ATTACHMENT 2 - Drawings 1 of 2.pdf
PDF 21 MB Posted
- Solicitation number
- 36E77620B0005
About this file
This notice provides information about an anticipated solicitation for design-build renovation and construction services. The Department of Veterans Affairs plans to issue an Invitation for Bid for the Renovate for Relocation of Oncology, Hematology, and Dialysis 1st Floor Construction project at the Robert J. Dole VA Medical Center in Wichita, Kansas. The contractor will furnish all labor, materials, equipment, and supervision to renovate and relocate oncology, hematology, and dialysis services on the first floor. The solicitation will be set aside for Service-Disabled Veteran-Owned Small Businesses and have a magnitude between $2-5 million. The period of performance is approximately 270 calendar days from notice to proceed. Questions must be submitted in writing by mid-June 2020.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
212 N. CRAWFORD AVE.
NORMAN, OK. 73069
VETERANS
HEALTH
ADMINISTRATION
U.S. Department of Veterans Affairs
US ROUTE 400
IN
T
E R
S T
A T
E
HWY 96
IN
TERSTATE 35
US ROUTE 400
E WATERMAN ST
E KELLOGG DR N
S E
D G
E M
O O
R S
T
ROBERT J. DOLE
VA MEDICAL
CENTER
N
O L
IV
E R
ROBERT J. DOLE VA MEDICAL CENTER & REGIONAL OFFICE
CENTER
RENOVATE FOR RELOCATION OF ONCOLOGY, HEMATOLOGY
AND DIALYSIS 1ST FLOOR, WICHITA, KS
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
CONSTRUCTION
DOCUMENTS
FULLY SPRINKLERED
Robert J. Dole VA
Medical Center &
Regional Office Center
Wichita, KS
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
CONSULTANT
B
IM
/1
-V A
W
IC
H
IT
A /V
A
W ic h it a
C e n tr a l.
rv t
/2
/2
:5
:3
P
M
G-001
COVER SHEET AND SHEET INDEX
Prime Architects
212 N Crawford Ave
Norman, OK 73069
866.226.8071
Gene Lavastida, Owner
RENOVATE FOR RELOCATION OF
ONCOLOGY, HEMATOLOGY, AND
DIALYSIS 1ST FLOOR
WICHITA, KS
589A7-19-401
Building 1
Conrad Pierce General Engineer/COR
2020.05.15 BJM JRC
VICINITY MAP
ALTERNATE SUMMARY:
ALTERNATE NO. 1: DELETE REQUIREMENT FOR PANIC FOBS.
ALTERNATE NO. 2: EXISTING VESTIBULE TO REMAIN. DEMO AND MODIFY PORTIONS ONLY AS
NEEDED TO ACCOMMODATE EXPANSION OF VESTIBULE AS INDICATED ON
BASE BID DOCUMENTS.
ALTERNATE NO. 3: DELETE PLACEMENT OF BOLLARDS ACROSS DROP OFF DRIVE. DEMO AND
REMOVE DROP OFF DRIVE AND REPLACE WITH SOD TO THE EXTENT
INDICATED ON DRAWINGS.
SHEET INDEX
SHEET NO. SHEET NAME
M601 MECHANICAL SCHEDULES SHEET
M602 MECHANICAL CONTROLS SHEET
M603 MECHANICAL CONTROLS SHEET
M604 MECHANICAL AIR BALANCE
ELECTRICAL
EA001 ELECTRICAL NOTES, LEGENDS & ABBREVIATIONS
ED101 ELECTRICAL LIGHTING DEMO SHEET
ED102 ELECTRICAL POWER & FIRE DEMO SHEET
EL101 ELECTRICAL LIGHTING PLAN
EP101 ELECTRICAL POWER PLAN
EP102 ELECTRICAL SCHEDULES SHEET
EP103 ELECTRICAL PWR PLAN - ELEVATIONS
EP104 ELECTRICAL PWR PLAN - ELEVATIONS
EP105 ELECTRICAL DETAILS SHEET
ES101 ELECTRICAL FIRE ALARM PLAN
TELECOMMUNICATIONS
TD101 TECHNOLOGY DEMO SHEET
TF100 TECHNOLOGY SITE PLAN
TF101 TECHNOLOGY FLOOR PLAN
TF102 TECHNOLOGY FLOOR PLAN - CABLE RUN LAYOUT
TF301 TECHNOLOGY ENLARGED PLAN
TF400 TECHNOLOGY NOTES AND LEGENDS
TF501 TECHNOLOGY DETAILS
TF502 TECHNOLOGY DETAILS
TF503 TECHNOLOGY DETAILS
TF504 TECHNOLOGY DETAILS
TF505 TECHNOLOGY DETAILS
TF506 TECHNOLOGY DETAILS
TF600 TECHNOLOGY SCHEDULES
SHEET INDEX
SHEET NO. SHEET NAME
INTERIORS
IN101 FIRST FLOOR LOBBY ANNOTATION PLAN
IN102 EQUIPMENT / INTERIOR ANNOTATION PLAN
IN103 FIRST FLOOR PATTERN PLAN
IN104 FIRST FLOOR SIGNAGE PLAN
IN201 INTERIOR ELEVATIONS
IN202 INTERIOR ELEVATIONS
IN203 INTERIOR ELEVATIONS
IN210 INTERIOR SECTIONS & DETAILS
IN501 ROOM FINISH SCHEDULE / TRANSITION DETAILS
FIRE PROTECTION
FA001 FIRE PROTECTION LEGEND & DETAILS
FD101 FIRE PROTETCTION - DEMOLITION - FIRST FLOOR
FA101 FIRE PROTECTION PLAN FIRST FLOOR
PLUMBING
PA001 PLUMBING LEGENDS, SYMBOLS & ABBREVIATIONS
PD100 PLUMBING PLAN BASEMENT DEMOLITION
PD101 PLUMBING PLAN FIRST FLOOR DEMOLITION
PL101 PLUMBING PLAN FIRST FLOOR - OVERALL
PL102 PLUMBING PLAN BASEMENT
PL103 PLUMBING PLAN - FIRST FLOOR
PL501 PLUMBING DETAILS
PL901 PLUMBING ISOMETRICS
MECHANICAL
M001 MECHANICAL NOTES, LEGENDS & ABBREVIATIONS
MD111 MECHANICAL DUCTWORK DEMOLITION PLAN - BASEMENT
MD112 MECHANICAL DUCTWORK DEMOLITION PLAN - FIRST FLOOR
MD122 MECHANICAL PIPING DEMOLITION PLAN - FIRST FLOOR
MH101 MECHANICAL DUCTWORK PLAN - BASEMENT
MH102 MECHANICAL DUCTWORK PLAN - FIRST FLOOR
MP102 MECHANICAL PIPING PLAN - FIRST FLOOR
M501 MECHANICAL DETAILS SHEET
M502 MECHANICAL DETAILS SHEET
SHEET INDEX
SHEET NO. SHEET NAME
GENERAL
G-001 COVER SHEET AND SHEET INDEX
G-101 LIFE SAFETY PLAN
CIVIL
CD101 EXISTING, DEMOLITION & STORM WATER POLLUTION
PREVENTION PLAN
CS101 SITE PLAN
CG101 GRADING PLAN
CP101 PAVING PLAN
CP501 SITE DETAILS
STRUCTURAL
S001 GENERAL NOTES
S002 SPECIAL INSPECTIONS
S003 3-D VIEW
S101 FOUNDATION AND FRAMING PLAN
S501 FOUNDATION DETAILS
S502 FOUNDATION DETAILS
S521 FRAMING DETAILS
ARCHITECTURAL
A-001 ARCHITECTURAL ABBREVIATIONS
A-002 SYMBOLS, MOUNTING HEIGHTS
A-003 WALL PARTITIONS
AD102 FIRST FLOOR DEMOLITION PLAN
AE101 OVERALL FIRST FLOOR PLAN
AE102 FIRST FLOOR DIMENSION PLAN
AE103 FIRST FLOOR ANNOTATION PLAN
AE110 ROOF PLAN - VESTIBULE
AE201 BUILDING ELEVATIONS
AE301 BUILDING SECTIONS
AE302 WALL SECTIONS / PLAN DETAILS
AE501 DOOR SCHEDULE / DOOR AND WINDOW DETAILS
AE502 EXTERIOR WINDOW ELEVATIONS
AC101 FIRST FLOOR CEILING PLAN
Revisions: Date:
BJPM99
Text Box 5/15/20
DN
2 2
1 1
2 2
2 22
2 2
2 2
2 2
S S
S S
1 1
TO BLDG #4 & #60 BASEMENT
SLOPE SLOPE
LADDER
LADDER
0CORR
001A 001 0ELEV
008A
0STAIRC
014A
014A
019A
ROOM
LOUNGE
ELECTRICAL CLOSET
GENERAL
CLOSET
MECHANICAL ROOM
MECHANICAL
ROOM
ROOM
HAC
MECHANICAL
ROOM
ELECTRICAL
CLOSET
MECHANICAL ROOM
WOMEN'S
ELEVATOR
ELEVATOR
MACHINE
ROOM
STORAGE
VESTIBULE
ELEVATOR
CORRIDOR
DIRTY
SHAFT
LINEN
MECHANICAL
STAIR
OFFICE
STAFF
TOILET
LOCKER
LOCKER ROOM
MEN'S
STORAGE
GENERAL
STORAGE
GENERAL
STORAGE
GENERAL
STORAGE
TELEPHONE
GENERAL
STORAGE
CLOSET
TELEPHONE
ROOF OF
FIRST FLOOR
ROOF OF
FIRST FLOOR
EPDM ROOF
RE C-DE6
SCUPPER
PARAPET
SCUPPER
RE C-DE6
EPDM ROOF
PARAPET
RE C-DE6
SCUPPER
225224222216B
216A
2B123
215A
2STAIR-W
226A
202203
222A
200 286
2CORR
2ELEV
220A
241240
237A
2STAIR-C
262261
209A
2STAIR-E
256A
280A
2STAIR-SE
CORRIDOR
ROOM
OFFICE OFFICE OFFICE
CONFERENCE ROOM
NURSE
STATION
1-BED ROOM
MALE PATIENT
TOILET
BED ROOM
ON-CALLOFFICE
OFFICE
SOILED UTILITY ROOM
MEDICATION
CONFERENCE ROOM
LINEN ROOM
LOUNGE
LOUNGE
MALE
VISITOR TOILET
OFFICE
CHAPEL
STORAGE
TOILET
CHAPEL
OFFICE
PREP
ELECTRICAL
IRM
CLOSET
LAUNDRY
OFFICE
OFFICE
HSK
STORAGE
CONFERENCE
OFFICE
OFFICE
CHIEF
STORAGE
CHIEF
OFFICE
ELECTRICAL
CLEAN
ROOM
SHAFT
TELEPHONE
EXAM/TREATMENT ROOM
LOCKER OFFICE
HSK
CLOSET
FIRE
EXTINGUISHER
CLOSET
FIRE
EXTINGUISHER
CLOSET
STAIR
ELEVATOR
CORRIDOR
CORRIDOR
1-BED ROOM
1-BED ROOM
1-BED ROOM
1-BED ROOM
1-BED ROOM1-BED ROOM
EQUIPMENT ROOM
EXAM/
TREATMENT
ROOM
ROOM
STAFF TOILET
CLOSET
GENERAL
OFFICE
GENERAL
STORAGE
LOUNGE
GENERAL
STORAGE
GENERAL
OFFICE
CLINICAL
TOILET
STAIR
VISITOR
TOILET
BED ROOM
ON-CALL
SOILED UTILITY
ROOM
ELECTRICAL
CLOSET
UTILITY ROOM
CHIEF
TELEPHONE
LAB
SUPPLIES
WARD
TELEPHONE
1-BED
STAIR
1-BED ROOM
CLOSET
STAFF
TOILET
1-BED ROOM
1-BED ROOMCLEAN
GENERAL
STORAGE
CLOSET
ROOM
1-BED
ROOM
MALE PATIENT
TOILET
STAIR
FIRE
EXTINGUISHER
CLOSET
TOILET
TOILET
TOILET
CLOSET
CLOSET
CLOSET
CLOSET
CLOSET
CLOSET
CLOSET CLOSET
COUNTER
COUNTER
COUNTER
COUNTER
C
OU
N
TE
R
COUNTER
341340
301302
324323
303304
320319
325A
314B
319A
3STAIRW
3ELEV
3CORR
350A
374 373
353A 355
3STAIRE
356 357
357A
358 359
362A
363A
367 366
321A
365A
363B
313 312
3STAIRC
STAIR
23 HOUR OBSERVATION
MEDICAL CARE
INPT.
