This document outlines a federal contract solicitation for infrastructure improvement projects at the Fargo National Cemetery in North Dakota. The Department of Veterans Affairs is seeking a contractor to provide all labor, equipment, materials and supervision necessary to construct a new restroom, storage structure, and wind walls. The solicitation is set aside exclusively for verified Service-Disabled Veteran-Owned Small Businesses. The anticipated period of performance is 270 calendar days from notice to proceed. Interested parties must register in the System for Award Management and Vendor Portal databases. Bids are due electronically by the specified date and time. A site visit is scheduled upon request prior to bidding.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C78622B0004 Amendment 0002.pdf | ||
| 36C78622B0004 Amendment 0001.pdf | ||
| 36C78622B0004.docx | DOCX document | |
| Fargo - Technical Specifications.pdf | ||
| Copy of Cost Estimate Worksheet.xlsx | XLSX spreadsheet | |
| Wage Determination Fargo Cass County 01072022.pdf | ||
| 36C78622B0004_2.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
94 94 52
10 10
294 294
FARGO NATIONAL CEMETERY
NORTH
DAKOTA
MINNESOTAFargo
Moorhead
DEPARTMENT OF VETERANS AFFAIRS
FARGO NATIONAL CEMETERY
RESTROOMS, STORAGE, WIND WALLS DESIGN
VA PROJECT NO. 939.940-MM20-004
VA CONTRACT NO. 36C78618D0025
CONSULTANTS
ANDERSON ENGINEERING OF MN, LLC
ARCHITECTURE, LANDSCAPE ARCHITECTURE,
PLANNING, CIVIL ENGINEERING
13605 1ST AVENUE NORTH, SUITE 100
PLYMOUTH, MN 55441
CONTACT: GARY JOHNSON, PROJECT MANAGER
PHONE: (763) 412-4000
IMEG
ELECTRICAL ENGINEERING,
STRUCTURAL ENGINEERING, MEP
623 26TH AVENUE
ROCK ISLAND, IL 61201
CONTACT: MATT SNYDER
PHONE: (916) 817-4924
REGIONAL LOCATION MAP PROJECT SITE MAPN.T.S.
N
N.T.S.
N
PROJECT SITE
12TH AVE. N
40TH AVE. N
MAPLE SHEYENNE
LUTHERAN CHURCH
& CEMETERY
EXIT 69
C O
U N
TY
R
O
AD
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Fi le
P at h:
y:
\1
\1 fa rg o nc a nd n or th w oo ds n c
- r es tro om s, s to ra ge , w in d w al ls a e\ _0 ci vi l\_ c ad fi le s\
_0 sh ee ts \1
.1 _x
_c ov er .d w g e di t:e br od m ar kl e s av ed :9/
/2
1:
P M p lo t:9
/2 0/
:1
PM
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORDSTAMPCONSULTANTS
321 4 5 6 7 8 9 10
Project Director
Revisions:
13605 1st Ave. N. #100 Pl ymout h, MN 55441 P 763.412.4000 | F 763.412.4090 | ae-mn.com Anderson Engineering of Minnesota, LLC | Proj#16315.1
RESTROOMS, STORAGE & WIND
WALLS
939.940-MM20-004
September 8, 2021
FARGO NATIONAL CEMETERY
8709 40TH AVENUE N. HARWOOD, ND 58042
BIDDING DOCUMENTS
09.08.2021
BIDDING DOCUMENTS
Date:
Mechanical Engineering, Electrical Engineering, Structural Engineering:
IMEG
623 26th Avenue Rock Island, IL 61201 (916)-817-4924 Matt Snyder / Todd Barrett
Cost Estimating:
OCMI
1722 Routh Street #900 Dallas, TX 75201 (469)-431-0571 Kyle Veater OF 22
OCMI
COST ESTIMATOR
1772 ROUTH STREET #900
DALLAS, TX 75201
CONTACT: KYLE VEATER
PHONE: 469-431-0571
COVER SHEET
GI001
EJB KAA 1
SHEET INDEX
SHEET
NUMBER SHEET TITLE
BASE BID
GI001 COVER SHEET 1 OF 22
VF101 EXISTING CONDITIONS 2 OF 22
D-101 DEMOLITION PLAN 3 OF 22
CG101 GRADING & UTILITY PLAN 4 OF 22
CS101 SITE PLAN 5 OF 22
CG102 SWPPP 6 OF 22
CS501 RESTROOM STORAGE BUILDING DETAILS 7 OF 22
CS502 RESTROOM STORAGE BUILDING DETAILS 8 OF 22
CS503 SITE DETAILS 9 OF 22
LP101 PLANTING PLAN 10 OF 22
LP501 PLANTING DETAILS 11 OF 22
AE101 WIND WALL PLAN, ELEVATION AND DETAIL 12 OF 22
S-001 STRUCTURAL GENERAL NOTES 13 OF 22
SB101 FOUNDATION PLAN & DETAILS 14 OF 22
ADD ALTERNATE 1
E-000 ELECTRICAL COVER SHEET 15 OF 22
E-001 SITE - ELECTRICAL 16 OF 22
CU301 UTILITY PLAN 17 OF 22
CS504 RESTROOM STORAGE BUILDING DETAILS 18 OF 22
ADD ALTERNATE 2
CS201 SITE PLAN 19 OF 22
ADD ALTERNATE 3
AE201 WIND WALL & STORAGE PLAN, ELEVATIONS AND DETAILS 20 OF 22
SB102 FOUNDATION PLAN & DETAILS 21 OF 22
SF101 FRAMING PLAN & DETAILS 22 OF 22
1 DELETE TOILET FLUSH VALVE 09/14/2021
AutoCAD SHX Text S
AutoCAD SHX Text R
AutoCAD SHX Text I
AutoCAD SHX Text A
AutoCAD SHX Text F
AutoCAD SHX Text F
AutoCAD SHX Text A
AutoCAD SHX Text S
AutoCAD SHX Text N
AutoCAD SHX Text A
AutoCAD SHX Text R
AutoCAD SHX Text E
AutoCAD SHX Text T
AutoCAD SHX Text E
AutoCAD SHX Text V
AutoCAD SHX Text F
AutoCAD SHX Text O
AutoCAD SHX Text T
AutoCAD SHX Text N
AutoCAD SHX Text E
AutoCAD SHX Text A
AutoCAD SHX Text C
AutoCAD SHX Text I
AutoCAD SHX Text R
AutoCAD SHX Text E
AutoCAD SHX Text M
AutoCAD SHX Text A
AutoCAD SHX Text F
AutoCAD SHX Text O
AutoCAD SHX Text S
AutoCAD SHX Text E
AutoCAD SHX Text T
AutoCAD SHX Text A
AutoCAD SHX Text T
AutoCAD SHX Text S
AutoCAD SHX Text D
AutoCAD SHX Text E
AutoCAD SHX Text T
AutoCAD SHX Text I
AutoCAD SHX Text N
AutoCAD SHX Text U
6 7 8 9 10
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Fi le
P at h:
y
:\1
\1 fa rg o nc a nd n or th w oo ds n c
- r es tro om s, s to ra ge , w in d w al ls a e\ _0 su rv ey c ad fi le s fa rg o\
5_ s_ ba se
_f ar go .d w ed it:
eb ro dm ar kl sa ve d:
9/
8/
:1
P M p lo t:9 /8
/2
4:
P
M
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD STAMPCONSULTANTS
321 4 5 6 7 8 9 10
Project Director
Revisions:
1 3 6 0 5 1 s t A v e . N . # 1 0 0 P l y m o u t h , M N 5 5 4 4 1 P 7 6 3 . 4 1 2 . 4 0 0 0 | F 7 6 3 . 4 1 2 . 4 0 9 0 | a e - m n . c o m Anderson Engineering of Minnesota, LLC | Proj#16315.1
RESTROOMS, STORAGE & WIND
WALLS
939.940-MM20-004
September 8, 2021
FARGO NATIONAL CEMETERY
8709 40TH AVENUE N. HARWOOD, ND 58042
BIDDING DOCUMENTS
09.08.2021
BIDDING DOCUMENTS
Date:
Mechanical Engineering, Electrical Engineering, Structural Engineering:
IMEG
623 26th Avenue Rock Island, IL 61201 (916)-817-4924 Matt Snyder / Todd Barrett
Cost Estimating:
OCMI
1722 Routh Street #900 Dallas, TX 75201 (469)-431-0571 Kyle Veater OF 22
EXISTING CONDITIONS
VF101
EJB KAA 2
6 7 8 9 10
EX.
PUMP
HOUSE
OVERHEAD WIRES
CULVERT
STORM SEWER
FENCE
POWER POLE
LIGHT POLE
CONTROL POINT
LEGEND
COMMUNICATION JUNCTION BOX
SOIL BORING
FOUND IRON MONUMENT
SET IRON PIPE WITH P.L.S. NO. 5364
COTTONWOOD
HACKBERRY
ASH
ELM
SPRUCE
DENOTES GRAVEL SURFACE
DENOTES BITUMINOUS SURFACE
CONIFEROUS TREE
DECIDUOUS TREE
1 COMMITTAL SHELTER AREA
1" = 10'
0 10' 20'
N
2 PUMP HOUSE AREA
1" = 10'
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Fi le
P at h:
y
:\1
\1 fa rg o nc a nd n or th w oo ds n c
- r es tro om s, s to ra ge , w in d w al ls a e\ _0 ci vi l\_ c ad fi le s\
_0 sh ee ts \1
.1 _x
_e xi st .d w eb ro dm ar kl d:
9/
8/
:1 lo t:9 /8
/2
4:
P
M
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD STAMPCONSULTANTS
321 4 5 6 7 8 9 10
Project Director
Revisions:
1 3 6 0 5 1 s t A v e . N . # 1 0 0 P l y m o u t h , M N 5 5 4 4 1 P 7 6 3 . 4 1 2 . 4 0 0 0 | F 7 6 3 . 4 1 2 . 4 0 9 0 | a e - m n . c o m Anderson Engineering of Minnesota, LLC | Proj#16315.1
RESTROOMS, STORAGE & WIND
WALLS
939.940-MM20-004
September 8, 2021
FARGO NATIONAL CEMETERY
8709 40TH AVENUE N. HARWOOD, ND 58042
BIDDING DOCUMENTS
09.08.2021
BIDDING DOCUMENTS
Date:
Mechanical Engineering, Electrical Engineering, Structural Engineering:
IMEG
623 26th Avenue Rock Island, IL 61201 (916)-817-4924 Matt Snyder / Todd Barrett
Cost Estimating:
OCMI
1722 Routh Street #900 Dallas, TX 75201 (469)-431-0571 Kyle Veater OF 22
0 10' 20'
N
REMOVE CURB
& GUTTER
KEY NOTES
REMOVE STORM SEWER. PROTECT EXISTING
COMMITTAL SHELTER STORM DRAINS.
