892-043 Ft Rosecrans - Add No 1 - revised sheets.pdf

PDF 3 MB Posted

Attached to
Y1JZ--Proj #: 892-045 Roads Improvement; 892-043 Sewer Improvement Fort Rosecrans Nat'l Cemetery; San Diego, CA
Solicitation number
36C78622B0019
Issued by

About this file

This package includes construction drawings and specifications for road and sewer improvement projects at Fort Rosecrans National Cemetery in San Diego, California. The drawings show demolition plans, utility relocation details, and construction plans for replacing roads, upgrading the sanitary sewer system, and installing a new force main. Key aspects include replacing asphalt and concrete pavement; removing trees, curbs and utilities; installing a new lift station and 1.25-inch polyethylene force main running under Cabrillo Memorial Drive via directional drilling; and connecting existing sanitary services to the new infrastructure. The related solicitation seeks bids for the road improvements under project number 892-045 and sewer improvements under project number 892-043, issued by the Department of Veterans Affairs National Cemetery Administration.

View the file

Other files

Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

LEGEND

REMOVE ASPHALT PAVEMENT

MILL ASPHALT PAVEMENT

REMOVE CONCRETE PAVEMENT

REMOVE CURB & GUTTER

CONSTRUCTION LIMITS

REMOVE EXISTING UTILITY

FULL DEPTH SAWCUT

REMOVE TREE

TREE PROTECTION FENCE

KEY NOTES

FULL DEPTH SAWCUT

REMOVE BITUMINOUS PAVEMENT

REMOVE CONCRETE PAVEMENT / CONCRETE PAVERS

REMOVE & REINSTALL EXISTING GUARDRAIL (1/LP501)

PROTECT EXISTING WALL/COLUMNS

PROTECT STONE MONUMENT

PROTECT/RELOCATE IRRIGATION

REMOVE FLOWER WATER STATION, TRASH CAN, AND VASE RECEPTACLE

RAISE AND REALIGN FLAT MARKERS

REMOVE CONCRETE BOLLARD

GENERAL NOTES

1. ALL CURB TO BE REMOVED AND REPLACED, EXCEPT CURB ALONG

EASTERN DRIVE IN FRONT OF COLUMBARIA WALL. SEE TYPICAL

SECTIONS - SHEET CD104

2. IRRIGATION SPRINKLERS AND PIPE\ING EXIST WITHIN ROADWAY

AREAS ALONG BACK OF CURB. SEE DETAIL 11/CD101 FOR TEMPORARY

RELOCATION AND INSTALLATION/REPLACEMENT OF NEW ROTORS.

3. ALL PAVEMENT REMOVAL SHALL BE TERMINATED WITH A FULL DEPTH

SAWCUT. ALL CONCRETE PAVEMENT AND WALK REMOVALS SHALL BE

TERMINATED WITH A FULL DEPTH SAWCUT AT NEAREST JOINT.

4. ALL PAVEMENT REMOVAL FOR UTILITY INSTALLATION SHALL BE

PATCHED WHEN COMPLETED PER DETAIL 10/CD101. PATCHING SHALL

BE COMPLETED IN ALL AREAS INCLUDING THOSE AREAS SCHEDULED

FOR FULL DEPTH PAVEMENT RECONSTRUCTION AND BITUMINOUS

OVERLAYS.

5. REMOVE AND REPLACE IN-KIND ALL HANDHOLES AND VALVE BOXES

WITHIN PAVEMENT AREAS TO BE REPLACED OR OVERLAYED.

6. CONTRACTOR SHALL MAINTAIN STAFF AND VISITOR ACCESS TO ALL

PUBLIC AREAS OF THE CEMETERY. SEE PHASING PLAN C102 FOR

MORE INFO.

