This solicitation is for construction services to reconstruct roads, signage, and gates at Fort Scott National Cemetery in Kansas. The contractor will provide management, supervision, labor, equipment, materials and tools to complete storm drainage improvements, pavement and curb repair, full depth pavement replacement, mill and overlay work, signage upgrades, and entrance gate repairs. The work must be performed according to drawings, specifications and manufacturer requirements.
The period of performance is 240 calendar days from notice to proceed for base work, with an additional 60 days if the optional work is awarded. Normal work hours are weekdays from 7:30am to 4pm. The contractor must coordinate work schedules with the contracting officer's representative to avoid interfering with burial services and ceremonies. The solicitation specifies conduct, personal protective equipment, and safety requirements for working in the cemetery. The Department of Veterans Affairs National Cemetery Administration is the contracting agency.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| BID SPECS.pdf | ||
| 36C78622B0018 _ Solicitation.pdf | ||
| Cost Estimate Worksheet.pdf | ||
| RECONSTRUCT ROADS BID PLANS.pdf | ||
| RFI Form.pdf | ||
| DOL Wage Determination _ Bourbon County.pdf | ||
| Past Performance.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE 7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER 3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO. 1. CONTRACT ID CODE
FACILITY CODE CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office. is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30 PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243
(Type or print) (Type or print)
(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code)
(If other than Item 6)
(Specify type of modification and authority)
(such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer)
1 7
0001 08/22/2022 Funds Assurance 893CM3017
36C786
Department of Veterans Affairs National Cemetery Administration Contracting Services 18434 Joplin Road Triangle VA 22172
36C786
Department of Veterans Affairs National Cemetery Administration Contracting Services 18434 Joplin Road Triangle VA 22172
To all Offerors/Bidders 36C78622B0018
06-27-2022 X
X X
X 1
Reconstruct Roads, Signage Improvements and Gate Repair, Fort Scott National Cemetery, Kansas Amendment 0001 is issued to:
Respond to RFI questions (See attached Continuation Page(s)).
The Bid Opening Due Time/Date is unchanged and stays as September 2, 2022, at 4 PM EDT.
No other changes are made at this time.
All other solicitation Terms and Conditions remain unchanged.
Claude Humphrey Contracting Office
VA-NCA-2021-5F4C545C
CONTINUATION PAGE
AMENDMENT 0001
Request for Information (RFI) Responses:
The following Request for Information (RFI) questions have been submitted to the Contracting Officer regarding this solicitation. The questions and responses represent all questions submitted to the Contracting Officer prior to the deadline established in the Solicitation. The following questions and responses are provided for bidder’s information and use.
RFI 1. Please confirm the scheduled Bid Opening Date; the SAM.GOV solicitation states bids are due August 26, 2022, whereas the SF1442 states bids are due September 2, 2022.
Which date is correct?
Response: Bids are due No Later Than September 2, 2022, as stated on the SF 1442.
RFI 2. Page 7 of the solicitation states that all bids must be submitted to the CO and provides an email to submit them. Page 8 states that bids are to be submitted through the Vendor Portal. Are we to submit bids to both?
Response: Bids are to be submitted either via the Vendor Portal or to the CO at the address identified. The solicitation provides the email option to submit bids in case an offeror cannot submit via the Department of Veterans Affairs eCMS Vendor Portal.
The language will be clarified to be more specific and read:
All bids must be submitted to the attention of the Contracting Officer identified
No Later Than the date/time specified. If an interested bidder can not submit its bid via the Department of Veterans Affairs eCMS Vendor Portal link provided email bids will be acceptable at claude.humphrey@va.gov No Later Than the date/time specified.
Interested bidders are reminded that if an Offeror experience difficulty in submitting its bid via the Vendor Portal the Contracting Officer may accept an Offeror’s quote via email under the following circumstances:
1. Bidder must provide evidence that an email discussions or verbal discussion with the VAAS helpdesk could not resolve registration issues.