PLUG HOLE IN STRUCTURE
REMOVE PLANTING BED
SALVAGE TRESS FOR RELOCATION
PROTECT EXISTING TREES. SEE DETAIL 6/LP501
PROTECT EXISTING SECTION MARKER
PROTECT EXISTING SIGN
PROTECT EXISTING PAVEMENT. CONTRACTOR
SHALL REPLACE IN KIND ANY DAMAGED
PAVEMENT AT NO COST TO THE GOVERNMENT
DEMOLITION PLAN
D-101
EJB KAA
REMOVE CONCRETE
PAVEMENT
SAW CUT PAVEMENT
REMOVE PAVEMENT
I HEREBY CERTIFY THAT THIS PLAN,
SPECIFICATION, OR REPORT, WAS
PREPARED BY ME OR UNDER MY
DIRECT SUPERVISION AND THAT I AM A
DULY LICENSED PROFESSIONAL
ENGINEER UNDER THE LAWS OF THE
STATE OF MINNESOTA
EDWIN J. BRODMARKLE, PE
DATE: 2021.09.08 LICENSE NO: 55409
STORAGE
EG 904.82
EG 905.40EG/RIM 905.14 EG 905.18
PG 905.60
PG 905.60
PG 905.10
PG 905.60
STORAGE
REST
ROOM
EXISTING
PUMP
HOUSE
TC/TBC 897.90
TC 898.00
TC 897.90
ME/TC 898.21
ME/TC 898.21
TC/TBC 897.99
TC 898.10
TC 898.10
TC 898.10
RIM 898.05
RIM 898.05
STORAGE
INV = 902.20
INV = 902.00
INV = 902.25
INV = 896.10
STORAGE
REST
ROOM
EXISTING
PUMP
HOUSE
INV = 895.70
FES
INV = 895.55
INV = 896.50
INV = 895.83
RIM 898.05
INV = 896.00
RIM 898.05
GRADING & UTILITY PLAN
CG101
LEGEND
PROPERTY LIMITS
EXISTING MINOR CONTOUR
EXISTING UNDERGROUND ELECTRIC
EXISTING WATERMAIN
EXISTING STORM SEWER
EXISTING MAJOR CONTOUR
PROPOSED MINOR CONTOUR
PROPOSED MAJOR CONTOUR
PROPOSED STORM SEWER
PROPOSED DRAINTILE
TOP OF CURB
TOP BACK OF CURB
MATCH EXISTING
PROPOSED GRADE
EXISTING GRADE
RIM ELEVATION
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Fi le
P at h:
y
:\1
\1 fa rg o nc a nd n or th w oo ds n c
- r es tro om s, s to ra ge , w in d w al ls a e\ _0 ci vi l\_ c ad fi le s\
_0 sh ee ts \1
.1 _c
_g ra d.
dw eb ro dm ar kl d:
9/ 8/
:2 lo t:9
/8 /2
4:
P M
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD STAMPCONSULTANTS
321 4 5 6 7 8 9 10
Project Director
Revisions:
1 3 6 0 5 1 s t A v e . N . # 1 0 0 P l y m o u t h , M N 5 5 4 4 1 P 7 6 3 . 4 1 2 . 4 0 0 0 | F 7 6 3 . 4 1 2 . 4 0 9 0 | a e - m n . c o m Anderson Engineering of Minnesota, LLC | Proj#16315.1
RESTROOMS, STORAGE & WIND
WALLS
939.940-MM20-004
September 8, 2021
FARGO NATIONAL CEMETERY
8709 40TH AVENUE N. HARWOOD, ND 58042
BIDDING DOCUMENTS
09.08.2021
BIDDING DOCUMENTS
Date:
Mechanical Engineering, Electrical Engineering, Structural Engineering:
IMEG
623 26th Avenue Rock Island, IL 61201 (916)-817-4924 Matt Snyder / Todd Barrett
Cost Estimating:
OCMI
1722 Routh Street #900 Dallas, TX 75201 (469)-431-0571 Kyle Veater OF 22
1 COMMITTAL SHELTER AREA - GRADING
1" = 10'
0 10' 20'
N
2 PUMP HOUSE AREA - GRADING
1" = 10'
0 10' 20'
N
TC
TBC
KEY NOTES
CONNECT TO COMMITTAL SHELTER ROOF DRAINS
CONNECT TO EX. STRUCTURE.
6" HDPE STORM DRAIN
6" HDPE PERFORATED DRAINTILE
CONNECT RESTROOMS & STORAGE ROOF DRAINS
6" AREA DRAIN
PROTECT EXISTING UTILITIES
PROTECT EXISTING SECTION MARKERS
PROTECT EXISTING SIGN
PROTECT EXISTING TREE (SEE DETAIL 6/LP101)
PROTECT EXISTING PAVEMENT. CONTRACTOR
SHALL REPLACE IN KIND ANY DAMAGED PAVEMENT
AT NO COST TO THE GOVERNMENT
ME
3 COMMITTAL SHELTER AREA - UTILITES
1" = 10'
0 10' 20'
N
0 10' 20'
N
4 PUMP HOUSE AREA - UTILITES
1" = 10'
6 5
PG
FFE=898.10
EG
RIM
9 10
10 10
I HEREBY CERTIFY THAT THIS PLAN,
SPECIFICATION, OR REPORT, WAS
PREPARED BY ME OR UNDER MY
DIRECT SUPERVISION AND THAT I AM A
DULY LICENSED PROFESSIONAL
ENGINEER UNDER THE LAWS OF THE
STATE OF MINNESOTA
REST
ROOM
EXISTING
PUMP
HOUSE
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Fi le
P at h:
y
:\1
\1 fa rg o nc a nd n or th w oo ds n c
- r es tro om s, s to ra ge , w in d w al ls a e\ _0 ci vi l\_ c ad fi le s\
_0 sh ee ts \1
.1 _c
_l ay ou t.d w eb ro dm ar kl d:
9/
8/
:1 lo t:9 /8
/2
4:
P
M
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD STAMPCONSULTANTS
321 4 5 6 7 8 9 10
Project Director
Revisions:
1 3 6 0 5 1 s t A v e . N . # 1 0 0 P l y m o u t h , M N 5 5 4 4 1 P 7 6 3 . 4 1 2 . 4 0 0 0 | F 7 6 3 . 4 1 2 . 4 0 9 0 | a e - m n . c o m Anderson Engineering of Minnesota, LLC | Proj#16315.1
RESTROOMS, STORAGE & WIND
WALLS
939.940-MM20-004
September 8, 2021
FARGO NATIONAL CEMETERY
8709 40TH AVENUE N. HARWOOD, ND 58042
BIDDING DOCUMENTS
09.08.2021
BIDDING DOCUMENTS
Date:
Mechanical Engineering, Electrical Engineering, Structural Engineering:
IMEG
623 26th Avenue Rock Island, IL 61201 (916)-817-4924 Matt Snyder / Todd Barrett
Cost Estimating:
OCMI
1722 Routh Street #900 Dallas, TX 75201 (469)-431-0571 Kyle Veater OF 22
1 COMMITTAL SHELTER AREA
1" = 10'
0 10' 20'
N
2 PUMP HOUSE AREA
1" = 10'
0 10' 20'
N
7.6'
24.0'
5.0'
RESTROOM & STORAGE BUILDING.
SEE SHEETS CS501, CS502, &
DETAIL 4/CS503
4.
5'
5.
9'
24.0'
24.0'
0.8'
KEY NOTES
NEW CONCRETE SIDEWALK (SEE DETAIL 3/CS503)
RESTROOM & STORAGE STRUCTURE (SEE CS501
& CS502)
NEW FLAT CURB WITH ADA RAMP AND DETECTABLE
WARNING PLATES (SEE DETAIL 1/CS503)
ADD ALTERNATE 1 WIND WALL & STORAGE CABINET. SEE
STRUCTURAL & ARCHITECTURAL.
PROTECT EXISTING TREES. SEE DETAIL 6/LP501
PROTECT EXISTING UTILITIES
PROTECT EXISTING SIGNAGE
PROTECT EXISTING SECTION MARKER
PROTECT EXISTING PAVEMENT. CONTRACTOR SHALL
REPLACE IN KIND ANY DAMAGED PAVEMENT AT NO COST
TO THE GOVERNMENT
LEGEND
PROPERTY LIMITS
NEW FLAT CURB
NEW CONCRETE SIDEWALK
EXISTING ASPHALT PAVEMENT
SITE PLAN
CS101
EJB KAA
I HEREBY CERTIFY THAT THIS PLAN,
SPECIFICATION, OR REPORT, WAS
PREPARED BY ME OR UNDER MY
DIRECT SUPERVISION AND THAT I AM A
DULY LICENSED PROFESSIONAL
ENGINEER UNDER THE LAWS OF THE
STATE OF MINNESOTA
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Fi le
P at h:
y
:\1
\1 fa rg o nc a nd n or th w oo ds n c
- r es tro om s, s to ra ge , w in d w al ls a e\ _0 ci vi l\_ c ad fi le s\
_0 sh ee ts \1
.1 _x
_s w pp p.
dw eb ro dm ar kl d:
9/
8/
:2 lo t:9 /8
/2
4:
P
M
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD STAMPCONSULTANTS
321 4 5 6 7 8 9 10
Project Director
Revisions:
1 3 6 0 5 1 s t A v e . N . # 1 0 0 P l y m o u t h , M N 5 5 4 4 1 P 7 6 3 . 4 1 2 . 4 0 0 0 | F 7 6 3 . 4 1 2 . 4 0 9 0 | a e - m n . c o m Anderson Engineering of Minnesota, LLC | Proj#16315.1
RESTROOMS, STORAGE & WIND
WALLS
939.940-MM20-004
September 8, 2021
FARGO NATIONAL CEMETERY
8709 40TH AVENUE N. HARWOOD, ND 58042
BIDDING DOCUMENTS
09.08.2021
BIDDING DOCUMENTS
Date:
Mechanical Engineering, Electrical Engineering, Structural Engineering:
IMEG
623 26th Avenue Rock Island, IL 61201 (916)-817-4924 Matt Snyder / Todd Barrett
Cost Estimating:
OCMI
1722 Routh Street #900 Dallas, TX 75201 (469)-431-0571 Kyle Veater OF 22
SWPPP
CG102
EJB KAA
ORGANIZATION CONTACT NAME PHONE
NATIONAL CEMETERY ADMINISTRATION (OWNER)
ANDERSON ENGINEERING (SWPPP DESIGN) ERIK HEADMAN 763-412-4000
(GENERAL CONTRACTOR)
*CERTIFIED FOR DESIGN OF CONSTRUCTION SWPPP BY UNIVERSITY OF MINNESOTA, EXPIRES 5/31/19
ACREAGE SUMMARY
AREA ACRES
PROPERTY AREA 4.81
DISTURBED AREA 0.14
IMPERVIOUS AREA PRE-CONSTRUCTION 0.52
IMPERVIOUS AREA POST-CONSTRUCTION 0.52
NEW IMPERVIOUS AREA 0
PERVIOUS AREA AT COMPLETION 4.34
RECEIVING WATERS
NAME OF WATER BODY
TYPE
(LAKE, RIVER,
WETLAND,
DITCH, ETC)
LISTED ON THE
TMDL LIST?
