36C78619B0004-014.pdf
PDF 4 MB Posted
- Attached to
- (MM) 835CM3035 | 36C786-19-AP- 0145 Gravesite Expansion PPC & IGB Chattanooga National Cemetery
- Solicitation number
- 36C78619B0004
About this file
36C78619B0004 181126 Chattanooga 835-035 Bid Specifications Final.pdf
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C78619C0102-000.docx | DOCX document | |
| 36C78619B0004-0006001.pdf | ||
| 36C78619B0004-0006000.docx | DOCX document | |
| 36C78619B0004-0005000.docx | DOCX document | |
| 36C78619B0004-0005002.pdf | ||
| 36C78619B0004-0005001.pdf | ||
| 36C78619B0004-0004018.pdf | ||
| 36C78619B0004-0004019.pdf | ||
| 36C78619B0004-0004016.docx | DOCX document | |
| 36C78619B0004-0004017.pdf | ||
| 36C78619B0004-0003000.docx | DOCX document | |
| 36C78619B0004-0002000.docx | DOCX document | |
| 36C78619B0004-0001000.docx | DOCX document | |
| 36C78619B0004-018.pdf | ||
| 36C78619B0004-016.pdf | ||
| 36C78619B0004-013.docx | DOCX document | |
| 36C78619B0004-015.pdf | ||
| 36C78619B0004-019.pdf | ||
| 36C78619B0004-017.pdf | ||
| 36C78619B0004-000.docx | DOCX document |
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Chattanooga National Cemetery Project 835CM3035 28 September 2018
TABLE OF CONTENTS
00 01 10-1
DEPARTMENT OF VETERANS AFFAIRS
NCA MASTER SPECIFICATIONS
Section 00 01 10
DIVISION 00 - SPECIAL SECTIONS DATE
00 01 13 Signature Pages 09-20 00 01 15 List of Drawing Sheets 03-18
DIVISION 01 - GENERAL REQUIREMENTS
01 00 02 General Requirements (Minor NCA Projects) 06-14 01 32 17 Network Analysis Schedules 10-10 01 33 23 Shop Drawings, Product Data, and Samples 05-17 01 42 19 Reference Standards 05-16 01 45 29 Testing Laboratory Services 08-17 01 57 19 Temporary Environmental Controls 01-11 01 74 19 Construction Waste Management 09-13 01 81 13 Sustainable Construction Requirements 10-17
DIVISION 02 – EXISTING CONDITIONS
02 41 10 Demolition and Site Clearing 03-18
DIVISION 03 – CONCRETE
03 30 53 (Short-Form) Cast-in-Place Concrete 03-18 03 48 21 Precast Concrete Burial Crypts (Double Depth Lawn
Crypt) 03-18
DIVISION 04 – MASONRY
04 05 13 Masonry Mortaring 03-18 04 05 16 Masonry Grouting 03-18 04 20 00 Unit Masonry 03-18 04 72 00 Cast Stone Masonry 03-18
DIVISION 05 – METALS
05 12 00 Structural Steel Framing 02-16 05 50 00 Metal Fabrications 03-18
DIVISION 06 – WOOD AND PLASTIC
06 10 00 Rough Carpentry 10-17 06 20 00 Finish Carpentry 08-16
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 41 13 Standing Seam Metal Roofing 03-18 07 46 46 Fiber-Cement Siding 07 60 00 Flashing and Sheet Metal 03-18 07 71 00 Roof Specialties 03-18 07 92 00 Joint Sealants 03-18
00 01 10-2
DIVISION 08 – DOORS AND WINDOWS
08 11 13 Hollow Metal Doors and Frames 08 71 00 Door Hardware
DIVISION 09 – FINISHES
09 91 00 Painting 03-18
DIVISION 10 – SPECIALTIES
10 14 00 Exterior Signage 03-18
DIVISION 26 – ELECTRICAL
26 05 11 Requirements for Electrical Installations 03-18 26 05 19 Low-Voltage Electrical Power Conductors and Cables 03-18 26 05 26 Grounding and Bonding for Electrical Systems 03-18 26 05 33 Raceway and Boxes for Electrical Systems 03-18 26 05 41 Underground Electrical Construction 03-18 26 24 16 Panelboards 03-18 26 27 26 Wiring Devices 03-18 26 51 00 Interior Lighting 03-18
DIVISION 31 – EARTHWORK
31 20 11 Earth Moving (Short Form) 03-18 31 23 19 Dewatering 11-16
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 05 23 Cement and Concrete for Exterior Improvements 03-18 32 12 16 Asphalt Paving 03-18 32 30 00 Site Furnishings 03-18 32 31 19 Decorative Metal Fence and Gates 11-16 32 84 00 Planting Irrigation 03-18 32 90 00 Planting 03-18
DIVISION 33 – UTILITIES
33 40 00 Storm Sewer Utilities 03-18 33 41 13 Foundation Drainage 03-18
APPENDIX
A Geotechnical Report B Submittal Register
SIGNATURE - 1
SIGNATURE PAGE
Lead Consultant/ Landscape Architect:
JG&A
Sections covered by this seal include:
00 01 15, 01 00 02, 01 32 17, 01 33 23, 01 42 19,01 45 29, 01 57 19, 01 74 19, 01 81 13, 10 14 00, 32 30 00, 32 31 19, 32 90 00
Civil Engineer:
Atriax
Sections covered by this seal include:
02 41 10, 31 20 11, 31 23 19, 32 05 23, 32 12 16, 33 40 00 ,33 41 13
Architect:
Wood LLC
Sections covered by this seal include:
03 30 53, 03 48 21, 04 05 13, 04 05 16, 04 20 00, 04 72 00, 06 10 00, 06 20 00, 07 41 13, 07 46 46, 07 60 00, 07 71 00, 07 92 00, 08 11 13, 08 71 00, 09 91 00
SIGNATURE - 2
Electrical Engineer:
Wood LLC 26 05 11, 26 05 19, 26 05 26, 26 05 33, 26 05 41, 26 24 16, 26 27 26, 26 51 00
Structural Engineer:
Wood 05 12 00, 05 50 00
Irrigation Designer:
Aqua Engineering, Inc.
