TECHNICAL QUESTIONS AND
| SOLICITATION #: |
| 36C77626R0009 |
| RESPONSES TRACKING SHEET |
| PROJECT TITLE: |
| Doris Miller VAMC - EHRM Infrastructure Upgrades Construction Project |
| # |
| RECEIVED |
| ANSWERED |
| CONTRACTOR QUESTION |
| VA RESPONSE |
| 1 |
| 3/10/2026 |
| 3/10/2026 |
| Will the government pay for materials stored per VAAR 852.232-70 and FAR 52.232-5? We have experienced PCAC Contracting Officers refusal to pay for materials stored on site during these periods of material shortages and the need to expedite procurement of materials when available to meet schedule obligations and prevent project delays. This is an important factor in preparing Price proposals. |
| In accordance with contract terms and conditions, Contractors should not submit an offer assuming the Government will approve monthly progress payments for material and/or equipment procured by the Contractor and stored on the construction site, as space is available, or at a local approved location off the site. Payment of stored materials and/or equipment is at the Contracting Officer’s discretion and will be handled on a case-by-case basis during the contract and under such terms and conditions as the Contracting Officer approves. |
| 2 |
| 3/10/2026 |
| 3/10/2026 |
| Please confirm that any designers or consultants who provided professional services for the construction documents, including reports, are precluded from pursuing this project as a Prime contractor, Mentor-Protégé partner, or subcontractor. |
| Any member of the design team of this project is not permitted to be part of the construction team. |
| 3 |
| 3/10/2026 |
| 3/10/2026 |
| Please confirm that this project is a competitive SDVOSB set-aside and that any bonding provided by a contractor must be through a SDVOSB or SBA/VA APPROVED Mentor-Protégé partnership under the SBA/VA Mentor-Protégé program in which the partnership has been approved prior to the due date. |
| This project is set aside for SDVOSBs. The bonding requirements must be met for this project per the applicable clauses, provisions, and instructions to offerors. |
| 4 |
| 3/10/2026 |
| 3/10/2026 |
| Please confirm that a large business not part of an SBA/VA APPROVED Mentor-Protégé team under the VA Mentor-Protégé program cannot provide a bid guarantee or a payment & performance bond for a SDVOSB. |
| This project is set aside for SDVOSBs. The bonding requirements must be met for this project per the applicable clauses, provisions, and instructions to offerors. |
| 5 |
| 3/10/2026 |
| 3/10/2026 |
| When visiting the link, I noticed the project was “set aside for Service-Disabled Veteran Owned Small Business” – does this mean that General Contractors cannot bid the project unless they meet that requirement? |
| Yes, this project is a 100% set-aside for SDVOSBs. The prime contractor submitting the offer must be certified as such in the SBA VetCert database. |
| 6 |
| 3/10/2026 |
| 3/10/2026 |
| Is this project tax exempt? If the project is sales tax exempt will the government/VA provide a sales tax exemption certificate? |
| See Special Note regarding FAR 52.229-3 Federal, State, and Local Taxes in the solicitation. It is solely the responsibility of the offeror to include all state and local sales or use taxes for construction materials, and all other applicable taxes, in their bid or proposal price. |
| 7 |
| 3/10/2026 |
| 3/10/2026 |
| Will the Government provide detailed written requirements for contractor badging? Please clarify the process for obtaining PIV badges, including required documentation, background checks, and estimated processing timeframes. |
| Regardless of affiliation, everyone working within VA facilities or requiring access to VA information systems requires a VA PIV Card. PIV badging requirements can be found at https://www.osp.va.gov/How_To_Get_A_VA_ID_Badge.asp |
Immediately after the bonds are provided to the Government, the contractor shall immediately start working with the identified COR at the site to commence the VA PIV process for all known contractor personnel that will be working the project. All contractors must have a PIV Card in order to work on site.
| 8 |
| 3/10/2026 |
| 3/10/2026 |
| How soon after award is NTP expected to be issued? |
| The Government anticipates issuance within 90 calendar days after award. |
| 9 |
| 3/10/2026 |
| 3/10/2026 |
| Will the VA allow deviations to Buy American Act if the noted products are not available? |
| The process of requesting exceptions to the Buy American Act is detailed in the provision at FAR 52.225-12, Notice of Buy American Requirement—Construction Materials Under Trade Agreements, and the clause at FAR 52.225-11 Buy American—Construction Materials under Trade Agreements, in the solicitation. Any items not compliant must be specifically listed in the offer. |
| 10 |
| 3/10/2026 |
| 3/10/2026 |
| Due to current potentially significant tariffs being placed on the importation of building materials such as wood or steel by the current Presidential Executive Branch, if a tariff is placed after bid time and before award will the government consider a price escalation on a contract value for products such as steel or wood should the executive branch levee tariffs effecting such materials? Most of these materials would still have been Buy American compliant as the tariffs would increase pricing on all steel or wood materials, regardless of origin. |
| This will be awarded as a Firm Fixed Price (FFP) contract and all escalation should be factored in your FFP. Additionally, FAR 52.216-4 “Economic Price Adjustment – Labor and Material” is not included in the solicitation and will not be added. |
| 11 |
| 3/10/2026 |
| 3/10/2026 |
| Please confirm if commissioning is required for this project. |
| All references (SECTION 23 08 00, SECTION 26 08 00, and SECTION 28 08 00, etc) to Cx will be removed. CX is not required for this project. |
| 12 |
| 3/10/2026 |
| 3/10/2026 |
| Also will the VA still keep in VAAR 852.232-71 or will VAAR 852.232-70 replace this Clause? |
| VAAR 852.232-71 is to be replaced by VAAR 852.232-70. This project will now adhere to VAAR 852.232-70. |
| 13 |
| 3/10/2026 |
| 3/10/2026 |
| Could you please clarify whether projects within the $5 million to $10 million range, reflecting comparable technical and operational complexity, are considered acceptable for inclusion in our submission? |
| Page 10 of the Solicitation states: “Size: Have a value exceeding $30 million and have been completed within the past five (5) years”. |
The value has been changed to $15 Million. Projects must be at least 75% completed or have been completed within the past five (5) years from the date proposals are due.