(YES OR NO)
LISTED ON THE
303(d) LIST?
(YES OR NO)
APPROVED
TMDL
SHEYENNE RIVER RIVER NO NO N/A
PROJECT DESCRIPTION/LOCATION
PROJECT IS LOCATED IN THE CITY OF HARWOOD, ND IN CASS COUNTY, WITHIN THE REGION BOUNDED BY 40TH AVENUE N, 93RD STREET N, 81ST STREET N, AND 31ST STREET SE. LATITUDE 46.935690 LONGITUDE -96.934945.
THE SITE ENCOMPASSES 4.8 ACRES.
THE PLANNED SCOPE OF THE PROJECT INCLUDES:
· THE INSTALLATION OF EROSION CONTROL MEASURES AS REQUIRED FOR THE MASS GRADING OF
THE SITE FOR THE INSTALLATION THE NEW RESTROOM AND STORAGE BUILDING.
· GRADING AS REQUIRED FOR THE INSTALLATION OF THE STRUCTURES.
· INSTALLATION OF STORM SEWER.
· PLACEMENT OF CONCRETE AS REQUIRED TO ESTABLISH CURB, GUTTER, AND SIDEWALKS
THROUGHOUT THE SITE.
RECEIVING WATERS
THESE WATERS ARE LOCATED WITHIN ON MILE (AERIAL RADIUS) OF THE PROJECT LIMITS AND RECEIVE RUNOFF FROM THE PROJECT SITE. DUE TO THE PROXIMITY OF THE RECEIVING WATERS. THE BMPS DESCRIBED
IN APPENDIX A OF THE NDPDES PERMIT MAY APPLY TO ALL AREAS OF THE SITE.
- STABILIZATION OF ALL EXPOSED SOIL AREAS MUST BE INITIATED IMMEDIATELY TO LIMIT SOIL EROSION BUT IN NO CASE COMPLETED LATER THAN SEVEN (7) DAYS AFTER THE CONSTRUCTION ACTIVITY IN THAT
PORTION OF THE SITE HAS TEMPORARILY OR PERMANENTLY CEASED.
SOIL TYPES
SOIL TYPES TYPICALLY FOUND ON THIS PROJECT ARE PRIMARILY CH (FAT CLAY). SOME AREAS CONTAINED SOIL TYPE SC (CLAYEY SAND) ROUGHLY 12-15 BELOW GRADE. SOIL BORINGS WERE TAKEN BY TTL IN NOVEMBER OF 2015 AND BY BRAUN-INTERTEC IN NOVEMBER 2017. BRAUN-INTERTEC REPORT IS TO BE KEPT
ON SITE AS PART OF THE SWPPP AND IS TO BE MADE AVAILABLE UPON REQUEST.
PROJECT PERSONNEL AND TRAINING
THIS SWPPP WAS PREPARED BY PERSONNEL THAT ARE VERIFIED IN THE DESIGN OF CONSTRUCTION SWPPPS.
COPIES OF THE CERTIFICATIONS ARE ON FILE WITH THE ENGINEER.
PROVIDE A CERTIFIED EROSION CONTROL SUPERVISOR IN GOOD STANDING WHO IS KNOWLEDGEABLE AND EXPERIENCED IN THE APPLICATION OF EROSION PREVENTION AND SEDIMENT CONTROL BEST MANAGEMENT PRACTICES. THE EROSION CONTROL SUPERVISOR WILL WORK WITH THE PROJECT ENGINEER TO OVERSEE THE IMPLEMENTATION OF THE SWPPP AND THE INSTALLATION, INSPECTION, AND MAINTENANCE OF THE EROSION PREVENTION AND SEDIMENT CONTROL BMPS BEFORE, DURING, AND AFTER CONSTRUCTION UNTIL THE NOTICE OF TERMINATION (NOT) HAS BEEN FILED WITH THE NDDH. PROVIDE PROOF OF CERTIFICATION AT
THE PRECONSTRUCTION MEETING. WORK WILL NOT BE ALLOWED TO COMMENCE UNTIL PROOF OF
CERTIFICATION HAS BEEN PROVIDED TO THE PROJECT ENGINEER.
PROVIDE AT LEAST ONE CERTIFIED INSTALLER FOR EACH CONTRACTOR OR SUBCONTRACTOR THAT INSTALLS THE PRODUCTS LISTED IN SPECIFICATION SECTION 2573.3.A.2 PROVIDE PROOF OF CERTIFICATION AT THE PRECONSTRUCTION MEETING. WORK WILL NOT BE ALLOWED TO COMMENCE UNTIL PROOF OF CERTIFICATION
HAS BEEN PROVIDED TO THE PROJECT ENGINEER.
CHAIN OF RESPONSIBILITY
THE OWNER AND CONTRACTOR ARE CO-PERMITTEES FOR THE NORTH DAKOTA POLLUTANT DISCHARGE ELIMINATION SYSTEM (NDPDES) CONSTRUCTION PERMIT. THE CONTRACTOR IS RESPONSIBLE TO COMPLY WITH ALL ASPECTS OF THE NDPDES CONSTRUCTION PERMIT AT ALL TIMES UNTIL THE NOTICE OF TERMINATION (NOT) HAS BEEN FILED WITH THE NDDH THE CONTRACTOR WILL DEVELOP A CHAIN OF COMMAND WITH ALL OPERATORS ON THE SITE TO ENSURE THAT THE SWPPP WILL BE IMPLEMENTED AND STAY IN EFFECT UNTIL THE CONSTRUCTION PROJECT IS COMPLETE, THE ENTIRE SITE HAS UNDERGONE FINAL STABILIZATION, AND A
NOTICE OF TERMINATION (NOT) HAS BEEN SUBMITTED TO THE NDDH.
PROJECT CONTACTS
THE CONTRACTOR IS RESPONSIBLE FOR IMPLEMENTATION OF THE SWPPP AND INSTALLATION, INSPECTION, AND MAINTENANCE OF THE EROSION PREVENTION AND SEDIMENT CONTROL BMPS BEFORE, DURING, AND
AFTER CONSTRUCTION UNTIL THE NOTICE OF TERMINATION (NOT) HAS BEEN FILED.
NDDH 24 HOUR EMERGENCY NOTIFICATION:
800-472-2121
SITE INSPECTION AND MAINTENANCE
CONTRACTOR SHALL PROVIDE NAME, CONTACT INFO, AND TRAINING DOCUMENTATION FOR THE PERSON
RESPONSIBLE FOR SWPPP IMPLEMENTATION AND INSPECTION/MAINTENANCE OF BMPS.
INSPECT THE ENTIRE CONSTRUCTION SITE A MINIMUM OF ONCE EVERY SEVEN DAYS DURING ACTIVE CONSTRUCTION AND WITHIN 24 HOURS AFTER A RAINFALL EVENT GREATER THAN 0.5 INCHES IN 24 HOURS.
INSPECT ALL TEMPORARY AND PERMANENT WATER QUALITY MANAGEMENT, EROSION PREVENTION AND SEDIMENT CONTROL BMPS UNTIL THE SITE HAS UNDERGONE FINAL STABILIZATION AND THE NOT HAS BEEN SUBMITTED. INSPECT SURFACE WATER INCLUDING DRAINAGE DITCHES FOR SIGNS OF EROSION AND SEDIMENT DEPOSITION. INSPECT CONSTRUCTION SITE VEHICLE EXIT LOCATIONS FOR EVIDENCE OF TRACKING ONTO PAVED SURFACES. INSPECT SURROUNDING PROPERTIES FOR EVIDENCE OF OFF SITE SEDIMENT
ACCUMULATION.
RECORD ALL INSPECTIONS AND MAINTENANCE ACTIVITIES IN WRITING WITHIN 24 HOURS. SUBMIT INSPECTION REPORTS IN A FORMAT THAT IS ACCEPTABLE TO THE PROJECT ENGINEER. INCLUDE THE FOLLOWING IN THE
RECORDS OF EACH INSPECTION AND MAINTENANCE ACTIVITY:
A. DATE AND TIME OF INSPECTIONS
B. NAME OF PERSONS CONDUCTION INSPECTIONS
C. FINDINGS OF INSPECTIONS, INCLUDING RECOMMENDATIONS FOR CORRECTIVE ACTIONS
D. CORRECTIVE ACTION TAKEN, INCLUDING DATES, TIMES, AND PARTY COMPLETING MAINTENANCE
ACTIVITIES
E. DATE AND AMOUNT OF ALL RAINFALL EVENTS GREATER THAN 0.5 INCH IN 24 HOURS
F. DOCUMENTS AND CHANGES MADE TO THE SWPPP
REPLACE, REPAIR OR SUPPLEMENT ALL NONFUNCTIONAL BMPS BY THE END OF THE NEXT BUSINESS DAY
FOLLOWING DISCOVERY UNLESS LISTED DIFFERENTLY BELOW:
A. REPAIR, REPLACE, OR SUPPLEMENT PERIMETER CONTROL DEVICES WHEN IT BECOMES
NONFUNCTIONAL OR SEDIMENT REACHES 12 THE HEIGHT OF THE DEVICE. COMPLETE REPAIRS BY
THE END OF THE NEXT BUSINESS DAY FOLLOWING DISCOVERY.
B. REPAIR OR REPLACE INLET PROTECTION DEVICES WHEN THEY BECOME NONFUNCTIONAL OR
SEDIMENT REACHES 12 THE HEIGHT AND/OR DEPTH OF THE DEVICE.