INPT. MEDICAL CARE
MEDICAL CARE
INPT.
INPT. SURGICAL INPT. SURGICALSTORAGE OFFICE SHOWER
TOILET
SURGICAL
INPT.
DUCT CHASE
PATIENT ROOM
ELECTRICAL
NURSING STATION
EMPLOYEE LOUNGEOFFICEPATIENT ROOMPATIENT ROOMMEDICAL ROOMSTORAGE
ELECTRICAL
PATIENT ROOM
PATIENT ROOM
DOCTORS WORK STATION
MEDICAL ROOM
UTILITY ROOM
PATIENT ROOM
PATIENT ROOM PATIENT ROOM
PATIENT ROOM
TELECOM
PATIENT ROOM STORAGE PATIENT ROOM
PATIENT ROOM
LOCKER ROOM
HSK
NURSE MANAGER
OFFICE NURSE OFFICE
RN OFFICE
PATIENT ROOM PATIENT ROOM MED.ROOM PATIENT ROOM
PATIENT ROOM PATIENT ROOM PATIENT ROOM
DOCTORS WORK STATION
PATIENT ROOM
PATIENT ROOM
PATIENT ROOM PATIENT ROOM
PATIENT ROOM
TOILET TOILET TOILET
STAIR
CORRIDOR
ELEVATOR
TOILET
TOILET
TOILET
TOILET
TOILET
TOILET
TOILET TOILET
TOILET
STAIR
TOILET
MED.ROOM
TOILETTOILETTOILET
CLOSET
CLOSET
TOILET
TELECOM CLOSET
LINEN ROOM
CLOSET
CLOSET
CLOSET CLOSET
CLOSETCLOSET
CLOSET
CLOSET
CABINET
CABINET
CABINET
CLOSETCLOSET
CLOSETCLOSET
CABINET
CABINET
CLOSET
IRM
ROOF
418419
414A
415A
4CORR
4STAIR-W
4STAIR-E
470 471
410402
4ELEV
4STAIR-C
ELEVATOR
STAIR
CENTER
EEGAUDIOLOGY
AUDIOLOGY OFFICE
WORK ROOM EXAM ROOM CARE
SPECIAL
STORAGE
SECURITY
STORAGE
CANTEEN
EXAM ROOM
ELECTRICAL
BED2
SLEEP CENTER
OFFICE
SLEEP
SLEEP
BED1
SOUND
ROOM
SOUND
ROOMEXAM ROOM
MECHANICAL ROOM
MECHANICAL ROOM
AUDIOLOGY OFFICE
STAIR
CORRIDOR
STAIR
CORRIDOR
TOILET
TOILET
TOILET
TOILET
PROCEDURE
ROOM
160-1
EXAM /
TELE
MED
143-1
EXAM
ROOM
142-1
SEC
WORK
140-1
WAITING
139-1
ELECTRICAL
162A-1
INFUSION
BAY
164-1
EXAM
ROOM
167-1
SOILED
STORAGE
170-1
EYE
WASH
173-1
CLEAN
LINEN
STORAGE
174-1
CHEMO
TRTMT
176-1
CHEMO
TRTMT
177-1
CHEMO
TOILET
180-1 CHEMO
TRTMT
179-1
STERILE
STOR
181-1
CHEMO
TRTMT
182-1
CHEMO
TRTMT
184-1
CHEMO
TRTMT
185-1
CHEMO
TRTMT
186-1
NURSE
STATION
178-1
PAT
WEIGH-IN
188-1
CHEMO
TRTMT
175-1
MEDS
172-1
NOUR
171-1
CHEMO
TOILET
169-1
INFUSION
BAY
166-1
NURSE
STATION
165-1
CORRIDOR
183-1
C O
R R
ID
O
R -1
C O
R R
ID
O
R -1
SHARED
LOUNGE
138-1
DEPT
CHIEF
136-1
MAS
CHIEF
135-1
MAS
WORK
AREA
133-1
IT
CLOSET
131-1
INTERVIEW
132-1
WOMEN'S
128-1
REFERENCED BUILDING CODES
2018 NFPA 101 LIFE SAFETY CODE
2018 IBC (INTERNATIONAL BUILDING CODE)
2012 IFC (INTERNATIONAL FIRE CODE)
2017 NEC (NATIONAL ELECTRICAL CODE)
2018 IMC (INTERNATIONAL MECHANICAL CODE)
2015 IPC (INTERNATIONAL PLUMBING CODE)
2017 ICC A117.1 ACCESSIBLE AND USABLE BUILDINGS
2006 IECC (INTERNATIONAL ENERGY CONSERVATION CODE)
CLASSIFICATION OF OCCUPANCY
OCCUPANCY CLASSIFICATION: AMBULATORY HEALTH CARE
CONSTRUCTION TYPE
TYPE II - NON COMBUSTIBLE
FIRE-RESISTANCE RATING FOR BUILDING ELEMENTS (HOURS)
PRIMARY STRUCTURAL FRAME: 2 (REDUCE TO 1 IF ONLY SUPPORTING ROOF)
BEARING WALLS
EXTERIOR 2
INTERIOR 2
NON BEARING WALLS AND PARTITIONS
EXTERIOR 1 (- 5'), 1 (5'-10'), 1 (10'-30'), 0 (+30'-0)
INTERIOR 0
FLOOR CONSTRUCTION / SECONDARY 2
ROOF CONSTRUCTION / SECONDARY 1
MEANS OF EGRESS
MAXIMUM COMMON PATH OF EGRESS: B OCCUPANCY: 100'-0"
EXIT ACCESS TRAVEL DISTANCE: 200'-0", ALL AREAS TO BE WITHIN 200' OF A SMOKE BARRIER.
DEAD END CORRIDOR (B OCCUPANCY): 50'-0"
103'
91'
1 1 1 1 1
MAS
WAITING
129-1
INTERVIEW
130-1
CORRIDOR
127-1
ACCESSIBLE
VESTIBULE
125-1
VESTIBULE
126-1
LOBBY
LOBBY-1
CORR.
CORR-1
ELEVATOR
LOBBY
EL LOB-1
RELEASE
OF INFO
134-1
CORRIDOR
168A-1
CORRIDOR
168B-1
STAIR
STAIR-SE-1
EXISTING SMOKE BARRIER TO REMAIN
HAC
161-1
STORAGE
162-1
AREA OF WORK
OCCUPANT LOAD NUMBER AT EXIT
COMPONENT
EXIT COMPONENT MAXIMUM OCCUPANT
CAPACITY NUMBER
DRY CHEMICAL TYPE FIRE EXTINGUISHER -
WALL BRACKET
MOUNTED AT 48" AFF
XX
MULTI-PURPOSE TYPE FIRE EXTINGUISHER -
WALL BRACKET
MOUNTED AT 48" AFF
TWO HOUR CONSTRUCTION2
ONE HOUR CONSTRUCTION
SMOKE BARRIER- (ONE HOUR
CONSTRUCTION)
MULTI-PURPOSE TYPE FIRE EXTINGUISHER -
SEMI-RECESSED CABINET
MOUNTED AT 48" AFF
LIFE SAFETY LEGEND
S
EXIT SIGN
WORK AREA
EGRESS ROUTE (FEET)
AMBULATORY HEALTH CARE
OCCUPANCY
HEALTH CARE OCCUPANCY
2 SPACE OCCUPANT COUNT
NOT IN CONTRACT
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
CONSTRUCTION
DOCUMENTS
FULLY SPRINKLERED
Robert J. Dole VA
Medical Center &
Regional Office Center
Wichita, KS
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
CONSULTANT
B
IM
/1
-V A
W
IC
H
IT
A /V
A
W ic h it a
C e n tr a l.
rv t
/2
/2
:5
:4
P
M
G-101
LIFE SAFETY PLAN
Prime Architects
212 N Crawford Ave
Norman, OK 73069
866.226.8071
Gene Lavastida, Owner
RENOVATE FOR RELOCATION OF
ONCOLOGY, HEMATOLOGY, AND
DIALYSIS 1ST FLOOR
WICHITA, KS
589A7-19-401
Building 1
Conrad Pierce General Engineer/COR
2020.05.15 BJM JRC
1/8" = 1'-0"1
FIRST FLOOR PLAN LIFE SAFETY PLAN
NTS2
BASEMENT FLOOR USE AND OCCUPANCY PLAN
NTS3
SECOND FLOOR USE AND OCCUPANCY PLAN
NTS4
THIRD FLOOR USE AND OCCUPANCY PLAN
NTS5
FOURTH FLOOR USE AND OCCUPANCY PLAN
0 4' 8' 16'
1/8" = 1'-0"
N
Revisions: Date:
BJPM99
Text Box 5/15/20
EXIST. BLDG.
EXIST. BLDG.
EXIST. BLDG.
