36C77626R0009.pdf
PDF 803 KB Posted
- Solicitation number
- 36C77626R0009
About this file
This is a Request for Proposals (RFP) for a Service-Disabled Veteran-Owned Small Business (SDVOSB) set-aside construction project issued by the Department of Veterans Affairs (VA). The solicitation number is 36C77626R0009, issued February 10, 2026, with proposals due April 7, 2026 at 2:00 PM EST. The project number is 674A4-21-700, and the contract number is 36C776.
The project involves Electronic Health Record Modernization (EHRM) Infrastructure Upgrades Construction at the Doris Miller VAMC in Waco, Texas. The scope includes general construction, alterations, electrical panel upgrades, power systems, bonding, UPS installation, Building Management System interfaces, HVAC assessment and upgrades, space reconfiguration, data communications infrastructure, physical security upgrades, fiber infrastructure assessment and upgrades across 23 buildings and the campus site, and hazardous material abatement. The contract is firm fixed price with a VAAR magnitude of $20,000,000 to $50,000,000. The mandatory performance period is 730 calendar days after issuance of Construction Notice to Proceed, with a 10-calendar-day start requirement. A bid guarantee of 20 percent (not to exceed $3,000,000) is required, along with performance and payment bonds. Offerors must be certified SDVOSBs listed in the SBA certification database at proposal submission and award. Proposals must be submitted electronically in three volumes: Volume I (Past Performance, maximum 30 pages), Volume II (Price, maximum 50 pages), and Volume III (Administrative information). Evaluation criteria include past performance (significantly more important than price) and price, with award made to the offeror offering best value. Construction wage rates apply per McLennan County prevailing wage determinations.
View the file
Other files
Show all 27
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1. SOLICITATION NUMBER 2. TYPE OF SOLICITATION 3. DATE ISSUED PAGE OF PAGES
4. CONTRACT NUMBER 5. REQUISITION/PURCHASE REQUEST NUMBER 6. PROJECT NUMBER
7. ISSUED BY CODE 8. ADDRESS OFFER TO
a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
12b. CALENDAR DAYS
13. ADDITIONAL SOLICITATION REQUIREMENTS:
STANDARD FORM 1442 (REV. 8/2014) STANDARD FORM 1442
Prescribed by GSA-FAR (48 CFR) 52.236-1(d)
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
SOLICITATION SOLICITATION
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR INFORMATION
CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
SEALED BID (IFB)
NEGOTIATED (RFP)
11. The Contractor shall begin performance within ____________ calendar days and complete it within ____________ calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).
YES NO
a. Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________
(hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.
b. An offer guarantee is, is not required.
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d. Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
1 72
36C77626R0009
X
02-10-2026
674A4-21-700
36C776
Department of Veterans Affairs
Program Contracting Activity Central
6100 Oak Tree Blvd, Suite 490
Independence OH 44131
Department of Veterans Affairs
Program Contract Activity Central
Shawn Tavernia 216-447-8321
In accordance with 38 U.S.C. § 8127 (Public Law 109-461), this project is a competitive Service-Disabled Veteran - Owned
Small Business (SDVOSB) Set-Aside.
The contractor shall provide all tools, equipment, materials, labor, supervision, personnel, and shall do all things necessary that will result in the completion of Project 674A4-21-700 EHRM Infrastructure Upgrades Construction project, in accordance with the attached Specifications and Drawings.
The project is located at the:
Doris Miller VAMC
4800 Memorial Drive
Waco TX 76711
VAAR Magnitude of Construction: $20,000,000 to $50,000,000
For instructions concerning the organized Site Visit - see Attachment 9 - Site Visit Instructions.
The proposed period of performance is 730 calendar days after issuance of Construction Notice to Proceed.
10 (Ten) 730
X X
X 10 (Ten)
0 (Zero) 2:00 PM EST
04-07-2026
X
90 (Ninety)
14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NUMBER
16. REMITTANCE ADDRESS
CODE FACILITY CODE
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
AMENDMENT
NUMBER
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c)( ) 41 U.S.C. 3304(a) ( )
26. ADMINISTERED BY 27. PAYMENT WILL BE MADE BY
PHONE: FAX:
28. NEGOTIATED AGREEMENT 29. AWARD Your
Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.
shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER
TO SIGN
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE
BY
OFFER
AWARD
STANDARD FORM 1442 (REV. 8/2014) BACK
(Include ZIP Code) (Include area code)
(Include only if different than Item 14.)
(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
(Type or print)
(4 copies unless otherwise specified)
(Type or print) (Type or print)
(Contractor is required to sign this document and return _______ copies to issuing office.)
(Contractor is not required to sign this document.)