Sections covered by this seal include:
32 84 00
LIST OF DRAWING SHEETS
00 01 15 - 1
SECTION 00 01 15
The drawings listed below accompanying this specification form a part of the contract.
Drawing No. Title
1 X-100 COVER SHEET
2 X-101 CONSTRUCTION ACCESS AND STAGING PLAN
3 V-100 BURIAL SECTIONS EXISTING CONDITIONS
4 V-101 NEW COMMITTAL SHELTER B EXISTING CONDITIONS
5 CD-101 BURIAL SECTIONS DEMOLITION PLAN
6 CD-102 COMMITTAL SHELTER DEMOLITION PLAN
7 C-101 BURIAL SECTION GRADING AND DRAINAGE PLAN
8 C-102 COMMITTAL SHELTER GRADING AND DRAINAGE PLAN
9 C-103 BURIAL SECTION INITIAL EROSION CONTROL PLAN
10 C-104 COMMITTAL SHELTER INITIAL EROSION CONTROL PLAN
11 C-105 BURIAL SECTION INTERIM EROSION CONTROL PLAN
12 C-106 COMMITTAL SHELTER, INTERIM EROSION CONTROL PLAN
13 C-107 BURIAL SECTION FINAL EROSION CONTROL PLAN
14 C-108 COMMITTAL SHELTER FINAL EROSION CONTROL PLAN
15 C-109 BURIAL SECTIONS LAYOUT PLAN
16 C-110 GRAVESITE NUMBERING PLAN
17 C-200 ROAD PLAN AND PROFILE
18 C-501 SITE DETAILS
19 C-502 SITE DETAILS
20 C-503 EROSION CONTROL DETAILS
21 C-504 EROSION CONTROL DETAILS
22 C-505 BURIAL SECTION DETAILS
23 C-506 PRE-PLACED CRYPT DETAILS
00 01 15 - 2
24 L-101 LANDSCAPE / SITE PLAN
25 L-102 CRYPT SITE PLANTING PLAN
26 L-103 COMMITTAL SHELTER PLANTING PLAN
27 L-501 SITE DETAILS
28 L-502 SITE DETAILS
29 A-001 ARCHITECTURE GENERAL NOTES
30 A-101 COMMITTAL SHELTER PLANS AND ELEVATIONS
31 A-301 COMMITTAL SHELTER SECTIONS & COLUMN DETAILS
32 A-501 COMMITTAL SHELTER DETAILS
33 S-001 COMMITTAL SHELTER GENERAL NOTES
34 S-002 COMMITTAL SHELTER WIND DIAGRAMS
35 S-101 COMMITTAL SHELTER FOUNDATION AND ROOF FRAMING PLAN
36 S-301 COMMITTAL SHELTER SECTIONS
37 S-501 COMMITTAL SHELTER DETAILS
38 E-001 GENERAL ELECTRICAL NOTES
39 E-100 SITE PLAN EXISTING SHELTER B
40 E-101 SITE PLAN NEW SHELTER B
41 E-200 PLANS, SCHEDULES, AND ONE LINE DIAGRAM
42 IR-101 IRRIGATION COVER SHEET
43 IR-201 IRRIGATION PLAN
44 IR-202 IRRIGATION PLAN
45 IR-501 IRRIGATION DETAILS
46 IR-502 IRRIGATION DETAILS
47 IR-503 IRRIGATION DETAILS
- - - END - - -
i
SECTION 01 00 02
GENERAL REQUIREMENTS (MINOR NCA PROJECTS)
1.1 GENERAL INTENTION
1.2 STATEMENT OF BID ITEM(S)
1.3 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
1.4 CONSTRUCTION SECURITY REQUIRMENTS 2
1.5 FIRE SAFETY
1.6 OPERATIONS AND STORAGE AREAS
1.7 ALTERATIONS
1.8 ENVIRONMENTAL CONTROLS 9
1.9 DISPOSAL AND RETENTION
1.10 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT,
UTILITIES, AND IMPROVEMENTS
1.11 RESTORATION
1.12 PHYSICAL DATA
1.13 PROFESSIONAL SURVEYING SERVICES
1.14 LAYOUT OF WORK
1.15 AS-BUILT DRAWINGS
1.16 USE OF ROADWAYS
1.17 TEMPORARY TOILETS
1.18 AVAILABILITY AND USE OF UTILITY SERVICES
1.19 INSTRUCTIONS
1.20 GOVERNMENT-FURNISHED PROPERTY
1.21 RELOCATED EQUIPMENT
1.22 CONSTRUCTION SIGN
1.23 SAFETY SIGN
1.24 CONSTRUCTION DIGITAL IMAGES
1.25 FINAL ELEVATION PHOTOGRAPHS
1.26 HISTORIC PRESERVATION
1.27 PROJECT HEALTH AND SAFETY PLAN
ii
This page intentionally blank
GENERAL REQUIREMENTS
01 00 02 - 1
SECTION 01 00 02
GENERAL REQUIREMENTS (MINOR NCA PROJECTS)
1.1 GENERAL INTENTION
A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor, materials, equipment and services and perform and complete all work for Gravesite Expansion and Cemetery Improvements at Chattanooga
National Cemetery as required by drawings and specifications.