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Fi le

P at h:

y

:\1

\1 n ca fo rt ro se cr an s

- c em et er y ro ad s\

_0 ci vi l\_ c ad fi le s\ _0 sh ee ts

\1

_c d_ de m ol iti on

.d w g ed it:

jri ch ne r s av ed :8

/2 9/

0:

A

M p lo t:8

/2 9/

1:

A

M

Office of Design and Construction

Services

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PhaseARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT

321 4 5 6 7 8 9 10

Project Director

Revisions:

1 3 6 0 5 1 s t A v e . N . # 1 0 0 P l y m o u t h , M N 5 5 4 4 1 P 7 6 3 . 4 1 2 . 4 0 0 0 | F 7 6 3 . 4 1 2 . 4 0 9 0 | a e - m n . c o m Anderson Engineering of Minnesota, LLC | Proj # 16157

FORT ROSECRANS NATIONAL CEMETERY

ROADS AND SANITARY SEWER

IMPROVEMENTS

892-043/045

06-30-2022

1700 CABRILLO MEMORIAL DRIVE, SAN DIEGO, CA 92106

Date: Dwg. of 100

BID DOCUMENTS

COST ESTIMATING:GEOTECHNICAL :

TERRACON

1421 EDINGER AVE. SUITE C

TUSTIN, CA 92780

949-864-2082

RYAN HANKES

OCMI

6110 EXECUTIVE BLVD, SUITE 200

ROCKVILLE, MD 20852

202-299-0530

TOM STRANDBERG

IRRIGATION :

EC DESIGN GROUP

400 5TH STREET

WEST DES MOINES, IA 50265

515-215-6365

LISA ESSY

MECH/ELEC/PLUMB :

IMEG

623 26TH AVENUE

ROCK ISLAND, IL 61201

309-283-1595

GREG RYCKAERT

N

0 20' 40'

1 CABRILLO PARKING AREA - DEMOLITION PLAN ENLARGEMENT

SCALE: 1" = 20'

N

0 20' 40'

2 EAST ENTRANCE & UTILITY DRIVEWAY - DEMOLITION PLAN ENLARGEMENT

SCALE: 1" = 20' N

0 20' 40'

3. COMMITTAL SHELTER - DEMOLITION PLAN ENLARGEMENT

SCALE: 1" = 20'

EXISTING STAIRCASE

TO REMAIN IN PLACE

2 1

EXISTING LANDSCAPING

TO REMAIN IN PLACE

REMOVE AND SALVAGE EXISTING PRECAST

BENCHES (4) DURING DEMOLITION AND

NEW PAVEMENT INSTALLATION WORK.

RE-INSTALL BENCHES AFTER FLATWORK

COMPLETION.

CONCRETE WALK TO

REMAIN IN PLACE

VICINITY MAP

D101

SITE DEMOLITION

PLAN

AT MT 18

CONCRETE WALK TO

REMAIN IN PLACE

REMOVE TRENCH DRAIN

REMOVE CONCRETE HEADER

SURROUNDING CONCRETE PAVERS

PROTECT EXISTING

STRUCTURE COLUMNS

AND FOUNDATIONS

PROTECT EXISTING

MEMORIAL PLAQUES

SEE SHEET

D112 FOR

STREET

REMOVAL

1 2

CABRILLO MEMORIAL DRIVE

REMOVE & REINSTALL CONCRETE BENCH,

PLAQUE, AND BUS STOP SIGN

SECOND

DRIVE

EAST

CABRILLO MEMORIAL DRIVE

MILL EXISTING

PAVEMENT

ADDENDUM NO. 1 8/30/221

AutoCAD SHX Text

ACU

AutoCAD SHX Text

ET

0+00

1+00

1+85

0+00

1+00

2+00 2+32

5+

00AD

M

IN

BU

ILD

IN

G

0+00 1+00

2+00 2+5420

+0

+0

LEGEND

REMOVE ASPHALT PAVEMENT

MILL ASPHALT PAVEMENT

REMOVE CONCRETE PAVEMENT

REMOVE CURB & GUTTER

CONSTRUCTION LIMITS

REMOVE EXISTING UTILITY

FULL DEPTH SAWCUT

REMOVE TREE

TREE PROTECTION FENCE

KEY NOTES

POINT OF CONNECTION TO REMOVE 6" FIRE/IRRIGATION WATERMAIN

GENERAL NOTES

1. ALL CURB TO BE REMOVED AND REPLACED, EXCEPT CURB ALONG

EASTERN DRIVE IN FRONT OF COLUMBARIA WALL. SEE TYPICAL

SECTIONS - SHEET CD104

2. IRRIGATION SPRINKLERS AND PIPE\ING EXIST WITHIN ROADWAY

AREAS ALONG BACK OF CURB. SEE DETAIL 11/CD101 FOR TEMPORARY

RELOCATION AND INSTALLATION/REPLACEMENT OF NEW ROTORS.