(Must be fully completed by offeror)
(To be completed by Government)
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
See Price Schedule
36C776
Department of Veterans Affairs
Program Contracting Activity Central
VAFSC
Department of Veterans Affairs
Financial Services Center
Invoices to be Submitted Electronically https://www.fsc.va.gov/einvoice.asp e-Invoice Setup Info Phone 877-489-6135
877-353-9791 512-460-5429
Bridget May
VA-VHA-RPOC-2023-0037
Table of Contents
PART I - THE SCHEDULE
SECTION A - SOLICITATION/CONTRACT FORM
A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or
Repair)
A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION,
ALTERATION, OR REPAIR)– BACK
A.3 PRICE/COST SCHEDULE
ITEM INFORMATION
INFORMATION REGARDING PROPOSAL MATERIAL, BID GUARANTEE AND BONDS
1.1 BID MATERIAL
1.2 BID GUARANTEE
1.3 PAYMENT & PERFORMANCE BONDS
1.4 TAXES
INSTRUCTIONS, CONDITIONS, AND OTHER STATEMENTS TO OFFERORS
2.1 AVAILABILITY OF SOLICITATION DOCUMENTS
2.2 REQUEST FOR PROPOSALS
2.3 SDVOSB SET-ASIDE
2.4 PRE-PROPOSAL SITE VISIT
2.5 TECHNICAL QUESTIONS
2.6 AMENDMENTS
2.7 PREPARATION OF PROPOSALS
2.8 PROPOSAL REQUIREMENTS
2.9 EVALUATION METHODOLOGY
2.10 DETERMINATION OF RESPONSIBILITY
2.11 VETS 4212
2.12 SYSTEM FOR AWARD MANAGEMENT (SAM)
2.13 DEVIATION NOTICE (FEB 2025)
2.14 REVIEW REQUIRED REGISTRATION WITH CONTRACTOR PERFORMANCE
ASSESSMENT REPORTING SYSTEM (CPARS)
2.15 BACKGROUND INVESTIGATIONS AND SPECIAL AGREEMENT CHECKS
2.16 REFERENCES TO VA ENGINEER, RESIDENT ENGINEER, OR PROJECT
MANAGER
2.17 52.216-1 TYPE OF CONTRACT (APR 1984) (DEVIATION NOV 2025)
2.18 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS-SECONDARY SITE
OF THE WORK (MAY 2014)(DEVIATION NOV 2025)
2.19 52.225-12 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION
MATERIALS UNDER TRADE AGREEMENTS (MAY 2014)
2.20 52.228-1 BID GUARANTEE (SEP 1996)
2.21 52.233-2 SERVICE OF PROTEST (DEVIATION NOV 2025)
2.22 52.240-90 SECURITY PROHIBITIONS AND EXCLUSIONS
REPRESENTATIONS AND CERTIFICATIONS (DEVIATION NOV 2025)
2.23 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE
(FEB 1998)
2.24 VAAR 852.252-70 SOLICITATION PROVISIONS OR CLAUSES
INCORPORATED BY REFERENCE (JAN 2008)
REPRESENTATIONS AND CERTIFICATIONS
3.1 52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT
2018)(DEVIATION NOV 2025)
3.2 52.209-13 VIOLATION OF ARMS CONTROL TREATIES OR AGREEMENTS-
CERTIFICATION (NOV 2021) (DEVIATION NOV 2025)
3.3 52.229-11 TAX ON CERTAIN FOREIGN PROCUREMENTS – NOTICE AND
REPRESENTATION (FEB 2021) (DEVIATION SEP 2025)
GENERAL CONDITIONS
4.1 52.203-14 DISPLAY OF HOTLINE POSTER(S) (NOV 2021)
4.2 52.219-28 POSTAWARD SMALL BUSINESS PROGRAM REREPRESENTATION
(JAN 2025) (DEVIATION NOV 2025)
4.3 52.223-2 REPORTING OF BIOBASED PRODUCTS UNDER SERVICE AND
CONSTRUCTION CONTRACTS (MAY 2024)(DEVIATION NOV 2025)
4.4 52.223-20 AEROSOLS (MAY 2024)
4.5 52.223-21 FOAMS (MAY 2024)
4.6 52.225-11 BUY AMERICAN—CONSTRUCTION MATERIALS UNDER TRADE
AGREEMENTS (NOV 2023) (DEVIATION NOV 2025)
4.7 52.228-5 INSURANCE—WORK ON A GOVERNMENT INSTALLATION (JAN 1997)
4.8 SUPPLEMENTAL INSURANCE REQUIREMENTS
4.9 52.228-11 INDIVIDUAL SURETY—PLEDGE OF ASSETS (FEB 2021)
4.10 52.228-15 PERFORMANCE AND PAYMENT BONDS—CONSTRUCTION (JUN
2020)
4.11 52.229-3 FEDERAL, STATE, AND LOCAL TAXES (FEB 2013) (DEVIATION SEP
2025)
4.12 52.240-91 SECURITY PROHIBITIONS AND EXCLUSIONS (DEVIATION NOV
2025)
4.13 52.240-93 BASIC SAFEGUARDING OF COVERED CONTRACTOR
INFORMATION SYSTEMS (DEVIATION NOV 2025)
4.14 52.252-6 AUTHORIZED DEVIATIONS IN CLAUSES (NOV 2020)
4.15 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)
4.16 VAAR 852.219-73 VA NOTICE OF TOTAL SET-ASIDE FOR CERTIFIED
SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESSES (JAN 2023)
(DEVIATION)
4.17 VAAR 852.219-75 VA NOTICE OF LIMITATIONS ON SUBCONTRACTING—
CERTIFICATE OF COMPLIANCE FOR SERVICES AND CONSTRUCTION (JAN 2023)
(DEVIATION)
4.18 VAAR 852.236-71 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION
(APR 2019)
4.19 VAAR 852.236-90 RESTRICTION ON SUBMISSION AND USE OF EQUAL
PRODUCTS (APR 2019)
4.20 VAAR 852.239-76 INFORMATION AND COMMUNICATION TECHNOLOGY
ACCESSIBILITY (FEB 2023)
4.21 VAAR 852.242-71 ADMINISTRATIVE CONTRACTING OFFICER (OCT 2020) .. 70
4.22 VAAR 852.243-70 CONSTRUCTION CONTRACT CHANGES—SUPPLEMENT
(SEP 2019)
4.23 MANDATORY WRITTEN DISCLOSURES
4.24 LIST OF ATTACHMENTS
A.3 PRICE/COST SCHEDULE
ITEM INFORMATION
ITEM
NUMBER
DESCRIPTION OF
SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
1.00 JB __________________ __________________
ITEM I, GENERAL CONSTRUCTION: BASE BID: Work includes general construction, alterations, roads, walks, grading, drainage, necessary removal of existing materials and construction and certain other items as defined in the bid documents. This project will upgrade the facility infrastructure to support the new Electronic Health Record Modernization (EHRM) system in accordance with VA OEHRM Site Infrastructure Requirements (provided by VHA). The scope of this project includes but not limited to the following infrastructure improvements: Electrical (electrical panel upgrade, power (normal, emergency)), Bonding, UPS, Building Management System interfaces, assess for new and upgrades to existing HVAC, reconfiguration, expansion and renovation of existing space (demo, new construction, finishes), communication infrastructure (new Data outlets, patch panels, upgrade to Cat 6Acable) in buildings as necessary, physical security upgrades, assess and upgrade fiber infrastructure backbone campus wide within buildings and between buildings, hazardous material abatement. Project Building locations include Buildings 2, 4, 5, 6, 7, 8, 10, 11, 15, 16, 18, 24, 90, 91, 92, 93,94, 00, 189, 202, 219, 221, 224, 225, 226 and site.
