Z1AZ--IFB (FY-23) | GERALD B. H. SOLOMON SARATOGA NC | IRRIGATION SYSTEM UPGRADES | PROJECT NO. 917-MM23-01 (MM)
Solicitation number
36C78623B0005
Issued by

About this file

This document provides an amendment to an invitation for bid for irrigation system upgrades at the Gerald B.H. Solomon Saratoga National Cemetery. The amendment notifies bidders of the applicability of VAAR Clause 852.236-92 regarding additive or deductive bid line items. The related federal contract opportunity is an invitation for bid to provide irrigation system upgrades at the Gerald B.H. Solomon Saratoga National Cemetery in Schuylerville, New York. The project number is 917-MM23-01. Bidders are to provide all labor, materials, equipment, and supervision to complete the work described in the statement of work, specifications and drawings. No further details are provided on response dates, pricing terms, or other bid requirements.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE

7.

ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER

3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF

PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO.

1. CONTRACT ID CODE

FACILITY CODE

CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE

OF YOUR

ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office.

is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO:

Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERE

D CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES

SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendmen t, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED

STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER

16A. NAME AND TITLE OF

CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30

PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF

SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer) A0001 01-25-2323

917-MM23-01

36C786 Department of Veterans Affairs National Cemetery Administration Contracting Services 18434 Joplin Road Triangle VA 22172 36C786 Department of Veterans Affairs National Cemetery Administration Contracting Services 18434 Joplin Road Triangle VA 22172 To all Offerors/Bidders

36C78623B0005 05-23-2022 A0001 X X

X AMENDMENT (A0001) | Gerald B.H. Solomon, Saratoga Natl Cem

| IFB

Sol No. 36C78623B0005 | Project No. 917-MM23-01 The Purpose of Amendment (A0001) is to Notify the Public of the Government's required FAR/VAAR Clause for this IFB Construction Procurem ent, located at the Gerald B.H. Solomon, Saratoga National Cemetery, NY.

NOTE" Please See Page #3 for Content.

Sheryl Palacio-Davis Contracting Officer A.1 IFB SOLICITATION DESCRIPTION FOR GERALD B.H. SOLOMON, SARATOGA NATIONAL CEMETERY

PROJECT LOCATION:

· GERALD B.H. SOLOMON, SARATOGA NATIONAL CEMETERY

Saratoga National Cemetery 200 Duell Rd.

Schuylerville, NY 12871

PROJECT TITLE: Irrigation System Upgrades

PROJECT NUMBER: 917-MM23-01

STATEMENT OF WORK SUMMARY:

· Contractor shall furnish all tools, labor, materials, equipment, and professional supervision to perform work described in the Statement of Work (SOW), Specification & Drawings, for the Irrigation System Upgrades, located at the Gerald B.H. Solomon, Saratoga National Cemetery, (Saratoga County) in the State of New York.

A.2 CONTINUATION PAGE

VAAR 852.236-92 NOTICE TO BIDDERS—ADDITIVE OR DEDUCTIVE BID LINE ITEMS (APR 2019)

(a) Additive or deductive line items in the bid schedule shall be evaluated to determine the low offeror and the items to be awarded. The evaluation shall be made as follows—

(1) Prior to the opening of bids, the Government will determine the amount of funds available for the project.

(2) The low bid shall be the Bidder that—

(i) Is otherwise eligible for award; and

(ii) Offers the lowest aggregate amount for the first or base line item, plus or minus (in the order stated in the list of priorities in the bid schedule) those additive or deductive line items that provide the most features within the funds determined available.

(3) All bids shall be evaluated on the basis of the same additive or deductive line items.

(i) If adding another item from the bid schedule list of priorities would make the award exceed the available funds for all offerors, the Contracting Officer will skip that item and go to the next item from the bid schedule of priorities; and

(ii) Add that next item if an award may be made that includes that line item and is within the available funds.

(b) The Contracting Officer will use the list of priorities in the bid schedule only to determine the low offeror. After determining the low offeror, an award may be made on any combination of items if—

(1) It is in the best interest of the Government;

(2) Funds are available at the time of award; and

(3) The low offeror’s price for the combination to be awarded is less than the price offered by any other responsive, responsible offeror.

(c) Example: ‘‘The amount available is $100,000. Offeror A’s base bid and four additives (in the order stated in the list of priorities in the bid schedule) are $85,000, $10,000, $8,000, $6,000, and $4,000. Offeror B’s base bid and four additives are $80,000, $16,000, $9,000, $7,000, and $4,000. Offeror A is the low offeror. The aggregate amount of offeror A’s bid for purposes of award would be $99,000, which includes a base bid plus the first and fourth additives. The second and third additives were skipped because each of them would cause the aggregate bid to exceed $100,000.’’ (End of Clause)

END OF DOCUMENT

File details come from the government source that posted it. Updated .