B. Visits to the site by Bidders may be made only by appointment with the
Cemetery Director.
C. Offices of JG&A, as Architect-Engineers (A/E), may render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting Officers Representative (COR) or his duly authorized representative.
D. All Testing Laboratory services will be retained and paid for by the
Contractor (see Spec Section 01 45 29, Testing Laboratory Services).
However, the Department of Veterans Affairs may elect to retain its own
Testing Laboratory for any purpose. Before placement and installation of work subject to tests by testing laboratory retained by Department of Veterans Affairs, the Contractor shall notify the CO/COR in sufficient time to enable testing laboratory personnel to be present at the site in time for proper taking and testing of specimens and field inspection. Such prior notice shall be not less than three work days unless otherwise designated by the CO/COR.
E. All employees of general contractor and subcontractors shall comply with security requirements as established by the Government, be identified by name and employer. They shall be restricted from unauthorized access.
F. Prior to commencing work, general contractor shall provide proof that a
OSHA certified “competent person” (CP) (29 CFR 1926.20(b)(2) will maintain a presence at the work site whenever the general or subcontractors are present.
G. Training:
1. All employees of general contractor or subcontractors shall, at the minimum, have successfully completed the 10-hour OSHA certified
01 00 02 - 2
Construction Safety course and/or other relevant competency training, as determined by VA CP.
2. Submit OSHA training records of all employees for approval before the start of work.
H. Working Hours: Working Hours: Contractor shall be permitted to work between the hours of 8:00 am and 4:30pm unless approved by CO/COR and
Cemetery Director. Coordinate with Cemetery staff on the schedule of services each week and any required adjustments to working hours.
1.2 STATEMENT OF BID ITEM(S)
A. ITEM I, GENERAL CONSTRUCTION: Installation of all work shown on the plans and described in the specifications including but not limited to:
site clearing and demolition, site grading, concrete, unit paving, in-ground cremains units, committal services shelter, asphalt paving, asphalt paving milling and repaving, landscaping, irrigation, site furnishings, signage and storm drainage.
1.3 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
A. AFTER AWARD OF CONTRACT, electronic .pdf set(s) of specifications and drawings will be furnished.
B. Additional sets of drawings may be made by the Contractor, at
Contractor's expense, from digital files furnished by the Issuing
Office.
1.4 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Plan:
1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.
2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.
B. Security Procedures:
1. General Contractor’s employees shall not enter the project site without following the procedures approved by the CO/COR. They may also be subject to inspection of their personal effects when entering or leaving the project site.
2. For working outside the “regular hours” as defined in the contract, The General Contractor shall give 3 days’ notice to the CO/COR so that appropriate arrangements can be provided for the Cemetery
01 00 02 - 3 employees. This notice is separate from any notices required for utility shutdown described later in this section.
3. No photography of VA premises is allowed without written permission of the CO/COR.
4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the CO/COR.
C. Key Control:
1. The General Contractor shall provide duplicate keys and lock combinations to the CO/COR for the purpose of security inspections of every area of project including tool boxes and parked machines, and to take any necessary emergency action.
1.5 FIRE SAFETY
A. Applicable Publications: Publications listed below form part of this
Article to the extent referenced. Publications are referenced in text by basic designations only.
1. American Society for Testing and Materials (ASTM):
E84-2009a Surface Burning Characteristics of Building
Materials
2. National Fire Protection Association (NFPA):
10-2010 Standard for Portable Fire Extinguishers
30-2008 Flammable and Combustible Liquids Code
51B-2009 Standard for Fire Prevention During Welding, Cutting and Other Hot Work
70-2008 National Electrical Code
241-2009 Standard for Safeguarding Construction, Alteration, and Demolition Operations
3. Occupational Safety and Health Administration (OSHA):
29 CFR 1926 Safety and Health Regulations for Construction
B. Fire Safety Plan: Establish and maintain a fire protection program in accordance with 29 CFR 1926. Prior to start of work, prepare a plan detailing project-specific fire safety measures, including periodic status reports, and submit to COCO/COR/Cemetery Director for review for compliance with contract requirements in accordance with Section 01 33
23, SHOP DRAWINGS, PRODUCT DATA AND SAMPLES. Prior to any worker for the contractor or subcontractor’s beginning work, they shall undergo a safety briefing provided by the General Contractor’s competent person
01 00 02 - 4 per OSHA requirements. This briefing shall include information on the construction limits, safety guidelines, means of egress, break areas, work hours, locations of restrooms, use of NCA equipment, etc.
