MANAGEMENT (SAM):

Federal Acquisition Regulations require that federal contractors register in the System for Award Management (SAM) database at http://www.sam.gov and enter all mandatory information into the system. Offerors are required to be registered in SAM at the time an offer is submitted in order to comply with the annual representations and certifications requirements. The Offeror shall also be registered at time of award.

2.12 BACKGROUND INVESTIGATIONS AND SPECIAL AGREEMENT CHECKS:

All contractor employees are subject to the same level of investigation as VA employees who have access to VA Sensitive Information. The level of background investigation commensurate with the level of access needed to perform the statement of work is: Low Risk. This requirement is applicable to all subcontractor personnel requiring the same access. As per VA Directive 0710, costs of background investigations will be borne by the contractor.

2.13 REVIEW REQUIRED REGISTRATION WITH CONTRACTOR PERFORMANCE ASSESSMENT SYSTEM (CPARS):

As prescribed in Federal Acquisition Regulation (FAR) Part 42.1502(e), the Department of Veterans Affairs (VA) evaluates contractor past performance on all construction contracts that exceed $700,000, and shares those evaluations with other Federal Government contract specialists and procurement officials. The FAR requires that the contractor be provided an opportunity to comment on past performance evaluations prior to each report closing. To fulfill this requirement VA uses an online database, CPARS, which is maintained by the Naval Seal Logistics Center in Portsmouth, Virginia. CPARS has connectivity with the Past Performance Information Retrieval System (PPIRS) database, which is available to all Federal agencies. PPIRS is the system used to collect and retrieve performance assessment reports used in source selection determinations and completed CPARS report cards transferred to PPIRS. CPARS also includes access to the federal awardee performance and integrity information system (FAPIIS). FAPIIS is a web-enabled application accessed via CPARS for contractor responsibility determination information.

Each contractor whose contract award is estimated to exceed $700,000 is required to register with CPARS database at the following web address: http://www.cpars.gov/. Help in registering can be obtained by contacting Customer Support Desk @ DSN: 684-1690 or COMM: 207- 438-1690. Registration should occur no later than thirty days after contract award, and must be kept current should there be any change to the contractor’s registered representative.

For contracts with a period of one year or less, the contracting officer will perform a single evaluation when the contract is complete. For contracts exceeding one year, the contracting officer will evaluate the contractor’s performance annually. Interim reports will be filed each year until the last year of the contract, when the final report will be completed. The report shall be assigned in CPARS to the contractor’s designated representative for comment. The contractor representative will have thirty days to submit any comments and re-assign the report to the VA contracting officer.

Failure to have a current registration in the CPARS database, or to re-assign the report to the VA contracting officer within those thirty days, will result in the Government’s evaluation being placed on file in the database with a statement that the contractor failed to respond.

2.14 REFERENCES TO VA ENGINEER, RESIDENT ENGINEER OR PROJECT MANAGER:

Any reference contained within the solicitation/contract specifications and/or drawings to the “VA Engineer,” “Resident Engineer,” or “Project Manager” or their abbreviations shall be replaced with “Contracting Officer’s Representative (COR).”

2.15 52.216-1 TYPE OF CONTRACT (APR 1984)

The Government contemplates award of a Firm-Fixed-Price contract resulting from this solicitation.

(End of Provision)

2.16 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014) (a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.

(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.

(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.

(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.

(End of Provision)

2.17 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)

(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.

(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:

Goals for minority participation for each trade
Goals for female participation for each trade
19.6 %
6.9 %

These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.

(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction," and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.

(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the—

(1) Name, address, and telephone number of the subcontractor;

(2) Employer's identification number of the subcontractor;

(3) Estimated dollar amount of the subcontract;

(4) Estimated starting and completion dates of the subcontract; and

(5) Geographical area in which the subcontract is to be performed.

(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is Yavapai County - Prescott, AZ

(End of Provision)

2.18 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014)

(a) Definitions. "Commercially available off-the-shelf (COTS) item," "construction material," "domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American—Construction Materials" (Federal Acquisition Regulation (FAR) clause 52.225-9).

(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.

(c) Evaluation of offers.

(1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.

(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.

(d) Alternate offers.

(1) When an offer includes foreign solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.

(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.

(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested—

(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or

(ii) May be accepted if revised during negotiations.

(End of Provision)

2.19 52.228-1 BID GUARANTEE (SEP 1996)

(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.

(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds—

(1) To unsuccessful bidders as soon as practicable after the opening of bids; and

(2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.

(c) The amount of the bid guarantee shall be percent of the bid price or , whichever is less.