All work shall be completed in accordance with the attached specifications and drawings. The contractor shall complete the entire project no later than 730 calendar days after the contractor receives the NOTICE TO PROCEED.
GRAND TOTAL __________________
NOTICE
1. Line Item 0001 (Base) contains all the work for this project.
2. Offerors must provide a lump sum price for Line Item 0001 (Base). Failure to do so may render their offer unacceptable.
3. Award will be made on the Grand Total (Line Item 0001 - Base).
4. Pricing must be submitted in whole dollar values. Do NOT include pricing in cents.
5. Contractor is required to fill in their Unique Entity Identifier associated with SAM.gov in Block
No. 14 on Standard Form (SF) 1442.
INFORMATION REGARDING PROPOSAL MATERIAL, BID
GUARANTEE AND BONDS
1.1 BID MATERIAL
Proposal materials consisting of drawings, specifications, and contract forms are included and/or attached as part of this Request For Proposals (RFP). The VA will not provide printed copies of drawings or specifications. It is the responsibility of the offeror to obtain the proposal materials in a time and manner sufficient to respond to this solicitation by the specified due date.
1.2 BID GUARANTEE
A Bid Guarantee, Standard Form 24 (SF 24), is required in an amount not less than 20 percent of the proposal price but shall not exceed $3,000,000. Failure to furnish the required bid guarantee in the proper form and amount, by the time set for receipt of proposals, may result in the proposal being deemed unacceptable. Copies of the SF 24 may be obtained from https://www.gsa.gov/forms.
1.3 PAYMENT & PERFORMANCE BONDS
The offeror to whom award is made will be required to furnish two bonds. A Payment Bond shall be provided on Standard Form 25A (SF 25A) and a Performance Bond shall be provided on Standard Form 25 (SF 25). Both bonds shall be submitted in accordance with FAR 52.228-15 Performance and Payment Bonds - Construction. Copies of SFs 25A and 25 may be obtained from https://www.gsa.gov/forms.
1.4 TAXES
Contractor must take into account FAR 52.229-3; “Federal, State and Local Taxes” (DEVIATION SEP 2025) and its Special Note in their pricing. The FAR clause and its Special Note provide guidance on taxes being applied to pricing.
https://gcc02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fwww.gsa.gov%2Fforms&data=05%7C02%7C%7C7197924ab06b4510c2cb08dd1867cd0b%7Ce95f1b23abaf45ee821db7ab251ab3bf%7C0%7C0%7C638693556286629207%7CUnknown%7CTWFpbGZsb3d8eyJFbXB0eU1hcGkiOnRydWUsIlYiOiIwLjAuMDAwMCIsIlAiOiJXaW4zMiIsIkFOIjoiTWFpbCIsIldUIjoyfQ%3D%3D%7C0%7C%7C%7C&sdata=MT5QogE1p45j8KY7G3NL%2BRIn0UgyKEY8mmn8Lp5c5oQ%3D&reserved=0 https://gcc02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fwww.gsa.gov%2Fforms&data=05%7C02%7C%7C7197924ab06b4510c2cb08dd1867cd0b%7Ce95f1b23abaf45ee821db7ab251ab3bf%7C0%7C0%7C638693556286629207%7CUnknown%7CTWFpbGZsb3d8eyJFbXB0eU1hcGkiOnRydWUsIlYiOiIwLjAuMDAwMCIsIlAiOiJXaW4zMiIsIkFOIjoiTWFpbCIsIldUIjoyfQ%3D%3D%7C0%7C%7C%7C&sdata=MT5QogE1p45j8KY7G3NL%2BRIn0UgyKEY8mmn8Lp5c5oQ%3D&reserved=0
INSTRUCTIONS, CONDITIONS, AND OTHER STATEMENTS TO
OFFERORS
2.1 AVAILABILITY OF SOLICITATION DOCUMENTS
All solicitation-related documents will be published to Contract Opportunities at https://sam.gov/.