C. DRAIN AND REMOVE SEDIMENT FROM TEMPORARY AND PERMANENT SEDIMENT BASINS ONCE THE
SEDIMENT HAS REACHED 12 THE STORAGE VOLUME. COMPLETE WORK WITHIN 72 HOURS OF
DISCOVERY.
D. REMOVE ALL DELTAS AND SEDIMENT DEPOSITED IN SURFACE WATER INCLUDING DRAINAGE WAYS, CATCH BASINS, AND OTHER DRAINAGE SYSTEMS. RE-STABILIZED ANY AREA THAT ARE DISTURBED BY SEDIMENT REMOVAL OPERATION. SEDIMENT REMOVAL AND STABILIZATION MUST BE COMPLETED WITHIN 7 DAYS OF DISCOVERY. PREPARE AND SUBMIT A SITE MANAGEMENT PLAN FOR WORKING IN
SURFACE WATERS.
E. REMOVE TRACKED SEDIMENT FROM PAVED SURFACES BOTH ON AND OFF SITE WITHIN 24 HOURS OF DISCOVERY. STREET SWEEPING MAY HAVE TO OCCUR MORE OFTEN TO MINIMIZE OFF SITE IMPACTS.
LIGHTLY WET THE PAVEMENT PRIOR TO SWEEPING
F. MAINTAIN ALL BMPS UNTIL WORK HAS BEEN COMPLETED, SITE HAS GONE UNDER FINAL
STABILIZATION, AND THE NOTICE OF TERMINATION (NOT) HAS BEEN SUBMITTED TO THE NDDH.
SPECIAL SITE NOTES
NONE
THE SWPPP COORDINATOR MUST BE AVAILABLE FOR AN ONSITE INSPECTION WITHIN 72 HOURS UPON
REQUEST BY THE NDDH AND SHALL BE RESPONSIBLE FOR THE FOLLOWING:
· SUBMIT THE NPDES PERMIT APPLICATION AND COMPLY WITH ALL REQUIREMENTS
· IMPLEMENT THE SWPPP.
· OVERSEE INSTALLATION AND MAINTENANCE PRACTICES AND REPAIRS IDENTIFIED IN THE SWPPP.
· IMPLEMENT AND OVERSEE EMPLOYEE TRAINING AND RECORD IN OR WITH THE SWPPP.
· CONDUCT OR PROVIDE FOR INSPECTION AND MONITORING ACTIVITIES AND MAINTAIN LOGS AS
PERMIT REQUIRES.
· IDENTIFY OTHER POTENTIAL POLLUTANT SOURCES NOT LISTED IN THE SWPPP AND ADD THEM.
· IDENTIFY ANY DEFICIENCIES IN THE SWPPP AND CORRECT THEM.
· ENSURE THAT CHANGES TO CONSTRUCTION PLANS ARE ADDRESSED IN THE SWPPP.
· FILE THE NOTICE OF TERMINATION UPON PROJECT COMPLETION.
AFTER THE NOTICE OF TERMINATION HAS BEEN FILED, THE OWNER SHALL BE RESPONSIBLE FOR ASSIGNING
RESPONSIBILITY FOR PERMANENT MAINTENANCE MEASURES.
LOCATION OF SWPPP REQUIREMENTS
THE REQUIRED SWPPP ELEMENTS MAY BE LOCATED IN MANY PLACES WITHIN THE PLAN SET.
STABILIZATION TIME FRAMES
ALL AREAS DISTURBED BY CONSTRUCTION WILL RECEIVE SEED AND MULCH OR SOD ACCORDING TO THE PLANS AND SPECIFICATIONS AND WITHIN THE SPECIFIED VEGETATIVE TIME SCHEDULE. FINAL STABILIZATION WILL OCCUR WHEN THE SITE HAS A UNIFORM VEGETATIVE COVER WITH A DENSITY OF 70% OVER THE ENTIRE DISTURBED AREA. ALL TEMPORARY SYNTHETIC EROSION PREVENTION AND SEDIMENT CONTROL BMPS MUST BE REMOVED AS PART OF THE SITE FINAL STABILIZATION. ALL SEDIMENT MUST BE CLEANED OUT OF CONVEYANCES
AND TEMPORARY SEDIMENTATION BASINS IF APPLICABLE.
1. INITIATE INLET STABILIZATION IMMEDIATELY WHEN CONSTRUCTION HAS TEMPORARILY OR PERMANENTLY CEASED ON ANY PORTION OF THE SITE. COMPLETE STABILIZATION WITHIN THE TIME FRAME LISTED. IN MANY INSTANCES THIS WILL REQUIRE STABILIZATION TO OCCUR MORE THAN ONCE DURING THE COURSE OF THE PROJECT. TEMPORARY SOIL STOCKPILES WITHOUT SIGNIFICANT CLAY OR SILT AND STOCKPILED AND CONSTRUCTED ROAD BASE ARE NOT APPROPRIATE AND THEREFORE EXEMPT FROM THE STABILIZATION
REQUIREMENT.
2. APPLICATION OF MULCH, HYDROMULCH, TACKIFIER AND POLYACRYLAMIDE ARE NOT ACCEPTABLE
STABILIZATION METHODS IN THESE AREAS.
3. STABILIZE ALL AREAS OF THE SITE PRIOR TO THE ONSET OF WINTER, ANY WORK STILL BEING PERFORMED WILL BE SNOW MULCHED, SEEDED, AND BLANKETED WITHIN THE TIME FRAMES IN THE NPDES PERMIT.
4. TOPSOIL BERMS MUST BE STABILIZED IN ORDER TO BE CONSIDERED PERIMETER CONTROL BMPS. USE RAPID
STABILIZATION METHOD 1, 2, OR 3 AS DIRECTED BY THE ENGINEER.
5. THE SEED MIX USED IN THE RAPID STABILIZATION IS AS FOLLOWS:
ND DOT MIX CLASS IV (TEMPORARY COVER)
WINTER WHEAT 50# / ACRE
6. KEEP DITCHES AND EXPOSED SOILS IN AN EVEN ROUGH GRADED CONDITION IN ORDER TO BE ABLE TO APPLY
EROSION CONTROL MULCHES, HYDROMULCHES AND BLANKETS.
GENERAL SWPPP NOTES FOR CONSTRUCTION ACTIVITY
1. CONTRACTOR SHALL AMEND THE SWPPP AND DOCUMENT ANY AND ALL CHANGES TO THE SWPPP AND ASSOCIATED PLAN SHEETS IN A TIMELY MANNER. STORE THE SWPPP AND ALL AMENDMENTS ON SITE AT ALL
TIMES.
2. PREPARE AND SUBMIT A SITE MANAGEMENT PLAN FOR THE ENGINEER'S ACCEPTANCE FOR CONCRETE MANAGEMENT, CONCRETE SLURRY APPLICATION AREAS, WORK IN AND NEAR AREAS OF ENVIRONMENTAL SENSITIVITY, AREAS IDENTIFIED IN THE PLANS AS "SITE MANAGEMENT PLAN AREA", ANY WORK THAT WILL REQUIRE DE-WATERING, AND AS REQUESTED BY THE ENGINEER. SUBMIT ALL SITE MANAGEMENT PLANS TO THE ENGINEER IN WRITING. ALLOW ALL MINIMUM OF 7 DAYS FOR THE ENGINEER TO REVIEW AND ACCEPT SITE MANAGEMENT PLAN SUBMITTALS. WORK WILL NOT BE ALLOWED TO COMMENCE IF A SITE MANAGEMENT PLAN IS REQUIRED UNTIL ACCEPTANCE HAS BEEN GRANTED BY THE ENGINEER. THERE WILL BE NO EXTRA TIME
ADDED TO THE CONTRACT DUE TO THE UNTIMELY SUBMITTAL.
3. IT IS THE DESIGNER'S INTENT THAT THE CONTRACTOR BUILD PONDS AND INSTALL EROSION CONTROL BMPS
BEFORE PUTTING THEM INTO ACTIVE SERVICE TO THE MAXIMUM EXTENT PRACTICABLE.
4. BURNING OF ANY MATERIAL IS NOT ALLOWED WITHIN PROJECT BOUNDARY.
5. DO NOT DISTURB AREAS OUTSIDE OF THE CONSTRUCTION LIMITS. DELINEATE AREAS NOT TO BE DISTURBED PRIOR TO STARTING GROUND DISTURBING ACTIVITIES. IF IT BECOMES NECESSARY TO DISTURBED AREAS OUTSIDE OF THE CONSTRUCTION LIMITS OBTAIN WRITTEN PERMISSION FROM THE PROJECT ENGINEER PRIOR
TO PROCEEDING. PRESERVE ALL NATURAL BUFFERS SHOWN ON THE PLANS.
6. ROUT STORMWATER AROUND UNSTABILIZED AREAS OF THE SITE WHENEVER FEASIBLE. PROVIDE EROSION CONTROL AND VELOCITY DISSIPATION DEVICES AS NEEDED TO KEEP CHANNELS FROM ERODING AND TO
PREVENT NUISANCE CONDITIONS AT THE OUTLET.
7. DIRECT DISCHARGES FROM BMPS TO VEGETATED AREA WHENEVER FEASIBLE. PROVIDE VELOCITY
DISSIPATION DEVICES AS NEEDED TO PREVENT EROSION.
8. THE EROSION PREVENTION AND SEDIMENT CONTROL BMPS SHALL BE PLACED AS NECESSARY TO MINIMIZE EROSION FROM DISTURBED SURFACES AND TO CAPTURE SEDIMENT ON SITE. ALL EROSION CONTROL MEASURES SHALL BE IN PLACE PRIOR TO COMMENCEMENT OF ANY REMOVAL WORK AND/OR GROUND
DISTURBING ACTIVITIES COMMENCE.
9. ESTABLISH SEDIMENT CONTROL DEVICES ON ALL DOWN GRADIENT PERIMETERS AND UP GRADIENT OF ANY BUFFER ZONES BEFORE AND UP GRADIENT LAND DISTURBING ACTIVITIES BEGIN. MAINTAIN SEDIMENT
CONTROL DEVICES UNTIL CONSTRUCTION IS COMPLETE AND THE SITE IS STABILIZED.
10. LOCATE PERIMETER CONTROL ON THE CONTOUR TO CAPTURE OVERLAND, LOW-VELOCITY SHEET FLOWS DOWN GRADIENT OF ALL EXPOSED SOILS AND PRIOR TO DISCHARGING TO SURFACE WATERS. PLACE
J-HOOKS AT A MAXIMUM OF 100 FOOT INTERVALS.