| 14 |
| 3/10/2026 |
| 3/10/2026 |
| The solicitation states that subcontractor past performance may be used, provided that at least one submitted project was completed by the prime contractor. If an offeror submits one qualifying project performed by the prime contractor and one qualifying project performed by a subcontractor, will this approach be evaluated less favorably than submissions where both projects were performed by the prime? |
| The projects submitted that meet the requirements will be reviewed based on the methodology. |
| 15 |
| 3/10/2026 |
| 3/10/2026 |
| An attachment sheet was provided for past performance experience. Please confirm whether this attachment is also required to be completed for subcontractor past performance projects when such experience is submitted. |
| Yes, this attachment is required to be completed for subcontractor past performance projects. |
| 16 |
| 3/10/2026 |
| 3/10/2026 |
| If subcontractor past performance is utilized, are subcontractors required to submit Past Performance Questionnaires (PPQs) and/or CPARS documentation for their referenced projects? |
| Yes, subcontractors are required to submit Past Performance Questionnaires and/or CPARS documentation for referenced projects. |
| 17 |
| 3/10/2026 |
| 3/10/2026 |
| If an offeror has an EHRM project that is relevant in scope and complexity but does not meet the $30 million threshold, would this project still be considered acceptable or otherwise evaluated as part of the past performance submission? |
| No, this project would not meet the minimum size requirement. |
Please refer to Technical Question #15, which has lowered the minimum size requirement to $15 Million.
| 18 |
| 3/10/2026 |
| VA |
| Will there be PLA requirements on this project? |
| Contractors shall comply with all applicable federal labor standards and contract clauses as included in the solicitation. |
| 19 |
| 3/10/2026 |
| VA |
| As this project is a small business set-aside please confirm FAR clauses 52.225-11 and 52.225-12 are applicable on this contract |
| Contractor shall comply fully with all Contract Documents. In the event of discrepancies, Contractor shall perform all work required to deliver a complete, functional system per applicable specifications, drawings, and VA standards. No additional compensation will be allowed for coordination or interpretation of contract requirements. |
| 20 |
| 3/10/2026 |
| VA |
| Is this project tax-exempt? If so, will a certificate be provided? |
| This project is not tax-exempt for purposes of contractor material purchases. In accordance with FAR 52.229-3, contractors shall include all applicable federal, state, and local taxes in their proposal. The VA will not provide a tax exemption certificate. |
| 21 |
| 3/10/2026 |
| VA |
| Please confirm this project must meet the buy American act requirements. |
| Yes. The project must comply with the Buy American Act requirements as stated in the solicitation, including all referenced FAR clauses. Any non-compliant items must be identified in the proposal per solicitation requirements. |
| 22 |
| 3/10/2026 |
| VA |
| The VA’s Master Specification 01 32 16.15, 'Project Schedules' (Small Projects – Design/Bid/Build), was revised effective December 1, 2025. The updated version is now available on the Technical Information Library (TIL). Will the VA be updating the 01 32 16.15 spec for this project to include this spec instead of the older one? |
| 01 32 16.16 Project Schedules will be revised and provided. |
| 23 |
| 3/10/2026 |
| IMEG |
| There are several Buildings that that only show 1 cable entry point for the new fiber cables. For instance, building 225 only shows 1. Is the contractor to utilize the same conduit for both A & B fiber routes in this instance? |
0. If the answer is yes, is the contractor required to utilize diverse path around the campus for these buildings?
0. If yes can the VA specify what buildings can utilize a single pathway for clarity?
Certain non-clinical buildings were approved to only have (1) route into the building.
A. A & B fiber routes throughout the campus must remain diverse up to the consolidated building enter point.
These instances are already coordinated and represented on the construction drawings.
VA
1. What is the ICRA classification for this project bearing in mind many of the TR rooms will require dust & noise generating work?
2. Will there be a public bid opening for this project?
1. Assume level 4
2. There will be no public bid opening as this is a Request for Proposal.
| 25 |
| 3/10/2026 |
| IMEG |
| 1. Drawing # TN426 under sequence notes: # 5 Contractor to relocate existing fiber to Campus to server rack. Can the VA quantify how many cables and strands are required to relocate? |
2. Drawing # TN426 can the VA verify that the contractor is to furnish and install the 18”x4” cable tray and 4”x4” fiber trough depicted in the drawing?
1. Quantity of fibers to be relocated is to be determined based on demolition sequence and installation plan provided by the contractor. Contractor to provide cost to support full removal of cables from rack for proposed plan.
2. Yes, the contractor to provide install.
| 27 |
| 3/10/2026 |
| IMEG |
| ET series drawings for CCTV camera. Bid spec documents do not specify what systems are currently in place for this project. Please answer the following questions: |
a. What is the manufacturer of the current video management system?
b. What version/existing is the current video management system operating?
c. Are we expected to support version upgrades as part of this contract?
d. Are there sufficient existing licenses to support the new cameras?
e. Are the cameras to be 2MP pan/tilt/zoom or fixed dome?
f. Is there a current vendor/installer of this system that we can contact. Please provide contact information.
A. Contractor shall provide a complete turnkey extension of the existing system.
B. This will need to be determined during the procurement of the system.
C. Refer to the specifications.
D. Refer to response C.
E. Refer to the equipment schedule on T-700 for performance requirements. Cameras are to be a minimum of 5 MP as shown on the drawings.
F. ILLUSTRA PRO GEN4 2MP MINIDOME, 2.7-13.5MM,
INDOOR/OUTDOOR, IP67, IK10, TDN W/IR, TWDR.
| 28 |
| 3/10/2026 |
| IMEG |
| ET series drawings for card reader/pin pad. Bid spec documents do not specify what systems are currently in place for this project. Please answer the following questions: |
a. What is the manufacturer of the current access control system?
b. What version/existing software is the access control system operating on?
c. Are we expected to support the version? updates as part of the contract?
d. Are there sufficient licenses to support the new doors?
e. Is there any existing integration between the access control and CCTV systems?
f. Is there a current vendor/installer of this system that we can contact? Please provide contact information.
