This document contains a technical specification table of contents and a federal contract opportunity notice. The technical specification table of contents lists the divisions and sections for construction specifications for a dental conference room conversion project at a VA medical center in Omaha, Nebraska. Work includes demolition, concrete, metals, wood, thermal and moisture protection, openings, finishes, specialties, equipment, furnishings, fire suppression, plumbing, HVAC, electrical, communications, security, earthwork, and exterior improvements.

The related federal contract opportunity is a solicitation notice for a SPECT/CT site preparation project at the Charlie Norwood VA Medical Center in Augusta, Georgia. The project includes design and construction to ready an exam room for a new medical imaging device, including removal of drywall, floors, ceiling, and ductwork modification. New framing, insulation, wall sheathing, windows, doors and finishes will be installed. The solicitation will be issued on March 20, 2020 as a total SDVOSB set-aside, with proposals due 180 days later. The construction value is estimated between $500,000 and $1,000,000.

36E77620R0031 A00002 S02 - Attachment 11 - VHA Master Specifications.docx

View the file

Other files

File Type Posted
36E77620R0031-A00004000.docx DOCX document
36E77620R0031-A00003000.docx DOCX document
36E77620R0031-A00002018.doc DOC document
36E77620R0031-A00002000.docx DOCX document
36E77620R0031-A00002002.doc DOC document
36E77620R0031-A00002001.docx DOCX document
36E77620R0031-A00002008.pdf PDF
36E77620R0031-A00002007.pdf PDF
36E77620R0031-A00002005.pdf PDF
36E77620R0031-A00002004.pdf PDF
36E77620R0031-A00002021.pdf PDF
36E77620R0031-A00002011.docx DOCX document
36E77620R0031-A00002013.doc DOC document
36E77620R0031-A00002015.docx DOCX document
36E77620R0031-A00002016.doc DOC document
36E77620R0031-A00002019.docx DOCX document
36E77620R0031-A00002010.docx DOCX document
36E77620R0031-A00002009.docx DOCX document
36E77620R0031-A00002003.docx DOCX document
36E77620R0031-A00002017.docx DOCX document
36E77620R0031-A00002014.docx DOCX document
36E77620R0031-A00002020.pdf PDF
36E77620R0031-A00002006.pdf PDF
36E77620R0031-A00001000.docx DOCX document
36E77620R0031-A00001001.doc DOC document
36E77620R0031-013.doc DOC document
36E77620R0031-012.docx DOCX document
36E77620R0031-009.docx DOCX document
36E77620R0031-008.pdf PDF
36E77620R0031-011.docx DOCX document
36E77620R0031-021.pdf PDF
36E77620R0031-007.pdf PDF
36E77620R0031-020.pdf PDF
36E77620R0031-005.pdf PDF
36E77620R0031-016.doc DOC document
36E77620R0031-010.docx DOCX document
36E77620R0031-001.docx DOCX document
36E77620R0031-014.docx DOCX document
36E77620R0031-018.doc DOC document
36E77620R0031-002.doc DOC document
36E77620R0031-019.docx DOCX document
36E77620R0031-003.docx DOCX document
36E77620R0031-006.pdf PDF
36E77620R0031-004.pdf PDF
36E77620R0031-015.docx DOCX document
36E77620R0031-017.docx DOCX document
Show all 46

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

07-01-14 636-19-305 Convert Dental Conference Room to Patient Rooms – Omaha, NE 04-24-19

VHA MASTER SPECIFICATIONS

SPEC SECTION 00 01 10

DIVISION 00 – SPECIAL SECTIONS

00 01 10
Table of Contents
00 01 15
List of Drawing Sheets
07-15
00 11 21
Request for Proposal to Design Build
11-15

