Technical Questions - FINAL - Reno Electrical 9-29-20.pdf
PDF 158 KB Posted
- Attached to
- Z2DA--Correct Electrical Deficiencies Building 1D Federal contract opportunity
- Solicitation number
- 36E77620B0007
About this file
This document contains technical questions and responses related to solicitation number 36E77620B0007 for correct electrical deficiencies at building 1D of the Reno VA Medical Center. The scope of work involves construction of a new building to house relocated and new electrical equipment, including general construction, mechanical, and electrical work for removal of an existing data closet and construction of a new one. Key details include responses to contractor questions on equipment locations and specifications, commissioning requirements, safety officer qualifications, maintaining sprinkler piping, and clarification that the electrical scope of work encompasses sheets 42 through 93 of the drawings. The anticipated award is a single fixed-price contract for a small business set-aside with an estimated value between $2-5 million and a performance period of approximately 475 calendar days.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Building 1D Asbestos Report.pdf | ||
| ATTACHMENT 6 - Construction Wage Rates - Washoe County - 9-18-20.pdf | ||
| 36E77620B0007 0002.docx | DOCX document | |
| Site Visit Sign-in Sheet - Reno Electrical 9-10-20.pdf | ||
| 36E77620B0007 0001.docx | DOCX document | |
| 36E77620B0007_1.docx | DOCX document | |
| ATTACHMENT 7 - Contractor Safety - Environmental Record Evaluation Form.docx | DOCX document | |
| ATTACHMENT 5 - Contractor Badging - Guidance to Contractor.pdf | ||
| ATTACHMENT 1 - SOW.pdf | ||
| ATTACHMENT 6 - Washoe County - 8-21-20.pdf | ||
| ATTACHMENT 2 - Specifications.pdf | ||
| ATTACHMENT 3 - Drawings.pdf | ||
| ATTACHMENT 4 - Drawings Addendum 1.pdf |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION # 36E77620B0007 CORRECT ELECTRICAL DEFICIENCIES BLDG. 1D - RENO
TECHNICAL QUESTIONS AND VA RESPONSE TRACKING SHEET
ITEM
NO.
DATE
QUESTION
RECEIVED
DATE
QUESTION
ANSWERED
QUESTION GOVERNMENT RESPONSE
1. 9-16-20 9-17-20 At the end of the virtual meeting I was told the slide show could be sent out. Do you know if that’s still in the works?
If you would like this version of the site visit, Please forward a request to the presenter Steven Elliot at Steven.Elliott3@va.gov and Cc the Contract Specialist Thomas Council at Thomas.Council@va.gov. These are large files for both the photos and the videos. All together they are about 85MB of data, too large to send in an e-mail. You will need to provide Steven with your FTP site, so he can upload them.
2. 9-18-20 9-22-20 Exhaust Fans: Architectural Dwg's (A-101/A-102) show one fan at both 1st and 2nd floor levels at the South all whereas Mechanical Dwg MH-2.1 Shows the Fans on the East wall, please confirm the South wall is the correct orientation.
Confirmed. South wall is the correct orientation.
3. 9-18-20 9-22-20 Fire Stop at Expansion Joint: Do you have a preferred model number or Vendor for style illustrated, see detail 3/A-501?
Inpro Expansion joints were used as the basis-of design product and customized for the application.
4. 9-18-20 9-22-20 Doors: It looks like at least door openings on first floor level are in CMU walls. Assuming an 8” block, 7’0” doors with a 2” head won’t work very well with your block layout. Would the VA prefer to proceed per design drawings or amend to have either a 4” head, of 7’-2 tall doors?
It is acceptable to have a 4” head, of 7’-2” tall door.
5. 9-18-20 9-22-20 Asbestos: Has testing been done previously, and if so, are there any reports available?
Prior asbestos testing has been completed and the report is attached for reference. Reference Building 1D Asbestos Report attachment posted with this Amendment 0002. We do not anticipate any existing asbestos on this project.
mailto:Steven.Elliott3@va.gov mailto:Thomas.Council@va.gov
DATE
QUESTION
RECEIVED
DATE
QUESTION
ANSWERED
QUESTION GOVERNMENT RESPONSE
6. 9-18-20 9-22-20 Commissioning: The specifications call for Commissioning for both the Electrical and Mechanical, to what extent does the Commissioning need to be completed?