EXIST.
CONC.
AREA
EXIST. BLDG.
EXIST. BLDG.
EXIST. BLDG.
EXIST.
CONC.
AREA
EROSION CONTROL AND STORMWATER MANAGEMENT
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
A
CONSTRUCTION
DOCUMENTS
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
STAMP
MENDEZ NGINEERING
Registration # F-14070 12950 Country Parkway, Suite 120 San Antonio, Texas 78216 Office: 210-802-0808 www.MendezEngineering.com
E
RENOVATE FOR RELOCATION OF
ONCOLOGY, HEMATOLOGY, AND
DIALYSIS 1ST FLOOR
WICHITA, KS
589A7-19-401
Building 1
2020.05.15 DTC JRC
Gene Lavastida, Owner 866.226.8071 Norman, OK 73069 212 N Crawford Ave Prime Architects A/E:
Conrad Pierce General Engineer/COR
Date:Revisions:
Robert J. Dole VA Medical Center &
Regional Office Center Wichita, KS
5/15/2020
-1' - 6"
PROJECT
LIMITS
KEY MAP
N.T.S.
EXISTING, DEMOLITION & STORM WATER
POLLUTION PREVENTION PLAN
CONTRACTOR TO EXERCISE EXTREME CAUTION WHEN WORKING
UNDER AND / OR AROUND OVERHEAD ELECTRIC LINES. CONTRACTOR
SHALL COORDINATE WITH LOCAL ELECTRIC/UTILITY COMPANY TO
ESTABLISH THE MAXIMUM WORKING HEIGHT FROM GROUND
ELEVATION. COORDINATE ALL WORK WITH LOCAL ELECTRIC/UTILITY
COMPANY.
CAUTION ! ! !
THE LOCATIONS AND DEPTHS OF EXISTING UTILITIES, INCLUDING
SERVICE LATERALS AND DRAINAGE STRUCTURES SHOWN ON THE
PLANS ARE APPROXIMATE ONLY. THE CONTRACTOR SHALL VERIFY
THE EXACT LOCATION AND DEPTHS OF UNDERGROUND UTILITIES AT
LEAST 48 HOURS PRIOR TO CONSTRUCTION WHETHER SHOWN ON
PLANS OR NOT, AND TO PROTECT THE SAME DURING CONSTRUCTION.
NOTE:
CONTRACTOR IS NOT TO IMPEDE OR OBSTRUCT, THE FLOW OF ANY
FIRE AND EMERGENCY VEHICLES WITH CONSTRUCTION MATERIALS
AND VEHICLES DURING THE DURATION OF CONSTRUCTION.
NOTE:
CD101
STAGING AND STORAGE AREA
INSTALL SILT FENCE 2' FROM PROPERTY LINE
(REF. SITE DETAILS SHT CP501 DETAIL #1)
KEYNOTES
EASEMENT / SETBACK LINE
EXISTING CONTOUR ELEVATIONS
LIMITS OF CONSTRUCTION /
DISTURBANCE
TEMPORARY SILT FENCE
LIMITS OF TEMPORARY PARKING,
STORAGE, SPOILS, AND STAGING
AREA.
NOTES:
1. CONTRACTOR SHALL COMPLY WITH THE LATEST STANDARD OF OSHA DIRECTIVES OR
LOCAL AGENCY HAVING JURISDICTION FOR EXCAVATION AND TRENCHING
PROCEDURES. THE CONTRACTOR SHALL USE SUPPORT SYSTEMS, SLOPING, BENCHING
AND OTHER MEANS OF PROTECTION. THIS IS TO INCLUDE BUT NOT LIMITED TO ACCESS
AND EGRESS FROM ALL EXCAVATION AND TRENCHING. CONTRACTOR IS RESPONSIBLE
TO COMPLY WITH PERFORMANCE CRITERIA FOR OSHA. ALL TREES WITHIN PROJECT
LIMITS SHALL BE PROTECTED, SEE SHEET CP501 FOR DETAILS.
2. PROVIDE BAGGED GRAVEL INLET FILTERS AT ALL EXPOSED DRAINAGE STRUCTURES.
3. SOIL DISTURBANCES WILL OCCUR OVER MAJORITY OF THE SITE.
4. LOCATIONS OF MAJOR STRUCTURAL AND NON STRUCTURAL CONTROLS ARE LABELED.
5. THESE ARE THE TEMPORARY AND PERMANENT BEST MANAGEMENT PRACTICES.
6. SOIL STABILIZATION PRACTICES SHALL OCCUR OVER THE ENTIRE SITE WITH THE USE
OF PAVEMENT, BUILDINGS, SIDEWALKS, GRASS SOD, GRASS SEEDING AND MULCH.
7. THERE ARE NO LOCATIONS WHERE STORMWATER DISCHARGES TO SURFACE WATER.
8. CONTRACTOR TO ADJUST LOCATIONS OF STABILIZED CONSTRUCTION ENTRANCE/EXIT
AND/OR CONSTRUCTION STAGING AREA AND WASHOUT PIT AS NECESSARY TO
SUPPORT CONSTRUCTION.
9. THE CONTRACTOR IS RESPONSIBLE FOR ALL DE-WATERING, PUMPING AND
TREATMENT OF WATER. NO WATER FROM ANY CONSTRUCTION WORK SHALL BE
RELEASED DOWNSTREAM OR INTO STORM SYSTEMS WITHOUT FIRST BEING TREATED
OR HAVING SEDIMENT, OILS OR OTHER POLLUTANTS REMOVED IN ACCORDANCE WITH
THE STORM WATER POLLUTION PREVENTION PLAN.
10. STABILIZATION MEASURES SHALL BE INITIATED AS SOON AS PRACTICAL IN PORTIONS
OF THE SITE WHERE CONSTRUCTION ACTIVITIES HAVE TEMPORARILY OR
PERMANENTLY CEASED, BUT IN NO CASE MORE THAN 14 DAYS AFTER THE
CONSTRUCTION ACTIVITY IN THAT PORTION OF THE SITE HAS TEMPORARILY OR
PERMANENTLY CEASED. WHERE THE INITIATION OF STABILIZATION MEASURES BY THE
14TH DAY DAY AFTER CONSTRUCTION ACTIVITY TEMPORARILY OR PERMANENTLY
CEASE IS PRECLUDED BY WEATHER CONDITIONS, STABILIZATION MEASURES SHALL BE
BE INITIATED AS SOON AS PRACTICAL. WHERE CONSTRUCTION ACTIVITY ON A PORTION
OF THE SITE IS TEMPORARILY CEASED, AND EARTH DISTURBING ACTIVITIES WILL NOT
BE RESUMED WITHIN 21 DAYS, TEMPORARY STABILIZATION DO NOT HAVE TO BE
INITIATED ON THAT PORTION OF THE SITE. IN AREAS EXPERIENCING DROUGHTS
WHERE THE INITIATION OF STABILIZATION MEASURES B THE 14TH DAY AFTER
CONSTRUCTION ACTIVITY HAS TEMPORARILY OR PERMANENTLY CEASED IS
PRECLUDED BY SEASONAL ARID CONDITIONS, STABILIZATION MEASURES SHALL BE
INITIATED AS SOON AS PRACTICAL.
11. THIS SHEET IS FOR INCLUSION IN THE OPERATOR'S OVERALL STORMWATER
POLLUTION PREVENTION PAN AND GENERAL PERMIT TXR 150000 PACKAGE. THIS
SHEET SHOULD NOT BE CONSIDERED TO BE THE ENTIRE STORMWATER POLLUTION
PREVENTION PLAN.
12. GENERAL CONTRACTOR IS RESPONSIBLE FOR SUBMITTING THE KDHE NOTICE OF
INTENT (NOI) AND NOTICE OF TERMINATION (NOT) UNDER THE NPDES CONSTRUCTION
GENERAL PERMIT XXX-XXXXXX.
1. IT IS UNLAWFUL FOR ANY GENERAL CONTRACTOR, SUBCONTRACTOR OR OWNER TO
PERMIT, OR CAUSE TO BE PERMITTED, EROSION OF MATERIAL FROM A
CONSTRUCTION SITE.
2. ALL CONSTRUCTION-RELATED VEHICLE PARKING AND ACTIVITY (INCLUDING
EMPLOYEE PERSONAL VEHICLES AND DELIVERY VEHICLES) MUST BE LOCATED
WITHIN THE LIMITS OF CONSTRUCTION, WITH APPROPRIATE CONTROLS, OR
DESIGNATED PARKING/ACCESS ON APPROVED SURFACES OUTSIDE THE LIMITS OF
CONSTRUCTION.
3. CERTAIN EROSION CONTROL MEASURES IDENTIFIED BY THE CITY OF WICHITA ARE TO
BE EMPLOYED TO PREVENT EROSION; HOWEVER, THESE ARE ONLY MINIMUM
STANDARDS.
4. IN THE EVENT OF UNUSUAL SITE CONDITIONS ALONG ANY WATER FEATURES OR
WEATHER RELATED EVENTS,MORE STRINGENT REQUIREMENTS MAY BE NECESSARY
(ON-SITE OR OFF) TO MAINTAIN EROSION CONTROL.
5. THE OWNER OR THEIR DESIGNEE IS RESPONSIBLE FOR ALL CHANGES, UPGRADES
AND CONTINUED MAINTENANCE OF ALL EROSION CONTROL AND STORMWATER
MANAGEMENT FEATURES AT ALL TIMES.
6. EROSION CONTROL MEASURES AND STORMWATER MANAGEMENT PRACTICES WILL
BE INSPECTED BY THE CITY OF WICHITA PRIOR TO AND DURING THE CONSTRUCTION
PROCESS.
7. ALL DESIGNS TO PREVENT THE EROSION OF SOIL AND DEBRIS FROM THE
CONSTRUCTION SITE OR SURROUNDING AREAS DAMAGED BY CONSTRUCTION SHALL
BE MAINTAINED BY THE CONTRACTOR DURING CONSTRUCTION.
8. SITE WORK PERMITTED BY THE SITE PREPARATION PERMIT AND WORK PERMITTED
BY A DEMOLITION PERMIT CANNOT BEGIN UNTIL EROSION CONTROL AND TREE
PROTECTION MEASURES ARE IN PLACE.
9. DOWNSTREAM STORM DRAIN INLETS WITHIN 200 FOOT OF ANY PERMITTED
CONSTRUCTION AREA MUST BE PROTECTED PER DETAIL.
10. DEWATERING PRACTICES MUST COMPLY WITH EPA 2012 CONSTRUCTION GENERAL
PERMIT, SECTION 2.1.3.4., AS APPLICABLE.