3. ALL PAVEMENT REMOVAL SHALL BE TERMINATED WITH A FULL DEPTH

SAWCUT. ALL CONCRETE PAVEMENT AND WALK REMOVALS SHALL BE

TERMINATED WITH A FULL DEPTH SAWCUT AT NEAREST JOINT.

4. ALL PAVEMENT REMOVAL FOR UTILITY INSTALLATION SHALL BE

PATCHED WHEN COMPLETED PER DETAIL 10/CD101. PATCHING SHALL

BE COMPLETED IN ALL AREAS INCLUDING THOSE AREAS SCHEDULED

FOR FULL DEPTH PAVEMENT RECONSTRUCTION AND BITUMINOUS

OVERLAYS.

5. REMOVE AND REPLACE IN-KIND ALL HANDHOLES AND VALVE BOXES

WITHIN PAVEMENT AREAS TO BE REPLACED OR OVERLAYED.

6. CONTRACTOR SHALL MAINTAIN STAFF AND VISITOR ACCESS TO ALL

PUBLIC AREAS OF THE CEMETERY. SEE PHASING PLAN C102 FOR

MORE INFO.

FULL DEPTH SAWCUT

REMOVE BITUMINOUS PAVEMENT

REMOVE CONCRETE PAVEMENT / CONCRETE PAVERS

REMOVE & REINSTALL EXISTING GUARDRAIL (1/LP501)

PROTECT EXISTING WALL/COLUMNS

PROTECT STONE MONUMENT

PROTECT/RELOCATE IRRIGATION

REMOVE FLOWER WATER STATION, TRASH CAN, AND VASE RECEPTACLE

RAISE AND REALIGN FLAT MARKERS

REMOVE CONCRETE BOLLARD

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Fi le

P at h:

y

:\1

\1 n ca fo rt ro se cr an s

- c em et er y ro ad s\

_0 ci vi l\_ c ad fi le s\ _0 sh ee ts

\1

_c

_d em o w es t d riv es

.d w jri ch ne r s av ed :8

/2 9/

1:

lo t:8

/2 9/

1:

A

M

Office of Design and Construction

Services

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PhaseARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT

321 4 5 6 7 8 9 10

Project Director

Revisions:

1 3 6 0 5 1 s t A v e . N . # 1 0 0 P l y m o u t h , M N 5 5 4 4 1 P 7 6 3 . 4 1 2 . 4 0 0 0 | F 7 6 3 . 4 1 2 . 4 0 9 0 | a e - m n . c o m Anderson Engineering of Minnesota, LLC | Proj # 16157

FORT ROSECRANS NATIONAL CEMETERY

ROADS AND SANITARY SEWER

IMPROVEMENTS

892-043/045

06-30-2022

1700 CABRILLO MEMORIAL DRIVE, SAN DIEGO, CA 92106

Date: Dwg. of 100

BID DOCUMENTS

COST ESTIMATING:GEOTECHNICAL :

TERRACON

1421 EDINGER AVE. SUITE C

TUSTIN, CA 92780

949-864-2082

RYAN HANKES

OCMI

6110 EXECUTIVE BLVD, SUITE 200

ROCKVILLE, MD 20852

202-299-0530

TOM STRANDBERG

IRRIGATION :

EC DESIGN GROUP

400 5TH STREET

WEST DES MOINES, IA 50265

515-215-6365

LISA ESSY

MECH/ELEC/PLUMB :

IMEG

623 26TH AVENUE

ROCK ISLAND, IL 61201

309-283-1595

GREG RYCKAERT

D105

DEMO PLAN - WEST

PORTAL & 3RD

DRIVE SOUTH

AT MT 22

N 0 20' 40'

1 WEST PORTAL - DEMOLITION

SCALE: 1" = 20'

2 3RD DRIVE SOUTH - DEMOLITION

SCALE: 1" = 20'