11. PROVIDE PERIMETER CONTROL AROUND ALL STOCKPILES. PLACE BMP A MINIMUM 5 FEET FROM THE TOE OF SLOPE WHERE FEASIBLE. DO NOT PLACE STOCKPILES IN NATURAL BUFFER AREAS, SURFACE WATERS OR
STORMWATER CONVEYANCES.
12. FLOATING SILT CURTAIN IS ALLOWED AS PERIMETER CONTROL FOR IN WATER WORK ONLY. INSTALL THE FLOATING SILT CURTAIN AS CLOSE TO SHORE AS POSSIBLE. PLACE PERIMETER CONTROL BMP ON LAND
IMMEDIATELY AFTER THE IN WATER WORK IS COMPLETED.
13. DITCH CHECKS WILL BE PLACED AS INDICATED ON THE PLANS DURING ALL PHASES OF CONSTRUCTION.
14. PLACE CONSTRUCTION EXITS, AS NECESSARY, TO PREVENT TRACKING OF SEDIMENT ONTO PAVED SURFACES BOTH ON AND OFF THE PROJECT SITE. PROVIDE CONSTRUCTION EXITS OF SUFFICIENT SIZE TO PREVENT TRACK OUT. MAINTAIN CONSTRUCTION EXITS WHEN EVIDENCE OF TRACKING IS DISCOVERED.
REGULAR STREET SWEEPING IS NOT AN ACCEPTABLE ALTERNATIVE TO PROPER CONSTRUCTION EXIT
INSTALLATION AND MAINTENANCE. CONSTRICTION EXITS ARE INCIDENTAL.
GENERAL SWPPP NOTES FOR CONSTRUCTION ACTIVITY (CONT.)
15. DISCHARGE TURBID OR SEDIMENT LADEN WATER TO TEMPORARY SEDIMENT BASINS WHENEVER FEASIBLE. IN THE EVENT THAT IT IS NOT FEASIBLE TO DISCHARGE THE SEDIMENT LADEN WATER TO A TEMPORARY SEDIMENT BASIN, THE WATER MUST BE TREATED SO THAT IT DOES NOT CAUSE A NUISANCE CONDITION IN THE RECEIVING WATERS OR TO DOWNSTREAM LANDOWNERS. CLEAN OUT ALL PERMANENT STORMWATER BASINS REGARDLESS OF WHETHER USED AS TEMPORARY SEDIMENT BASINS OR TEMPORARY SEDIMENT TRAPS TO THE DESIGN CAPACITY AFTER ALL UP GRADIENT LAND DISTURBING ACTIVITY IS COMPLETED.
16. PROVIDE SCOUR PROTECTION AT ANY OUTFALL OF DE-WATERING ACTIVITIES.
17. PROVIDE STABILIZATION IN ANY TRENCHES CUT FOR DE-WATERING OR SITE DRAINING PURPOSES.
POLLUTION PREVENTION
1. PROVIDE A SPILL KIT AT EACH WORK LOCATION ON THE SITE.
2. STORE ALL BUILDING MATERIALS THAT HAVE THE POTENTIAL TO LEACH POLLUTANTS, PESTICIDES, HERBICIDES, INSECTICIDES. FERTILIZERS, TREATMENT CHEMICALS, AND LANDSCAPE MATERIALS UNDER
COVER WITH SECONDARY CONTAINMENT.
3. PROVIDE A SECURE STORAGE AREA WITH RESTRICTED ACCESS FOR ALL HAZARDOUS MATERIALS AND TOXIC WASTE. RETURN ALL HAZARDOUS MATERIALS AND TOXIC WASTE TO THE DESIGNATED STORAGE AREA AT THE END OF THE BUSINESS DAY UNLESS INFEASIBLE. STORE ALL HAZARDOUS MATERIALS AND TOXIC WASTE (INCLUDING BUT NOT LIMITED TO OIL, DIESEL FUEL, GASOLINE, HYDRAULIC FLUIDS, PAINT, PETROLEUM BASED PRODUCTS, WOOD PRESERVATIVES, ADDITIVES, CURING COMPOUNDS, AND ACIDS) IN SEALED CONTAINERS
WITH SECONDARY CONTAINMENT. CLEAN UP SPILLS IMMEDIATELY.
4. STORE, COLLECT AND DISPOSE OF ALL SOLID WASTE.
5. POSITION ALL PORTABLE TOILETS SO THAT THEY ARE SECURE AND CANNOT BE TIPPED OR KNOCKED OVER.
PROPERLY DISPOSE OF ALL SANITARY WASTE.
6. FUEL AND MAINTAIN VEHICLES IN A DESIGNATED CONTAINED AREA WHENEVER FEASIBLE. USE DRIP PANS OR ABSORBENT MATERIALS TO PREVENT SPILLS OR LEAKED CHEMICALS FORM DISCHARGING TO SURFACE WATER OR STORMWATER CONVEYANCES. PROVIDE A SPILL KIT AT EACH LOCATION THAT VEHICLES AND
EQUIPMENT ARE FUELED OR MAINTAINED AT.
7. LIMIT VEHICLE AND EQUIPMENT WASHING TO A DEFINED AREA OF THE SITE. CONTAIN RUNOFF FROM THE WASHING AREA TO A TEMPORARY SEDIMENT BASIN OR OTHER EFFECTIVE CONTROL. PROPERLY DISPOSE OF ALL WASTE GENERATED BY VEHICLE AND EQUIPMENT WASHING. ENGINE DEGREASING IS NOT ALLOWED ON
THE SITE.
8. PROVIDE EFFECTIVE CONTAINMENT FOR ALL LIQUID AND SOLID WASTES GENERATED BY WASHOUT OF CONCRETE, STUCCO, PAINT, FORM RELEASE OILS, CURING COMPOUNDS AND OTHER CONSTRUCTION MATERIALS. LIQUID AND SOLID WASHOUT WASTES MUST NOT CONTACT THE GROUND. DESIGN THE
CONTAINMENT SO THAT IT DOES NOT RESULT IN RUNOFF FROM THE WASHOUT OPERATIONS OR
CONTAINMENT AREA.
9. CREATE AND FOLLOW A WRITTEN DISPOSAL PLAN FOR ALL WASTE MATERIALS. INCLUDE IN THE PLAN HOW THE MATERIAL WILL BE DISPOSED OF AND THE LOCATION OF THE DISPOSAL SITE. SUBMIT PLAN TO THE
ENGINEER.
10. USE METHODS AND OPERATIONAL PROCEDURES THAT PREVENT DISCHARGE OR PLACEMENT OF BITUMINOUS GRINDINGS, CUTTING, MILLINGS, AND OTHER BITUMINOUS WASTES FROM AREAS OF EXISTING OR FUTURE VEGETATED SOILS AND FROM ALL WATER CONVEYANCE SYSTEMS, INCLUDING INLETS, DITCHES AND CURB
FLOW LINES.
11. USE METHODS AND OPERATIONAL PROCEDURES THAT PREVENT CONCRETE DUST, PARTICLES, CONCRETE WASH OUT, AND OTHER CONCRETE WASTES FROM LEAVING SITE, DEPOSITING IN EXISTING OR FUTURE VEGETATED AREAS, AND FROM ENTERING STORMWATER CONVEYANCE SYSTEMS, INCLUDING INLETS, DITCHES AND CURB FLOW LINES. USE METHODS AND OPERATIONAL PROCEDURES THAT PREVENT SAW CUT SLURRY AND PLANING WASTE FROM LEAVING SITE AND FROM ENTERING STORMWATER CONVEYANCE
SYSTEMS INCLUDING DITCHES AND CULVERTS.
PERMITS
THE FOLLOWING PERMITS APPLY TO THIS PROJECT:
NOTE: IF THE 25' BUFFERS ARE MAINTAINED FROM THE WETLANDS, ADDITIONAL PERMITS WILL NOT BE REQUIRED.
SITE DATA (TOTAL SITE)
· AREA OF DISTURBANCE = 0.14 AC
· SEEDED AREA (PER LANDSCAPE PLAN, EST.) = .016 AC
· EROSION CONTROL QUANTITIES (ESTIMATED) :
STORM DRAIN INLET PROTECTION = 3 INLETS TO BE PROTECTED
RECORD RETENTION
THE SWPPP, ALL CHANGES TO IT AND INSPECTION AND MAINTENANCE RECORDS MUST BE KEPT ON-SITE DURING CONSTRUCTION. THE OWNER MUST RETAIN A COPY OF THE SWPPP ALONG WITH THE FOLLOWING RECORDS FOR THREE
(3) YEARS AFTER SUBMITTAL OF THE NOTICE OF TERMINATION (NOT).
1. ANY OTHER PERMITS REQUIRED FOR THE PROJECT.
2. RECORDS OF ALL INSPECTION AND MAINTENANCE CONDUCTED DURING CONSTRUCTION
3. ALL PERMANENT OPERATIONS AND MAINTENANCE AGREEMENT THAT HAVE BEEN IMPLEMENTED INCLUDING ALL RIGHT OF WAY, CONTRACTS, COVENANTS AND OTHER BINDING REQUIREMENTS REGARDING PERPETUAL
MAINTENANCE; AND
4. ALL REQUIRED CALCULATIONS FOR DESIGN OF THE TEMPORARY AND PERMANENT STORMWATER
MANAGEMENT SYSTEMS.
AREA TIME FRAME NOTES
LAST 200 LINEAL FEET OF DRAINAGE DITCH OR SWALE WITHIN 24 HOURS OF CONNECTION TO
SURFACE WATER OR PROPERTY EDGE
1, 2, 3
REMAINING PORTIONS OF DRAINAGE DITCH OR SWALE 7 DAYS 1, 3
PIPE AND CULVERT OUTLETS 24 HOURS
STOCKPILES 7 DAYS 1
CALL 48 HOURS
BEFORE DIGGING:
DIAL 811
STORMWATER POLLUTION & PREVENTION PLAN (SHEET
CG102 - SWPPP) SHALL ACCOMPANY CG101 - GRADING &
UTILITY PLAN
AGENCY TYPE OF PERMIT PERMIT # AND DATES
NORTH DAKOTA DEPARTMENT
OF HEALTH (NDDH)
NDPDES CONSTRUCTION
PERMIT
RAYMOND TOWNSHIP BUILDING PERMIT
PROJECT SITE
SHEYENNE RIVER
MAPLE RIVER
1-MILE RADIUS
AROUND PROJECT
40TH AVE N
I-29
C O
R D
RAPID STABILIZATION
METHOD MATERIALS
1 TYPE 3 MULCH (1.5 TON / ACRE), STABILIZED FIBER MATRIX (750# / ACRE)
STABILIZED FIBER MATRIX (330# / 1,000 GAL), ND DOT MIX CLASS IV (10# / 1,000 GAL), SLOW RELEASE
FERTILIZER 10-10-10 (50# / 1,000 GAL), WATER (875 GAL / 1,000 GAL). APPLY SLURRY MIX AT 6,000 GAL / ACRE.