A. Software house. Contractor shall provide an extension of the existing system.
B. This will need to be determined during the procurement of the system.
C. Refer to the specifications.
D. All new licenses are to be provided. Refer to specifications for additional information.
E. These are separate systems.
F. CARD READER - HID multiCLASS: RP40E-920P DUAL AUTHENTICATION - HID multiCLASS: RPK40E-921P ELECTRIFIED LOCKING HARDWARE (1500c-DLMS-630 made by HES)
ELECTRIFIED LOCKING HARDWARE WITH
INTEGRATED REQUEST TO EXIT (MG-250M/MG-500M/IMXDa-12/24)
| 29 |
| 3/10/2026 |
| VA |
| Is there an allowance of Cat 6A cables & 1” data rough-in that should be carried within the Div.26&27 pricing? Some previous requirements on other projects requested 5%-10% additional Cat 6A cables and 1” data rough-in to cover what may have been missed during design. Please advise. |
| Provide a 10% allowance for additional cable installation. A/E to provide direction on use of allowance. If allowance is not used, contractor shall provide allowance credit back to VA at end of construction. |
| 30 |
| 3/10/2026 |
| IMEG |
| Existing Fire Alarm System. |
a. Is there a current maintenance vendor/installer of this system that we can contact? Please provide contact information.
There is an existing campus-wide fire alarm system on site. The manufacturer is Simplex, the point of contact may be obtain from the VA.
VA
Existing Nurse Call System.
a. Is there a current maintenance vendor/installer of this system that we can contact? Please provide contact information.
This is outside the scope of the project.
| 32 |
| 3/10/2026 |
| IMEG |
| Is conduit required for grounding conductors running/installed ceiling & risers? |
| Refer to grounding specifications and drawings for additional information. Grounding shall be installed per code. |
| 33 |
| 3/10/2026 |
| VA |
| Is there a requirement for x-ray scanning of concrete floor slabs prior to core drilling for floor-to-floor sleeves/conduits? |
| Yes. Non-destructive scanning (e.g., GPR or equivalent) is required prior to coring or drilling in structural slabs. Contractor shall include scanning costs in base bid. |
| 34 |
| 3/10/2026 |
| VA |
| Is there a location where site asphalt and concrete can be stored/separated? Can this material be removed from the site once per week? |
| Potential temporary staging locations will be identified post-award in coordination with the COR. Material separation and storage must comply with VA environmental and site control requirements. Removal frequency shall be coordinated but shall not disrupt operations. |
| 35 |
| 3/10/2026 |
| VA |
| 1Will soil testing be performed prior to construction, to determine if any soils are contaminated? |
| No contaminated soil has been identified in design documents. Contractor shall comply with all environmental regulations. If suspect material is encountered, COR notified immediately. |
| 36 |
| 3/10/2026 |
| VA |
| Is there a location where spoil dirt can be stored? |
| Spoil location is determined by the Director and is dependent on amount of contractors are working on the campus and the amount of spoils needed to be stored. |
| 37 |
| 3/10/2026 |
| VA |
| Is there a specific location that will be used as a laydown yard during construction? |
| See Sheet C-104 for laydown yard location. Coordinate with COR after award for final laydown configuration. |
| 38 |
| 3/10/2026 |
| SBCC |
| Will erosion control plans be provided? |
| No. The site disturbance is expected to just exceed 1 acre but be less than 5 acres, which will require the contractor to prepare a SWPPP in accordance with the TCEQ Statewide General Construction Permit. |
| 39 |
| 3/10/2026 |
| SBCC |
| Have there been any boring samples/tests made for the duct bank pathway/trench to determine the subsurface condition? |
| No geotechnical investigations were performed, and no existing geotechnical information was made available during the design. No additional information is available. |
| 40 |
| 3/10/2026 |
| IMEG |
| WAO/WAP/CAM-Is this a 1-for-1 replacement for existing cables? |
| Refer to notes on outlet schedule on T-700. |
| 41 |
| 3/10/2026 |
| IMEG |
| Is a full survey of every room/above ceiling required to confirm cable count & WAO location? If so, who determines the outlet location and the number of cables per location? |
| Yes, the contractor is to do a full survey of all rooms/spaces and document outlets supplemental to the outlets shown on plan to be reviewed by the A/E. |
| 42 |
| 3/10/2026 |
| IMEG |
| Can the government provide a quantity of CAT6 A cables that need to be installed by TR? Please provide a Drop Count Matrix that needs to be provided. |
| The drawings are not intended to provide a complete bill of materials, including total cable quantities or port counts within telecommunications rooms. These drawings convey design intent, system layout, and performance requirements; not contractor means, methods, or final quantities. As is typical for construction projects, it is the responsibility of the contractors to perform their own detailed quantity take-offs based on the drawings and specifications. This ensures they account for their specific installation approach, routing, and field conditions when developing their proposals. |
| 43 |
| 3/10/2026 |
| IMEG |
| What is the drop count of each coverage zone? If it is a 1-for-1 swap, how many existing drops are located in each coverage zone? |
| Data will be a one for one swap. Voice is to remain. |
| 44 |
| 3/10/2026 |
| IMEG |
| Is a full/complete survey of every room/WAO pathway/above ceiling pathway required to determine if the existing pathway meets the VA/A&E plan T501 detail & spec? |
| Yes, the contractor is to do a full survey of all rooms/spaces and document outlets supplemental to the outlets shown on plan to be reviewed by the A/E. |
The contractor shall be responsible for providing new additional conduit sleeves as required for new cabling pathways. Existing conduits sleeves can be used if conditions and size allow for phasing of new cable installation. Provide new conduit sleeves as necessary. All cable passing through a wall must be installed within a conduit sleeve.
