This is a request for quotation (RFQ) from the Department of Veterans Affairs National Cemetery Administration for topsoil furnish and delivery services at Calverton National Cemetery in Calverton, New York. The contractor shall supply and deliver topsoil consisting of fertile, friable, natural earth of loamy character with 5% composted material and free of refuse. The base year of performance is from date of award through September 30, 2020, with four optional one-year renewal periods. The RFQ establishes estimated quantities of 3,000 cubic yards of topsoil per year and minimum order quantities of 2,000 cubic yards. Responses are due by October 3, 2019 and the award will be an indefinite delivery/indefinite quantity contract to the responsible offeror providing the best value. This is a 100% set-aside for service-disabled veteran-owned small businesses.
36C78620Q0049 Statement of Work.docx
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C78620Q0049-0003001.pdf | ||
| 36C78620Q0049-0003000.docx | DOCX document | |
| 36C78620Q0049-0003001.pdf | ||
| 36C78620Q0049-0003000.docx | DOCX document | |
| 36C78620Q0049-0002000.docx | DOCX document | |
| 36C78620Q0049-0002000.docx | DOCX document | |
| 36C78620Q0049-0001000.docx | DOCX document | |
| 36C78620Q0049-0001000.docx | DOCX document | |
| 36C78620Q0049-002.docx | DOCX document | |
| 36C78620Q0049-004.pdf | ||
| 36C78620Q0049-001.pdf | ||
| 36C78620Q0049-000.docx | DOCX document | |
| 36C78620Q0049-003.docx | DOCX document | |
| 36C78620Q0049-000.docx | DOCX document | |
| 36C78620Q0049-003.docx | DOCX document | |
| 36C78620Q0049-004.pdf | ||
| 36C78620Q0049-001.pdf |
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SUPPLIES OR SERVICES & PRICES / COSTS
PRICE SCHEDULE
Scope: The Contractor shall Supply & Deliver (F.O.B. Destination within Consignee’s Premises) Topsoil to Calverton National Cemetery, 210 Princeton Boulevard, Calverton, NY 11933.
Site Visit: Offerors or quoters are urged and expected to inspect the site(s) where services are to be performed and to satisfy themselves regarding all general and local conditions that may affect the cost of contract performance. In no event shall failure to inspect the site constitute grounds for a claim after contract award. If you plan to conduct a site visit / inspection at the Calverton National Cemetery, YOU MUST CONTACT the following cemetery personnel to make arrangements:
Jeff Tavares, Assistant Director .............................................................................(631) 727-5410 James Burke, Grounds Foreman…………………..……..………...……………..(631) 727-5410 FAX ........................................................................................................................(631) 727-5815
Duration: The term of the contract is from date of award thru September 30, 2020 with four (4) one-year renewal options.
Unit Price: The unit cost indicated in the Schedule is all-inclusive and covers supply and delivery of all topsoil ordered.
Type of Contract: This is an indefinite-quantity contract for the supplies / services specified and effective for the period stated in the Schedule. This contract provides for an indefinite quantity of services within stated limits, to be furnished during the contract period with deliveries or performance being scheduled by placing orders with the Contractor. The quantities of services specified in the Price Schedule are estimates only and are not purchased by this contract.
| Base Year: October 1, 2019 or from date of award through September 30, 2020 |
| Est Qty |
| Unit |
| Unit Cost |
| Total Cost |
TOPSOIL (Dry Weight Measured) Furnish / Deliver Topsoil consisting of fertile, friable, natural earth of loamy character, without a mixture of subsoil, uniform in quality with 5% composted material and free of refuse of any nature (i.e., hard clods, stiff clay, sod hard pan, pebbles larger than 1/4” in diameter, course sand, noxious weeds, stick brush, other rubbish, etc.)