VICINITY MAP

STREET SECTION C-C

SEE DETAIL 3/CD104

M

AT

C H

L

IN

E

- S

H

EE

T D

C

AB

R

IL

LO

M

EM

O

R

IA

L D

R

IV

E

C

AB

R

IL

LO

M

EM

O

R

IA

L D

R

IV

E

M

AT

C H

L

IN

E

- S

H

EE

T D

M

AT

C H

L

IN

E

- S

H

EE

T D

STREET SECTION A-A

SEE DETAIL 1/CD104

STREET SECTION C-C

SEE DETAIL 3/CD104

STREET SECTION B-B

SEE DETAIL 2/CD104

EXCAVATION IN TREE ROOT AREAS

SHALL BE PERFORMED UNDER THE

OBSERVATION OF A LICENSED ARBORIST

TO MINIMIZE DAMAGE TO ROOTS

N 0 20' 40'

PATCHED AREA TO BE MILLED

AT TIME OF ADJACENT

PAVEMENT MILLING

ADDENDUM NO. 1 8/30/221

0+57

1+

2+00 3+00

0+00

1+00

2+00 3+00

+0

+0

+7

0+

1+

2+

3+

LEGEND

REMOVE ASPHALT PAVEMENT

MILL ASPHALT PAVEMENT

REMOVE CONCRETE PAVEMENT

REMOVE CURB & GUTTER

CONSTRUCTION LIMITS

REMOVE EXISTING UTILITY

FULL DEPTH SAWCUT

REMOVE TREE

TREE PROTECTION FENCE

KEY NOTES

GENERAL NOTES

1. ALL CURB TO BE REMOVED AND REPLACED, EXCEPT CURB ALONG

EASTERN DRIVE IN FRONT OF COLUMBARIA WALL. SEE TYPICAL

SECTIONS - SHEET CD104

2. IRRIGATION SPRINKLERS AND PIPE\ING EXIST WITHIN ROADWAY

AREAS ALONG BACK OF CURB. SEE DETAIL 11/CD101 FOR TEMPORARY

RELOCATION AND INSTALLATION/REPLACEMENT OF NEW ROTORS.

3. ALL PAVEMENT REMOVAL SHALL BE TERMINATED WITH A FULL DEPTH

SAWCUT. ALL CONCRETE PAVEMENT AND WALK REMOVALS SHALL BE

TERMINATED WITH A FULL DEPTH SAWCUT AT NEAREST JOINT.

4. ALL PAVEMENT REMOVAL FOR UTILITY INSTALLATION SHALL BE

PATCHED WHEN COMPLETED PER DETAIL 10/CD101. PATCHING SHALL

BE COMPLETED IN ALL AREAS INCLUDING THOSE AREAS SCHEDULED

FOR FULL DEPTH PAVEMENT RECONSTRUCTION AND BITUMINOUS

OVERLAYS.

5. REMOVE AND REPLACE IN-KIND ALL HANDHOLES AND VALVE BOXES

WITHIN PAVEMENT AREAS TO BE REPLACED OR OVERLAYED.

6. CONTRACTOR SHALL MAINTAIN STAFF AND VISITOR ACCESS TO ALL

PUBLIC AREAS OF THE CEMETERY. SEE PHASING PLAN C102 FOR

MORE INFO.

FULL DEPTH SAWCUT

REMOVE BITUMINOUS PAVEMENT

REMOVE CONCRETE PAVEMENT / CONCRETE PAVERS

REMOVE & REINSTALL EXISTING GUARDRAIL (1/LP501)

PROTECT EXISTING WALL/COLUMNS

PROTECT STONE MONUMENT

PROTECT/RELOCATE IRRIGATION

REMOVE FLOWER WATER STATION, TRASH CAN, AND VASE RECEPTACLE

RAISE AND REALIGN FLAT MARKERS

REMOVE CONCRETE BOLLARD

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Fi le

P at h:

y

:\1

\1 n ca fo rt ro se cr an s

- c em et er y ro ad s\

_0 ci vi l\_ c ad fi le s\ _0 sh ee ts

\1

_c

_d em o ea st d riv es

.d w jri ch ne r s av ed :8

/2 9/

1:

lo t:8

/2 9/

1:

A

M

Office of Design and Construction

Services

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PhaseARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT

321 4 5 6 7 8 9 10

Project Director

Revisions:

1 3 6 0 5 1 s t A v e . N . # 1 0 0 P l y m o u t h , M N 5 5 4 4 1 P 7 6 3 . 4 1 2 . 4 0 0 0 | F 7 6 3 . 4 1 2 . 4 0 9 0 | a e - m n . c o m Anderson Engineering of Minnesota, LLC | Proj # 16157