For bidding purposes contractor shall provide cost to include a new surface mount raceway, or fixed flexible conduit in walls, for all locations where outlet existing conditions are insufficient in size/fill capacity, or include open cabling fished down walls. Assume 30% of outlets represent this condition and provide cost for new pathway within bid.
| 45 |
| 3/10/2026 |
| IMEG |
| Are there a count and length for Cat6A patch cords? |
| Provide patch cords for 100% of the outlets. Coordination with VA OIT will be required to determine lengths. Refer to specifications. |
| 46 |
| 3/10/2026 |
| IMEG |
| Are there counts and lengths for Fiber Patch cords? |
| Provide patch cords for 100% of ports. Coordination with VA OIT will be required to determine lengths. Refer to specifications. |
| 47 |
| 3/10/2026 |
| IMEG |
| Is armored fiber acceptable, or is Maxcell or innerduct required for ISP fiber? |
| Refer to Response #85. |
| 48 |
| 3/10/2026 |
| IMEG |
| Clarify that fiber cable is to be installed with J-hooks and/or share the same pathway/cable tray as Cat 6. NO dedicated pathway/conduit system shown on plan for fiber from the OSP. Please advise |
| Refer to pat 3 of specification section 27 13 23 for requirements on fiber pathway. |
Bidding contractor to provide a dedicated non-continuous pathway for fiber optic backbone interior routing. Existing cable tray can be utilized if existing conditions allow suffecient capacity.
| 49 |
| 3/10/2026 |
| IMEG |
| Are there specific lengths for the CAT6A patch Cords? |
| Provide patch cords for 100% of the outlets. Coordination with VA OIT will be required to determine lengths. Refer to specifications. |
| 50 |
| 3/10/2026 |
| IMEG |
| Are we to provide one patch cord at each end for every new CAT6A cable installed? Or will the VA specify a quantity for the Technology contractor to provide? |
| Provide patch cords for 100% of the outlets. Coordination with VA OIT will be required to determine lengths. Refer to specifications. |
| 51 |
| 3/10/2026 |
| IMEG |
| Are we to provide patch cables for each pair of strands at each end? |
| Provide patch cords for 100% of ports. Coordination with VA OIT will be required to determine lengths. Refer to specifications. |
| 52 |
| 3/10/2026 |
| IMEG |
| Are we to provide one fiber jumper on each end for every strand of new Fiber cable installed? Or will the VA specify a quantity for the Technology contractor to provide? |
| Provide patch cords for 100% of ports. Coordination with VA OIT will be required to determine lengths. Refer to specifications. |
| 53 |
| 3/10/2026 |
| IMEG |
| Is there any copper backbone (25-pair or larger) needed? |
| This is not in the scope of the project. |
| 54 |
| 3/10/2026 |
| IMEG |
| Are there specific lengths for the Fiber jumpers? |
| Provide patch cords for 100% of ports. Coordination with VA OIT will be required to determine lengths. Refer to specifications. |
| 55 |
| 3/10/2026 |
| VA |
| Please confirm if we will be allowed to keep a locked storage container or Conex box within the grounds. |
| See Sheet C-104 for laydown yard location. Coordinate with COR after award for final laydown configuration. |
| 56 |
| 3/10/2026 |
| IMEG |
| To confirm that the existing analog phone cable/system to remain & reterminated/tested on new WAO plate, as per “Information Out Schedule” on T700 |
| Yes, existing analog will remain. |
| 57 |
| 3/10/2026 |
| IMEG |
| On the “T” series Plan (Technology plans) shows the cable tray layout/routing in the hallway & corridors with the A&B Fiber backbone installation in the same cable tray as the WAO CAT6 cable. Is the intent to install both fiber and CAT6 cable in the same cable tray? Please advise. |
a. Please confirm/clarify the existing CAM/CCTV location.
b. NO new equipment required, reuse/connect to existing equipment.
c. NO new licensing required
d. Confirm 1 for 1 cabling to the existing CAM/CCTV location
e. Confirm new Cat 6 cable installation to the new TR/rack Fiber and copper can be shared in the same tray. Refer to 27 10 00 part 2.2 for additional information on fiber routing requirements.
A. Provide new permanent link connections to all existing camera locations as noted on plan.
B. Provide new permanent link connections to all existing outlets/equipment locations as noted on plan.
C. Licensing is only required for newly installed cameras in TR spaces.
D. Yes, provide 1 for 1 replacement of permanent link cable.
Incorrect. Category 6A cable. All terminations will route back to new/remodeled TRs as noted on plan.
| 58 |
| 3/10/2026 |
| BT |
| Ref. Drawing A111.1, Detail F5 – Brick Chase Section, drawing note: “New Raised Access Flooring in Data Center- See also Deductive Alt # 1.” |
Is New Access Flooring in the Data Center in the Scope of Work? If yes, please provide a demo and finish drawings, specifications, and bid line-item descriptions.
Delete this note in its entirety. It was left on the sheet in error.
| 59 |
| 3/10/2026 |
| BT |
| Ref. Drawing TN 425, Detail E1 Campus Support Center – Demo shows a partition with windows and two doors at the southeast corner to be removed. |
Ref. Drawing TN 426, Detail E1 Campus Support Center – NEW shows southeast demoed door to corridor infilled and new double door at southwest corner. Please provide New Door Schedule, details of existing and new Server Room flooring and other finishes.
Demolition of the entry to the CSC is not in this contract.
New double door into the CSC is not in this contract.
| 60 |
| 3/10/2026 |
| IMEG |
| Ref. Drawing TN 425, Detail E1 Campus Support Center – Demo shows Mechanical and Electrical equipment with Keynote 3 attached – “Refer to Mechanical and Electrical Drawings for applicable information regarding electrical and mechanical systems.” Ref. Drawing TN 426, Detail E1 Campus Support Center – NEW no longer shows the above mentioned Mechanical and Electrical equipment. |
Following Keynote 3, the Mechanical and Electrical Drawings provide no information regarding electrical and mechanical systems in the Campus Support Center (Server Room 1A106 in Bldg 4).
IMEG: Drawing TN425 Keynote #3 is void. Mechanical and electrical work has been removed from the project scope for room 1A106. Existing mechanical and electrical equipment in Server Room 1A106 shall remain in place. The Server Room Foyer scope and ceiling, including the ramp and related elements, may be removed, as the space is not being fully upgraded to a CSC data center.
| 61 |
| 3/10/2026 |
| IMEG |
| Please clarify the Mechanical and Electrical scopes of work associated with upgrading the Campus Support Center (Server Room 1A106 in Bldg 4). |
| IMEG: No mechanical or electrical work is required. All existing mechanical and electrical equipment shall remain in place for room 1A106. |
| 62 |
| 3/10/2026 |
| BT |
| Ref. Drawing A128, Detail D1 Window Infill describes installing a perforated metal panel on existing windows, but no specifications were provided. |
Please provide the specifications and installation details necessary to ensure appropriate security.