2. Bid submitted must meet the time constraints as set forth in the solicitation.
3. Bids submitted via email without set requirements will not be accepted and will be considered to be NONRESPONSIVE.
4. Late or incomplete Bids will NOT be considered and deemed to be nonresponsive.
RFI 3. On Plan sheet GI200 SEQUENCE OF CONSTRUCTION:
1. CONTRACTOR TO KEEP ONE LANE/PATH CLEAR FOR CEMETERY
OPERATIONS AT ALL TIMES.
Is the intent to use flaggers during work hours to protect the cemetery visitors and staff while the work is ongoing?
mailto:claude.humphrey@va.gov
Response: No, it is not the NCA intent to direct means and methods for the Contractor to employ, the intent is for the Contractor to protect cemetery visitors and staff while the work is ongoing with an approved plan of action.
RFI 4. On Plan sheet GI200 SEQUENCE OF CONSTRUCTION:
1. CONTRACTOR TO KEEP ONE LANE/PATH CLEAR FOR CEMETERY
OPERATIONS AT ALL TIMES.
Can the road be closed while installing the storm drain shown on CU260?
Response: Yes, with proper advance notification, coordination and scheduling with the COR.
RFI 5. Plan Sheet CI501:
Are the signposts to be integrally colored concrete?
If so what color?
Response: The signposts do not have integrally colored concrete. Natural concrete color is intended.
RFI 6. Plan Sheet CI502 & CI503:
What base color does the cemetery want for the new signs?
Response: As indicated on details and specifications, signs shall be NCA standard bronze/dark brown color (Matthews #MP07458).
RFI 7. Specs didn't address any gate work, but it is referenced on the drawing plans. Which is correct?
Response: Per FAR 52.236-21 Specifications and Drawings for Construction language – Anything mentioned in the specifications and not shown on the drawings or shown on the drawings and not mentioned in the specifications, shall be of like effect as if shown or mentioned in both. In case of difference between drawings and specifications, the specifications shall govern.
RFI 8. Specs reference Planting, masonry, earth moving, but these are not in the drawings?
Response: Same response as provided in response to RFI 7 above.
RFI 9. On drawing CI201 for the Visitor Information & Floral Regulation Signs, the site signage details numbers do not match what is called out on CI503. We have attached a “Sign Layout vs. Sign Details Discrepancy” drawing referencing these discrepancies.
Please advise if the descriptions are correct for these items.
Response: The site signage detail callouts for the Visitor Info and Floral Regulations signs on drawing CI201 were incorrect. As shown on detail 2/sheet CI503, the Visitor Info sign shall be NC-1.02A-C1, and the Floral Regulations sign shall be NC-1.02B-C1 (4’ wide panels).
RFI 10. On drawing CI502 items NC-03.02A-C1 and NC-03.02B-C1, it looks like these traffic signs are double-sided, not just “standard flat” one-sided panels. Can you please confirm that these DOT signs will be double-sided for all traffic signs?
a. Also, if this is the type of build the National Cemetery wants, on the “PLAN View” on drawing CI502, is the sign cabinet referenced to be square, and we are to assume we will slide in the Traffic Signs, or is the cabinet supposed to have the same shape as the called-out traffic signs?
Response: The traffic regulatory signs per detail 3/sheet CI502 are NCA standard low profile traffic signs, not DOT signs. As shown in the detail “Sign Frame and Mounting Section Enlargement”, the sign panel assembly is a square frame constructed of 1”x1” extruded aluminum members with 1/8” aluminum sign panels attached to both sides of the frame. For signs where information is to be shown on only one side (such as the burial processions sign), one sign assembly is attached to the front side of the post. For signs where information is to be shown on both sides (such as the stop and yield signs), the “Side A” sign assembly is attached to the front side of the post, and the “Side B” sign assembly is attached to the rear side of the post. All traffic regulatory sign panels are 1’-6” square and shall have the indicated graphics or text applied to the sign panels as dimensioned in the detail.
RFI 11 Provide a copy of the Pre-Bid Attendee sheet.
Response: See attached.