2.2 REQUEST FOR PROPOSALS
This is a Request for Proposals (RFP) in accordance with FAR Part 15. The Government intends to award a contract resulting from this solicitation to the responsible Offeror whose proposal represents the best value to the Government. A responsibility determination will be made in accordance with FAR 9.1, Responsible Prospective Contractors.
2.3 SDVOSB SET-ASIDE
This procurement is a 100% set-aside for Service-Disabled Veteran-Owned Small Business (SDVOSB) concerns. To be considered eligible to receive award of a resulting contract, offerors must be certified as SDVOSBs by the U.S. Small Business Administration (SBA) and listed in the SBA certification database at the time of proposal submission and at time of award. Offers received from entities that are not certified SDVOSBs will not be considered. Failure to be certified at the time of proposal submission and at time of award will result in the offer being deemed unacceptable and ineligible for award. A joint venture may be considered eligible as an SDVOSB if the joint venture complies with the requirements in 13 CFR 128.402.
2.4 PRE-PROPOSAL SITE VISIT
A formal site visit has been scheduled for this project. This will be the only opportunity for potential offerors to visit the site. See Attachment 9 - Site Visit Instructions for further information.
All potential offerors, subcontractors and suppliers are strongly encouraged to attend this site visit.
2.5 TECHNICAL QUESTIONS
Questions of a technical nature must be submitted by prospective offerors via e-mail to:
shawn.tavernia@va.gov. The subject line of each e-mail must read: Waco EHRM - Technical Questions. Oral questions of a technical nature are not acceptable due to the possibility of misunderstanding or misinterpretation. THE CUT-OFF DATE AND TIME FOR RECEIPT OF QUESTIONS IS March 10, 2026, at 2:00 PM (EST).
2.6 AMENDMENTS
Amendments to this solicitation will be posted at https://sam.gov/. Paper copies of the amendments will NOT be individually mailed. No other notification of amendments will be provided. Potential offerors are advised that they are responsible for obtaining and acknowledging any amendments to the solicitation. Failure to acknowledge an amendment may result in a proposal being considered ineligible for award as incomplete.
2.7 PREPARATION OF PROPOSALS
The Government will not pay for any costs incurred in the preparation and submission of proposals.
https://sam.gov/ mailto:shawn.tavernia@va.gov https://sam.gov/
2.8 PROPOSAL REQUIREMENTS
A. General:
Proposal Submission: Offerors must submit their proposals via e-mail to shawn.tavernia@va.gov copy (cc) bridget.may@va.gov. Proposals must be based on solicitation documents issued for RFP number 36C77626R0009. Proposals will be in the format set forth in this document. Proposals shall be received on or before the date and time specified in Block 13 of the SF 1442. There will be no public opening of the proposals. Only proposals submitted by email will be accepted. Hard-copy proposals will not be accepted.
B. Proposal Format:
1. Past Performance, Price and Administrative sections of the Offerors proposals will be evaluated independently; therefore, the Offeror must submit the proposal in three (3) Volumes: Volume I Past Performance, Volume II Price and Volume III Administrative.
Offerors must send Volumes I, II and III as attachments in separate e-mails. Each volume must be labeled with the Offeror's organization, business address, and VA Solicitation Number. Each volume must be submitted as searchable PDF documents attached to an e-mail. Portions of proposals submitted via drop-box, hyperlink, or format rather than a searchable PDF attached to an email will not be considered, which may render the proposal incomplete. The proposal, in its entirety, shall not exceed three (3) e-mails (one e-mail for each volume). Each e-mail, including its attachments, must be less than 5MB in size. Offerors must Include page numbers and its company name in the header or footer of each page of all attachments.
2. Volume I Past Performance: Offerors shall format Volume I Past Performance proposal as listed below. The specific evaluation criteria and methodology is below.
a. Volume I Past Performance must include a title page, detailed table of contents and preface Volume I Past Performance shall be submitted in one (1) PDF document for Volume I Past Performance and shall not exceed a total of Thirty (30) pages. The title page, table of contents and preface are excluded from the page limits. Offerors must not include any price or price related material in the Volume I Past Performance proposal. Use graphic presentations where such use will contribute to the compactness and clarity of the proposal.
b. A page is defined as each face of an 8.5 X 11-inch sheet of paper with 1-inch margins around the page perimeter containing information. Submission of the project schedule can be submitted by utilizing larger paper (11 X 17 inch). The background color of each page of the submission shall be white or ivory stock and each page shall count as one (1) page. Excess pages will not be evaluated. Text lines must be single-spaced, and proposals shall be submitted using Times New Roman, with font no smaller than 12 point with normal proportional spacing. A smaller font size for any graphics presented in a proposal is permitted as long as the information is legible to the human eye. Fonts other than Times New Roman are permissible in the presentation of graphic material only.
c. The Offeror’s proposal must address each evaluation factor listed in this solicitation.
Failure to submit a proposal in the format required that addresses each factor may result in the proposal being deemed ineligible for award.
d. Volume I Past Performance, Proposal Requirements: The proposal must address the following submission requirements for Factor 1 Past Performance.