McNICHOLS® Perforated Metal Infill Panels Square, Carbon Steel, Cold Rolled, 16 Gauge (.0598" Thick), 3/8" Square on 1/2" Straight Centers, 56% Open Area – provide standard U-Edging with mitered corners for installation in HM frames.
OR Equal Detail D1 clearly shows how to install the panels.
| 63 |
| 3/10/2026 |
| IMEG |
| T-700 shows: |
Technology Equipment Schedule table - AC-R1-W = card reader with keypad Controlled Security Scheme (CSS) Type Schedule – card reader type = R1 (that is a regular card reader according to T-000). So, what card reader model needs to be provided? With or without a keypad?
Question is unclear. AC-R1-W on T-700 specifies card reader with keypad. Dual authentication, FIPS compliant.
| 64 |
| 3/10/2026 |
| IMEG |
| Confirm camera model on T-700 Technology Equipment Schedule as AXIS P3267-LV. |
Normally, only the Illustra Pro Fisheye 12mp was acceptable for the VA projects.
Provide as specified. Refer to specifications for additional information.
| 65 |
| 3/10/2026 |
| IMEG |
| Does the security integrator need to provide storage for the new cameras, or will they be connected to the existing NVR? If an additional NVR is needed, what are the recording parameters for it? Days of storage, FPS, etc. |
| Storage and licenses need to be provided for all new cameras. Existing cameras are to remain with the existing NVR. |
| 66 |
| 3/10/2026 |
| IMEG |
| Building Enlarged Plans (TN400 to TN424) show a motion detector on each Telecom Room, but Controlled Security Scheme (CSS) Type Schedule on TN-700 does not show the motion detector to be provided. Please clarify. |
| An intrusion detection motion detector is required in each of the telecom rooms as shown on plan. Refer to ID-MD1-C on T-700 for information on the equipment. |
| 67 |
| 3/10/2026 |
| IMEG |
| If motion detectors need to be provided, where will they be connected? To the closest access control panel or to an intrusion detection system? If connected to the intrusion detection system, what is the manufacturer? Where are the panels located, and should the security integrator provide expansion boards? |
| The motion detector will be tied to the nearest intrusion detection panel as an extension of the existing system. |
| 68 |
| 3/10/2026 |
| VA |
| Is there a proprietary Fire Alarm Contractor at the facility? If so, please provide the company name and point of contact. |
| No |
| 69 |
| 3/10/2026 |
| VA |
| Is there a proprietary Controls Contractor at the facility? If so, please provide the company name and point of contact. |
| JCI |
| 70 |
| 3/10/2026 |
| VA |
| Is there a proprietary Cameras at the facility? If so, please provide the company name and point of contact. |
| Refer to Contract Documents |
| 71 |
| 3/10/2026 |
| VA |
| For tech requirements, concerning page limitations: Can you confirm that (CPARS/PPQs, Draft Project Schedule, etc.) does not count towards page limitations? |
| Please refer to Section 2.8 – Proposal Requirements for applicable exclusions from the page limitations. |
| 72 |
| 3/10/2026 |
| VA |
| Reference Solicitation Page 9 of 72 Volume 1 Past Performance paragraph b. |
a. Paragraph b. defines what’s considered a page and mentions a project schedule, but is not mentioned under Volume 1 Past Performance, Proposal Requirements. Please confirm a project schedule is not required for the proposal.
Confirmed. A schedule is not required.
| 73 |
| 3/10/2026 |
| BT |
| Reference Drawing A111 Detail F1 B4-1A135 New TR: |
a. Please provide door schedule for New TR B4-1A135
DOOR 1A135
W=3’-0”; H=7’-0”;
DOOR TYPE=EXG;
DR MAT’L/FIN=WD/STAIN;
FRAME TYPE=DOUBLE RABBET;
FRAME MAT’L/FIN=HM/PAINT;
HARDWARE=HW-SH-3D
DOOR BA165
EXISTING DOOR WITH NEW HARDWARE = HW-SH-3D
| 74 |
| 3/10/2026 |
| BT |
| Reference Drawing A113 Building 5 Door Schedule: |
a. Door schedule references Building 5 door 122. Is this a new door only? Where is room 122 located in building 5?
Delete reference to door 122 in building 5. It is an existing door that should not have appeared in the schedule.
| 75 |
| 3/10/2026 |
| SBCC |
| C-501 – Detail 2 Note 4 |
a. Note 4 indicates a sump but there are no related drawings for a detail install or electrical or plumping drawings indicated power and plumbing for sump.
b. Are we just to provide a cover at the bottom of the manhole for a future sump?
There is no powered sump required to be placed in the bottom of the pull box. The cover shall be provided at the base of the pull box per the mfgr and this provides a low spot to drain the pull box to the crushed stone base placed below the pullbox when installed per the mfgr recommendations.
| 76 |
| 3/10/2026 |
| IMEG |
| Reference Drawing T100 fiber pathway matrix. |
a. Please confirm the pathways shown for fiber A and Fiber B are correct. Example Building 91: Matrix shows Pathway A as MH’s A-B-C-D-E, that only gets you to building 10. Should the pathway be MH’s A-B-C-D-E-F-F1? Matrix shows pathway B as MH’s P-O-N-M-L-K-J-I-H-G-F which starts at Building 5. Should the pathway include starting at Building 4 and MH’s S-R-Q Yes, the pathway should be A-B-C-D-E-F-F1. All B leg fiber will route through maintenance hole S. All A leg fiber will route through maintenance hole A.
| 77 |
| 3/10/2026 |
| IMEG |
| Reference Drawings T100, TN128, TN 120, TN116, and T600 |
a. Buildings 90, 8, and 6 are not listed in the fiber matrix please confirm no new fiber is to be run to these buildings.
b. Please confirm no data drop work is to be performed on these buildings A. Fiber is required for Buildings 6 and 8. Building 90 does not require any fiber. As shown on plans.
