36E77620R0031-A00003000.docx

DOCX document Posted

Attached to
Y1DA--SPECT/CT Site Preparation Project (Design-Build) Augusta, Georgia Charlie Norwood VAMC (Downtown)
Solicitation number
36E77620R0031
Issued by

About this file

This document provides details regarding a federal contract opportunity for a SPECT/CT site preparation project at the Charlie Norwood VA Medical Center in Augusta, Georgia. The Department of Veterans Affairs seeks to award a single, firm-fixed-price design-build contract to remove and replace walls, flooring, ceilings, ductwork, electrical systems, and finishes in an exam room and control room to accommodate a new Siemens Symbia Intevo scanner. The project magnitude is between $500,000 and $1,000,000, and the period of performance is approximately 180 calendar days. The solicitation will be a total SDVOSB set-aside issued as a request for proposal on or around March 20, 2020. Questions must be submitted in writing by the deadline.

36E77620R0031 A00003 36E77620R0031 A00003.docx

View the file

Other files

File Type Posted
36E77620R0031-A00004000.docx DOCX document
36E77620R0031-A00002018.doc DOC document
36E77620R0031-A00002000.docx DOCX document
36E77620R0031-A00002002.doc DOC document
36E77620R0031-A00002001.docx DOCX document
36E77620R0031-A00002008.pdf PDF
36E77620R0031-A00002007.pdf PDF
36E77620R0031-A00002005.pdf PDF
36E77620R0031-A00002004.pdf PDF
36E77620R0031-A00002021.pdf PDF
36E77620R0031-A00002011.docx DOCX document
36E77620R0031-A00002013.doc DOC document
36E77620R0031-A00002015.docx DOCX document
36E77620R0031-A00002016.doc DOC document
36E77620R0031-A00002012.docx DOCX document
36E77620R0031-A00002019.docx DOCX document
36E77620R0031-A00002010.docx DOCX document
36E77620R0031-A00002009.docx DOCX document
36E77620R0031-A00002003.docx DOCX document
36E77620R0031-A00002017.docx DOCX document
36E77620R0031-A00002014.docx DOCX document
36E77620R0031-A00002020.pdf PDF
36E77620R0031-A00002006.pdf PDF
36E77620R0031-A00001000.docx DOCX document
36E77620R0031-A00001001.doc DOC document
36E77620R0031-013.doc DOC document
36E77620R0031-012.docx DOCX document
36E77620R0031-009.docx DOCX document
36E77620R0031-008.pdf PDF
36E77620R0031-011.docx DOCX document
36E77620R0031-021.pdf PDF
36E77620R0031-007.pdf PDF
36E77620R0031-020.pdf PDF
36E77620R0031-005.pdf PDF
36E77620R0031-016.doc DOC document
36E77620R0031-010.docx DOCX document
36E77620R0031-001.docx DOCX document
36E77620R0031-014.docx DOCX document
36E77620R0031-018.doc DOC document
36E77620R0031-002.doc DOC document
36E77620R0031-019.docx DOCX document
36E77620R0031-003.docx DOCX document
36E77620R0031-006.pdf PDF
36E77620R0031-004.pdf PDF
36E77620R0031-015.docx DOCX document
36E77620R0031-017.docx DOCX document
Show all 46

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE

7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER

3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO.

1. CONTRACT ID CODE

FACILITY CODE

CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office.

is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER

16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30

PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer) A00003 04-14-2020

509-CSI-502

PCAC

Department of Veterans Affairs Program Contracting Activity Central 6150 Oak Tree Blvd, Suite 300 Independence

OH

44131

PCAC

Department of Veterans Affairs Program Contracting Activity Central 6150 Oak Tree Blvd, Suite 300 Independence

OH

44131 To all Offerors/Bidders

36E77620R0031 04-14-2020

X X X

The purpose of this amendment is to provide answers/clarifications to the Request for Proposal.

Response date shall remain April 20, 2020 @ 2:00 p.m. for Phase I qualifications.

All other terms and conditions shall remain the same and in full effect.

Yolanda M. Ray Contracting Officer Department of Veterans Affairs (VA) Veterans Health Administration (VHA) Program Contracting Activity Central (PCAC) SPECT/CT Site Preparation Project – Augusta, Georgia Request for Proposal: 36E77620R0031 Amendment Number A00003 April 14, 2020

1. The Magnitude of Construction on this project is $500,000 - $1,000,000. However, under Factor 1 – Past Performance, the Government is requiring that Contractors submit projects with a “minimum value of $1,500,000”. Can the Government please revise the minimum value of relevant past performance to $500,000 to be more in-line with the expected magnitude of construction on this project?

Answer: The Past Performance Magnitude is hereby changed from $1,500,000.00 to $500,000.00 - $1,000,000.00.

2. Due to the extenuating circumstances because of the Coronavirus (e.g. partially staffed offices, people trying to work from home, etc.), it is going to prove extremely difficult for Contractors to get their Customers to fill out PPQ’s for projects that don’t have CPARS completed on them. Would the Government be willing to accept previously submitted PPQ’s from our customers submitted in our response document?

Answer: Yes

2. Has a site visit been scheduled?

Answer: In Two-Phase Design Build, the contractor shall submit qualifications (SF330’s) based on the evaluation criteria in the first phase. A site visit will be scheduled and will be offered after the review of the most highly qualified candidates in Phase II.

3. Please, clarify the following statement on Page 6 of the Solicitation, Offer and Award docx. #A00002001 in the A.3 Price Schedule section “*PLEASE NOTE: Pricing will only be required for Phase II of the Design-Build process. NO Pricing is to be submitted as part of Phase I.” Is this a qualification only solicitation for Phase I at this time with that submission being due on 4-20-20 and will there be a new submission date issued for Phase II for selected contractors?

Answer: No pricing shall be submitted in Phase I, only qualifications (SF330s). There will be a scheduled site visit, question/answer period and submission date in Phase II for only the most highly qualified candidates.

File details come from the government source that posted it. Updated .