Offerors shall demonstrate successful experience in large-scale communication infrastructure construction projects. Past performance will be evaluated based on mailto:shawn.tavernia@va.gov mailto:bridget.may@va.gov the size, scope, and complexity of completed projects, within active healthcare environments, particularly within the Veterans Health Administration (VHA). Offerors shall provide at least two (2) and no more than three (3) projects that demonstrate their ability to perform the proposed effort. Projects must be at least 75% completed or have been completed within the past five (5) years from the date proposals are due.
i. Size: Have a value exceeding $30 million and have been completed within the past five (5) years.
Projects meeting or exceeding this threshold demonstrate an offeror’s capacity to manage the scale of work similar to the EHRM Infrastructure
Upgrades project, which includes extensive IT, mechanical, electrical, and telecommunications reconfiguration within an active 24/7 VHA medical facility.
ii. Scope: Relevant past performance must demonstrate experience with phased construction and infrastructure upgrades in a medical or similarly sensitive operational environment. Required scope elements include:
• Telecommunications and IT infrastructure upgrades (aligned with
EHRM modernization goals).
• Electrical, mechanical, and HVAC reconfiguration, including after-hours cutovers and shutdown coordination.
• Demolition and renovation with protection of adjacent patient care areas and minimal operational disruption.
• Life-safety system coordination, including fire alarm, sprinklers, smoke detectors, nurse call, isolation monitors, and emergency power systems.
• Infection Control Risk Assessment (ICRA) compliance, IC permit posting, dust control, and worker IC training.
• Utility interruptions, utility rerouting, and temporary systems to maintain hospital operations.
Preference will be given to projects performed in VHA facilities or other accredited acute care healthcare environments requiring continuous patient care and uninterrupted facility operations.
iii. Complexity: Offerors must show past performance demonstrating the ability to manage projects of comparable complexity, including:
• Phased construction in a fully operational hospital, with one wing or zone completed at a time.
• Coordination of critical utility shutdowns requiring 72-hour minimum notifications, and up to 10 working days for major system outages.
• Management of telecommunications and IT infrastructure relocation, including temporary installations of data, telephone, Wi-Fi, and network systems.
• Maintaining compliance with NFPA, NEC, OSHA, VA Master
Specifications, and all federal/state regulatory requirements referenced in the SOW.
• Coordination of ICRA/ILSM, fire safety impairments, false alarm prevention, fire watch procedures, and dust mitigation.
Projects demonstrating minimal downtime, strong communication protocols, and successful completion within occupied, medically sensitive areas will be rated most highly.
iv. Other Elements: The Government will evaluate each submitted project on the following factors:
• Infection Control and Environmental Controls:
o Experience implementing ICRA, HEPA containment, dust barriers, and active controls in sensitive hospital environments.
• Utility & Life-Safety Coordination o Ability to manage:
▪ Temporary power
▪ Fire alarm and sprinkler outages
▪ Smoke detector protection
▪ Coordination with medical center safety officers
▪ Fire watch requirements for impairments exceeding four hours.
• Construction Phasing and Continuity of Operations o Demonstrated capability to perform:
▪ Night/weekend work
▪ Phased wing-by-wing construction
▪ Operational continuity in 24/7 healthcare facilities.
• Hazardous Material Handling / Demolition o Demonstrated Control of demolition debris, recycling practices, and protection of adjacent spaces.
v. Narrative: Each project submitted for past performance evaluation shall use
Attachment 11 - Project Information Sheet for Contractors and include all the required/requested information. Offerors shall also provide a narrative describing past performance on projects requiring complex coordination and the risk mitigation actions taken. This shall include:
• How the project met similar coordination, phasing, and infrastructure requirements to the EHRM Waco project.
• Management of site outages, system cutovers, and the communication standards used to inform multiple stakeholders of key coordination dates
• Handling of long-lead item procurement and adherence to critical path schedules
• Resolution of past performance issues, including corrective actions taken for substandard performance
• Description of the mitigation plan for any current performance challenges such as cost overruns, schedule delays, subcontractor issues, or changes in key personnel or subcontractors.
• Discussion of the contractor’s ability to manage: System outages and communication with COR and stakeholders, Long-lead procurement, Critical path scheduling, Fire alarm/sprinkler impairments, ICRA/ILSM implementation, and Temporary utilities and life-safety systems.
At least one of the projects submitted must have been completed by the
Prime. Offerors lacking relevant past performance history may submit information regarding predecessor companies or key personnel who have performed on other contracts. Such information shall, as a minimum, include:
• Name(s) of Predecessor Company/Sub-contractor and/or Key
Personnel and include: Complete Address and Point of Contact;
Telephone Number; and email address.
• For offerors that are joint ventures, the evaluation will take into account past performance of the joint venture as well as the past performance of each party to the joint venture.
• PPQ/CPARS: If an Offeror has recent and relevant past performance to submit, a corresponding completed and signed Past Performance
Questionnaire (PPQ) or a Contractor Performance Assessment Rating
System (CPARS) must be submitted for each project in accordance with the direction below. If a completed past performance evaluation is available in CPARS, it shall be submitted with the proposal for each project identified. If there is not a completed past performance evaluation available in CPARS, then the Offeror shall submit PPQ (See
Attachment 10 - PPQ) for that project. The Offeror shall notify their client that the PPQ shall be submitted back to the Offeror and incorporated into the proposal submission. If the Offeror is unable to obtain a completed PPQ from a client for a project before the proposal closing date, the Offeror shall complete and submit with the proposal the first page of the PPQ, which will provide contract and client information for the respective project(s), and documentation of the attempts to have the PPQ signed. The Government may make reasonable attempts to contact the client noted for that project(s) to obtain the PPQ information; however, the Government is not responsible for the failure to obtain information from a POC on a PPQ.
