ATTACHMENT_8_-_ADDENDUM_2.pdf

PDF 3 MB Posted

Attached to
Clinical Expansion for Mental Health and Sleep Lab - San Fancisco
Solicitation number
36E77619R0005
Issued by

About this file

36E77619R0005 ATTACHMENT 8 - ADDENDUM 2.pdf

View the file

Other files

File Type Posted
36E77619R0005-0003001.pdf PDF
36E77619R0005-0003002.pdf PDF
36E77619R0005-0003000.docx DOCX document
36E77619R0005-0002003.docx DOCX document
36E77619R0005-0002001.pdf PDF
36E77619R0005-0002002.docx DOCX document
36E77619R0005-0002004.pdf PDF
36E77619R0005-0002000.docx DOCX document
ATTACHMENT_11_-_CONTRACTOR_SAFETY_AND_ENVIRONMENTAL_RECORD_EVALUATION_FORM.docx DOCX document
Geotech_Report.pdf PDF
Technical_Questions_Tracking_Spreadsheet_-_SF_Mental_Health_-_01-16-2019.pdf PDF
Door_Schedule.pdf PDF
36E77619R0005_0001.docx DOCX document
Site_Visit_Sign_In_Sheet_-_San_Fran_Mental_Health_-_01-16-2019.pdf PDF
ATTACHMENT_9_-_CONSTRUCTION_WAGE_RATES_-_SAN_FRANCISCO_-_01-04-2019.pdf PDF
ATTACHMENT_3_-_FINAL_DRAWINGS_B24_-_ELECTRICAL.pdf PDF
36E77619R0005_1.docx DOCX document
ATTACHMENT_5_-_FINAL_DRAWINGS_B24_-_STRUCTURAL.pdf PDF
ATTACHMENT_10_-_J_A_BRAND_NAME_ITEM.pdf PDF
ATTACHMENT_11_-_PAST_PERFORMANCE_QUESTIONNAIRE.docx DOCX document
ATTACHMENT_1_-_FINAL_DRAWINGS_B24_-_ARCHITECTURAL_-_08-17-2018.pdf PDF
ATTACHMENT_2_-_FINAL_DRAWINGS_B24_-_CIVIL_-_V2_-__08-17-2018.pdf PDF
ATTACHMENT_9_-_CONSTRUCTION_WAGE_RATES_-_SAN_FRANCISCO_-_12-07-2018.pdf PDF
ATTACHMENT_6_-_FINAL_SPECIFICATIONS_B24_-_VOLUME_1_-_10-31-2018.pdf PDF
ATTACHMENT_7_-_FINAL_SPECIFICATIONS_B24_-_VOLUME_2_-_02-10-_2017.pdf PDF
ATTACHMENT_4_-_FINAL_DRAWINGS_B24_-_MECHANICAL-PLUMBING.pdf PDF
36E77619R0005-000.docx DOCX document
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Addendum 2

Drawing sheets A‐2.1, A‐2.12, A‐ 2.21, A‐8.31, A‐8.36, M0.2, M‐2.2, M‐3.2, EL‐102 &

EP‐102

Demolition of Building 20: Contractor is responsible for complete demolition and removal of Building 20

(Sheet C‐2.0, 1A) to include; all footings/structures below grade, all abandoned utility piping within footprint, disconnection of electrical utility to the building. Area of work and temporary construction fence shall encompass Entire Building 20 and work shall comply with specifications. Contractor shall compact site to be flat and graded with gravel to be flush with existing asphalt. Provide new 6’ high chain link fence per detail G/C‐8.0 No reduction of work otherwise included on these referenced sheets or elsewhere in the contract documents shall be implied by this Addendum.