Documentation shall be provided to the CO/COR that individuals have undergone the Contractor’s safety briefing.
C. Site and Building Access: Maintain free and unobstructed access to emergency services and for fire, police and other emergency response forces in accordance with NFPA 241.
D. Separate temporary facilities, such as trailers, storage sheds, and dumpsters, from existing buildings and new construction by distances in accordance with NFPA 241. For small facilities with less than 6 m (20 feet) exposing overall length, separate by 3m (10 feet).
E. Means of Egress: Do not block exiting for occupied buildings, including paths from exits to roads. Minimize disruptions and coordinate with
CO/COR/Cemetery Director.
F. Egress Routes for Construction Workers: Maintain free and unobstructed egress. Inspect daily. Report findings and corrective actions weekly to
CO/COR.
G. Fire Extinguishers: Provide and maintain extinguishers in construction areas and temporary storage areas in accordance with 29 CFR 1926, NFPA
241 and NFPA 10.
H. Flammable and Combustible Liquids: Store, dispense and use liquids in accordance with 29 CFR 1926, NFPA 241 and NFPA 30.
I. Hot Work: Perform and safeguard hot work operations in accordance with
NFPA 241 and NFPA 51B. Coordinate with CO/COR.
J. Fire Hazard Prevention and Safety Inspections: Inspect entire construction areas weekly. Coordinate with, and report findings and corrective actions weekly to CO/COR.
K. Smoking: Smoking is prohibited in and adjacent to construction areas inside existing buildings and additions under construction. P.
Dispose of waste and debris in accordance with NFPA 241. Remove from site weekly.
L. Perform other construction, alteration and demolition operations in accordance with 29 CFR 1926.
1.6 OPERATIONS AND STORAGE AREAS
A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the CO/COR. The Contractor shall hold and save the Government, its
01 00 02 - 5 officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
B. Temporary buildings (e.g., storage trailers, office trailers) and utilities may be erected by the Contractor only with the approval of the CO/COR and shall be built with labor and materials furnished by the
Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the Contractor and shall be removed by the Contractor at its expense upon completion of the work.
C. The Contractor shall, under regulations prescribed by the CO/COR, use only established roadways, or use temporary roadways constructed by the
Contractor when and as authorized by the CO/COR. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the
Contractor shall protect them from damage. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
D. Working space and space available for storing materials shall be as shown on the drawings. as determined by the CO/COR with agreement of the Cemetery. Contractor parking will be only in areas and on roadways designated and agreed to by the CO/COR in agreement of the Cemetery.
E. Workmen are subject to rules of the Cemetery applicable to their conduct.
F. Execute work so as to interfere as little as possible with normal functioning of Cemetery as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others.
1. Do not store materials and equipment in other than assigned areas.
2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by the Cemetery in quantities sufficient for not more than two work days. Provide unobstructed access to the Cemetery areas required to remain in operation.
3. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.
01 00 02 - 6
G. Phasing: Refer to Access and Phasing Plans.
H. The Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the Cemetery’s operations will not be hindered. The Contractor shall permit access to Cemetery personnel through other construction areas which serve as routes of access to such affected areas and equipment. Coordinate alteration work in areas occupied by Cemetery Staff so that Cemetery operations will continue during the construction period.
2. Immediate areas of alterations not mentioned in preceding
Subparagraph 1 will be temporarily vacated while alterations are performed.
I. Construction Fence: Before construction operations begin, the
Contractor shall provide a chain link construction fence, 2.1m (seven feet) minimum height, around the construction area indicated on the drawings. Provide gates as required for access with necessary hardware, including hasps and padlocks. Fasten fence fabric to terminal posts with tension bands and to line posts and top and bottom rails with tie wires spaced at maximum 375mm (15 inches). Bottom of fences shall extend to 25mm (one inch) above grade. The temporary fencing shall encompass the construction work area(s) to serve as a pedestrian barrier to alert cemetery patrons of the construction site. Remove the fence when directed by CO/COR.
1. Install polyethylene knitted design privacy screen to construction fence as noted on drawings. Visibility Blockage: 85%. Tape and brass grommets placed evenly 12'' O.C. on all 4 sides. Fabricated with
2.5'' binding. Double grommets on every corner edge for extra strength.
J. Utilities Services: Maintain existing utility services for the Cemetery at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services.
Where necessary to cut existing water, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by CO/COR. All such actions shall be coordinated with the Utility Company involved.
01 00 02 - 7
1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of CO/COR.
2. The Contractor shall submit a request to interrupt any such services to both CO/COR and the Cemetery Director in writing, 48 hours in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.
3. The Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of the Cemetery. Interruption time approved by the Cemetery and CO/COR may occur at other than
Contractor's normal working hours.
4. Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the CO/COR.
5. In case of a contract construction emergency, service will be interrupted on approval of CO/COR. Such approval will be confirmed in writing as soon as practical.
6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.
K. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, which are to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged. The lines shall not be capped in finished areas, but shall be removed and sealed.
L. To minimize interference of construction activities with flow of
Cemetery traffic, comply with the following:
1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles. Wherever excavation for new utility lines cross existing roads, at least one lane must be open to traffic at all times.
2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the CO/COR.
01 00 02 - 8
M. Coordinate the work for this contract with other construction operations as directed by CO/COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF
ROADWAYS.
N. Coordination of Construction with Cemetery Director: The burial activities at Chattanooga National Cemetery shall take precedence over construction activities. The Contractor must cooperate and coordinate with the Cemetery Director, through the CO/COR, in arranging construction schedule to cause the least possible interference with
Cemetery activities in actual burial areas. Construction noise during the committal services shall not disturb the service. Trucks and workmen shall not pass through the service area during this period.
1. The Contractor is required to discontinue his work sufficiently in advance of Easter Sunday, Mother's Day, Father's Day, Memorial Day, Veteran's Day and/or Federal holidays, to permit him to clean up all areas of operation adjacent to existing burial plots before these dates.
2. Cleaning up shall include the removal of all equipment, tools, materials and debris and leaving the areas in a clean, neat condition.
1.7 ALTERATIONS
A. Survey: Before any work is started, the Contractor shall make a thorough survey with the CO/COR of areas in which alterations occur and areas which are anticipated routes of access, and furnish a signed report, to the Contracting Officer.
1. Existing condition and types of site amenities not required to be altered throughout affected areas.
2. Existence and conditions of items such as section markers and trash receptacles, required by drawings to be either reused or relocated, or both.
3. Shall note any trees requiring pruning to allow for construction vehicle access and circulation. Refer to paragraph 1.6 TREE
PROTECTION, Section 01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS, for tree pruning requirements.
4. Shall note any discrepancies between drawings and existing conditions at site.
B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of
01 00 02 - 9
CO/COR, to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by the Contractor with new items in accordance with specifications which will be furnished by the Government. Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled "DIFFERING SITE CONDITIONS" (FAR
52.236-2) and "CHANGES" (FAR 52.243-4 and VAAR 852.236-88).
C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and CO/COR together shall make a thorough re-survey of the areas involved. They shall furnish a report on conditions then existing, of site amenities as compared with conditions of same as noted in first condition survey report.
1. Re-survey report shall also list any damage caused by the Contractor to such site amenities, despite protection measures; and, will form the basis for determining extent of repair work required of the
Contractor to restore damage caused by the Contractor's workmen in executing work of this contract.
D. Protection: Provide the following protective measures:
1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.
2. Protect the interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, any indicated surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.
3. Protect trees and landscape to remain according to Specification
Section 01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS
4. Protect existing curbs with plywood mat.
1.8 ENVIRONMENTAL CONTROLS
A. In general, following preventive measures shall be adopted during construction to keep down dust and prevent mold.
1. Dampen debris to keep down dust and provide temporary construction partitions in existing structures where directed by CO/COR. Block off ducts and diffusers to prevent circulation of dust into occupied areas during construction.
B. Final Cleanup:
01 00 02 - 10
1. Upon completion of the project, or as work progresses, remove all construction debris from above ceiling, vertical shafts and utility chases that have been part of the construction.
2. All new air ducts shall be cleaned prior to final inspection.
1.9 DISPOSAL AND RETENTION
A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:
1. Reserved items which are to remain property of the Government are noted on drawings or in specifications as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by CO/COR.
2. Items not reserved shall become property of the Contractor and be removed by Contractor from the Cemetery.
1.10 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND
IMPROVEMENTS
A. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so, and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workmen, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the CO/COR.
B. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the
Contractor fails or refuses to repair the damage promptly, the CO/COR may have the necessary work performed and charge the cost to the
Contractor.
01 00 02 - 11
C. Refer to Section 01 57 19, TEMPORARY ENVIRONMENTAL CONTROLS, for additional requirements on protecting vegetation, soils and the environment. Refer to Articles, "Alterations", "Restoration", and
"Operations and Storage Areas" for additional instructions concerning repair of damage to structures and site improvements.
D. Refer to FAR clause 52.236-7, "Permits and Responsibilities," which is included in General Conditions. A National Pollutant Discharge
Elimination System (NPDES) permit is required for this project. The
Contractor is considered an "operator" under the permit and has extensive responsibility for compliance with permit requirements. VA will make the permit application available at the (appropriate NCA
Central/Cemetery) office. The contractor and affected subcontractors shall furnish all information and certifications that are required to comply with the permit process and permit requirements. Many of the permit requirements will be satisfied by completing construction as shown and specified. Some requirements involve the Contractor's method of operations and operations planning and the Contractor is responsible for employing best management practices. The affected activities often include, but are not limited to the following:
1. Designating areas for equipment maintenance and repair;
2. Providing waste receptacles at convenient locations and provide regular collection of wastes;
3. Locating equipment wash down areas on site, and provide appropriate control of wash-waters;
4. Providing protected storage areas for chemicals, paints, solvents, fertilizers, and other potentially toxic materials; and
5. Providing adequately maintained sanitary facilities.
1.11 RESTORATION
A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any water/irrigation or electric work without approval of the CO/COR.
Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the CO/COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.
01 00 02 - 12
B. Upon completion of contract, deliver work complete and undamaged.
Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, landscape stone, lawns, paving, roads, walks, etc.)
disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.
C. At the Contractor's own expense, the Contractor shall immediately restore to service and repair any damage caused by the Contractor's workmen to existing piping and conduits, wires, cables, etc., of utility services, fire protection systems, communications systems
(including telephone) irrigation system control and power which are indicated on drawings and which are not scheduled for discontinuance or abandonment.
D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES"
(FAR 52.243-4 and VAAR 852.236-88) and "DIFFERING SITE CONDITIONS" (FAR
52.236-2).
1.12 PHYSICAL DATA
A. Data and information furnished or referred to below is for the
Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.
B. A copy of the geotechnical investigation report is included in the specifications and shall be considered part of the contract documents.
C. The Government does not guarantee that other materials will not be encountered nor that proportions, conditions or character of several materials will not vary from those indicated by explorations. Bidders are expected to examine the site of work and logs of borings and, after investigation, decide for themselves the character of materials and make their bids accordingly. Upon proper application to the Department of Veterans Affairs, including approved scheduling bidders will be permitted to make subsurface explorations of their own at site.
1.13 PROFESSIONAL SURVEYING SERVICES
A registered professional land surveyor or registered civil engineer whose services are retained and paid for by the Contractor shall perform services specified herein and in other specification sections.
01 00 02 - 13
The Contractor shall certify that the land surveyor or civil engineer is not one who is a regular employee of the Contractor, and that the land surveyor or civil engineer has no financial interest in this contract.
1.14 LAYOUT OF WORK
A. The Contractor shall lay out the work from Government established base lines and bench marks indicated on the drawings, and shall be responsible for all measurements in connection with the layout. The
Contractor shall furnish, at the Contractor's own expense, all stakes, templates, platforms, equipment, tools, materials, and labor required to lay out any part of the work. The Contractor shall be responsible for executing the work to the lines and grades that may be established or indicated by the CO/COR. The Contractor shall also be responsible for maintaining and preserving all stakes and other marks established by the CO/COR until authorized to remove them. If such marks are destroyed by the Contractor or through Contractor's negligence before their removal is authorized, the CO/COR may replace them and deduct the expense of the replacement from any amounts due or to become due to the
Contractor.
B. Establish and plainly mark center lines for each building and/or addition to each existing building, lines for each gravesite control monument, and such other lines and grades that are reasonably necessary to properly assure that location, orientation, and elevations established for each such structure and/or addition, roads, parking lots, gravesite control monuments, are in accordance with lines and elevations shown on contract drawings.
C. Following completion of general mass excavation and before any other permanent work is performed, establish and plainly mark (through use of appropriate batter boards or other means) sufficient additional survey control points or system of points as may be necessary to assure proper alignment, orientation, and grade of all major features of work. The
Survey shall include, but not be limited to, location of lines and grades of footings, exterior walls, center lines of columns in both directions, major utilities and elevations of floor slabs:
1. Such additional survey control points or system of points thus established shall be checked and certified by a registered land surveyor or registered civil engineer. Furnish such certification to the CO/COR before any work (such as footings, floor slabs, 01 00 02 - 14 foundation slabs, columns, walls, utilities and other major controlling features) is placed.
D. During progress of work, the Contractor shall have lines, grades, locations and plumbness of all major form work checked and certified by a registered land surveyor or registered civil engineer as meeting requirements of contract drawings. Furnish such certification to the
CO/COR before any major items of concrete work are placed. In addition, furnish to the CO/COR certificates from a registered land surveyor or registered civil engineer that the following work is complete in every respect as required by contract drawings.
1. Lines of each structure and/or addition.
2. Elevations of bottoms of footings and tops of floors of each building and/or addition.
3. Lines and elevations of sewers and of all outside distribution systems.
4. Lines of grave plot documentation.
5. Lines of elevations of all swales and interment areas.
6. Lines and elevations of roads, streets and parking lots.
7. Lines and elevations and location of top of pre-placed crypts within their respective plots.
8. Lines and elevations of grade over pre-placed crypts.
9. Northing/Easting coordinate locations and elevation depth below finished grade of all water, sanitary, storm, gas and irrigation structures, directional fittings, control wire and lines.
10. Northing/Easting coordinate locations and elevation for each gravesite grid monument.
E. Upon completion of the work, the Contractor shall furnish the CO/COR with reproducible drawings, in AutoCAD form, at the scale of the contract drawings, showing the finished grade on the grid developed for constructing the work. These drawings shall bear the seal of the registered land surveyor or registered civil engineer.
F. The Contractor shall perform the surveying and layout work of this and other articles and specifications in accordance with the provisions of
Article "Professional Surveying Services".