Offerors should follow-up with clients/references to help ensure timely submittal of questionnaires.
3. Volume II Price: Offerors shall format the Volume II Price proposal as listed below. The specific evaluation criteria and methodology is below.
a. Volume II Price shall not exceed a total of FIFTY (50) pages in Times New Roman size 12 font.
b. Offerors shall complete the Price Schedule in part A of this solicitation.
c. Offerors shall ensure the Signed Standard Form (SF) 1442 is provided. Offerors shall acknowledge receiving amendments by filling out section 19 of the SF 1442.
d. Bid Guarantee: The Offeror shall furnish a bid guarantee as stipulated in the solicitation (see FAR 52.228-1). Pricing shall be Firm Fixed Price. The bid guarantee shall be provided on Standard Form 24. The bid bond shall be submitted as part of the electronic submission. In accordance with Class Deviation from the Federal Acquisition Regulation to Eliminate Hard Copy Original Documents, Signatures, Notarization, Seals on Bonds, and Other Seals for Certain Contract Requirements issued by the VA Executive Director, Office of Acquisition and Logistics and the Senior Procurement Executive on May 11, 2020, the requirement for an original bond, with the original signatures, notarization and seals has been eliminated.
e. Failure to furnish the required bid guarantee on the proper form and for the proper amount by the time specified in Block 13 of SF 1442, may result in rejection of the proposal.
f. Volume II Price, Proposal Requirements: The proposal must include the following for Factor 2 Price.
1. The Offeror shall provide their price for Line Item 0001 in the Price Schedule included in the solicitation. In addition to the Price Schedule, Offerors shall submit a complete Breakdown of the Division Pricing for Line Item 0001 (See Attachment 12 - Division Cost Breakdown - 5-29-24). The Division Pricing will be used to determine price reasonableness. The Government also reserves the right to use this Division Pricing breakdown as part of negotiations during the competitive range, if they are required.
2. The price must be Firm Fixed Price. The Offeror must take care not to include remarks that take exception to the Government’s Specifications/Drawings or pricing requirements or otherwise preclude the Government from evaluating the offer, which will result in the offeror’s proposal being rejected.
4. Volume III Administrative Information: If an offeror fails to include all of the below information in its proposal, then the proposal may be deemed incomplete and ineligible for award.
a. Representations & Certifications:
By submitting its offer, the Offeror verifies that, as of the date of its offer, its representations and certifications posted electronically in SAM for the applicable provisions are current, accurate, and complete. The Offeror’s representations and certifications in SAM are hereby incorporated by reference into its offer.
b. Information Regarding Responsibility Matters:
Offeror shall provide their response to FAR 52.209-7 (b) Information Regarding Responsibility Matters.
c. Certification Regarding Tax Matters:
Offeror shall provide their response to FAR 52.209-12 (b) Certification Regarding Tax Matters.
d. Violation of Arms Controls Treaties or Agreements:
Offeror must provide their response to FAR 52.209-13 (b)(1) or (2) Violation of Arms Controls Treaties or Agreements.
e. Tax on Certain Foreign Procurements – Notice and Representation:
The offeror shall provide their response to FAR 52.229-11 (d).
f. Post Award Small Business Program Representations:
Offeror must provided their response to FAR 52.219-28 (g), if applicable.
g. Limitations on Subcontracting:
The offeror must complete and sign the certification in VAAR 852.219-75, VA Notice of Limitations on Subcontracting—Certificate of Compliance for Services and Construction, and return it with their bid submission. The completed and signed certification will become part of the official award documentation. A copy of the clause to be completed and included with the bid is attached as a separate document (see Attachment 8 - Limitations on Subcontracting - Construction).
Failure to return the entire clause, with the appropriate box marked, the offeror’s name entered, and the certification completed and signed, with the offeror’s proposal will result in the offer being deemed nonresponsive and therefore ineligible for award.
h. Notice to SDVOSB Joint Venture/Mentor-Protégé:
Any offeror submitting a proposal as a joint venture must provide a copy of the joint venture agreement, as well as a certification from the certified SDVOSB joint partner, signed by an authorized official of each partner to the joint venture, stating that the parties to the joint venture (1) have entered into a joint venture agreement that fully complies with paragraph (c) of 13 CFR § 128.402, and (2) will perform the contract in compliance with the joint venture agreement. Provide the UEI for each partner in the agreement. Failure to submit the agreement and certification with the offeror’s proposal may result in the rejection of the proposal.
2.9 EVALUATION METHODOLOGY
A. The Government reserves the right to award without negotiations based upon the initial evaluation of the proposals but reserves the right to open negotiations if determined to be necessary. All proposals shall be subject to evaluation by a team of Government personnel. The proposals will be evaluated in accordance with the criteria provided in the solicitation. Using the tradeoff process under best value, it may be in the Government's best interest to consider award to other than the lowest price Offeror or other than highest rated Offeror. The intent is to award to the Offeror that offers the best value to the Government. “Best Value” means the expected outcome of an acquisition that, in the Government’s estimation, provides the greatest overall benefit in response to the requirements. Past Performance is significantly more important than Price.
B. Factor 1 Past Performance: Past Performance will be evaluated on the basis of recency, relevancy, and quality to arrive at an overall Confidence Rating.