B. Building 6, 8 and 90 does not data cabling renovation scope. As shown on plans.
| 78 |
| 3/10/2026 |
| BT |
| There are no enlarged drawings for buildings 90,8, and 6 please confirm no new TR/TE equipment is to be provided for these buildings. |
| Confirmed. However, there is fiber coming into and going out of these buildings. See civil and Technology drawings. |
| 79 |
| 3/10/2026 |
| IMEG |
| Please confirm all drops shown on the TN – Floor Plans are a one for one replacement. |
| Analog voice is to remain, data will be replaced 1 for 1. |
| 80 |
| 3/10/2026 |
| VA |
| 01 45 00 – Quality Control – References 01 45 35 Special Inspections |
a. Confirm that there will be no requirements for special inspections as the 01 45 35 - Special Inspections specifications section was not provided.
b. If required, please provide a schedule or special inspections.
Contractor shall include all required components to deliver a complete and operational system per Contract Documents. Omission of incidental items does not relieve contractor of responsibility to provide a complete installation.
| 81 |
| 3/10/2026 |
| IMEG |
| Reference T-000 Technology Cabling Plan General Note E3 |
a. Please provide the number of locations where new Conduit and backboxes will be required based on the 40% fill requirement.
b. If a number of locations can’t be provided will this work be viewed as an unforeseen condition?
c. If the conduit/backbox work won’t be viewed as an unforeseen site condition, please provide an allowance to be carried for this work.
For bidding purposes contractor shall provide cost to include a new surface mount raceway, or fixed flexible conduit in walls, for all locations where outlet existing conditions are insufficient in size/fill capacity, or include open cabling fished down walls.
Assume 30% of outlets represent this condition and provide cost for new pathway within bid.
| 82 |
| 3/10/2026 |
| BT |
| Is the contractor to assume ceilings in hallways are ACT drop ceilings unless noted otherwise? |
| Most corridor ceilings are suspended ACT. However, there are exceptions, as listed here: Building 16 (open to structure); Building 24 (open to structure); Building 90 (open with some suspended ACT “clouds”); Building 99 (some areas open to structure); Building 189 (open to structure); Building 202 (open to structure with some dropped gypsum board soffits); Building 221 (gypsum board); Building 224 (open to structure); Building 226 (laundry open to structure). |
| 83 |
| 3/10/2026 |
| IMEG |
| Please confirm, are all horizontal interior fiber backbone conduit pathways existing to be reused, or is the contractor to assume these are all to be provided as new? |
| Pathway will be new. Refer to section 27 10 00 part 2.2 for acceptable means of pathway throughout the building. |
Bidding contractor shall be responsible for providing new additional conduit sleeves as required for new cabling pathways should the existing pathway be insufficient. Existing conduit sleeves can be used if conditions and size allow for phasing of new cable installation. Provide new conduit sleeves as necessary. All cabling passing through a wall must be installed in a conduit sleeve.
| 84 |
| 3/10/2026 |
| BT |
| Please confirm, is all work in hallways and work areas to be done during off hours (nights / weekends) so as not to disturb normal facility operations? |
| Some buildings (5, 8, 10, 18) are mostly empty so work can be done during normal business hours. Warehouse buildings (16, 24, 189, 224) area also mostly empty so work can be done during the day. Buildings 7 and 94 will require extra coordination as they have overnight patients and some special security requirements. The rest of the buildings are offices or medical clinics that the GC will coordinate with the VA. |
| 85 |
| 3/10/2026 |
| IMEG |
| Please confirm, will maxcell innerduct be required for exterior underground cable pathways only? Or is the contractor provide maxcell innerduct in all fiber conduit pathways |
| Maxcell fabric innerduct is suggested for any fiber routed in conduit. The bidder may suggest alternates, such as armored fiber in lieu of Maxcell fabric innerduct, provided that the conduit fill ratio does not exceed National Electric Code, Chapter 9, Table 1 fill (40% fill rule). Submittals for alternates will be reviewed by the Contracting Officer Representative (COR) for compliance during the submittal phase after award. |
| 86 |
| 3/10/2026 |
| VA |
| Please confirm, the designated SSHO must be a separate individual from both the designated superintendent and QCM? |
| Yes. The Site Safety and Health Officer (SSHO) shall be a separate individual from the Superintendent and Quality Control Manager (QCM). |
| 87 |
| 3/10/2026 |
| VA |
| Is the contractor required to hire an SIOR to oversee all special inspections? |
| No. The contract does not require the Contractor to hire a Special Inspector of Record (SIOR). |
| 88 |
| 3/10/2026 |
| VA |
| Is the contractor required to hire a 3rd-party firestopping inspector as part of this contract? |
| No. The contract does not require a dedicated third-party firestopping inspector unless explicitly specified. |
| 89 |
| 3/10/2026 |
| VA |
| Is the contractor required to hire a 3rd party geotechnical engineer as part of this project? |
| No. The contract does not require the Contractor to retain a third-party geotechnical engineer unless specifically identified for defined scope activities. |
| 90 |
| 3/10/2026 |
| BT |
| Is the contractor responsible for any abatement of asbestos or hazardous material beyond quantities explicitly provided in the specifications? |
| The Contractor is only responsible for abatement of asbestos or hazardous materials explicitly identified and quantified in the contract documents. |
| 91 |
| 3/10/2026 |
| VA |
| Will the contractor be limited to the amount of rooms / work areas that can be accessed simultaneously? Or will the contractor be allowed to sequence work areas as they see fit to best move the project along to meet the schedule? |
| Scheduling and sequencing will have to be precisely coordinated with COR, Services, and Leadership. Simultaneous work will be on a case-by-case basis. |
| 92 |
| 3/10/2026 |
| VA |
| If room-specific phasing constraints are to be anticipated, for bidding purposes, please provide an approximate number of rooms that will be turned over to the contractor at a time. For example, in past EHRM projects, bidders have been advised to assume access to only 3-4 Telecom Rooms at a time, with work in each required to be completed in full before contractors would be permitted to advance to the next work area. |
| Contractors shall assume limited phased access. Assume access to no more than three TR per building. |
| 93 |
| 3/10/2026 |
| VA |
| Would HEPA carts be considered a sufficient means of infection control for contractors to use while working above ceilings in hallways? |
| Adherence to ICRA Level 4 requirements. |
| 94 |
| 3/10/2026 |
| VA |
| Is the contractor permitted to utilize plastic barrier containments to isolate hallway sections during above ceiling hallway work? If so, must this work be done on off-hours so as not to disturb facility operations? |
| Perform all work in accordance with the contract documents, including phasing and infectious control requirements. The project shall be executed under a level 4 ICRA. Contractor shall include all measures required for compliance (i.e. Containment, negative air, HEPA filtration, dust control, and daily cleaning). |
Contractor is responsible for field verification of existing conditions and coordination of all work to maintain continuous facility operations, including fire/life safety systems.