11. THE CONTRACTOR OR OWNER MUST HAVE A DESIGNATED PERSON RESPONSIBLE
FOR CONTINUOUS (24 HOURS) MONITORING EROSION CONTROL MEASURES TO
ENSURE THAT ALL FEDERAL, STATE, & LOCAL LAWS AND REGULATIONS ARE BEING
COMPLIED WITH. THIS PERSON SHALL BE RESPONSIBLE FOR ALL REQUIRED FORMS
AND DOCUMENTATION TO MEET REGULATIONS OF THE EPA AND NPDES GENERAL
PERMIT.
12. DO NOT WASH, SWEEP OR OTHERWISE CAUSE CONSTRUCTION SOIL OR DEBRIS TO
BE DEPOSITED INTO ANY OFF-SITE STORMWATER DRAINAGE OR CONVEYANCE
SYSTEM.
CAUTION:
CONTRACTOR TO VERIFY ALL EXISTING UTILITIES VERTICALLY AND
HORIZONTALLY PRIOR TO CONSTRUCTION. CONTRACTOR TO NOTIFY
THE ENGINEER IMMEDIATELY OF ANY DISCREPANCIES. THE ENGINEER
ASSUMES NO RESPONSIBILITY FOR THE ACCURACY OF THE LOCATION
OF UNDERGROUND UTILITIES. THE CONTRACTOR SHALL BE
RESPONSIBLE FOR AVOIDING ALL EXISTING UTILITIES BY CALLING 811
FOR LOCATION OF ALL UTILITIES, AT LEAST 2 WORKING DAYS PRIOR
TO BEGINNING CONSTRUCTION. ANY DAMAGE TO EXISTING UTILITIES
SHALL BE THE SOLE RESPONSIBILITY OF THE CONTRACTOR AND THE
REPAIR SHALL BE AT THE CONTRACTOR'S SOLE EXPENSE WHETHER
THE UTILITY IS SHOWN ON THESE PLANS OR NOT.
TRENCH EXCAVATION SAFETY PROTECTION:
CONTRACTOR AND/OR CONTRACTOR'S INDEPENDENTLY RETAINED
EMPLOYEE OR STRUCTURAL
DESIGN/GEOTECHNICAL/SAFETY/EQUIPMENT CONSULTANT, IF ANY,
SHALL REVIEW THESE PLANS, AVAILABLE GEOTECHNICAL
INFORMATION, AND THE ANTICIPATED INSTALLATION SITE(S) WITHIN
THE PROJECT WORK AREA IN ORDER TO IMPLEMENT CONTRACTOR'S
TRENCH EXCAVATION SAFETY PROTECTION SYSTEMS, PROGRAMS
AND/OR PROCEDURES. THE CONTRACTOR'S IMPLEMENTATION OF THE
SYSTEMS, PROGRAMS AND/OR PROCEDURES SHALL PROVIDE FOR
ADEQUATE TRENCH EXCAVATION SAFETY PROTECTION THAT
COMPLIES WITH, AS A MINIMUM, OSHA STANDARDS FOR TRENCH
EXCAVATIONS. SPECIFICALLY, CONTRACTOR AND/OR CONTRACTOR'S
INDEPENDENTLY RETAINED EMPLOYEE OF SAFETY CONSULTANT
SHALL IMPLEMENT A TRENCH SAFETY PROGRAM IN ACCORDANCE
WITH OSHA STANDARDS GOVERNING THE PRESENCE AND ACTIVITIES
OF INDIVIDUALS WORKING IN AND AROUND TRENCH EXCAVATION.
CONCRETE REMOVAL
EXISTING CONCRETE FILLED METAL
BOLLARDS
3 BEGINNING/END OF CURB REMOVAL
4 REMOVAL OF EXISTING CROSSWALK METAL SIGN POST WITH CONCRETE FOOTING
3 3
SCALE: 1" = 10'
LEGEND
PUBLIC
CORRIDOR
LOBBY
VESTIBULE RAMP DOWN
EXIST.
BLDG.
EXIST.
BLDG.
EXIST.
BLDG.
ACCESSIBLE
VESTIBULE
EXIST. SIDEWALK
ELEVATOR
R
AM
P D
O W
N
NOT A WALKWAY
NOT A WALKWAY
NOT A WALKWAY
SOD
7.
2'
5.4' 6.3'
6'
6'
6'
2.
2'
2'
40' 2'
6'
8 8
.6
4'
42.9'
114°15'28"
R15'
R1'
12.4'
±2 .0
EXIST. ASPHALT
TO REMAIN
2 2
13 13
HAZARD STRIPES
NO STOPPING OR STANDING "HAZARD STRIPES".
PERMANENTLY PAINTED (WHITE) ON PAVEMENT
UNDER THE ARM.
PEDESTRIAN ALERT WARNING
"NOT WALKWAY" PAVEMENT MARKING FACING
BOTH DIRECTIONS, PERMANENTLY PAINTED
(WHITE) ON PAVEMENT.
SOD
SEE ARCHITECTURAL
PLANS FOR CONTINUATION
INSTALL NEW SIDEWALK AT END
OF NEW STAIRS & ATTACH TO
EXIST. SIDEWALK. MATCH
ELEVATIONS.
PUBLIC
CORRIDOR
LOBBY
VESTIBULE RAMP DOWN
EXIST.
BLDG.
EXIST.
BLDG.
EXIST.
BLDG.
ACCESSIBLE
VESTIBULE
EXIST. SIDEWALK
ELEVATOR
R
AM
P D
O W
N
NOT A WALKWAY
NOT A WALKWAY
NOT A WALKWAY
4'
TYP.
8 8
EXIST. ASPHALT
TO REMAIN
±2 .0
7.
2'
6.3'
4'
5.4'
6'
6'
6'
2.
2'
2'
40' 2'
6'
.6
11 11
BOLLARDS @ 4' O.C.
BOLLARDS @ 4' O.C.
EXIST. CONCRETE
TO REMAIN
EXIST. CONCRETE
TO REMAIN
SEE ARCHITECTURAL
PLANS FOR CONTINUATION
INSTALL NEW SIDEWALK AT END
OF NEW STAIRS & ATTACH TO
EXIST. SIDEWALK. MATCH
ELEVATIONS.
HAZARD STRIPES
NO STOPPING OR STANDING "HAZARD STRIPES".
PERMANENTLY PAINTED (WHITE) ON PAVEMENT
UNDER THE ARM.
PEDESTRIAN ALERT WARNING
"NOT WALKWAY" PAVEMENT MARKING FACING
BOTH DIRECTIONS, PERMANENTLY PAINTED
(WHITE) ON PAVEMENT.
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
A
CONSTRUCTION
DOCUMENTS
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
STAMP
MENDEZ NGINEERING
Registration # F-14070 12950 Country Parkway, Suite 120 San Antonio, Texas 78216 Office: 210-802-0808 www.MendezEngineering.com
E
RENOVATE FOR RELOCATION OF
ONCOLOGY, HEMATOLOGY, AND
DIALYSIS 1ST FLOOR
WICHITA, KS
589A7-19-401
Building 1
2020.05.15 DTC JRC
Gene Lavastida, Owner 866.226.8071 Norman, OK 73069 212 N Crawford Ave Prime Architects A/E:
Conrad Pierce General Engineer/COR
Date:Revisions:
Robert J. Dole VA Medical Center &
Regional Office Center Wichita, KS
5/15/2020
-1' - 6"
PROJECT
LIMITS
KEY MAP
N.T.S.
SITE PLAN
LEGEND
EASEMENT LINE
EXISTING CURB
EXISTING OVERHEAD ELECTRIC LINE
EXISTING UTILITY POLE
EXISTING FIRE HYDRANT
EXISTING WASTEWATER LINE
EXISTING WATER LINE
NOTE:
ALL DRIVE APPROACHES IN THE RIGHT OF WAY SHALL BE IN COMPLIANCE WITH CURRENT
KANSAS ACCESSIBILITY STANDARDS AND CITY OF WICHITA DESIGN STANDARDS PRIOR TO
FINAL INSPECTION APPROVAL.
NOTES:
1. ALL ITEMS ARE TO BE FURNISHED & INSTALLED BY CONTRACTOR. REFERENCE
CONSTRUCTION DETAILS SHEETS FOR ADDITIONAL INFORMATION.
2. CONTRACTOR SHALL FORM SIDEWALKS AND VERIFY SLOPES PRIOR TO POURING
CONCRETE. CONTRACTOR SHALL ENSURE THAT CROSS SLOPES ARE NO GREATER
THAN 2% ALONG THE ACCESSIBLE ROUTE AND RUNNING SLOPE IS NO GREATER THAN
5%, UNLESS THE RUNNING SLOPE MATCHES THE EXISTING STREET SLOPE. IF ANY
DISCREPANCY ARISES, CONTRACTOR SHALL CONTACT ENGINEER FOR SOLUTION.
3. LIMITS OF CONSTRUCTION ARE SHOWN ON THE EROSION & SEDIMENTATION CONTROL
PLAN(S).
CAUTION:
CONTRACTOR TO VERIFY ALL EXISTING UTILITIES VERTICALLY AND HORIZONTALLY PRIOR
TO CONSTRUCTION. CONTRACTOR TO NOTIFY THE ENGINEER IMMEDIATELY OF ANY
DISCREPANCIES.
THE ENGINEER ASSUMES NO RESPONSIBILITY FOR THE ACCURACY OF THE LOCATION OF
UNDERGROUND UTILITIES. THE CONTRACTOR SHALL BE RESPONSIBLE FOR AVOIDING ALL
EXISTING UTILITIES BY CALLING 811 FOR LOCATION OF ALL UTILITIES, AT LEAST 2 WORKING
DAYS PRIOR TO BEGINNING CONSTRUCTION.
NOTES:
1. CONTRACTOR SHALL BE REQUIRED TO LOCATE ALL PUBLIC OR PRIVATE UTILITIES
INCLUDING BUT NOT LIMITING TO: WATER, SEWER, TELEPHONE AND FIBER OPTIC
LINES, SITE LIGHTING ELECTRIC, SECONDARY ELECTRIC, PRIMARY ELECTRICAL
DUCTBANKS, LANDSCAPE IRRIGATION FACILITIES, AND GAS LINES. ANY UTILITY
CONFLICTS THAT ARISE SHOULD BE COMMUNICATED TO THE ENGINEER IMMEDIATELY
AND PRIOR TO CONSTRUCTION. THE CONTRACTOR SHALL CONTACT 811 A MINIMUM OF
48 HOURS PRIOR TO THE START OF CONSTRUCTION. ANY DAMAGE TO EXISTING
UTILITIES SHALL BE THE SOLE RESPONSIBILITY OF THE CONTRACTOR AND THE REPAIR
SHALL BE AT THE CONTRACTOR'S SOLE EXPENSE WHETHER THE UTILITY IS SHOWN ON
THESE PLANS OR NOT.