Recency and Relevancy Evaluation: The Government will evaluate each project submitted to ensure the project is recent, meaning projects must have been completed within the last five years, or at least 75% complete. Projects older than five years or not completed at least 75% will not be evaluated. The Government will evaluate each recent project to determine the relevancy of the project to the solicitation requirements. The relevancy determination will be based on the Project Information Sheet provided by the Offeror and be based on specific size, scope, and detail of complexity.
Performance Quality Assessment: The Government will consider the performance quality of any submitted project determined to be recent and rated somewhat relevant, relevant, or very relevant. In addition to evaluating the extent to which the Offeror’s performance meets contract specification requirements, the assessment will also consider aspects such as: the Offeror’s adhering to schedules (including the administrative aspects of performance); reasonable and cooperative behavior and commitment to customer satisfaction; controlling project cost; the timeliness of contract completion and submission of deliverables; the contractor’s compliance with the terms and conditions of the contract; the overall quality of the work performed on the contract;
the Offeror’s managerial performance (to include use and control of subcontractors); and whether or not the reference would enter into a contract with the contractor again.
The Government reserves the right to conduct a past performance assessment using information obtained from CPARS and any other sources deemed appropriate by the CO. Other sources may include, but are not limited to, inquiries of owner representative(s), Federal Awardee Performance and Integrity Information System (FAPIIS), Electronic Subcontract Reporting System (eSRS), and any other known sources not provided by the Offeror. While the Government may elect to consider data obtained from other sources, the burden of providing current, accurate and complete past performance information rests with the Offeror.
Overall Performance Confidence Rating: The purpose of the past performance evaluation is to assess the degree of confidence the Government has in the Offeror’s ability to meet the solicitation requirements based on the Offeror’s demonstrated record of performance. The Government will combine the recency, relevancy, and performance quality assessment considered for the Offeror to assign a single Past Performance Confidence Rating of Substantial Confidence, Satisfactory Confidence, Neutral Confidence, Limited Confidence or No Confidence.
Per FAR 15.202 (C)(1), offerors without a record of relevant past performance or for whom information on past performance is not available may not be evaluated favorably or unfavorably on past performance. Offerors with no recent and relevant performance history or whose performance record is so sparse that no meaningful confidence assessment rating can be reasonably assigned shall receive the “Neutral Confidence” rating, meaning the rating is treated neither favorably nor unfavorably
C. Factor 2 Price: The total evaluated price will be determined by the Offeror's price provided on the Price Schedule.
Note: If none of the offerors are within the available funding limitation or is otherwise determined to be other than fair and reasonable, the VA reserves the right to enter into negotiations with those offerors who are determined to be within the competitive range.
If the Offeror communicates in its proposal any qualifications, exceptions, exclusions, or conditions to the proposed prices in the Offerors proposal documents, the Contracting Officer may reject the proposal and exclude the Offeror from further negotiations.
2.10 DETERMINATION OF RESPONSIBILITY
In accordance with FAR subpart 9.1, Responsible Prospective Contractors, a responsibility determination will be made for the apparent successful offeror prior to award of the project. The Contracting Officer reserves the right to request information to assist the Government in determining the apparent successful offeror responsible, including information regarding the offeror’s previous experience (including points of contact), organization (including company officers), technical qualifications, financial resources, and other information deemed necessary.
These requests for information do not constitute negotiations. NOTE: Any information received by the Government that would be cause for a negative responsibility determination may deem the offeror ineligible for award
2.11 VETS 4212
Title 38, USC Section 4212(d), codified at 41 CFR Section 61-300, requires that federal contractors report, at least annually, the number and category of veterans who are within their workforce. Submission of the VETS-4212 reporting information can be done electronically at:
http://www.dol.gov/vets/vets4212.htm. Award cannot be made unless the awardee has filed their VETS-4212 report. Therefore, all offerors are encouraged to file every year. The Contracting Officer may request a copy of the email confirmation of receipt notification prior to awarding the project.
2.12 SYSTEM FOR AWARD MANAGEMENT (SAM)
The FAR requires that federal contractors register in the SAM database at https://sam.gov/ and enter all mandatory information into the system. In compliance with FAR 52.204-7, an offeror must have an active registration in SAM at the time an offer is submitted and at the time of award. The initial screening of proposals includes reviewing SAM.gov for compliance with this section.
2.13 DEVIATION NOTICE (FEB 2025)
System updates may lag policy updates. The System for Award Management (SAM) may continue to require entities to complete representations based on provisions that are not included in agency solicitations, including 52.222-25, Affirmative Action Compliance, 52.223-22, Public Disclosure of Greenhouse Gas Emissions and Reduction Goals—Representation, and paragraphs (d) and (t) of 52.212-3, Offeror Representations and Certifications—Commercial
Products and Commercial Services. Contracting officers will not consider these representations when making award decisions or enforce requirements. Entities are not required to, nor are they able to, update their entity registration to remove these representations in SAM.
2.14 REVIEW REQUIRED REGISTRATION WITH CONTRACTOR
PERFORMANCE ASSESSMENT REPORTING SYSTEM (CPARS)
As prescribed in Federal Acquisition Regulation (FAR) 42.1102(e), the Department of Veterans Affairs (VA) evaluates contractor past performance on all construction contracts that exceed $900,000 and shares those evaluations with other Federal Government contract specialists and procurement officials. The FAR requires that the contractor be provided an opportunity to comment on past performance evaluations prior to each report closing. To fulfill this requirement, VA uses an online database, CPARS, which is maintained by the Naval Sea http://www.dol.gov/vets/vets4212.htm https://sam.gov/
Logistics Center in Portsmouth, New Hampshire. CPARS is available to all Federal agencies and is the system used to collect and retrieve performance assessment reports used in source selection determinations. CPARS also includes access to the federal awardee performance and integrity information system (FAPIIS). FAPIIS is a web-enabled application accessed via CPARS for contractor responsibility determination information.