CATEGORY 3 EROSION CONTROL BLANKET, ND DOT MIX CLASS IV (2# / 100 SY), SLOW RELEASE FERTILIZER
10-10-10 (8# / 100 SY)
I HEREBY CERTIFY THAT THIS PLAN,
SPECIFICATION, OR REPORT, WAS
PREPARED BY ME OR UNDER MY
DIRECT SUPERVISION AND THAT I AM A
DULY LICENSED PROFESSIONAL
ENGINEER UNDER THE LAWS OF THE
STATE OF MINNESOTA
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Fi le
P at h:
y
:\1
\1 fa rg o nc a nd n or th w oo ds n c
- r es tro om s, s to ra ge , w in d w al ls a e\ _0 ci vi l\_ c ad fi le s\
_0 sh ee ts \1
.1 _x
_d et ai l.d w cn el so n d:
7/
9/
1:
A lo t:7 /9
/2
2:
P
M
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD STAMPCONSULTANTS
321 4 5 6 7 8 9 10
Project Director
Revisions:
1 3 6 0 5 1 s t A v e . N . # 1 0 0 P l y m o u t h , M N 5 5 4 4 1 P 7 6 3 . 4 1 2 . 4 0 0 0 | F 7 6 3 . 4 1 2 . 4 0 9 0 | a e - m n . c o m Anderson Engineering of Minnesota, LLC | Proj#16315.1
RESTROOMS, STORAGE & WIND
WALLS
939.940-MM20-004
FARGO NATIONAL CEMETERY
8709 40TH AVENUE N. HARWOOD, ND 58042
CONSTRUCTION
DOCUMENTS
Date:
Mechanical Engineering, Electrical Engineering, Structural Engineering:
IMEG
623 26th Avenue Rock Island, IL 61201 (916)-817-4924 Matt Snyder / Todd Barrett
Cost Estimating:
OCMI
1722 Routh Street #900 Dallas, TX 75201 (469)-431-0571 Kyle Veater
RESTROOM STORAGE
BUILDING DETAILS
CS-501
EJB KAA
N CONSTRUCTION DOCUMENTS
STORAGE
NORTH ELEVATION
EAST ELEVATION
SOUTH ELEVATION
WEST ELEVATION
FLOOR PLAN
0 4' 8'2' 0 4' 8'2'
0 4' 8'2'
0 4' 8'2'
0 4' 8'2'
102.1
102.2
OPENING SCHEDULE
ASSOCIATED ROOMS PANEL INFORMATION FRAME INFORMATION
H D
W G
R O
U P
F
IR
E L
A B
E L
(M
IN
G A
S K
E T
E
LE
C T
R
IC
A L
S L
A B
E L
COMMENTSFROM ROOM NAME TO ROOM NAME NUMBER WIDTH HEIGHT
PANEL
TYPE
2ND
PANEL
TYPE
PANEL
GLAZING FRAME TYPE
FRAME
GLAZING
NONE NONE - - - -
DOOR SIZE
RESTROOM - 101 3'-0" 6'-8" HM - HM 15
STORAGE - 102.1 3'-0" 6'-8" HM - NONE HM NONE 18
STORAGE - 102.2 6'-0" 6'-0" Overhead - NONE - - 23
PLAN NOTES:
TOILET ACCESSORIES TO BE INCLUDED IN PROJECT SCOPE OF WORK (BUT NOT PROVIDED
BY PRE-FABRICATED STRUCTURE MANUFACTURER)
1 GRAB BARS
2 TOILET PAPER HOLDER
3 SANITARY NAPKIN DISPOSAL
4 TOILET SEAT COVER DISPENSOR
5 MIRROR
6 WALL MOUNT WASTE RECEPTICAL
7 MANUAL HAND SANITIZER DISPENSOR
8 RESTROOM SUPPLIES SHELVING
5 4
OPENING SCHEDULE NOTES:
1. REFER TO SPECIFICATION SECTIONS 08 71 00 HARDWARE AND 13 34 00
FABRICATED PRE-ENGINEERED PRECAST CONCRETE STRUCTURES FOR
DOOR, FRAME, AND HARDWARE ITEMS PROVIDED BY PRE-FABRICATED
STRUCTURE MANUFACTURER.
PRE-FABRICATED PRECAST CONCRETE STRUCTURE FINISHES:
1. EXTERIOR WALLS: PRECAST SPLIT-BLOCK SURFACE, APPLIED STAIN FINISH.
2. INTERIOR WALLS AND CEILING: SMOOTH FORM SURFACE, IN RESTROOM PROVIDE FIELD APPLIED
PAINT FINISH PER SPEC SECTION O9 90 00.
3. ROOF: PRECAST FAUX STANDING SEAM METAL ROOF SURFACE, APPLIED STAIN FINISH
4. DOORS AND FRAMES: PAINT FINISH
5. REFER TO SPECIFICATION SECTION 13 34 00 FABRICATED PRE-ENGINEERED PRECAST CONCRETE
STRUCTURES FOR ADDITIONAL FINISH REQUIREMENTS.
STAINLESS STEEL TOILET BY
PRE-FABRICATED STRUCTURE
MANUFACTURER
18" x 42"
WINDOW
NOTE: BUILDING PLAN AND ELEVATION DRAWINGS ON THIS SHEET
PROVIDED BY EASI-SET BUILDINGS COMPANY. ADDITIONAL MATERIAL
AND PRODUCT INFORMATION REQUIRED FOR COMPLETE RESTROOM/
STORAGE CONSTRUCTION HAS BEEN ADDED. REFER TO PROJECT
SPECIFICATIONS.
GRAB BAR
(BOTH SIDES @
AMBULATORY STALL)
ACCESSIBLE TOILET/WATER CLOSETS
3'-6"MIN
MAX
1'-0"
7"-9"
MIN
1'-0"
MIN
2'-0"
SIDE WALL BACK WALL
CLEAR FLOOR SPACE
5'-0"MIN
1. SANITARY NAPKIN DISPOSAL. PROVIDE AT UNISEX, & WOMEN'S BATHROOMS ONLY.
2. DISPENSERS MAY NOT BE LOCATED BEHIND GRAB BARS.
56" @ WALL HUNG WC**
1' -3
"M
IN
DISPENSER OUTLET
ZONE
WC
LINE OF CLEAR
FLOOR SPACE
16"-18"
SND
1'-4"
SANITARY NAPKIN DISPOSAL
: 4' -0" ABOVE
FINISHED FLOOR MAXIMUM HEIGHT TO OPERATE
: SEE ACCESSIBLE TOILET ELEVATIONS
FOR DIMENSIONS AND MOUNTING HEIGHTS
: SEE ACCESSIBLE
TOILET ELEVATIONS FOR LOCATION
: SEE ACCESSIBLE TOILET
ELEVATIONS FOR LOCATION AND MOUNTING HEIGHTS
: BOTTOM EDGE OF REFLECTING
SURFACE 40" MAXIMUM ABOVE FINISHED FLOOR
: 4' -0"
ABOVE FINISHED FLOOR MAXIMUM HEIGHT TO OPERATE
: 4' -0" ABOVE
FINISHED FLOOR MAXIMUM HEIGHT TO OPERATE
: TWO (2)
12" X 36" STAINLESS STEEL SHELVES
RESTROOM
08.16.2021
PUSH PADS FOR
POWER OPERATED
DOOR
August 16, 2021
BIDDING
DOCUMENTS
09.08.2021
BIDDING DOCUMENTS
September 8, 2021
CS501
I HEREBY CERTIFY THAT THIS PLAN,
SPECIFICATION, OR REPORT, WAS
PREPARED BY ME OR UNDER MY
DIRECT SUPERVISION AND THAT I AM A
DULY LICENSED PROFESSIONAL
ENGINEER UNDER THE LAWS OF THE
STATE OF MINNESOTA
EDWIN J. BRODMARKLE, PE
DATE: 2021.09.08 LICENSE NO: 55409
DELETE TOILET FLUSH VALVE 09/14/20211
1 1
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Fi le
P at h:
y
:\1
\1 fa rg o nc a nd n or th w oo ds n c
- r es tro om s, s to ra ge , w in d w al ls a e\ _0 ci vi l\_ c ad fi le s\
_0 sh ee ts \1
.1 _x
_d et ai l.d w eb ro dm ar kl d:
9/
8/
:2 lo t:9 /8
/2
4:
P
M
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD STAMPCONSULTANTS
321 4 5 6 7 8 9 10
Project Director
Revisions:
1 3 6 0 5 1 s t A v e . N . # 1 0 0 P l y m o u t h , M N 5 5 4 4 1 P 7 6 3 . 4 1 2 . 4 0 0 0 | F 7 6 3 . 4 1 2 . 4 0 9 0 | a e - m n . c o m Anderson Engineering of Minnesota, LLC | Proj#16315.1
RESTROOMS, STORAGE & WIND
WALLS
939.940-MM20-004
September 8, 2021
FARGO NATIONAL CEMETERY
8709 40TH AVENUE N. HARWOOD, ND 58042
BIDDING DOCUMENTS
09.08.2021
BIDDING DOCUMENTS
Date:
Mechanical Engineering, Electrical Engineering, Structural Engineering:
IMEG
623 26th Avenue Rock Island, IL 61201 (916)-817-4924 Matt Snyder / Todd Barrett
Cost Estimating:
OCMI
1722 Routh Street #900 Dallas, TX 75201 (469)-431-0571 Kyle Veater OF 22
RESTROOM STORAGE
BUILDING DETAILS
CS502
EJB KAA
RECOMMENDED FOUNDATION FOR EASI-SET TRANSPORTABLE PRECAST CONCRETE BUILDINGS
BUILDING DESIGN
EASI-SET TRANSPORTABLE PRECAST CONCRETE BUILDINGS HAVE BEEN DESIGNED TO ELIMINATE THE NEED FOR FOUNDATIONS OR FOOTINGS VIRTUALLY ALL INSTALLATIONS. THE BUILT-IN FLOOR OF THE EASI-SET BUILDINGS IS DESIGNED FOR USE ON FLOATING FOUNDATIONS COMPRISED OF 4"-6" OF CRUSHED STONE OR SAND. THIS DESIGN, AND THE USE OF APPROPRIATE FOUNDATIONS OF STONE OR SAND, HAVE PROVEN TO BE EFFECTIVE AND PROBLEM FREE IN THE FIELD FOR A WIDE VARIETY OF INSTALLATIONS. THE EFFECTIVENESS OF THE DESIGN HAS NOT BEEN ADVERSELY AFFECTED BY THE SIZE
OF THE EASI-SET BUILDING.