Commissioning agent is to be retained by the General Contractor and will be responsible for the commissioning of both HVAC and Electrical Systems in accordance with Specification Section 01 91 00 - General Commissioning Requirements.
7. 9-18-20 9-22-20 Safety Requirements: Spec section 01 35 26 – 10 item
1.7 calls for designation of one Site Safety and Health Officer (SSHO) and Competent Person (CP). Can the Site Superintendent dual hat these positions providing they are qualified?
The SSHO shall be independent to the Site Superintendent. Each sub-contractor trade shall have a competent person that can have collateral duties the sub-contractor superintendent.
8. 9-18-20 9-22-20 Fire Protection: Is there seismic separation between existing building new building?
Yes, there is a seismic separation between the existing and the new building.
9. 9-18-20 9-22-20 Fire Protection: How to keep fire sprinkler pipe from freezing going from existing building to new building with a 1’ separation?
Fire sprinkler pipe shall be wrapped with foam insulation tape and a plastic bag or rubber sleeve, preventing pipe from freezing.
10. 9-18-20 9-22-20 Roofing: Sheet A-501 shows EPDM Membrane roofing adhered approximately 1’ up parapet walls with a flashing of some sort. Can the roofer run the membrane roofing up to the top of parapet with metal coping covering?
This will be acceptable, provided the warranty is received for the roofing material and installation
11. 9-22-20 9-28-20 I have noticed a design issue that needs some direction in order to quote the equipment. On plan sheet ED-302 there shows panel LECRS2B and Transformer T- LECRS2B as existing. They also show up on plan sheet EP-302 as new replacements. The problem is they are not included on the one-line drawings. Amendment #1 did add in the panel schedule for the panel but says nothing about the size of the transformers or where they are fed from. We need this in order to get a quote. Can you get an answer for me?
The Panel LECRS2B and Transformer T- LECRS2B are shown as new in the new sheet EP-
302. The panel and the transformer on Sheet ED- 302 has the subscript as “RP” meaning that the existing equipment is to be removed and replaced with new at the same location.
Size of panel “LECRS2B”- 225 A, with Bus size 200Amps.
Size of Transformer “T-LECRS2B” - 75 KVA, 480/120-208V, 3-Phase, 4-Wire.
Transformer “T-LECRS2B” is being fed off from Distribution Board “DBHECRS”.
DATE
QUESTION
RECEIVED
DATE
QUESTION
ANSWERED
QUESTION GOVERNMENT RESPONSE
12. 9-22-20 9-28-20 Circuits MRS-3, DBLNA-4, & DBLNA-7 are show going to two different locations on sheet EPG-100 and EP-101. Please advise. Also, Circuit Designated ICU (clouded) does not seem to be in reference to the originating circuit. Where does this circuit originate from? What are its electrical characteristics and what is the overall length?
“MRS-3”
Originates from - New Electrical Room (1st Floor) To - Radiology Distribution Board DBHNRS.
Approx. Length - 140’ Feeder Size- (2)4”C,4#250KCMIL,1#2/0 EG (See sheet EP-001)
“DBLNA-4”
Originates from - New Electrical Room (1st Floor) To - PBLNA1A (Runs along the wall of building to the panel) Approx. Length - 295’ Feeder Size- 3”C,4#300KCMIL,1#4 EG (See sheet EP-001)
“DBLNA-7”
Originates from - New Electrical Room (1st Floor) To - PBLNA2C (Runs along the wall of building to the panel) Approx. Length - 190’ Feeder Size- 2 1/2”C,4#4/0,1#4 EG (See sheet
EP-001).
Circuit designated “ICU” was the label on one of the conduit in the basement during our field investigation running from “JB#01” to “JB#02”/ “JB#06” as shown on sheet EPG-100. Approx.
length between JB#01 and JB#02 is 128’-0”.
DATE
QUESTION
RECEIVED
DATE
QUESTION
ANSWERED
QUESTION GOVERNMENT RESPONSE
13. 9-23-20 9-28-20 May you please confirm that this project’s scope of work entails only the electrical portion (Sheets 42-93) of the set of drawings?
Sheets 42 thru 93 in the set of drawings submitted in the bid package and additional sheets added in Addendum #1 is the complete Electrical scope of work. All other sheets of the bid set relates to the Architectural, Structural &Mechanical discipline.
ITEM