Each contractor whose contract award is estimated to exceed $900,000 is required to register with CPARS database at the following web address: http://www.cpars.gov/. Help in registering can be obtained by contacting the CPARS Customer Service Desk at cpars-helpdesk@us.navy.mil. Registration should occur no later than thirty days after contract award and must be kept current should there be any change to the contractor’s registered representative.
For contracts with a period of one year or less, the contracting officer will perform a single evaluation when the contract is complete. For contracts exceeding one year, the contracting officer will evaluate the contractor’s performance annually. Interim reports will be filed each year until the last year of the contract, when the final report will be completed. The report shall be assigned in CPARS to the contractor’s designated representative for comment. The contractor representative will have thirty days to submit any comments and re-assign the report to the VA contracting officer.
Failure to have a current registration in the CPARS database, or to re-assign the report to the VA contracting officer within those thirty days, will result in the Government’s evaluation being placed on file in the database with a statement that the contractor failed to respond.
2.15 BACKGROUND INVESTIGATIONS AND SPECIAL AGREEMENT
CHECKS
All contractor employees are subject to the same level of investigation as VA employees who have access to VA Sensitive Information. The level of background investigation is commensurate with the level of access needed to perform all work as identified in the solicitation documents. This requirement is applicable to all subcontractor personnel requiring the same access. As per VA Directive 0710, costs of background investigations will be borne by the contractor. Please be advised that the awardee will need to coordinate with the VA Medical Center concerning badging requirements.
2.16 REFERENCES TO VA ENGINEER, RESIDENT ENGINEER, OR
PROJECT MANAGER
Any reference contained within the solicitation/contract specifications and/or drawings to the “VA
Engineer,” “Resident Engineer,” or “Project Manager,” or their abbreviations shall be replaced with “Contracting Officer’s Representative (COR).”
2.17 52.216-1 TYPE OF CONTRACT (APR 1984) (DEVIATION NOV 2025)
The Government contemplates award of a Firm-Fixed-Price contract resulting from this solicitation.
(End of Provision) http://www.cpars.gov/ mailto:cpars-helpdesk@us.navy.mil mailto:cpars-helpdesk@us.navy.mil
2.18 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS-
SECONDARY SITE OF THE WORK (MAY 2014)(DEVIATION NOV 2025)
(a) (1) The offeror must notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.
(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror must request a determination from the Contracting Officer.
(b) (1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror must request a wage determination from the Contracting Officer.
(2) The due date for receipt of offers will not be extended as a result of an offeror’s request for a wage determination for a secondary site of the work.
(End of Provision)
2.19 52.225-12 NOTICE OF BUY AMERICAN REQUIREMENT—
CONSTRUCTION MATERIALS UNDER TRADE AGREEMENTS (MAY 2014)
(a) Definitions. "Commercially available off-the-shelf (COTS) item," "construction material,"
"designated country construction material," "domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American—Construction Materials Under Trade Agreements" (Federal Acquisition
Regulation (FAR) clause 52.225-11).
(b) Requests for determination of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the
Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of
FAR clause 52.225-11 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.
(c) Evaluation of offers.
(1) The Government will evaluate an offer requesting exception to the requirements of the
Buy American statute, based on claimed unreasonable cost of domestic construction materials, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(4)(i) of FAR clause 52.225-11.
(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.
https://www.acquisition.gov/far-overhaul/far-part-deviation-guide/far-overhaul-part-52#FAR_52_222_6
(d) Alternate offers.
(1) When an offer includes foreign construction material, other than designated country construction material, that is not listed by the Government in this solicitation in paragraph (b)(3) of FAR clause 52.225-11, the offeror also may submit an alternate offer based on use of equivalent domestic or designated country construction material.
(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of FAR clause 52.225-11 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.
(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of FAR clause 52.225-11 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic or designated country construction material, and the offeror shall be required to furnish such domestic or designated country construction material. An offer based on use of the foreign construction material for which an exception was requested—
(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or
(ii) May be accepted if revised during negotiations.
(End of Provision)
2.20 52.228-1 BID GUARANTEE (SEP 1996)
(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.
(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury
Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds—
(1) To unsuccessful bidders as soon as practicable after the opening of bids; and
(2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.
(c) The amount of the bid guarantee shall be 20 percent of the bid price or $3,000,000, whichever is less.
(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.
(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.
(End of Provision)
2.21 52.233-2 SERVICE OF PROTEST (DEVIATION NOV 2025)
(a) Protests, (as defined in FAR 33.102), that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), must be served on the Contracting Officer identified in the solicitation by obtaining written and dated acknowledgment of receipt from them.
(b) The copy of any protest must be received in the office designated above within one day of filing a protest with the GAO.
(End of Provision)
2.22 52.240-90 SECURITY PROHIBITIONS AND EXCLUSIONS
REPRESENTATIONS AND CERTIFICATIONS (DEVIATION NOV 2025)
(a) Definitions. As used in this provision-—
Backhaul, covered article, covered telecommunications equipment or services, critical technology, FASCSA order,…