DIVISION 01 GENERAL REQUIREMENTS

01 00 00
General Requirements
10-17
01 32 16.17
Project Schedules (Small Projects – Design/Build)
04-11
01 33 23
Shop Drawings, Product Data, and Samples
05-17
01 33 24
Electronic Submittal Requirements
01 35 26
Safety Requirements
02-17
01 42 19
Reference Standards
05-16
01 45 00
Quality Control
01 45 29
Testing Laboratory Services
08-17
01 57 19
Temporary Environmental Controls
01 74 19
Construction Waste Management
09-13
01 81 13
Sustainable Construction Requirements
10-17
01 91 00
General Commissioning Requirements
10-15

DIVISION 02 – EXISTING CONDITIONS

02 21 13
Site Surveys
08-16
02 41 00
Demolition
08-17

DIVISION 03 – CONCRETE

03 30 53
(Short-Form) Cast-in-Place Concrete
02-16
03 41 13
Precast Concrete Hollow Core Planks
03 45 00
Precast Architectural Concrete
10-15

DIVISION 05 – METALS

05 12 00
Structural Steel Framing
02-16
05 21 00
Steel Joist Framing
05 31 00
Steel Decking
02-16
05 40 00
Cold-Formed Metal Framing
05-16
05 50 00
Metal Fabrications
04-18
05 51 00
Metal Stairs
10-15

DIVISION 06 – WOOD, PLASTICS AND COMPOSITES

06 10 00
Rough Carpentry
10-17
06 16 63
Cementitious Sheathing
02-16
06 20 00
Finish Carpentry
08-16

DIVISION 07 THERMAL AND MOISTURE PROTECTION

07 08 00
Facility Exterior Closure Commissioning
16-11
07 21 13
Thermal Insulation
10-17
07 22 00
Roof and Deck Insulation
02-16
07 53 23
EPDM Roofing
16-02
07 54 23
Thermoplastic Polyolefin (TPO) Roofing
10-15
07 71 00
Roof Specialties
10-15
07 72 00
Roof Accessories
10-15
07 84 00
Firestopping
02-16
07 92 00
Joint Sealants
10-17
07 95 13
Expansion Joint Cover Assemblies
02-16

DIVISION 08 OPENINGS

08 11 13
Hollow Metal Doors and Frames
08-16
08 14 00
Interior Wood Doors
02-16
08 31 13
Access Doors and Frames
02-16
08 51 13
Aluminum Windows
02-16
08 71 00
Door Hardware
01-16
08 71 13
Automatic Door Operators
02-16
08 80 00
Glazing
10-15

DIVISION 09 – FINISHES

09 05 16
Subsurface Preparation for Floor Finishes
02-15
09 06 00
Schedule for Finishes
04-15
09 22 16
Non-Structural Metal Framing
05-16
09 29 00
Gypsum Board
11-14
09 30 13
Ceramic/Porcelain Tiling
10-15
09 51 00
Acoustical Ceilings
12-16
09 65 13
Resilient Base and Accessories
02-16
09 65 16
Resilient Sheet Flooring
05-18
09 65 19
Resilient Tile Flooring
05-18
09 6 13
Portland Cement Terrazzo Flooring
10-15
09 68 00
Carpeting
10-15
09 91 00
Painting
01-16

DIVISION 10 – SPECIALTIES

10 11 13
Chalkboards and Markerboards
10 14 00
Signage
10 21 23
Cubicle Curtain Tracks
05-15
10 25 13
Patient Bed Service Walls
05-18
10 26 00
Wall and Door Protection
10-15
10 28 00
Toilet, Bath, and Laundry Accessories
02-16
10 44 13
Fire Extinguisher Cabinets
08-14

DIVISION 11 – EQUIPMENT

11 73 00
Ceiling Mounted Patient Lift System
01-17

DIVISION 12 – FURNISHINGS

12 24 00
Window Shades
12 31 00
Manufactured Metal Casework
05-15
12 32 00
Manufactured Wood Casework
09-15
12 36 00
Countertops
12-15

DIVISION 21- FIRE SUPPRESSION

21 08 00
Commissioning of Fire Suppression Systems
11-16
21 13 13
Wet-Pipe Sprinkler Systems
06-15