CAVEATS
THE FLOATING FOUNDATION OF CRUSHED STONE OR SAND SHOULD BE PLACED ON A WELL-DRAINED AND
GRADED AREA, TO PRECLUDE THE RETENTION OF STANDING WATER. ON A WELL-DRAINED AND
PROPERLY GRADED SITE, ANY GROUND SWELL SHOULD BE MINIMAL AND LINEAR, WITH NO DAMAGE TO
THE EASI-SET BUILDING OR ITS CONTENTS.
IT IS IMPORTANT TO NOTE THAT THE DESIGN OF AN EASI-SET BUILDING ENABLES THE TRANSPORTATION OF THE BUILDING, WHICH MAXIMIZES THE FLEXIBILITY AND LONG TERM-USEFULNESS OF THE STRUCTURE.
FURTHERMORE, THE ELIMINATION OF FOUNDATIONS AND FOOTINGS MINIMIZES THE IMPACT ON, AND DAMAGE TO, THE ENVIRONMENT OF THE BUILDING SITE. THE USE OF STANDARD FOUNDATIONS OR FOOTINGS WOULD COUNTER SOME OF THE SIGNIFICANT BENEFITS, WHICH CAN BE ACHIEVED BY INSTALLING EASI-SET BUILDINGS. IN THOSE AREAS WHERE LOCAL BUILDINGS CODES MAY NOT ACCOMMODATE THE USE OF A FLOATING FOUNDATION FOR AN EASI-SET BUILDING, A VARIANCE TO SUCH
CODES MAY BE AVAILABLE.
SITE PREPARATION REQUIREMENTS
(MANUFACTURER'S RECOMMENDATION)
A. EASI-SET BUILDING SHALL BEAR FULLY ON A CRUSHED STONE BASE THAT IS AT LEAST TWO FEET
LARGER THAN THE LENGTH AND WIDTH OF BUILDING
B. STONE SHALL BE MINIMUM OF 18" THICK DOWN TO FIRM SUBGRADE. THE VERTICAL SOIL CAPACITY UNDER STONE SHALL BE COMPACTED TO HAVE MINIMUM BEARING OF 1,500 POUNDS PER SQUARE FOOT. STONE SHALL BE 3/8" OR SMALLER AND MUST BE SCREEDED LEVEL WITHIN 1/4" IN BOTH DIRECTIONS. STONE SHALL BE PLACED WITHIN A PERIMETER FORM WITH FLAT AND LEVEL TOP
EDGE FOR SCREEDING. FORMING MATERIAL SHALL REMAIN AROUND STONE UNTIL AFTER THE
BUILDING IS SET.
C. THE CRUSHED STONE BASE SHALL BE KEPT WITHIN THE CONFINES OF THE SOIL OR PERIMETER
FORM. DO NOT ALLOW THE BASE TO BECOME UNCONFINED SO THAT IS MAY WASH, ERODE, OR
OTHERWISE BE UNDERMINED.
OR
IF BUILDING IS PLACED ON PAVEMENT OR CONCRETE SLAB, SUBSTRATE BELOW PAVEMENT OR
SLAB MUST HAVE A VERTICAL SOIL CAPACITY OF 1,500 POUNDS PER SQUARE FOOT. PLACE STONE OR SAND TO 1" ABOVE HIGHEST POINT OF AREA WHERE BUILDING WILL BE PLACED AND AT LEAST 1'-0" ALL AROUND THE BUILDING FOOTPRINT. RETAIN STONE OR SAND WITH A PERIMETER FORM TO
PREVENT THE MATERIAL FROM WASHING OUT.
D. PROVIDE POSITIVE DRAINAGE FOR THE FILL, PAD, OR SLAB AS REQUIRED.
ACCESS
A. CONTRACTOR MUST PROVIDE LEVEL UNOBSTRUCTED AREA LARGE ENOUGH FOR A CRANE AND A TRACTOR-TRAILER TO PARK ADJACENT TO THE PAD. CRANE MUST BE ABLE TO PLACE OUTRIGGERS WITHIN 5'-0" OF EDGE OF PAD AND TRUCK AND CRANE MUST BE ABLE TO GET SIDE BY SIDE UNDER
THEIR OWN POWER. NO OVERHEAD LINES MAY BE WITHIN 75' RADIUS OF CENTER OF PAD. A
MINIMUM OF 24" CLEARANCE IS REQUIRED BETWEEN THIS BUILDING AND ADJACENT BUILDINGS
I HEREBY CERTIFY THAT THIS PLAN,
SPECIFICATION, OR REPORT, WAS
PREPARED BY ME OR UNDER MY
DIRECT SUPERVISION AND THAT I AM A
DULY LICENSED PROFESSIONAL
ENGINEER UNDER THE LAWS OF THE
STATE OF MINNESOTA
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Fi le
P at h:
y
:\1
\1 fa rg o nc a nd n or th w oo ds n c
- r es tro om s, s to ra ge , w in d w al ls a e\ _0 ci vi l\_ c ad fi le s\
_0 sh ee ts \1
.1 _x
_d et ai l.d w eb ro dm ar kl d:
9/
8/
:2 lo t:9 /8
/2
4:
P
M
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD STAMPCONSULTANTS
321 4 5 6 7 8 9 10
Project Director
Revisions:
1 3 6 0 5 1 s t A v e . N . # 1 0 0 P l y m o u t h , M N 5 5 4 4 1 P 7 6 3 . 4 1 2 . 4 0 0 0 | F 7 6 3 . 4 1 2 . 4 0 9 0 | a e - m n . c o m Anderson Engineering of Minnesota, LLC | Proj#16315.1
RESTROOMS, STORAGE & WIND
WALLS
939.940-MM20-004
September 8, 2021
FARGO NATIONAL CEMETERY
8709 40TH AVENUE N. HARWOOD, ND 58042
BIDDING DOCUMENTS
09.08.2021
BIDDING DOCUMENTS
Date:
Mechanical Engineering, Electrical Engineering, Structural Engineering:
IMEG
623 26th Avenue Rock Island, IL 61201 (916)-817-4924 Matt Snyder / Todd Barrett
Cost Estimating:
OCMI
1722 Routh Street #900 Dallas, TX 75201 (469)-431-0571 Kyle Veater OF 22
SITE DETAILS
CS503
EJB KAA
ENGINEERING FABRIC
FABRIC ANCHORAGE TRENCH
BACKFILL WITH TAMPED
NATURAL SOILMETAL OR WOOD
POST OR STAKE
WIRE MESH
REINFORCEMENT
(OPTIONAL)
NATURAL SOIL
2' MIN
6" MIN.
6" MIN.
NOTE: DEPENDING UPON CONFIGURATION, ATTACH FABRIC TO WIRE MESH WITH
HOG RINGS, STEEL POSTS WITH TIE WIRES, OR WOOD POSTS WITH STAPLES.
DIRECTION OF
RUNOFF FLOW
TYPICAL INSTALLATION
TYPICAL FLUSH CURB DETAIL
N.T.S. 2
PEDESTIRAN CURB RAMPS
N.T.S. 3
TYPICAL CONCRETE PAVEMENT SECTION DETAIL (SIDEWALK)
N.T.S.
STORAGE BUILDING SITE PREPERTAION
N.T.S.
STORM BEDDING
N.T.S.
SILT FENCE DETAIL
N.T.S.
R= 2'-
1/
4"
1:20 MAX
7"
2'-7"
NOTE: CURB AGGREGATE BASE TO BE
MIN. 6" DEPTH AND EXTEND 1' BEHIND
BACK OF CURB
2-3 % R=1
4"
4" MIN.
2" MAXR=1
4"
EDGE OF CURB/
EDGE OF WALK
2'
2'
DIA.
L
MINIMUM RIPRAP REQUIRED
DIA. OF
PIPE (IN)
LENGTH
(FT)
QUANTITY
(CY) CLASS
12 8 5 III
15 8 5 III
18 10 6 III
24 12 8 III
30 14 12 III
36 16 14 III
42 18 22 IV
48 20 26 IV
>48 22-28 30-40 IV
1' (12"-27" DIA. PIPE)
1.5' (30"+ DIA. PIPE)
SECTION B-B'
NOTE:
ONE CUBIC YARD ~ 1.4 TONS
SECTION A-A'
PLAN
NOTE:
TIE THE LAST 6 JOINTS ON INLET
AND OUTLET PIPES AND BED IN
GRANULAR MATERIAL. ANY COVER
LESS THAN 2' OVER TOP OF PIPE
SHALL BE GRANULAR MATERIAL.
1' (12"-27" DIA. PIPE)
1.5' (30"+ DIA. PIPE)
RIPRAP
NONWOVEN GEOTEXTILE
FABRIC EXTEND 1' UNDER FES
RIP-RAP DETAIL FOR FLARED END SECTIONS
N.T.S.
TYPE 2
EXPANSION JOINT
CURB & GUTTER
DETECTABLE WARNINGS
(TRUNCATED DOMES - MIN.
24" X 24")
6'
2' 6'
2'
CONCRETE
WALK
DOME SPACING
DOME SECTION
TRUNCATED
DOME (TYP)1.6"-2.4"
1.
6"
2.
4"
M
IN
5/8" MIN. (TYP.)
0.
9"
(T Y
P
0.9"-1.4" 0.2"
50%-65% OF BASE
DIAMETER
RAMP FLUSH
WITH GUTTER
SECTION A
SLOPE PER PLAN
1:12 MAX SLOPE.
VARIES, SEE PLAN
NOTE
DETECTABLE WARNING PLATES TO BE FLUSH
(NOT RECESSED). INSTALL PRE-FABRICATED
UNITS PER MANUFACTURER INSTRUCTIONS.
COLOR TO BE UNIFORM THROUGHOUT (NO
PAINTED OR APPLIED COLORS). COLOR SHALL
BE GRAY.