No additional cost or time will be granted for ICRA compliance, coordination, phasing, or adjustment requirements to complete the work.
| 95 |
| 3/10/2026 |
| IMEG |
| Is the contractor to assume new fire sleeves are required at all new through-wall cable penetrations associated with cat6a cable drop locations? |
| Fire rated sleeves are required for all fire rated wall penetrations. |
Bidding contractor shall be responsible for providing new additional conduit sleeves as required (including fire stopping requirements) for new cabling pathways should the existing pathway be insufficient. Existing conduit sleeves can be used if conditions and size allow for phasing of new cable installation. Provide new conduit sleeves as necessary. All cabling passing through a wall must be installed in a conduit sleeve.
| 96 |
| 3/10/2026 |
| VA |
| Is there an existing proprietary fire alarm contractor at the facility? If so, please provide company name and point of contact. |
| See previous response |
| 97 |
| 3/10/2026 |
| VA |
| Is there an existing proprietary controls contractor at the facility? If so, please provide company name and point of contact. |
See previous response
| 98 |
| 3/10/2026 |
| VA |
| Is there an existing proprietary PACS and/or CCTV contractor at the facility? If so, please provide company name and point of contact. |
See previous response
| 99 |
| 3/10/2026 |
| SBCC |
| Where disturbed by construction, is grass area to be restored using seed or sod? |
| Seed disturbed area where grass is restored in accordance with 31 20 11 para 3.5.D. Sodding is not required. |
| 100 |
| 3/10/2026 |
| SBCC |
| Is the contractor responsible for maintenance and watering for an establishment period of a predetermined duration after initial grass restoration? If so, how long is this establishment period? |
| There is no establishment period. Contractor is responsible for watering restored areas in accordance with 31 20 11 para 3.5.F. Once area is installed and accepted the COR is responsible for watering and maintenance. |
| 102 |
| 3/10/2026 |
| BT |
| Please confirm that all firestopping must be either installed by an FM global approved contractor, or a UL qualified firestop contractor certified. |
| Per 07 84 00 paragraph 1.5: |
Installer Qualifications: A firm that has been approved by FM Global according to FM Global 4991 or been evaluated by UL and found to comply with UL’s “Qualified Firestop Contractor Program Requirements.” Submit qualification data.
| 103 |
| 3/10/2026 |
| VA |
| If rooms are required to be isolated in phases, will there be any downtime in the schedule between phases to allow the VA time for relocation of staff / equipment / devices? If so, how much downtime should the contractor anticipate for this? |
| Coordination of relocating personnel is on-going. Final movement of personnel is dependent upon award and contractor schedule. |
| 104 |
| 3/10/2026 |
| VA |
| Please confirm the contractor will be required to submit post award the requested information that the telecommunications contractor shall be a BICSI licensed Contractor with a minimum of five (5) years’ experience installing and servicing systems of similar scope and complexity. The Contractor shall provide four (4) current references from clients with systems of similar scope and complexity which became operational in the past three (3) years. At least three (3) of the references shall be utilizing the same system components, in a similar configuration as the proposed system. The references must include a current point of contact, company or agency name, address, telephone number, complete system description, date of completion, and approximate cost of the project. |
| Refer to contract documents |
| 105 |
| 3/10/2026 |
| VA |
| Please confirm that the telecommunications contractor must submit copies of system manufacturer certification for all technicians. The Contractor shall provide proof project superintendent with BICSI Certified Commercial Installer Level 1, Level 2, or Technician to provide oversight of the project. |
| Contractor shall submit: |
Manufacturer certification documentation for all technicians performing installation.
Proof that project superintendent holds a current BICISI certification as required by contract documents.
| 106 |
| 3/10/2026 |
| VA |
| Please confirm cable installer must have on staff a Registered Communication Distribution Designer (RCDD) certified by Building Industry Consulting Service International (BICSI). |
| Refer to Contract documents |
| 108 |
| 3/10/2026 |
| BT |
| Please confirm level 4 finish for all finished gypsum board including patches |
| Per 09 29 00, paragraph 3.4: a level 4 finish is required on exposed gypsum board. |
Patches shall match adjacent finish.
| 109 |
| 3/10/2026 |
| IMEG |
| Are we required to use plenum rated cabling for all areas? Can we use riser rated cabling in non plenum spaces? |
| Non-plenum cable is acceptable for non-plenum spaces only. Provide plenum cabling as required. |
| 110 |
| 3/10/2026 |
| IMEG |
| Will flexible metal conduit be allowed? |
| IMEG: Flexible metal conduit shall be permitted to be used in exposed and concealed location, the limitation are per specification 26 05 19 and the NEC requirements. |
For Division 27:
For bidding purposes contractor shall provide cost to include a new surface mount raceway, or fixed flexible conduit in walls, for all locations where outlet existing conditions are insufficient in size/fill capacity, or include open cabling fished down walls. Assume 30% of outlets represent this condition and provide cost for new pathway within bid.