END OF AMENDMENT 0001
End of Document
CONTRACTOR/VISITOR LOG IN (FY09)
NAME, iAJ Vo I> '1 !Mot> w'JH1.J) coMPANY: Nc-if}60LO. ·Lu:-., FORM OF ID:. _____________ _
PURPOSE OF VISIT: t;JT?: \//$ C(':
NAME OF PERSON VISITED:._·_____.I;�All�-------
DA TE: fl/ l} / Z,2, TIME IN: "',OP
NAME: Olli� BLootYICbll� :rv, L-LC-::
coMPANY: LE.OA/ltlatJD A�o
"FORM OF ID:. _____________ _
PURPOSE OF VISIT:_�=---'2/�/rl-�---------
NAME OF PERSON VISITED: _________ _
DATE: -s/t/�
TIME IN: TIME OUT:. ____ _
SIGNATUR�
NAME: ::?sa� J'k-41t::!if:
COMPANY: Be, ?7S t'lst?M 1, z-=
FORM OF IQ.:. _____________ _
PURPOSE OF VISIT: .f?te, - /$1 0 45,, !E, U)s. � ,r-
NAME OF PERSON VISITED:. _________ _
DATE: tq/1)'2oZ2-
TIME IN: ______ TIME OUT:. ______ _
SIGNATURE:_�.:c-...-;.____ .... _L_...---_2 __ �_d_· ____ _
· QTRLY CHECK:
1ST QTR: ·------
2N0 QTR: ·------
3RD QTR: ·------
4TH QTR: ·------
36C78622B0018, 893CM3017: Reconstruct Roads
Fort Scott National Cemetery
Pre-Bid Site Visit Sign-in Sheet
CONTRACTOR/VISITOR LOG IN (FY09)
NAME: �V\ i)MJt'v'50V\.
COMPANY: �t\t,rso"' d: Sowi,s · e_6t/trr:�At
-FORM OF!�-------------
PURPOSE OF VISIT: ,SL, \)'er,+ ,pzt b.J
NAME OF PERSON VISITED:_-_J__._."1.._W\�------
DATE: 8: )'-1 f7,,o'P:L
TIMEIN: 12:ttS-- . · TIME:):._· ____ _
SIGNATURE: �
NAME: 4 4: /4.J �
COMPANY: /21-� C/CCliv?t-��
J;ORM OF ID: ______________ _
PURPOSE OF VISIT: Srh v, l, .. ;--
NAME OF PERSON VISITED: __________ _
DATE: $ J '-I I 7, '2-
r 1 _,,,---
TIME IN: / 2; C/ >
NAME: Va}l, l I l..r: ¥1,-c VV\
COMPANY: &loo}-'l�J,d 4 §f.c(l.va.l '1
FORM QF IC:
PURPOSE OF VISIT: � l k Jt{ rf
NAME OF PERSON VISITED:. __________ _
DATE: toll//22-
.TIME IN: f2" � TIME OUT:
SIGNATURE: @,�
· QTRLY CHECK:
1ST QTR: ·------
2ND QTR: ·------
3RD QTR:. ______
4TH Cl.TR: ·------
CONTRACTOR/VISITOR LOG IN (FV09)
NAME: bbaJ Pzt/kr$§17 Lhp/� tb.WoTRLVCHECK:
coMPANv: 1/o. l)lb<Y- fbj {n<:ce...�tqj · 15T QTR: ____ _
FiOR.M OFl�------------
PURPOSE OF VISIT: 6<, -f v,, la I c cJ NAME OF PER5011SITED: . 6bCII d fi;; /lo -s:-� DATE: 1/o/22 TIME IN: , ; C)O 1· . Tl��T:
SIGNATURE: �£ l �
NAME: 138'/A:blT c:.. 6 �� l f&. lSR, COMPANvcff)-t:Y) Co S �B\' 1 C-5l I N. � f'eRM OF tf>: ____________ _
PURPOSE OF VISIT: 21 ($ V /Stl=
NAME OF P TED: ________ _
DATE: �
NAME: _s ·--==__i.:IA..t-l.,..__�.l"-&,4.�-4-4:,___ _ __:__ __ _ coMPANY: RK Si c"-u11±1an
PURPOSE oF v1s1T: � \\-:e, \Ji� 1 t-
NAME OF PERSON VISITED: ________ _
DATE: �--2\.., 1.. l-- TIME IN: \ 'l\ � � /)f�t
SIGNATURE: 4-�
2N° QTR: ·-----
3RD QTR: ·-----
4TH QTR: -----