DIVISION 22 – PLUMBING

22 05 11
Common Work Results for Plumbing
07-16
22 05 19
Meters and Gages for Plumbing Piping
09-15
22 05 23
General-Duty Valves for Plumbing Piping
09-15
22 07 11
Plumbing Insulation
09-15
22 08 00
Commissioning of Plumbing Systems
11-16
22 11 00
Facility Water Distribution
09-15
22 13 00
Facility Sanitary and Vent Piping
09-15
22 14 00
Facility Storm Drainage
09-15
22 15 00
General Service Compressed-Air System
09-15
22 40 00
Plumbing Fixtures
09-15
22 62 00
Vacuum Systems for Laboratory and Healthcare Facilities
09-15
22 63 00
Gas Systems for Laboratory and Healthcare Facilities
09-15

DIVISION 23 – HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)

23 05 11
Common Work Results for HVAC
08-17
23 05 12
General Motor Requirements for HVAC and Steam Generation Equipment
08-17
23 05 41
Noise and Vibration Control for HVAC Piping and Equipment
02-15
23 05 51
Noise and Vibration Control for Boiler Plant
08-17
23 05 93
Testing, Adjusting, and Balancing for HVAC
02-15
23 07 11
HVAC and Boiler Plant Insulation
02-15
23 08 00
Commissioning of HVAC Systems
11-16
23 09 23
Direct-Digital Control System for HVAC
09-11
23 21 13
Hydronic Piping
08-17
23 22 13
Steam and Condensate Heating Piping
23 23 00
Refrigerant Piping
02-15
23 31 00
HVAC Ducts and Casings
23 34 00
HVAC Fans
23 36 00
Air Terminal Units
02-15
23 37 00
Air Outlets and Inlets
02-15
23 74 13
Packaged, Outdoor, Central-Station Air-Handling Units
23 82 16
Air Coils
04-11

DIVISION 26 – ELECTRICAL

26 05 11
Requirements for Electrical Installations
01-16
26 05 19
Low-Voltage Electrical Power Conductors and Cables
01-17
26 05 26
Grounding and Bonding for Electrical Systems
01-17
26 05 33
Raceway and Boxes for Electrical Systems
01-18
26 08 00
Commissioning of Electrical Systems
11-16
26 09 23
Lighting Controls
01-18
26 11 16
Secondary Unit Substations
01-18
26 24 16
Panelboards
01-18
26 27 26
Wiring Devices
01-18
26 29 21
Enclosed Switches and Circuit Breakers
01-17
26 41 00
Facility Lightning Protection
01-17
26 51 00
Interior Lighting
01-18
26 56 00
Exterior Lighting
01-18

DIVISION 27 – COMMUNICATIONS

27 05 11
Requirements for Communications Installations
06-15
27 05 33
Raceways and Boxes for Communications Systems
06-15
27 08 00
Commissioning of Communications Systems
11-16
27 52 23
Nurse Call and Code Blue Systems
10-15

DIVISION 28 – ELECTRONIC SAFETY AND SECURITY

28 05 13
Conductors and Cables for Electronic Safety and Security
09-11
28 05 26
Grounding and Bonding for Electronic Safety and Security
09-11
28 05 28.33
Conduits and Backboxes for Electronic Safety and Security
09-11
28 31 00
Fire Detection and Alarm
10-11

DIVISION 31-EARTHWORK

31 20 00
Earthwork
07-16
32 20 11
Earthwork (Short form)
31 32 23
Pressure Grouting Soil stabilization
31 62 00
Driven Piles

DIVISION 32-EXTERIOR IMPROVEMENTS

32 05 23
Concrete for Exterior Improvements
08-16
32 84 00
Planting Irrigation
08-16
32 90 00
Planting
08-16

DIVISION 33-UTILITIES

33 08 00
Commissioning of Site Utility Systems
11-16
33 10 00
Water Utilities
03-17
33 30 00
Sanitary Utilities
33 40 00
Storm Sewer Utilities
12-17

NOTE: All Specifications are available at https://www.cfm.va.gov/til/ - Technical Information Library (TIL)

Spec Section 00 01 10 – Specification Table of Contents 5

File details come from the government source that posted it. Updated .