FORT ROSECRANS NATIONAL CEMETERY

ROADS AND SANITARY SEWER

IMPROVEMENTS

892-043/045

06-30-2022

1700 CABRILLO MEMORIAL DRIVE, SAN DIEGO, CA 92106

Date: Dwg. of 100

BID DOCUMENTS

COST ESTIMATING:GEOTECHNICAL :

TERRACON

1421 EDINGER AVE. SUITE C

TUSTIN, CA 92780

949-864-2082

RYAN HANKES

OCMI

6110 EXECUTIVE BLVD, SUITE 200

ROCKVILLE, MD 20852

202-299-0530

TOM STRANDBERG

IRRIGATION :

EC DESIGN GROUP

400 5TH STREET

WEST DES MOINES, IA 50265

515-215-6365

LISA ESSY

MECH/ELEC/PLUMB :

IMEG

623 26TH AVENUE

ROCK ISLAND, IL 61201

309-283-1595

GREG RYCKAERT

D110

DEMO PLAN - EAST PORTAL AND

FOURTH STREET SOUTHEAST

AT MT 27

N 0 20' 40'

1 EAST PORTAL - DEMOLITION

SCALE: 1" = 20'

VICINITY MAP

STREET SECTION B-B

SEE DETAIL 2/CD104

STREET SECTION C-C

SEE DETAIL 3/CD104

C

AB

R

IL

LO

M

EM

O

R

IA

L D

R

IV

E

PROTECT CONCRETE

WALK TO REMAIN

M

AT

C H

L

IN

E

- S

H

EE

T D

MATCH LINE - SHEET D111

SEE SHEET D101 FOR

REMOVALS AT EAST ENTRANCE 5

REMOVE ARTIFICIAL TURF

MILL EXISTING BITUMINOUS PARKING AREA

MILL EXISTING BITUMINOUS PARKING AREA

PROTECT EXISTING

BITUMINOUS CURB TO REMAIN

ADDENDUM NO. 1 8/30/221

N O

PAR

KIN

G N

O

PAR

KIN

G

0+00

1+00

2+00

3+003+06

8+

-2.50%

-2.20%

-9.67%

PV

IS

: 0 +0

0.

PV

IE

: 3

.0

PV

IS

: 0 +7

1.

PV

IE

: 3

.2

PV

IS

: 1 +9

9.

PV

IE

: 3

.8

PV

IS

: 3 +0

5.

PV

IE

: 3

.5

4.

7.

0+00

2.

5.

9.

2.

1+00

4.

7.

9.

2.

2+00

8.

2.

7.

3.

3+00 3+11

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Fi le

P at h:

y

:\1

\1 n ca fo rt ro se cr an s

- c em et er y ro ad s\

_0 ci vi l\_ c ad fi le s\ _0 sh ee ts

\1

_w es t f m p p.

dw jri ch ne r s av ed :8

/2 9/

0:

lo t:8

/2 9/

1:

A

M

Office of Design and Construction

Services

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PhaseARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT

321 4 5 6 7 8 9 10

Project Director

Revisions:

1 3 6 0 5 1 s t A v e . N . # 1 0 0 P l y m o u t h , M N 5 5 4 4 1 P 7 6 3 . 4 1 2 . 4 0 0 0 | F 7 6 3 . 4 1 2 . 4 0 9 0 | a e - m n . c o m Anderson Engineering of Minnesota, LLC | Proj # 16157

FORT ROSECRANS NATIONAL CEMETERY

ROADS AND SANITARY SEWER

IMPROVEMENTS

892-043/045

06-30-2022

1700 CABRILLO MEMORIAL DRIVE, SAN DIEGO, CA 92106

Date: Dwg. of 100

BID DOCUMENTS

COST ESTIMATING:GEOTECHNICAL :

TERRACON

1421 EDINGER AVE. SUITE C

TUSTIN, CA 92780

949-864-2082

RYAN HANKES

OCMI

6110 EXECUTIVE BLVD, SUITE 200

ROCKVILLE, MD 20852

202-299-0530

TOM STRANDBERG

IRRIGATION :

EC DESIGN GROUP

400 5TH STREET

WEST DES MOINES, IA 50265

515-215-6365

LISA ESSY

MECH/ELEC/PLUMB :