2. CONTRACTOR TO EXERCISE EXTREME CAUTION WHEN WORKING UNDER AND/OR
AROUND OVERHEAD ELECTRIC LINES. CONTRACTOR SHALL COORDINATE WITH LOCAL
ELECTRIC/UTILITY COMPANY TO ESTABLISH THE MAXIMUM WORKING HEIGHT FROM
GROUND ELEVATION.
3. THE LOCATIONS AND DEPTHS OF EXISTING UTILITIES, INCLUDING SERVICE LATERALS
AND DRAINAGE STRUCTURES SHOWN ON PLANS ARE APPROXIMATE ONLY. THE
CONTRACTOR SHALL VERIFY THE EXACT LOCATION AND DEPTHS OF UNDERGROUND
UTILITIES AT LEAST 48 HOURS PRIOR TO CONSTRUCTION WHETHER SHOWN ON PLANS
OR NOT, AND PROTECT THE SAME DURING CONSTRUCTION.
4. CONTRACTOR TO CONTACT PROJECT MANAGER PRIOR TO COMMENCEMENT OF SITE
WORK FOR TREE INSPECTION.
5. REFERENCE SHEET CD101 FOR DETAILS AND SPECIFICATIONS OF THE TEMPORARY
BMP MEASURES FOR THE SITE.
6. ALL ITEMS ARE TO BE FURNISHED & INSTALLED BY CONTRACTOR. REFERENCE
CONSTRUCTION DETAILS SHEETS FOR ADDITIONAL INFORMATION.
7. LIMITS OF CONSTRUCTION ARE SHOWN ON THE EROSION & SEDIMENTATION CONTROL
PLAN(S).
ROW
SEE ARCHITECTS PLANS FOR LOCATIONS OF DOOR WAY LANDINGS. (SHT. S101)
INSTALL SIDEWALK ADA RAMP PER VA SPEC., SEE SHT. S101
APPLY ADA STRIPPING DENOTING 6' WIDE CONCRETE SIDEWALK
INSTALL NEW CONCRETE CURB SEE DETAIL SHT. CP501 DETAIL#5
CS101
NEW ADA RAMP TO MATCH EXIST. PAVEMENT ELEVATION, SEE SHT. CP501 DETAIL #7
MATCH EXISTING MOUNTABLE CURBS.
EXIST. CANOPY
EXIST. CANOPY
TRENCH EXCAVATION SAFETY PROTECTION:
CONTRACTOR AND/OR CONTRACTOR'S INDEPENDENTLY RETAINED EMPLOYEE OR
STRUCTURAL DESIGN/GEOTECHNICAL/SAFETY/EQUIPMENT CONSULTANT, IF ANY, SHALL
REVIEW THESE PLANS, AVAILABLE GEOTECHNICAL INFORMATION, AND THE ANTICIPATED
INSTALLATION SITE(S) WITHIN THE PROJECT WORK AREA IN ORDER TO IMPLEMENT
CONTRACTOR'S TRENCH EXCAVATION SAFETY PROTECTION SYSTEMS, PROGRAMS AND/OR
PROCEDURES. THE CONTRACTOR'S IMPLEMENTATION OF THE SYSTEMS, PROGRAMS
AND/OR PROCEDURES SHALL PROVIDE FOR ADEQUATE TRENCH EXCAVATION SAFETY
PROTECTION THAT COMPLIES WITH, AS A MINIMUM, OSHA STANDARDS FOR TRENCH
EXCAVATIONS. SPECIFICALLY, CONTRACTOR AND/OR CONTRACTOR'S INDEPENDENTLY
RETAINED EMPLOYEE OF SAFETY CONSULTANT SHALL IMPLEMENT A TRENCH SAFETY
PROGRAM IN ACCORDANCE WITH OSHA STANDARDS GOVERNING THE PRESENCE AND
ACTIVITIES OF INDIVIDUALS WORKING IN AND AROUND TRENCH EXCAVATION.
SCALE: 1" = 10'
INSTALL NEW 6" CONCRETE SIDEWALK TO MATCH WIDTH OF NEW STAIRS
& EXTEND TO EXIST. SIDEWALK & MATCH EX. SIDEWALK ELEVATION. SEE
DETAIL SHT. CP501 DETAIL #6
CONTRACTOR TO MATCH EXIST CURB AND GUTTER WITH POSITIVE
FLOW CONFIGURATION.
SAWCUT & REMOVE EXIST. ISLAND CURB, & INSTALL NEW CONCRETE
CURB & 6' WIDE 6" SIDEWALK. SEE DETAIL SHT. CP501 DETAILS #5 & 6
INSTALL 4' TALL, 6" Ø STEEL PIPE, CONCRETE FILLED BOLLARDS AT
4' SPACING. SEE DETAIL SHEET CP501 DETAIL #4.
INSTALL 3' LONG x 2' WIDE x 3' HIGH LIMESTONE BOULDERS AT ±3'
SPACING, ±1.0' OFF SIDEWALK. CONTRACTOR TO COORDINATE
WITH VA PROJECT ADMINISTRATOR FOR MATERIALS AND
SPECIFICS.
INSTALL HEADER CURB ALONG EXISTING PAVEMENT CORRIDOR.
SEE DETAIL SHEET CP501 DETAIL #8.
SEE ARCHITECTS PLANS FOR LOCATIONS OF NEW WINDOW ENCLOSURES.
(SHT. AE 201)
INSTALL NEW 6" CONCRETE SIDEWALK TO MATCH WIDTH OF NEW ADA
RAMP & EXTEND TO EXIST. SIDEWALK & MATCH EX. SIDEWALK
ELEVATION. SEE SHT. CG101.
SEE SHEET TF100 FOR INSTALLATION OF GATE SYSTEM.
ADA STRIPPING
CONCRETE
SOD
SEE ARCHITECTURAL
PLANS FOR CONTINUATION
INSTALL NEW SIDEWALK AT END
OF NEW STAIRS & ATTACH TO
EXIST. SIDEWALK. MATCH
ELEVATIONS. GRADE TO DRAIN
MATCH EXIST. FINISHED
FLOOR ELEVATION - 1360.31
EXIST. ASPHALT
TO REMAIN
RAMP DOWN
EXIST. SIDEWALK
R
AM
P D
O W
N
NOT A WALKWAY
NOT A WALKWAY
NOT A WALKWAY
SEE ARCHITECTURAL
PLANS FOR CONTINUATION
INSTALL NEW SIDEWALK AT END
OF NEW STAIRS & ATTACH TO
EXIST. SIDEWALK. MATCH
ELEVATIONS. GRADE TO DRAIN
MATCH EXIST. FINISHED
FLOOR ELEVATION - 1360.31
EXIST. ASPHALT
TO REMAIN
EXIST. CONCRETE
TO REMAIN
EXIST. CONCRETE
TO REMAIN
RAMP DOWN
EXIST. SIDEWALK
R
AM
P D
O W
N
NOT A WALKWAY
NOT A WALKWAY
NOT A WALKWAY
GRADING PLAN
NOTES:
1. ALL ITEMS ARE TO BE FURNISHED & INSTALLED BY CONTRACTOR. REFERENCE
CONSTRUCTION DETAILS SHEETS FOR ADDITIONAL INFORMATION.
2. CONTRACTOR SHALL FORM SIDEWALKS AND VERIFY SLOPES PRIOR TO POURING
CONCRETE. CONTRACTOR SHALL ENSURE THAT CROSS SLOPES ARE NO GREATER
THAN 2% ALONG THE ACCESSIBLE ROUTE AND RUNNING SLOPE IS NO GREATER THAN
5%, UNLESS THE RUNNING SLOPE MATCHES THE EXISTING STREET SLOPE. IF ANY
DISCREPANCY ARISES, CONTRACTOR SHALL CONTACT ENGINEER FOR SOLUTION.
3. LIMITS OF CONSTRUCTION ARE SHOWN ON THE EROSION & SEDIMENTATION CONTROL
PLAN(S).
CAUTION:
CONTRACTOR TO VERIFY ALL EXISTING UTILITIES VERTICALLY AND HORIZONTALLY PRIOR
TO CONSTRUCTION. CONTRACTOR TO NOTIFY THE ENGINEER IMMEDIATELY OF ANY
DISCREPANCIES.
THE ENGINEER ASSUMES NO RESPONSIBILITY FOR THE ACCURACY OF THE LOCATION OF
UNDERGROUND UTILITIES. THE CONTRACTOR SHALL BE RESPONSIBLE FOR AVOIDING ALL
EXISTING UTILITIES BY CALLING DIGTESS 811 FOR LOCATION OF ALL UTILITIES, AT LEAST 2
WORKING DAYS PRIOR TO BEGINNING CONSTRUCTION.
EASEMENT LINE
EXISTING CONTOUR ELEVATIONS
PROPOSED CONTOUR ELEVATIONS
BENCH MARK CHISELED SQ. ON SE COR.
LIGHT POLE SOUTH OF BLDG. 1 MAIN
ENTRANCE. (ELEV. = 1354.17')
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
A
CONSTRUCTION
DOCUMENTS
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
STAMP
MENDEZ NGINEERING
Registration # F-14070 12950 Country Parkway, Suite 120 San Antonio, Texas 78216 Office: 210-802-0808 www.MendezEngineering.com
E
RENOVATE FOR RELOCATION OF
ONCOLOGY, HEMATOLOGY, AND
DIALYSIS 1ST FLOOR
WICHITA, KS
589A7-19-401
Building 1
2020.05.15 DTC JRC
Gene Lavastida, Owner 866.226.8071 Norman, OK 73069 212 N Crawford Ave Prime Architects A/E:
Conrad Pierce General Engineer/COR
Date:Revisions:
Robert J. Dole VA Medical Center &
Regional Office Center Wichita, KS
5/15/2020
-1' - 6"
PROJECT
LIMITS
KEY MAP
N.T.S.
CG101
NOTES:
1. CONTRACTOR SHALL FIELD VERIFY ALL DIMENSIONS AND BENCHMARK ELEVATIONS
PRIOR TO BEGINNING CONSTRUCTION.
2. ALL WASTE MATERIAL SHALL BECOME THE PROPERTY OF THE CONTRACTOR AND IT
SHALL BE HIS SOLE RESPONSIBILITY TO DISPOSE OF THIS MATERIAL OFF THE LIMITS
OF THE SITE TO A STATE LICENSED LANDFILL. CONTRACTOR WILL BE REQUIRED TO
PROVIDE DOCUMENTATION WHERE DISPOSED MATERIAL IS TAKEN TO. THE OWNER
WILL NOT BE HELD LIABLE FOR WASTE MATERIAL.