6" 4"
CIP CONCRETE BROOM
FINISH SWEEP PERPENDICULAR
TO DIRECTION OF TRAFFIC
COMPACTED AGGREGATE BASE
- NDDOT SPEC 302.04
APPROVED SUBGRADE
EXTEND BASE MATERIALS
3" BEYOND EDGE
OF CONCRETE
NOTE
CONCRETE JOINT LAYOUT IS SHOWN ON THE
PLANS. CONTRACTOR SHALL SUBMIT JOINTING PLAN
FOR APPROVAL PRIOR TO FINAL PAVING. CONTROL
JOINTS AND EXPANSION JOINTS SHALL BE USED
ACCORDINGLY. PROVIDE EXPANSION JOINTS NEXT
TO ALL FIXED OBJECTS.
4" TOPSOIL AND SOD
NOTE 3'
NOTES
1. PROVIDE 18" AGGREGATE BENEATH PREFABRICATED
STRUCTURE TO ACHIEVE FFE LISTED ON GRADING PLAN
2. PROVIDE 12" AGGREGATE BASE BENEATH CONCRETE
SEPTIC VAULT
3. EXTEND BASE 1' UNDER ON ALL SIDES OF STRUCTURE
FLAT
6" PERFORATED
PIPE WITH SOCK
18" CLASS V BASE
SAND BEDDING FOR HDPE PIPE
HDPE
PIPE
COMPACTED
SAND
" M
IN
TY
P
IC
A
L
MIN. 4" OF BEDDING
12" MIN.
OVER PIPE
1" (25 mm) REBAR
FOR BAG REMOVAL
FROM INLET
EXPANSION RESTRAINT
[1/4" (6 mm) NYLON ROPE, 2" (51 mm) FLAT
WASHERS]
2 EACH DUMP
STRAPS
DUMP STRAP
SILT SACK
INLET PROTECTION SEDIMENT FILTER SACK
N.T.S.
TESTED AND APPROVED SUBGRADE
6" DEEP, COMPACTED CL 5 AGGREGATE BASE - NDDOT SPEC 302.04
6" CONCRETE PAVEMENT (4" CONC. ON SIDEWALKS &
COLUMBARIA) - NDDOT SPEC 550.04
CONCRETE PAVEMENTS (ROADWAY)
N.T.S.
I HEREBY CERTIFY THAT THIS PLAN,
SPECIFICATION, OR REPORT, WAS
PREPARED BY ME OR UNDER MY
DIRECT SUPERVISION AND THAT I AM A
DULY LICENSED PROFESSIONAL
ENGINEER UNDER THE LAWS OF THE
STATE OF MINNESOTA
STO
RAG
E
REST
RO
O
M
4 Admiration Japanese Barberry
5 GAL. CONT.
3 Karl Foerster Feather Reed Grass
5 GAL. CONT.
4 Autumn Fire Stonecrop
1 GAL. CONT.
11Autumn Fire Stonecrop
1 GAL. CONT.
26 Walker's Low Catmint
3 GAL. CONT.
10 Techny Arborvitae
TRANSPLANTED
STO
RAG
E
REST
RO
O
M
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
F i l e
P a t h y f a r g o n c a n d n o r t h w o o d s n c r e s t r o o m s s t o r a g e w i n d w a l l s a e l a c a d f i l e s s h e e t s l p l a n t i n g d d i t j f a h r e n k a m s a v e d l o t
A
M
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD STAMPCONSULTANTS
321 4 5 6 7 8 9 10
Project Director
Revisions:
1 3 6 0 5 1 s t A v e . N . # 1 0 0 P l y m o u t h , M N 5 5 4 4 1 P 7 6 3 . 4 1 2 . 4 0 0 0 | F 7 6 3 . 4 1 2 . 4 0 9 0 | a e - m n . c o m Anderson Engineering of Minnesota, LLC | Proj#16315.1
RESTROOMS, STORAGE & WIND
WALLS
939.940-MM20-004
September 8, 2021
FARGO NATIONAL CEMETERY
8709 40TH AVENUE N. HARWOOD, ND 58042
BIDDING DOCUMENTS
09.08.2021
BIDDING DOCUMENTS
Date:
Mechanical Engineering, Electrical Engineering, Structural Engineering:
IMEG
623 26th Avenue Rock Island, IL 61201 (916)-817-4924 Matt Snyder / Todd Barrett
Cost Estimating:
OCMI
1722 Routh Street #900 Dallas, TX 75201 (469)-431-0571 Kyle Veater OF 22
PLANTING PLAN
LP101
N
N
0 5' 10'
SCALE:
COMMITTAL SHELTER PLANTING PLAN - ADD ALT
1" = 5'
0 5' 10'
SCALE:
RESTROOM / STORAGE & PUMP HOUSE PLANTING PLAN - BASE BID
1" = 5'
N
0 5' 10'
SCALE:
COMMITTAL SHELTER PLANTING PLAN - BASE BID
1" = 5'
ADD ALT.
SEE 2/LP101 & 4/LP101
EXISTING
SIGNAGE
(2) SHRUBS THUS
RELOCATED WITH ADD
ALT ACCEPTANCE
N
0 5' 10'
SCALE:
RESTROOM / STORAGE & PUMP HOUSE PLANTING PLAN - ADD ALT
1" = 5'
EXISTING
GRAVESITE
LOCATOR
EXISTING
GRAVESITE
LOCATOR
CHC JAF
LEGEND
PROPERTY LIMITS
NOTES
1. SEE LP501 FOR PLANTING SCHEDULE
2. ALL PLANTING SHALL RECEIVE IRRIGATION.
IRRIGATION SHALL BE DESIGN BUILD PER
CONTRACTOR. (SEE SPECIFICATIONS FOR
IRRIGATION NOTES)
3. REFER TO SPECIFICATIONS FOR SODDING,
SEEDING, FERTILIZER AND TOPSOIL NOTES
4. ALL DISTURBED AREAS, BEYOND PLANTINGS,
SHALL BE RESTORED/REPLACED IN-KIND UNLESS
NOTED OTHERWISE.
3" DP SHREDDED HARDWOOD
MULCH WITHOUT FABRIC
(MATCH EXISTING)
SPADE EDGE
EXISTING TREE TO BE
RELOCATED / TRANSPLANTED
RELOCATED /
TRANSPLANTED TREE
EXISTING COMMITTAL
SERVICE SHELTER
EXISTING COMMITTAL
SERVICE SHELTER
EXISTING
PUMP HOUSE
EXISTING
PUMP HOUSE
TREE PROTECTION
REQUIRED
(2) THUS TRANSPLANTED
TREES RELOCATED NEAR
STORAGE /PUMP HOUSE IF
ADD ALT ACCEPTED
PRINT NAME:
SIGNATURE:
I HEREBY CERTIFY THAT THIS PLAN,
SPECIFICATION OR REPORT WAS PREPARED
BY ME OR UNDER MY DIRECT SUPERVISION
AND THAT I AM A DULY LICENSED
LANDSCAPE ARCHITECT UNDER THE LAWS
OF THE STATE OF MINNESOTA.
DATE
LICENSE #
CURT H. CLAEYS
9/9/2021
45613
MIN.
6"
LAWN / NATIVE GRASS
UNDISTURBED OR COMPACTED SOIL
PLANTING SOIL
LINE OF PLANTING PIT WHEN
PLANTED INDIVIDUALLY
UNDISTURBED OR COMPACTED SOIL
3" DEPTH HARDWOOD MULCH
PAVED SURFACE, IF APPLICABLE
MIN.
6"
3' MIN. TO PAVED
SURFACES
PLANTING SOIL
3" DEPTH HARDWOOD MULCH
PAVED SURFACE, LAWN OR NATIVE GRASS
UNDISTURBED OR COMPACTED SOIL
NOTE:
- KEEP MULCH APPX. 2" OFF PLANT TRUNK OR STEM
O
C
S
P
A
C
I
N
G
C
S P
A C
I N
G
EDGE OF GROUNDCOVER
AREA/WALK EDGE
DISTANCE FROM EDGE
IS
THE SPECIFIED
O.C. SPACING
TRIANGULAR SPACE,
AT SPECIFIED O.C.
DISTANCE - EQUIDISTANT
PLANT CENTER
HARDWOOD MULCH
ROOTBALL
PLANTING SOIL
NATIVE SOIL
BOUNDARY BETWEEN
LAWN &PLANTING AREA AS
SHOWN ON PLAN
PREPARED SUBGRADE
6" DEEP SHOVEL CUT
LAWN / NATIVE GRASS
MULCH
PLANTING AREA
12"
3"DP.
TYP.
2"
NOTE:
-3" DP. SHREDDED HARDWOOD MULCH SHALL BE USED IN ALL LANDSCAPE
PLANTINGS AREAS AND UNDER TREES ISOLATED FROM PLANTING AREAS UNLESS
IDENTIFIED OTHERWISE.
UNDISTURBED OR
COMPACTED SOIL
PLANTING SOIL
MOUND MIN. 6"
REMOVE BURLAP, TWINE,
ROPE AND WIRE FROM
TOP HALF OF ROOTBALL
FINISHED GRADE
LAWN OR PLANTING BED
EDGE (SPADE EDGE IN ALL
LAWN AREAS)
6' MIN. DIA. EARTH SAUCER
3" HEIGHT TAMPED WATER
BASIN AT EDGE OF EARTH
SAUCER
TREE TIE SECURED TO
DUCKBILL ANCHOR WITH
TURNBUCKLE. SECURE TO
TREE WITH ANTI-CHAFFING
MATERIAL. ALLOW FOR
MOVEMENT OF TREE.
3" DEPTH HARDWOOD MULCH
SINGLE STRAIGHT LEADER
CENTER TREE IN HOLE,
UPRIGHT
AFTER EXPOSING TREE ROOT FLAIR, PLANT SO
ROOT FLAIR IS AT 2" ABOVE ADJACENT FINISH
GRADE
NORTHWEST
PREVAILING
WINDS
SOUTHEAST
PREVAILING
WINDS
PLAN VIEW OF TREE STAKING
NOT TO SCALE
X
R
O
O
T
B
A
L
L
HARDWOOD MULCH
LAWN
TREE TIE SECURED TO
DUCKBILL ANCHOR WITH
TURNBUCKLE. SECURE TO
TREE WITH ANTI-CHAFFING
MATERIAL. ALLOW FOR
MOVEMENT OF TREE.
EQ EQ
ZONE A:
DIA=1/2X
ZONE B:
DIA=X
ZONE C:
DIA=2X
PLAN VIEW
ELEVATION VIEW
D
R I P
L I N
E
FENCING/ROOT PROTECTION
6' HIGH CHAIN LINK FENCING SHALL BE
PROVIDED AND…