Construct Office and Floor Finish: The contractor shall upgrade interior finishes as detailed in this

Addendum 2 using applicable details in the construction drawings and specifications to complete the work. Contractor shall build out between gridlines 8‐12, A‐G as shown on the on the following pages to construct rooms 201,202, 204, 205, 206, 207 & 200 where open space was shown on original referenced pages. This new work also includes the associated mechanical and electrical required for a functional office space. No reduction of work otherwise included on these referenced sheets or elsewhere in the contract documents shall be implied by this Addendum 2. Utilize this Finish Schedule and Finish

Selection throughout the building to replace the respective selection in A‐8.36. Other elements to remain as indicated unless otherwise noted. New rooms (200‐207) to match selections for “open area”:

F1 ‐ CENTIVA‐ LVT

EE0795‐C

COLOR: ORE 6" WIDE PLANKS

SURFACE: QU

EDGE: SE

LOCATION: PRIMARY CORRIDORS UNLESS OTHERWISE NOTED

F2 ‐ MANNINGTON ‐HETEROGENEOUS SHEET VINYL

PARADIGM COLLECTION

PATTERN: STREAMLINE

COLOR: MODEL

INSTALL WITH INTERGRAL COVE BASE PER 12/A‐9.81

F3 ‐ PATCRAFT BUTTERFLY EFFECT

STYLE: FLUTTER MODULAR 10349

COLOR: GRAY PANSY – Contractor to obtain final approval through VA

F4 ‐ USG TRUE WOOD PANELS OR SIMILAR

LOCATION: 2ND FLOOR CONFERENCE ROOM

F5 ‐ CERAMIC OR PORCELAIN TILE

INSTALL 48' HIGH ON WET WALLS

DESIGN IDEA‐ DAL TILE VERANDA SOLIDS AND TONES

LOCATION: RESTROOMS

F6 ‐ FLORAZZO GEM S'MORES

LOCATION: LOBBY AND ELEVATOR FLOORS

F7 ‐ RUBBER FLOORING ‐ COLOR THAT COMPLEMENTS LVT

LOCATION: STAIRWELLS

Room Number

Room Name Floor (Should Be)

Approximate

SF

101 Entry Lobby F6

102 Reception F6

103 Admin Cubicles F3

103A Admin Office/MSA F3

104 Interview Room F3

106 Exam Room F3

107 Machine/Room F8

108 Mental Health Exam Room F3

109 Group Room F3

110 Mental Health Exam Room F3

110B Mental Health Exam Room F3

111 Mental Health Exam Room F3

111A Secondary Entrance F3

112 Mental Health Exam Room F3

112B Mental Health Exam Room F3

113 Mental Health Exam Room F3

114 Mental Health Exam Room F3

115 Mental Health Exam Room F3

116 Women’s Toilet F5

117 Mental Health Exam Room F3

117A Mental Health Exam Room F3

118 Men’s Toilet F5

119 Mental Health Exam Room F3

119A Mental Health Exam Room F3

120 Electrical Room F8

122 Janitors Room F8

200 Open Area/Conference Room F6 183

201 Admin Office/MSA F3 90

202 Admin Office/MSA F3 90

203 Unisex Toilet F5

204 Admin Office/MSA F3 81

205 Admin Office/MSA F3 81

206 Admin Office/MSA F3 100

207 Admin Office/MSA F3 70

208 Admin Cubicles F3

209 Admin Cubicles F3

210 Mask‐Fit/Storage Consult Room F2

211 Sleep Studies Room F2

211A Bariatric Bathroom F5

212 Sleep Lab Control F2

212A Equipment Storage F2

213 Sleep Studies Room F2

213A Bariatric Bathroom F5

214 Alcove F1

215 Sleep Studies Room F2

215A Bariatric Bathroom F5

216 Clean Utility F2

217 Sleep Studies Room F2

217A Bariatric Bathroom F5

218 Trash/Linen F2

219 Exam Room F2

220 IT/Elec Closet F8

222 Janitors Closet F8

224 Exam Room F2

300 Penthouse/Boiler Room F8

Stairs 1 Stair F7

Stairs 2 Stair F7

Corridors Corridors (Level 1) C1+C2 F1

Corridors Corridors (Level 2) C1+C2 F1

Corridors Corridors 3 L1 F1

Corridors Corridors 3 L2 F1 245