(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.

(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.

(End of Provision)

2.20 52.233-2 SERVICE OF PROTEST (SEP 2006)

Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from:

Donald A. Marsh III

Hand-Carried Address:

Donald A. Marsh III Department of Veterans Affairs Program Contracting Activity Central 6150 Oak Tree Blvd, Suite 300 Independence OH 44131 Mailing Address:

Donald A. Marsh III Department of Veterans Affairs Program Contracting Activity Central 6150 Oak Tree Blvd, Suite 300 Independence OH 44131

(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.

(End of Provision)

2.21 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) An organized site visit has been scheduled for— August 11, 2020 at 10AM MT (12PM ET)

(c) Participants will meet at— NAVAHCS - In front of Bld 13 - See map in Attachment 17.

(End of Provision)

2.22 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)

This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):

http://www.acquisition.gov/far/index.html http://www.va.gov/oal/library/vaar/

(End of Provision)

FAR Number
Title
Date
52.204-7
SYSTEM FOR AWARD MANAGEMENT
OCT 2018
52.204-16
COMMERCIAL AND GOVERNMENT ENTITY CODE REPORTING
JUL 2016
52.204-22
ALTERNATIVE LINE ITEM PROPOSAL
JAN 2017
52.211-6
BRAND NAME OR EQUAL
AUG 1999
52.215-1
INSTRUCTIONS TO OFFERORS—COMPETITIVE ACQUISITION
JAN 2017
52.229-11
TAX ON CERTAIN FOREIGN PROCUREMENTS—NOTICE AND REPRESENTATION
JUN 2020
52.236-28
PREPARATION OF PROPOSALS—CONSTRUCTION
OCT 1997
852.233-70
PROTEST CONTENT/ALTERNATIVE DISPUTE RESOLUTION
OCT 2018

2.23 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (OCT 2018)

(a) As an alternative to filing a protest with the Contracting Officer, an interested party may file a protest by mail or electronically with: Executive Director, Office of Acquisition and Logistics, Risk Management and Compliance Service (003A2C), Department of Veterans Affairs, 810 Vermont Avenue NW, Washington, DC 20420 or Email: EDProtests@va.gov.

(b) The protest will not be considered if the interested party has a protest on the same or similar issue(s) pending with the Contracting Officer.

(End of Provision) PLEASE NOTE: The correct mailing information for filing alternate protests is as follows:

Deputy Assistant Secretary for Acquisition and Logistics,
Risk Management Team, Department of Veterans Affairs
810 Vermont Avenue, N.W.
Washington, DC 20420

Or for solicitations issued by the Office of Construction and Facilities Management:

Director, Office of Construction and Facilities Management
811 Vermont Avenue, N.W.
Washington, DC 20420

REPRESENTATIONS AND CERTIFICATIONS

3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (MAR 2020)

(a)(1) The North American Industry Classification System (NAICS) code for this acquisition is 236220.

(2) The small business size standard is $39.5 Million.

(3) The small business size standard for a concern which submits an offer in its own name, other than on a construction or service contract, but which proposes to furnish a product which it did not itself manufacture, is 500 employees.

(b)(1) If the provision at 52.204-7, System for Award Management, is included in this solicitation, paragraph (d) of this provision applies.

(2) If the provision at 52.204–7, System for Award Management, is not included in this solicitation, and the Offeror has an active registration in the System for Award Management (SAM), the Offeror may choose to use paragraph (d) of this provision instead of completing the corresponding individual representations and certifications in the solicitation. The Offeror shall indicate which option applies by checking one of the following boxes:

[ ] (i) Paragraph (d) applies.

[ ] (ii) Paragraph (d) does not apply and the offeror has completed the individual representations and certifications in the solicitation.

(c)(1) The following representations or certifications in SAM are applicable to this solicitation as indicated:

(i) 52.203-2, Certificate of Independent Price Determination. This provision applies to solicitations when a firm-fixed-price contract or fixed-price contract with economic price adjustment is contemplated, unless—

(A) The acquisition is to be made under the simplified acquisition procedures in Part 13;

(B) The solicitation is a request for technical proposals under two-step sealed bidding procedures; or

(C) The solicitation is for utility services for which rates are set by law or regulation.

(ii) 52.203-11, Certification and Disclosure Regarding Payments to Influence Certain Federal Transactions. This provision applies to solicitations expected to exceed $150,000.

(iii) 52.203-18, Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements or Statements—Representation. This provision applies to all solicitations.

(iv) 52.204-3, Taxpayer…

This is the start of the file's text. The full file is on GovTribe.