3,000
CY
| Option Year I: October 1, 2020 through September 30, 2021 |
| Est Qty |
| Unit |
| Unit Cost |
| Total Cost |
TOPSOIL (Dry Weight Measured) Furnish / Deliver Topsoil consisting of fertile, friable, natural earth of loamy character, without a mixture of subsoil, uniform in quality with 5% composted material and free of refuse of any nature (i.e., hard clods, stiff clay, sod hard pan, pebbles larger than 1/4” in diameter, course sand, noxious weeds, stick brush, other rubbish, etc.)
| Option Year II: October 1, 2021 through September 30, 2022 |
| Est Qty |
| Unit |
| Unit Cost |
| Total Cost |
TOPSOIL (Dry Weight Measured) Furnish / Deliver Topsoil consisting of fertile, friable, natural earth of loamy character, without a mixture of subsoil, uniform in quality with 5% composted material and free of refuse of any nature (i.e., hard clods, stiff clay, sod hard pan, pebbles larger than 1/4” in diameter, course sand, noxious weeds, stick brush, other rubbish, etc.)
| Option Year III: October 1, 2022 through September 30, 2023 |
| Est Qty |
| Unit |
| Unit Cost |
| Total Cost |
TOPSOIL (Dry Weight Measured) Furnish / Deliver Topsoil consisting of fertile, friable, natural earth of loamy character, without a mixture of subsoil, uniform in quality with 5% composted material and free of refuse of any nature (i.e., hard clods, stiff clay, sod hard pan, pebbles larger than 1/4” in diameter, course sand, noxious weeds, stick brush, other rubbish, etc.)
| Option Year IV: October 1, 2023 through September 30, 2024 |
| Est Qty |
| Unit |
| Unit Cost |
| Total Cost |
TOPSOIL (Dry Weight Measured) Furnish / Deliver Topsoil consisting of fertile, friable, natural earth of loamy character, without a mixture of subsoil, uniform in quality with 5% composted material and free of refuse of any nature (i.e., hard clods, stiff clay, sod hard pan, pebbles larger than 1/4” in diameter, course sand, noxious weeds, stick brush, other rubbish, etc.)
ORDERING
The Government anticipates ordering and the Contractor furnishing at least the stated "minimum" quantities of services and, if ordered, the Contractor to furnish any additional quantities, not to exceed the stated "maximum". Quantities beyond the stated maximum may be ordered if mutually agreed upon by the Government and the Contractor. Except as this contract may otherwise provide, if the Government' requirements do not result in orders in the quantities described as "estimated" or "maximum" in the Schedule, that fact shall not constitute the basis for an equitable price adjustment.
Maximum & Minimum Quantities: Delivery shall be made only as authorized by orders issued in accordance with the Ordering clause. The Contractor shall furnish to the Government the supplies and/or services specified up to and including the quantity designated in the Schedule as the “Maximum.” The Government shall order at least the quantity of topsoil designated in the Schedule as the “Minimum.” Maximum & Minimum quantity limitations are as provided in the following schedules:
DESCRIPTION / SPECIFICATIONS / WORK STATEMENT
SPECIFICATIONS
(a) The Contractor shall Supply & Deliver (F.O.B. Destination within Consignee’s Premises) Topsoil consisting of fertile, friable, natural earth of loamy character, without a mixture of subsoil, uniform in quality with 5% composted material and free of refuse of any nature hard clods, stiff clay, sod hard pan, pebbles larger than 1/4” in diameter, course sand, noxious weeds, stick brush, other rubbish, etc.
(b) Topsoil shall contain at least 5% organic matter determined by loss on ignition on moisture-free samples dried in accordance with the current method of the association of official agricultural chemist.
(c) The acidity range shall be PH 5.0 to 7.0 inclusive.
(d) Minimum amount will be 2,000 yards to be used as need basis.
DELIVERY
(a) Each truck shall carry at least 35 cubic yards of dry weight topsoil per truck load.
(b) The topsoil will be spread upon delivery by Calverton National Cemetery Personnel.
(c) Orders for Topsoil shall be placed on an “as-needed / as-requested” basis by the Calverton National Cemetery Contracting Officer’s Technical Representative (COR) or designee.
(d) Unless otherwise agreed upon, delivery shall be made between the hours of 8:00 A.M. and 1:00 PM. Orders shall be delivered within 5 hours after request.
(End of Work Statement)