3. CONTRACTOR IS REQUIRED TO SET AND VERIFY ALL PROJECT ELEVATIONS PRIOR TO
THE START OF CONSTRUCTION. "MATCH EXISTING" SHALL BE UNDERSTOOD TO
SIGNIFY THE SAME MATERIALS AS WELL AS VERTICAL AND HORIZONTAL ALIGNMENT.
4. GENERAL CONTRACTOR SHALL CHECK AND VERIFY ALL DIMENSIONS AND GRADE
CONDITIONS (BOTH NEW AND EXISTING). HE SHALL REPORT ANY DISCREPANCIES TO
THE ENGINEER AND PROJECT ARCHITECT BEFORE PROCEEDING WITH ANY PHASE OF
THE WORK AS HE WILL BE RESPONSIBLE FOR ALL WORK AS INTENDED BY THE
DRAWINGS AND SPECIFICATIONS.
5. CONTRACTOR AGREES THAT HE SHALL ASSUME SOLE RESPONSIBILITY FOR JOB SITE
CONDITIONS DURING THE CONSTRUCTION OF THE PROJECT, INCLUDING SAFETY OF
ALL PERSONS AND PROPERTY.
6. BARRICADES AND WARNING SIGNS SHALL CONFORM TO THE KANSAS MANUAL ON
UNIFORM TRAFFIC CONTROL DEVICES AND GENERALLY BE LOCATED TO AFFORD
MAXIMUM PROTECTION TO THE PUBLIC AS WELL AS CONSTRUCTION PERSONNEL AND
EQUIPMENT. TRAFFIC FLOW AND ACCESS TO SURROUNDING PROPERTIES SHALL BE
PERSEVERED AT ALL TIMES DURING CONSTRUCTION.
7. ANY EXISTING OFFSITE IMPROVEMENTS OR UTILITIES REMOVED, DAMAGED, OR
UNDERCUT BY CONTRACTOR'S OPERATIONS SHALL BE REPAIRED OR REPLACED AS
DIRECTED BY THE ENGINEER AND APPROVED BY THE PROJECT ARCHITECT AT THE
CONTRACTOR'S EXPENSE.
8. CONTRACTOR SHALL BE RESPONSIBLE FOR RESTORING TO ITS ORIGINAL OR BETTER
CONDITION ANY DAMAGE DONE TO EXISTING FENCES, CURBS, CONCRETE DRIVEWAYS,
SIDEWALK STRUCTURES, PAVEMENT, ETC, THAT ARE NOT INDICATED TO BE REMOVED.
AN INVENTORY OF EXISTING CONDITIONS SHALL BE CONDUCTED WITH CONTRACTOR
AND PROJECT ARCHITECT PRIOR TO CONSTRUCTION.
9. THE CONTRACTOR SHALL MAINTAIN CONTINUAL UTILITY SERVICES (GAS, TELEPHONE,
CABLE TELEVISION, ELECTRIC, WATER, SANITARY SEWER, STORM SEWER, ETC.) TO
ANY ADJACENT DEVELOPMENT. WHERE CONSTRUCTION IS IN THE PROXIMITY OF A
UTILITY, THE CONTRACTOR WILL TAKE PRECAUTION TO PROTECT AND/OR SUPPORT
THE UTILITY.
10. CONTRACTOR SHALL VERIFY ALL UNDERGROUND UTILITIES PRIOR TO CONSTRUCTION.
11. NOTIFY OWNER, HOMEOWNERS ASSOCIATION AND UTILITY PURVEYOR (IF APPLICABLE)
A MINIMUM OF 72 HOURS IN ADVANCE OF ANY UTILITY SHUTDOWN.
12. CONTRACTOR SHALL REFERENCE PAVEMENT MARKING / SIGNAGE / PARKING PLAN
SHEETS, IF ANY, FOR ADDITIONAL INFORMATION.
13. MATCH GRADE AT PROPERTY LINE UNLESS OTHERWISE NOTED.
14. ACHIEVE GRADE CHANGES WITH SMOOTH TRANSITIONS.
15. FINAL PAVING SURFACES TO BE FLOOD TESTED OR OBSERVED DURING RAINFALL. ANY
PONDING AREAS TO BE CORRECTED / ELIMINATED.
16. SURFACE DRAINAGE AND UTILITY FEATURES SHOWN ARE FOR REFERENCE ONLY. THE
LOCATIONS AND DEPTHS OF EXISTING UTILITIES, INCLUDING SERVICE LATERALS AND
DRAINAGE STRUCTURES SHOWN ON PLANS ARE APPROXIMATE ONLY. THE
CONTRACTOR SHALL VERIFY THE EXACT LOCATION AND DEPTHS OF UNDERGROUND
UTILITIES AT LEAST 48 HOURS PRIOR TO CONSTRUCTION WHETHER SHOWN ON PLANS
OR NOT, AND PROJECT THE SAME DURING CONSTRUCTION.
17. CONTRACTOR TO EXERCISE EXTREME CAUTION WHEN WORKING UNDER / AND / OR
AROUND OVERHEAD ELECTRIC LINES. CONTRACTOR SHALL COORDINATE WITH LOCAL
ELECTRIC / UTILITY COMPANY TO ESTABLISH THE MAXIMUM WORKING HEIGHT FROM
GROUND ELEVATION.
18. GUTTER (G) ELEVATIONS SHOWN TO BE FOLLOWED AS SHOWN ON PLAN.
19. TYPICAL 6" CURB TO BE CONSTRUCTED BASED ON GUTTER ELEVATION SHOWN,
UNLESS OTHERWISE NOTED ON THIS PLAN OR ON THE SITE DIMENSIONAL CONTROL
PLAN.
TRENCH EXCAVATION SAFETY PROTECTION:
CONTRACTOR AND/OR CONTRACTOR'S INDEPENDENTLY RETAINED EMPLOYEE OR
STRUCTURAL DESIGN/GEOTECHNICAL/SAFETY/EQUIPMENT CONSULTANT, IF ANY, SHALL
REVIEW THESE PLANS, AVAILABLE GEOTECHNICAL INFORMATION, AND THE ANTICIPATED
INSTALLATION SITE(S) WITHIN THE PROJECT WORK AREA IN ORDER TO IMPLEMENT
CONTRACTOR'S TRENCH EXCAVATION SAFETY PROTECTION SYSTEMS, PROGRAMS AND/OR
PROCEDURES. THE CONTRACTOR'S IMPLEMENTATION OF THE SYSTEMS, PROGRAMS
AND/OR PROCEDURES SHALL PROVIDE FOR ADEQUATE TRENCH EXCAVATION SAFETY
PROTECTION THAT COMPLIES WITH, AS A MINIMUM, OSHA STANDARDS FOR TRENCH
EXCAVATIONS. SPECIFICALLY, CONTRACTOR AND/OR CONTRACTOR'S INDEPENDENTLY
RETAINED EMPLOYEE OF SAFETY CONSULTANT SHALL IMPLEMENT A TRENCH SAFETY
PROGRAM IN ACCORDANCE WITH OSHA STANDARDS GOVERNING THE PRESENCE AND
ACTIVITIES OF INDIVIDUALS WORKING IN AND AROUND TRENCH EXCAVATION.
SCALE: 1" = 10'
LEGEND
PUBLIC
CORRIDOR
LOBBY
VESTIBULE RAMP DOWN
EXIST.
BLDG.
EXIST.
BLDG.
EXIST.
BLDG.
ACCESSIBLE
VESTIBULE
EXIST. SIDEWALK
ELEVATOR
R
AM
P D
O W
N
NOT A WALKWAY
NOT A WALKWAY
NOT A WALKWAY
PUBLIC
CORRIDOR
LOBBY
VESTIBULE RAMP DOWN
EXIST.
BLDG.
EXIST.
BLDG.
EXIST.
BLDG.
ACCESSIBLE
VESTIBULE
EXIST. SIDEWALK
ELEVATOR
R
AM
P D
O W
N
NOT A WALKWAY
NOT A WALKWAY
NOT A WALKWAY
EXIST. CONCRETE
TO REMAIN
EXIST. CONCRETE
TO REMAIN
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
A
CONSTRUCTION
DOCUMENTS
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
STAMP
MENDEZ NGINEERING
Registration # F-14070 12950 Country Parkway, Suite 120 San Antonio, Texas 78216 Office: 210-802-0808 www.MendezEngineering.com
E
RENOVATE FOR RELOCATION OF
ONCOLOGY, HEMATOLOGY, AND
DIALYSIS 1ST FLOOR
WICHITA, KS
589A7-19-401
Building 1
2020.05.15 DTC JRC
Gene Lavastida, Owner 866.226.8071 Norman, OK 73069 212 N Crawford Ave Prime Architects A/E:
Conrad Pierce General Engineer/COR
Date:Revisions:
Robert J. Dole VA Medical Center &
Regional Office Center Wichita, KS
5/15/2020
-1' - 6"
PROJECT
LIMITS
KEY MAP
N.T.S.
PAVING PLAN
PAVEMENT LEGEND
CP101
SCALE: 1" = 10'
LEGEND
1 1
NOTES:
STEEL POSTS WHICH SUPPORT THE SILT FENCE SHALL BE INSTALLED ON A SLIGHT ANGLE
TOWARD THE ANTICIPATED RUNOFF SOURCE. POST MUST BE EMBEDDED A MINIMUM OF
ONE FOOT.
THE TOE OF THE SILT FENCE SHALL BE TRENCHED IN WITH A SPADE OR MECHANICAL TRENCHER, SO THAT THE DOWNSLOPE FACE OF THE TRENCH IS FLAT AND PERPENDICULAR TO THE LINE OF FLOW.
WHERE FENCE CAN NOT BE TREATED (E.G. PAVEMENT) WEIGHT FABRIC FLAP WITH WASHED GRAVEL
ON UPHILL SIDE TO PREVENT FLOW UNDER FENCE.
THE TRENCH MUST BE A MINIMUM OF 6 INCHES DEEP AND 6 INCHES WIDE TO ALLOW FOR THE SILT
FENCE FABRIC TO BE LAID IN THE GROUND AND BACKFILLED WITH COMPACTED MATERIAL.
SILT FENCE SHOULD BE SECURELY FASTENED TO EACH STEEL SUPPORT POST OR TO WOVEN WIRE, WHICH IS IN TURN ATTACHED TO THE STEEL FENCE POST.
INSPECTION SHALL BE MADE WEEKLY OR AFTER EACH RAINFALL EVENT AND REPAIR OR
REPLACEMENT SHALL BE MADE PROMPTLY AS NEEDED.
SILT FENCE SHALL BE REMOVED WHEN THE SITE IS COMPLETELY STABILIZED SO AS NOT TO BLOCK
OR IMPEDE STORM FLOW OR DRAINAGE.