IMEG

623 26TH AVENUE

ROCK ISLAND, IL 61201

309-283-1595

GREG RYCKAERT

CU105

PLAN & PROFILE -

FORCEMAIN 3

AT MT 64

N

0 20' 40'

1 FORCEMAIN 3 - PLAN VIEW

SCALE: 1" = 20'

2 FORCEMAIN 3 - PROFILE VIEW

SCALE: V: 1" = 10' H: 1" = 20'

VICINITY MAP

CONNECT EXISTING SANITARY SERVICE TO NEW LIFT STATION

FIELD VERIFY SERVICE ELEVATION PRIOR TO COMMENCING WORK

LIFT STATION 1

E-ONE DR171 (OR APPROVED EQUAL)

FORCEMAIN 1

SEE SHEET CU102

EXISTING GRADE

1.25" PE FORCEMAIN

M

AI

N

TA

IN

6" M

IN

C

O

VE

R

LIFT STATION 3

RIM=398.00

INV=FIELD VERIFY

ADMIN

BUILDING

CABRILLO MEMORIAL

DRIVE ℄

1. CONTRACTOR SHALL OBTAIN ALL PERMITS PRIOR TO CONSTRUCTION

ACTIVITIES.

2. CONTRACTOR TO INSTALL EROSION COTROL MEASURES PRIOR TO

STARTING WORK.

3. PHASE DEMOLITION AS NEEDED TO MAINTAIN MINIMAL DISRUPTION OF

DRAINAGE AND UTILITIES.

4. PROTECT ALL EXISTING SITE ELEMENTS (TREES, UTILITIES, CURB, ETC.)

NOT NOTED FOR REMOVAL. REPLACE IN KIND IF DAMAGED.

5. CONTRACTOR SHALL REMOVE AND DISPOSE ALL DEMOLITION ITEMS

OFFSITE IN ACCORDANCE WITH APPLICABLE FEDERAL, STATE, AND LOCAL

REQUIREMENTS.

6. CONTRACTOR SHALL VERIFY ALL DIMENSIONS AND ELEVATIONS PRIOR

TO CONSTRUCTION.

7. COORDINATE ALLL UTILITY RELOCATIONS/DISRUPTIONS WITH VAMC

STAFFF.

8. ALL LANDSCAPED AREAS DISTURBED FOR CONSTRUCTION OF

FORCEMAIN TO BE RESTORED IN KIND.

9. MAINTAIN 3 FT MINIMUM COVER ABOVE TOP OF FORECEMAIN.

10. MAINTAIN 12 INCHES MINIMUM SEPARATION BETWEEN FORCEMAIN

AND OTHER UTILITIES.

NOTES

EXISTING FORCEMAIN

EXISTING SANITARY SEWER

EXISTING WATERMAIN

EXISTING UNDERGROUND ELECTRIC

EXISTING COMMUNICATION

EXISTING FIBER OPTIC

EXISTING MANHOLE

PROPOSED FORCEMAIN

PROPOSED SANITARY SEWER

PROPOSED MANHOLE/LIFT STATION

LEGEND

ABANDONED SEPTIC TANK

1 PROVIDE ELECTRICAL SERVICE AND CONTROL WIRING

FOR LIFT STATION. SEE SHEET E001.

FORCEMAIN CONNECTION

MANHOLE

BRING TRACER WIRE TO SURFACE AND INSTALL AT-GRADE ACCESS POINT

INSTALL (3) PIPE BOLLARDS

PER DETAIL 4/CD102

DIRECTIONAL DRILL

DIRECTIONAL DRILL 1.25" PE FORCEMAIN

UNDER CABRILLO MEMORIAL DRIVE

STA 2+25 TO 3+05

POTHOLE EXISTING UTIITIES TO

VERIFY ELEVATION PRIOR TO

DIRECTIONAL DRILLING WORK

ADDENDUM NO. 1 8/30/221

AutoCAD SHX Text

CABRILLO MEMORIAL DRIVE

AutoCAD SHX Text

WESTERN DRIVE

Sheets and Views
D101 SITE DEMOLITION PLAN
D105 DEMO PLAN - WEST PORTAL & 3RD DRIVE SOUTH
D110 DEMO PLAN - EAST PORTAL AND FOURTH STREET SOUTHEAST
CU105 PLAN & PROFILE - FORCEMAIN 3

File details come from the government source that posted it. Updated .