1.15 AS-BUILT DRAWINGS
A. The Contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, which will include all contract changes, modifications and clarifications.
01 00 02 - 15
B. All variations shall be shown in the same general detail as used in the contract drawings. To insure compliance, as-built drawings shall be made available for the CO/COR's review, as often as requested.
C. The Contractor shall deliver two approved completed sets of as-built drawings to the CO/COR within 15 calendar days after acceptance of the project by the CO/COR.
D. Paragraphs A, B, & C shall also apply to all shop drawings.
1.16 USE OF ROADWAYS
A. For hauling, use only established public roads and designated permanent roads on Cemetery property and, when indicated or authorized by the
CO/COR, such existing or Contractor constructed and/or modified temporary roads which are necessary in the performance of contract work. Temporary roads shall be constructed or modified by the
Contractor at the Contractor's expense following approved plans that include: construction, operation, maintenance and restoration. When necessary to cross curbing, sidewalks, or similar construction, they must be protected by well-constructed bridges.
B. When new permanent roads are to be a part of this contract, the
Contractor may construct them immediately to facilitate building operations. These roads may be used by all who have business thereon within zone of building operations.
1.17 TEMPORARY TOILETS
A. Provide where directed, (for use of all Contractor's workers) ample temporary sanitary toilet accommodations with suitable sewer and water connections, or when approved by CO/COR provide suitable dry closets where directed. Keep such places clean and free from flies, and all connections and appliances connected therewith are to be removed prior to completion of contract, and premises left perfectly clean.
1.18 AVAILABILITY AND USE OF UTILITY SERVICES
A. The Government shall make all reasonably required amounts of utilities available to the Contractor from existing outlets and supplies, as specified in the contract. The amount to be paid by the Contractor for chargeable electrical services shall be the prevailing rates charged to the Government. The Contractor shall carefully conserve any utilities furnished without charge.
B. Heat: Furnish temporary heat necessary to prevent injury to work and materials through dampness and cold. Use of open salamanders or any temporary heating devices which may be fire hazards or may smoke and
01 00 02 - 16 damage finished work, will not be permitted. Maintain minimum temperatures as specified for various materials:
C. Electricity (for Construction and Testing): Furnish all temporary electric services.
1. Obtain electricity by connecting to the Cemetery electrical distribution system. The Contractor shall meter and pay for electricity required for electric cranes and hoisting devices, electrical welding devices and any electrical heating devices providing temporary heat. Where not available or not convenient to connect to the Cemetery distribution system, the contractor shall supply power via portable generators at own expense. Generators shall be acoustically screened so as not to disturb committal services and/or visitation to the adjacent columbarium.
D. Water (for Construction and Testing): Furnish temporary water service.
1. Obtain water by connecting to the Cemetery irrigation distribution system. Backflow preventer may not be required at connections to the irrigation system. Water is available at no cost to the Contractor.
2. If potable water is required and convenient connection is available the contractor may connect to the Cemetery potable water distribution system. The contractor shall install reduced pressure backflow preventer at each connection at own expense.
3. Maintain connections, pipe, fittings and fixtures and conserve water-use so none is wasted. Failure to stop leakage or other wastes will be cause for revocation (at CO/COR's discretion) of use of water from the Cemetery's system.
4. Where not available or not convenient to connect to the Cemetery distribution system, the Contractor shall supply water via portable/temporary means at his own expense.
E. Fuel: Natural and LP gas required for burner cleaning, normal initial burner-burner setup and adjusting, and for performing the specified burner tests will be furnished by the Government. Fuel required for prolonged burner setup, adjustments, or modifications due to improper design or operation of burner, or control devices shall be furnished by the Contractor at Contractor's expense.
F. Conduct final tests required in various sections of specifications in presence of an authorized representative of the RE/COTR. Contractor shall furnish all labor, materials, equipment, instruments, and forms, to conduct and record such tests.
01 00 02 - 17
G. All related components as defined above shall be functioning when any system component is tested. Tests shall be completed within a reasonably short period of time during which operating and environmental conditions remain reasonably constant.
H. Individual test result of any component, where required, will only be accepted when submitted with the test results of related components and of the entire system.
1.19 INSTRUCTIONS
A. The Contractor shall furnish Maintenance and Operating manuals and verbal instructions when required by the various sections of the specifications and as hereinafter specified.
B. Manuals: Maintenance and operating manuals (four copies each) for each separate piece of equipment shall be delivered to the CO/COR coincidental with the delivery of the equipment to the job site.
Manuals shall be complete, detailed guides for the maintenance and operation of equipment. They shall include complete information necessary for starting, adjusting, maintaining in continuous operation for long periods of time and dismantling and reassembling of the complete units and sub-assembly components. Manuals shall include an index covering all component parts clearly cross-referenced to diagrams and illustrations. Illustrations shall include "exploded" views showing and identifying each separate item. Emphasis shall be placed on the use of special tools and instruments. The function of each piece of equipment, component, accessory and control shall be clearly and thoroughly explained. All necessary precautions for the operation of the equipment and the reason for each precaution shall be clearly set forth. Manuals must reference the exact model, style and size of the piece of equipment and system being furnished. Manuals referencing equipment similar to but of a different model, style, and size than that furnished will not be accepted.
C. Instructions: the Contractor shall provide qualified, factory-trained manufacturers' representatives to give detailed instructions to assigned Department of Veterans Affairs personnel in the operation and complete maintenance for each piece of equipment. All such training will be at the job site. These requirements are more specifically detailed in the various technical sections. Instructions for different items of equipment that are component parts of a complete system; shall be given in an integrated, progressive manner. All instructors for
01 00 02 - 18 every piece of component equipment in a system shall be available until instructions for all items included in the system have been completed.
This is to assure proper instruction in the operation of inter-related systems. All instruction periods shall be at such times as scheduled by the CO/COR and shall be considered concluded only when the CO/COR is satisfied in regard to complete and thorough coverage. The Department of Veterans Affairs reserves the right to request the removal of, and substitution for, any instructor who, in the opinion of the CO/COR, does not demonstrate sufficient qualifications in accordance with requirements for instructors above.
1.20 GOVERNMENT-FURNISHED PROPERTY
A. The Government shall deliver to the Contractor, the
Government-furnished property shown on drawings.
B. Materials furnished by the Government to be installed by the Contractor will be furnished to the Contractor at the Cemetery.
C. Storage space for materials will be provided by the Contractor and the
Contractor shall be prepared to unload and store such equipment therein upon its receipt at the Cemetery.
D. Notify CO/COR in writing, 60 days in advance, of date on which
Contractor will be prepared to receive materials furnished by
Government. Arrangements will then be made by the Government for delivery of materials.
1. Immediately upon delivery of materials, the Contractor shall arrange for a joint inspection thereof with a representative of the
Government. At such time the Contractor shall acknowledge receipt of materials described, make notations, and immediately furnish the
Government representative with a written statement as to its condition or shortages.
2. The Contractor thereafter is responsible for such material until such time as acceptance of contract work is made by the Government.
E. Equipment furnished by the Government will be delivered in a partially assembled (knock down) condition in accordance with existing standard commercial practices, complete with all fittings, fastenings, and appliances necessary for connections to respective services installed under contract. All fittings and appliances (i.e., couplings, ells, tees, nipples, piping, conduits, cables, and the like) necessary to make the connection between the Government furnished equipment item and
01 00 02 - 19 the utility stub-up shall be furnished and installed by the contractor at no additional cost to the Government.
F. Completely assemble and install the Government furnished equipment in place ready for proper operation in accordance with specifications and drawings.
G. Furnish supervision of installation of equipment at construction site by qualified factory trained technicians regularly employed by the equipment manufacturer.
1.21 RELOCATED EQUIPMENT
A. Contractor shall disconnect, dismantle as necessary, remove and reinstall in new location, all existing equipment shown to be relocated by the Contractor.
B. Perform relocation of such equipment or items at such times and in such a manner as directed by the CO/COR.
C. Suitably cap existing service lines, such as water, drain, gas, air, and/or electrical, whenever such lines are disconnected from equipment to be relocated. Remove abandoned lines in finished areas and cap as specified herein before under paragraph "Abandoned Lines".
D. Provide all mechanical and electrical service connections, fittings, fastenings and any other materials necessary for assembly and installation of relocated equipment; and leave such equipment in proper operating condition.
E. All service lines such as noted above for relocated equipment shall be in place at point of relocation ready for use before any existing equipment is disconnected. Make relocated existing equipment ready for operation or use immediately after reinstallation.
1.22 CONSTRUCTION SIGN
A. Provide a Construction Sign where directed by the CO/COR. All wood members shall be of framing lumber. Cover sign frame with 0.7 mm (24 gage) galvanized sheet steel nailed securely around edges and on all bearings. Sign face shall be 4 feet x 5 feet and 6 inches. Provide two 100 by 100 mm (4 inch by 4 inch) posts (or equivalent round posts) set 900 mm (three feet) into ground. Set bottom of sign level at 900 mm (three feet) above ground and secure to posts with through bolts.
Make posts full height of sign. Brace posts with 50mm x 100 mm (two by four inch) material as directed.
01 00 02 - 20
B. Paint all surfaces of sign and posts two coats of white semi-gloss paint. Border and letters shall be of black gloss paint, except project title which shall be blue gloss paint.
C. Maintain sign and remove it when directed by the CO/COR.
D. Detail Drawing of construction sign showing required legend and other characteristics of sign is a part of this specification.
1.23 SAFETY SIGN
A. Provide a Safety Sign where directed by CO/COR. Signboard shall be shall be three feet x four feet, 19 mm (3/4-inch) thick exterior grade plywood. Provide two 100 mm by 100 mm (four by four inch) posts extending full height of sign and 900 mm (three feet) into ground. Set bottom of sign level at 1200 mm (four feet) above ground.
B. Paint all surfaces of Safety Sign and posts with one prime coat and two coats of white gloss paint. Letters and design shall be painted with gloss paint of colors noted.
C. Maintain sign and remove it when directed by CO/COR.
D. Detail Drawing of safety sign showing required legend and other characteristics of sign is included in this specification.
E. Post the number of accident free days on a daily basis.
1.24…