ACCUMULATED SILT SHALL BE REMOVED WHEN IT REACHES A DEPTH OF 6 INCHES. THE SILT SHALL
BE DISPOSED OF IN AN APPROVED SITE AND IN SUCH A MANNER AS TO NOT CONTRIBUTE TO
ADDITIONAL SILTATION.
CONTRACTOR SHALL PROVIDE TRIANGULAR SEDIMENT FILTER DIKE PER DETAIL ON THIS SHEET
WHERE SILT FENCE IS REQUIRED BUT NOT INSTALLABLE.
1.
2.
3.
4.
5.
6.
7.
8.
1. DIKES SHALL BE PLACED IN A ROW WITH ENDS
TIGHTLY ABUTTING THE ADJACENT DIKE.
2. THE FABRIC COVER AND SKIRT SHALL BE A
CONTINUOUS WRAPPING OF GEOTEXTILE. THE SKIRT
SHALL BE A CONTINUOUS EXTENSION OF THE FABRIC ON
THE UPSTREAM FACE.
3. THE SKIRT SHALL BE WEIGHTED WITH A
CONTINUOUS LAYER OF 3"-5" OPEN GRADED ROCK, OR
TOED-IN 6" WITH MECHANICALLY COMPACTED MATERIAL.
OTHERWISE, THE ENTIRE STRUCTURE SHALL BE
TRENCHED IN 4 INCHES.
4. DIKES AND SKIRT SHALL BE SECURELY ANCHORED
IN PLACE USING 6 INCH WIRE STAPLES ON 2 FOOT
CENTERS ON BOTH EDGES AND SKIRT, OR STAKED USING
3/8 INCH DIAMETER REBAR WITH TEE ENDS.
5. FILTER MATERIAL SHALL BE LAPPED OVER ENDS 6
INCHES TO COVER DIKE TO DIKE JOINTS. JOINTS
SHALL BE FASTENED WITH GALVANIZED SHOAT RINGS.
6. THE DIKE STRUCTURE SHALL BE 6 GA. 6" X 6" WIRE
MESH, 18 INCHES ON A SIDE.
7. INSPECTION SHALL BE MADE WEEKLY OR AFTER
EACH RAINFALL EVENT AND REPAIR OR
REPLACEMENT SHALL BE MADE PROMPTLY AS NEEDED
BY THE CONTRACTOR.
8. ACCUMULATED SILT SHALL BE REMOVED WHEN IT
REACHES A DEPTH OF SIX INCHES, AND DISPOSED
OF IN A MANNER WHICH WILL NOT CAUSE ADDITIONAL
SILTATION.
9. AFTER THE DEVELOPMENT SITE IS COMPLETELY
STABILIZED, THE DIKES AND ANY REMAINING SILT
SHALL BE REMOVED. SILT SHALL BE DISPOSED OF AS
INDICATED IN NOTE 8 ABOVE.
NOTES:
NOTE
LEVEL II B TREE PROTECTION
ELEVATION NOT TO SCALE
8" MULCH UNDER DRIP LINE AS
4"
2X4
4'
TREE
TRUNK
CURB
5'
ROOT PROTECTION
ZONE (RPZ)
PROPERTY LINE
ESTABLISH FENCE PROTECTION
MINIMUM 5' FROM TRUNK
DRIP LINE
8" MULCH OUTSIDE RPZ
AND UNDER DRIP LINE AS
MINIMAL PROTECTION FOR ROOTS
FROM CONSTRUCTION ACTIVITIES
6" MULCH INSIDE RPZ
IF BARE DIRT
LEVEL II A TREE PROTECTION
ELEVATION
ROOT PROTECTION
ZONE
(RPZ)
NOT TO SCALE
STR
EET
WRAP TREE TRUNK WITH 2"X4" STUDS AND ROPE OR
BAND IN PLACE AS NEEDED TO PROTECT TREES IN WORK
AREAS.
MINIMAL PROTECTION FOR ROOTS
FROM CONSTRUCTION ACTIVITIESNOTE
1. OPTION USED FOR TIGHT CONSTRUCTION
AREAS OR WHEN CONSTRUCTION OCCURS IN
ROOT PROTECTION ZONE.
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
A
CONSTRUCTION
DOCUMENTS
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
STAMP
MENDEZ NGINEERING
Registration # F-14070 12950 Country Parkway, Suite 120 San Antonio, Texas 78216 Office: 210-802-0808 www.MendezEngineering.com
E
RENOVATE FOR RELOCATION OF
ONCOLOGY, HEMATOLOGY, AND
DIALYSIS 1ST FLOOR
WICHITA, KS
589A7-19-401
Building 1
2020.05.15 DTC JRC
Gene Lavastida, Owner 866.226.8071 Norman, OK 73069 212 N Crawford Ave Prime Architects A/E:
Conrad Pierce General Engineer/COR
Date:Revisions:
Robert J. Dole VA Medical Center &
Regional Office Center Wichita, KS
5/15/2020
N.T.S.
SITE DETAILS
CP501
NO SEAL
REQUIRED
GENERAL NOTES
DESIGN PARAMETERS
1. BUILDING CODE: 2015 INTERNATIONAL BUILDING CODE
2. DEAD LOADS:
A. ROOF-------------------------------------------------------------------------------------------------- 20 PSF
3. LIVE LOADS:
A. ROOF-------------------------------------------------------------------------------------------------- 20 PSF (UNIFORM)
4. SNOW LOADS:
A. GROUND SNOW LOAD, Pg---------------------------------------------------------------------- 15 PSF B. IMPORTANCE FACTOR, I------------------------------------------------------------------------ 1.25
5. WIND LOADS:
A. BASIC WIND SPEED (3 SECOND GUST)---------------------------------------------------- 120 MPH B. RISK CATEGORY----------------------------------------------------------------------------------- IV C. EXPOSURE CLASSIFICATION------------------------------------------------------------------ C D. INTERNAL PRESSURE COEFFICIENT------------------------------------------------------- +/-0.18 E. BASIC WIND PRESSURE (qh,UNFACTORED)--------------------------------------------- 26.6 PSF
F. DESIGN WIND PRESSURE ON EXTERIOR WALLS (C&C LOAD BASED ON 100 SQ.FT AREA)
• END ZONES, (10'-0")------------------------------------------------------------------------ 26.1 PSF
• INTERIOR ZONES--------------------------------------------------------------------------- 26.1 PSF
G. DESIGN UPLIFT PRESSURE ON ROOFS (C&C LOAD BASED ON 100 SQ.FT AREA)
• CORNER ZONES, (10'-0")------------------------------------------------------------------ 58.0 PSF
• EDGE ZONES, (10'-0")---------------------------------------------------------------------- 36.7 PSF
• INTERIOR ZONES---------------------------------------------------------------------------- 26.1 PSF
6. SEISMIC LOADS:
A. SPECTRAL RESPONSE ACCELERATION(SHORT PERIOD), Ss--------------------- 0.109
B. SPECTRAL RESPONSE ACCELERATION;(1-SEC. PERIOD), S1--------------------- 0.054
C. SPECTRAL RESPONSE COEFFICIENT;(SHORT PERIOD), Sds---------------------- 0.116 D. SPECTRAL RESPONSE COEFFICIENT;(1-SEC. PERIOD), Sd1---------------------- 0.087 E. SITE CLASS------------------------------------------------------------------------------------------- D F. IMPORTANCE FACTOR, I ------------------------------------------------------------------------ 1.5 G. SEISMIC DESIGN CATEGORY ----------------------------------------------------------------- C H. BASIC STRUCTURAL SYSTEM AND SEISMIC RESISTING SYSTEM-------------- STEEL SYSTEMS NOT SPECIFICALLY DETAILED FOR SEISMIC RESISTANCE I. RESPONSE MODIFICATION FACTOR, R -------------------------------------------------- 3 J. SYSTEM OVER-STRENGTH FACTOR, W -------------------------------------------------- 3 K. DEFLECTION AMPLIFICATION FACTOR, Cd --------------------------------------------- 3 L. ANALYSIS PROCEDURE --------------------------------------------------------------------------EQUIVALENT LATERAL FORCE
7. FOUNDATIONS:
ISOLATED AND CONTINUOUS FOUNDATIONS HAVE BEEN DESIGN FOR AN ASSUMED ALLOWABLE NET BEARING PRESSURE OF 1500 PSF. THE OWNER AND/OR CONTRACTOR IS RESPONSIBLE FOR VERIFYING THESE ASSUMPTIONS WITH ACTUAL CONDITIONS PRIOR TO CONSTRUCTION OR BUILD AT THEIR OWN RISK. ACHIEVING AN ALLOWABLE BEARING PRESSURE DOES NOT PRECLUDE THE BUILDING FROM BEING SUBJECT TO DIFFERENTIAL MOVEMENT. SHOULD THE OWNER BE CONCERNED, THEY SHALL ENGAGE THE SERVICES OF A LICENSED GEOTECHNICAL ENGINEER TO INVESTIGATE
AND PROVIDE RECOMMENDATIONS.
GENERAL
1. STRUCTURAL DRAWINGS ARE NOT STAND-ALONE DOCUMENTS AND ARE INTENDED TO BE USED IN CONJUNCTION WITH CIVIL, ARCHITECTURAL, MECHANICAL, ELECTRICAL, AND DRAWINGS FROM OTHER DISCIPLINES. THE CONTRACTOR SHALL COORDINATE ALL REQUIREMENTS OF THE CONTRACT
DOCUMENTS INTO THE SHOP DRAWINGS AND FIELD WORK.
2. WHERE CONFLICT EXISTS AMONG VARIOUS PARTS OF THE STRUCTURAL CONTRACT DOCUMENTS, STRUCTURAL DRAWINGS, GENERAL NOTES, AND SPECIFICATIONS, THE STRICTEST REQUIREMENTS, AS INDICATED BY THE ENGINEER, SHALL GOVERN.
3. WHERE MEMBER LOCATIONS ARE NOT SPECIFICALLY DIMENSIONED, THE FOLLOWING RULES SHALL APPLY:
A. COLUMNS ARE CENTERED ON GRID LINES.
B. FOOTINGS ARE CENTERED BENEATH COLUMNS.
C. CONTINUOUS FOOTINGS ARE CENTERED BENEATH WALLS.
D. FRAMING MEMBERS ARE EITHER LOCATED ON GRID LINES OR ARE EQUALLY SPACED BETWEEN LOCATED MEMBERS.
4. ALL STRUCTURAL ELEMENTS OF THE PROJECT HAVE BEEN DESIGNED BY THE STRUCTURAL ENGINEER TO RESIST THE REQUIRED CODE VERTICAL AND LATERAL FORCES THAT COULD OCCUR IN THE FINAL COMPLETED STRUCTURE ONLY. IT IS THE RESPONSIBILITY OF THE CONTRACTOR TO PROVIDE ALL REQUIRED BRACING DURING CONSTRUCTION TO MAINTAIN THE STABILITY AND SAFETY OF ALL STRUCTURAL ELEMENTS DURING THE CONSTRUCTION PROCESS UNTIL THE LATERAL LOAD RESISTING OR STABILITY-PROVIDING SYSTEM IS COMPLETELY INSTALLED AND THE STRUCTURE IS COMPLETELY
TIED TOGETHER.