| 111 |
| 3/10/2026 |
| VA |
| Please confirm the VA will be working and scheduling with the subsystem vendors on scheduling network outages. |
| VA will assist in scheduling outages |
| 112 |
| 3/10/2026 |
| VA |
| Please confirm the normal working hours of this contract are to be assumed as normal working hours; 7:00 am-5:00 pm |
| Refer to Contract documents |
| 113 |
| 3/10/2026 |
| SBCC |
| Is it anticipated that unsuitable soil will be encountered on this project? If so, is the contractor responsible for removal and disposal of any unsuitable soils? |
| There is no information indicating unsuitable materials as defined in 31 20 11 will be encountered. If unsuitable material is encountered the contractor shall notify the COR in accordance with 31 20 11 para. 3.2.F and the contractor is responsible for disposal of unsuitable material in accordance with 31 20 11 para. 3.6. |
| 114 | |
| 3/10/2026 | |
| VA | |
| Please confirm, is the prime contractor required to directly hire the controls system integrator? | |
| Provide control system integration per contract documents. Prime Contractor is responsible for a complete and operational system, regardless of subcontracting. Include all cost in base bid |
| 115 |
| 3/10/2026 |
| VA |
| Please confirm, per 23 31 00, is it mandatory that the Testing and Balancing contractor responsible for ductwork leakage testing be hired directly by the prime contractor? |
| The Prime Contractor is fully responsible for ensuring TAB services are properly executed, regardless of subcontracting arrangement. |
| 116 |
| 3/10/2026 |
| VA |
| Please confirm, is the prime contractor responsible for hiring a 3rd party TAB specialist to supervise all Testing and Balancing work? |
| Contractor is responsible for compliance with all certification and qualification requirements regardless of subcontracting structure. |
No additional compensation will be provided.
| 117 |
| 3/10/2026 |
| CT |
| Please confirm, is the contractor to hire a 3rd party certified industrial hygienist for monitoring and supervision of abatement work, in addition to the VA’s own VPIH? |
| Yes, the abatement contractor needs to hire an industrial hygienist to act as Contractor Industrial Hygienist Professional (CPIH) during the abatement work. |
| 118 |
| 3/10/2026 |
| IMEG |
| Please confirm, are all new cat6a cables to be factory terminated? |
| CAT 6A cables can be field terminated. Pre-terminated CAT 6A cables are for data center MDA/HDA backbone distribution only. |
| 119 |
| 3/10/2026 |
| IMEG |
| At cat6a cable drop locations, is the contractor permitted to reuse conduit and backboxes cable is being removed and replaced 1-for-1 or if more cables are being removed than are being replaced? |
| The contractor shall provide a 1 for 1 replacement of data through existing pathway. |
For bidding purposes contractor shall provide cost to include a new surface mount raceway, or fixed flexible conduit in walls, for all locations where outlet existing conditions are insufficient in size/fill capacity, or include open cabling fished down walls. Assume 30% of outlets represent this condition and provide cost for new pathway within bid.
| 120 |
| 3/10/2026 |
| BT |
| Are all interior partition walls to be disturbed / penetrated assumed to be drywall and non structural metal framing unless noted otherwise? |
| Most of these buildings have been renovated over the past 90+ years they have existed on this site, so most of the original plaster or hollow clay tile interior partitions have been replaced. Newer walls will likely be gypsum board over metal or wood studs. We did not test every wall that will be penetrated for this project to see how it is constructed. GC’s shall be prepared to drill or sawcut through wall types of various construction, including a rare HCT wall as occurs. |
| 121 |
| 3/10/2026 |
| IMEG |
| At cat6a cable drop locations throughout the facility where walls will need to be cut and patched for new in-wall cable installations, will these walls need to then be painted seam-to-seam, or would spot painting at patch locations suffice? |
Walls that are cut open for cable or installation are to match their previously existing state.
For bidding purposes contractor shall provide cost to include a new surface mount raceway, or fixed flexible conduit in walls, for all locations where outlet existing conditions are insufficient in size/fill capacity, or include open cabling fished down walls. Assume 30% of outlets represent this condition and provide cost for new pathway within bid.
| 122 |
| 3/10/2026 |
| IMEG |
| Please confirm, are all duct banks shown on CS drawings to be provided as new? Are there any areas where existing duct bank is to be reused? |
| All exterior duct banks specified in the project are new. Refer to civil plans for additional information on installation and procurement. |
| 123 |
| 3/10/2026 |
| SBCC |
| Is the contractor responsible for scanning and locating all utilities throughout site work areas? |
| Yes. See General note 12 on CN001 for existing utility crossing expectations. Potholing was not performed during design. The utilities shown are based on the best available VA provided information (CN001 General Notes 1 and 2). Per CN001 General Note 4 the Contractor can coordinate with the government to make field adjustments as necessary. |
| 124 |
| 3/10/2026 |
| VA |
| Is the contractor responsible for hiring a land surveyor to provide a topographic survey and benchmarking throughout site work areas? |
| Refer to Contract documents |
| 125 |
| 3/10/2026 |
| IMEG |
| Is the contractor to include an allowance for additional cat6a drops not shown on the drawings? If so, please include a percentage or quantity to be included in the allowance. |
| Provide a 10% allowance for additional cable installation. A/E to provide direction on use of allowance. If allowance is not used, contractor shall provide allowance credit back to VA at end of construction. |
| 126 |
| 3/10/2026 |
| BT |
| Where drywall is to be removed in work areas for installation of new data drops and associated backbox and conduit, are these walls to be painted seam-to-seam, or would patch spot painting suffice? |
| Reference General Note #11 on the cover sheet which says in part “…WHERE NOT INDICATED OTHERWISE, REPAIR SHALL MATCH ADJACENT SUBSTRATE, MATERIALS, TEXTURE, PATTERN, COLOR, AND FINISH. WHERE PATCHED AREA FINISHES DO NOT MATCH EXACTLY, THE ENTIRE AREA SHALL BE REPAIRED / REPLACED / REFINISHED TO PROVIDE A UNIFORM FINISH.” Patch spot painting is acceptable if it matches the adjacent surface. |
| 127 |
| 3/10/2026 |
| SBCC |
| Where new duct banks are to be installed below existing hard surfaces (sidewalks, pavement, curbs) are these surfaces to be sawcut, removed, and restored? Or is it the intent to bore beneath these so as not to disturb the existing surfaces? |