5. THE STRUCTURE HAS BEEN DESIGNED FOR THE LOADS IDENTIFIED WITHIN THESE STRUCTURAL DRAWINGS THAT ARE ANTICIPATED TO BE APPLIED TO THE FINAL STRUCTURE ONCE COMPLETED AND OCCUPIED. THE CONTRACTOR SHALL NOT OVERLOAD THE STRUCTURE DURING CONSTRUCTION. THE CONTRACTOR SHALL BE RESPONSIBLE FOR CHECKING THE ADEQUACY OF THE STRUCTURE TO SUPPORT ANY APPLIED CONSTRUCTION LOADS, INCLUDING THOSE DUE TO CONSTRUCTION VEHICLES OR EQUIPMENT, MATERIAL HANDLING OR STORAGE, SHORING AND RESHORING, OR ANY OTHER PROPOSED CONSTRUCTION LOADS THAT ARE IN EXCESS OF THE STATED DESIGN LOADS. THE STRUCTURAL ENGINEER IS NOT RESPONSIBLE TO DESIGN OR CHECK THE STRUCTURE FOR LOADS APPLIED TO THE STRUCTURE FOR ANY CONSTRUCTION ACTIVITY.
6. WEIGHTS OF MECHANICAL EQUIPMENT SHOWN ON THE STRUCTURAL PLANS ARE FOR UNITS SPECIFIED BY THE MECHANICAL ENGINEER. CONTRACTOR SHALL VERIFY THE WEIGHTS. ANY SUBSTITUTIONS THAT RESULT IN INCREASED WEIGHT SHALL BE APPROVED BY THE STRUCTURAL ENGINEER OF
RECORD.
7. THE SIZE AND LOCATION OF EQUIPMENT PADS AND PENETRATIONS THROUGH THE STRUCTURE FOR MECHANICAL, ELECTRICAL, AND PLUMBING WORK SHALL BE VERIFIED BY THE CONTRACTOR. OPENINGS AND PENETRATIONS NOT SPECIFICALLY SHOWN ON THE STRUCTURAL DRAWINGS SHALL BE
SUBJECT TO APPROVAL BY THE STRUCTURAL ENGINEER OF RECORD.
8. PRIOR TO FABRICATION AND/OR ERECTION OF ANY MATERIALS, THE CONTRACTOR SHALL FIELD VERIFY ALL PERTINENT EXISTING DIMENSIONS, ELEVATIONS, AND CONDITIONS AND SHALL REPORT ANY DISCREPANCIES TO THE STRUCTURAL ENGINEER OF RECORD OR THE ARCHITECT
IMMEDIATELY UPON DISCOVERY.
9. BACKFILL BOTH SIDES OF ALL FOUNDATION AND RETAINING WALLS EQUALLY UNTIL LOW SIDE IS UP TO FINISH GRADE. DO NOT BACKFILL ANY WALLS
UNTIL CONCRETE HAS REACHED ITS SPECIFIED 28-DAY COMPRESSIVE STRENGTH.
10. CONNECTIONS OF SYSTEMS DESIGNED BY THE CONTRACTOR’S ENGINEER SUCH AS, BUT NOT LIMITED TO, CLADDING, STAIRS, ELEVATORS AND MEP LOADS ARE ASSUMED TO IMPOSE VERTICAL AND/OR HORIZONTAL LOADS ON THE BASE BUILDING STRUCTURAL MEMBERS WITHOUT GENERATING TORSION IN THE SUPPORTING STRUCTURAL MEMBERS. CONTRACTOR IS RESPONSIBLE FOR FURNISHING AND INSTALLING ALL SUPPLEMENTARY
BRACING MEMBERS AS REQUIRED TO PREVENT TORSION ON THE BASE BUILDING STRUCTURE.
11. ANY MATERIALS OR PRODUCTS SUBMITTED FOR APPROVAL THAT ARE DIFFERENT FROM THE MATERIAL OR PRODUCTS SPECIFIED IN THE STRUCTURAL CONTRACT DOCUMENTS WILL BE APPROVED ONLY IF THE FOLLOWING CRITERIA ARE SATISFIED:
A. A COST SAVINGS TO THE OWNER IS DOCUMENTED AND SUBMITTED WITH THE REQUEST.
B. THE MATERIAL OR PRODUCT HAS BEEN APPROVED BY THE INTERNATIONAL CODE COUNCIL (ICC) AND THE ICC REPORT IS SUBMITTED WITH
THE REQUEST.
12. THE ENGINEER SHALL NOT HAVE CONTROL NOR CHARGE OF, AND SHALL NOT BE RESPONSIBLE FOR, CONSTRUCTION MEANS, METHODS, TECHNIQUES, SEQUENCES, OR PROCEDURES, FOR SAFETY PRECAUTIONS AND PROGRAMS IN CONNECTION WITH THE WORK, FOR THE ACTS OR OMISSION OF THE CONTRACTOR, SUBCONTRACTOR, OR ANY OTHER PERSONS PERFORMING ANY OF THE WORK, OR FOR THE FAILURE OF ANY OF THEM TO CARRY OUT
THE WORK IN ACCORDANCE WITH THE CONTRACT DOCUMENTS.
13. PERIODIC SITE OBSERVATION BY FIELD REPRESENTATIVES OF 360 ENGINEERING GROUP, PLLC. IS SOLELY FOR THE PURPOSE OF BECOMING GENERALLY FAMILIAR WITH THE PROGRESS AND QUALITY OF THE WORK COMPLETED AND DETERMINING, IN GENERAL, IF THE WORK OBSERVED IS BEING PERFORMED IN A MANNER INDICATING THAT THE WORK, WHEN FULLY COMPLETED, WILL BE IN ACCORDANCE WITH THE STRUCTURAL CONTRACT DOCUMENTS. THIS LIMITED SITE OBSERVATION SHOULD NOT BE CONSTRUED AS AN EXHAUSTIVE OR CONTINUOUS CHECK OF THE QUALITY OR QUANTITY OF THE WORK, BUT RATHER PERIODIC IN AN EFFORT TO GUARD THE OWNER AGAINST DEFECTS OR DEFICIENCIES IN THE WORK OF THE
CONTRACTOR.
DIVISION 2 - FOUNDATIONS
1. RECOMMENDATIONS CONTAINED IN "GEOTECHNICAL ENGINEERING REPORT ROBERT J. DOLE VA MEDICAL CENTER PAVEMENT INPROVEMENTS 5400 DELLOGG AVENE WICHITA, ANSAS", PROJECT NUMBER G19G1266 BY MENDEX ENGINEERING, PLLC DATED DECEMBER 6, 2019 WERE USE FOR FILL DESIGN. REFER TO DESIGN PARAMETERS FOR SOIL DESIGN CRITERIA BASED ON THESE RECOMMENDATIONS.
2. THE GENERAL CONTRACTOR SHALL BE RESPONSIBLE FOR REVIEWING THE GEOTECHNICAL REPORT AND SHALL FOLLOW THE RECOMMENDATIONS SPECIFIED THEREIN, INCLUDING, BUT NOT LIMITED TO, SUBGRADE PREPARATIONS, GROUND WATER MANAGEMENT AND
STEEP SLOPE BEST MANAGEMENT PRACTICES.
3. THE GEOTECHNICAL ENGINEER SHALL BE PRESENT DURING PROOF ROLLING AND SHALL INSPECT THE SUBGRADE PRIOR TO ANY FILL OPERATIONS. ALL COMPACTED FILL SHALL BE CONTINUOUSLY INSPECTED BY THE OWNER'S SELECTED INDEPENDENT TESTING
LABORATORY.
4. FOOTINGS SHALL BEAR EITHER ON COMPETENT NATIVE SOIL OR COMPACTED STRUCTURAL FILL AS PER THE GEOTECHNICAL REPORT.
EXTERIOR PERIMETER FOOTINGS SHALL BEAR NOT LESS THAN 24 INCHES BELOW FINISH GRADE UNLESS OTHERWISE SPECIFIED BY THE GEOTECHNICAL ENGINEER AND/OR BUILDING OFFICIAL. IF THE SOIL AT THE BEARING ELEVATIONS SHOWN IS OF QUESTIONABLE BEARING VALUE, THE STRUCTURAL ENGINEER OF RECORD OR ARCHITECT SHALL BE NOTIFIED IMMEDIATELY.
5. ALL FILL MATERIAL UNDER THE STRUCTURE SHALL COMPLY WITH REQUIREMENTS STATED IN THE GEOTECHNICAL REPORT, UNO.
6. PROVIDE A MINIMUM OF A 4-INCH CLEAN, FREE-DRAINING GRANULAR SUBBASE FILL BELOW ALL INTERIOR SLABS-ON-GRADE UNLESS NOTED
OR DETAILED OTHERWISE. SUBBASE SHALL MEET GRADATION REQUIREMENTS OF ASTM C-33 SIZE NO. 67, UNLESS SPECIFICALLY NOTED
OTHERWISE.
7. A POLYETHYLENE FILM VAPOR RETARDER, MEETING THE REQUIREMENTS IN THE SPECIFICATIONS, SHALL BE PLACED BELOW ALL INTERIOR
SLABS-ON-GRADE PER THE FOUNDATION PLAN NOTES.
8. THE CONTRACTOR IS CAUTIONED AGAINST LOADING SLAB-ON-GRADE WITH CONSTRUCTION EQUIPMENT. THE SLAB HAS NOT BEEN DESIGNED FOR CONSTRUCTION EQUIPMENT AND MAY REQUIRE AN INCREASE IN SLAB THICKNESS AND/OR REINFORCEMENT. IF THE CONSTRUCTION LOADING EXCEEDS THE DESIGN LOADS SHOWN IN THE DESIGN CRITERIA, THE CONTRACTOR IS REQUIRED TO SUBMIT CALCULATIONS SIGNED AND SEALED BY A REGISTERED STRUCTURAL, CIVIL, OR GEOTECHNICAL ENGINEER IN THE STATE WHERE THE PROJECT IS LOCATED
VERIFYING THE ADEQUACY OF THE SLAB.
9. EXTERIOR FOOTINGS FOR STAIRS AND RAMPS…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .