675-103 Addendum No. 01_2025.07.30.pdf

PDF 20 MB Posted

Attached to
Y1DZ--675-103 Create Cardiovascular Center Minor Construction - Lake Nona, FL VAMC
Solicitation number
36C77625B0030
Issued by

About this file

This document is an Addendum (No. 01) dated July 30, 2025, for the Create Cardiovascular Center project at the Orlando VA Healthcare System located at 13800 Veterans Way, Orlando, FL 32827. The addendum revises the project phasing, reducing the original three phases to two phases: the previous Phases 1 & 2 have been combined into Phase 1, while the previous Phase 3 has been renamed as Phase 2. Key changes include constructing a 2-hour fire-rated temporary egress corridor with ceiling, emergency/egress lighting, and sprinkler system, which must be completed prior to starting construction of the new building expansion shell area adjacent to the stair exit door.

The addendum also addresses specific technical requirements for the project, including maintaining access to an existing toilet room during Phase 1 with temporary construction partitions, and handling distributed antenna system (DAS) and wireless access point (WAP) devices. For DAS devices, contractors must move them above the ceiling, protect them during construction, and reinstall them at the same location in the new ceiling. WAP devices are to be turned over to the VA Contracting Officer's Representative (COR), with the contractor responsible for installing new cabling and the VA to reinstall the devices at new locations indicated in the contract documents. The document includes revised phasing plans and narratives across multiple drawing sheets to reflect these changes.

View the file

Other files

Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

524 Fernwood Drive, Altamonte Springs, Florida 32701 | rdcjpa.com | 800.362.1523

Addendum No. 01

Date: July 30, 2025

Project: 675-103

Create Cardiovascular Center at Lake Nona

Orlando VA Healthcare System

13800 Veterans Way

Orlando, FL 32827

To: David Mark, VA CO

William Klotzbach, VA CS

Kevin Glover, VA COR

This Addendum supplements and amends the original Drawings and Specifications for the above referenced project. This Addendum shall be forwarded to all Prime Bidders and all appropriate building code authorities. This Addendum shall be taken into account in the preparation of bids and shall become a part of the Contract Documents.

Receipt of this Addendum must be acknowledged on the Bid Form.

This addendum consists of the following items:

1. Project Phasing has been revised to reduce the project into two phases. Previous Phases

1 & 2 have been combined into Phase 1 while previous Phase 3 has been renamed as

Phase 2.

- Revised Phase 1 requires a 2-hr fire rated temporary egress corridor to be constructed with ceiling, emergency / egress lighting and sprinkler to be installed. The temporary corridor must be completed prior to the start of construction of the new building expansion shell area adjacent to the Stair exit door. The temporary corridor may be removed upon the reopening and safe exit discharge from the exterior Stair door.

- Project Phasing Plans and narrative have been revised to reflect this change per VA direction.

2. An existing Toilet room to be removed shall remain in Phase 1 and temporary construction partitions shall be installed to maintain access for patient use. See keynote

1.13 on sheet GC102.

3. Existing distributed antenna system (DAS) and wireless access point (WAP) devices were added to clarify scope for these devices to the contractor.

- DAS devices are to be moved above ceiling and protected during construction; re-installed at same location in new ceiling.

- WAP devices are to be turned over the VA COR. Contractor to install new cabling;

VA to re-install WAP devices at new locations indicated on contract documents.

Drawings

1. Sheet GC101 – Phasing Plan – Reissued.

a. Revised Project Phasing Plan, updated Project Phasing narrative & added the Existing

Floor Plan for reference.

2. Sheet GC102 – Phasing Plans – Reissued.

a. Revised Project Phasing Plan, updated Project Phasing narrative.

3. Sheet FPC101 – Fire Protection Phasing Plans – Reissued

a. Revised Project Phasing Plan and revised fire protection notes to correspond to the new phasing plans.

4. Sheet FPC102 – Fire Protection Phasing Plans – Reissued

a. Revised Project Phasing Plan and revised fire protection notes to correspond to the new phasing plans.

5. Sheet PC101 – Plumbing Phasing Plans – Reissued

a. Revised Project Phasing Plan and revised plumbing notes to correspond to the new phasing plans.

6. Sheet PC102 – Plumbing Phasing Plans – Reissued

a. Revised Project Phasing Plan and revised plumbing notes to correspond to the new phasing plans.

7. Sheet MC101 – Mechanical Phasing Plans – Reissued

a. Revised Project Phasing Plan and revised mechanical notes to correspond to the new phasing plans.

8. Sheet MC102 – Mechanical Phasing Plans – Reissued

a. Revised Project Phasing Plan and revised mechanical notes to correspond to the new phasing plans.

9. Sheet EC101 – Phasing Plan – Reissued.

a. Revised Project Phasing Plan and revised electrical notes to correspond to the new phasing plans. Enlarged electrical rooms provided for reference.

10. Sheet EC102 – Phasing Plans – Reissued.

a. Revised Project Phasing Plan and revised electrical notes to correspond to the new phasing plans. Enlarged electrical rooms provided for reference.

11. Sheet T-001 – Technology Legend, Abbreviations, & General Notes – Reissued.

a. Revised Technology Legend to delineate WAP and DAS devices and revised telecommunications abbreviations to correspond to the changes.

12. Sheet TC101 – System Phasing Plans – Reissued.

a. Revised Systems Phasing Plan and revised telecommunications notes to correspond to the new phasing plans.

13. Sheet TC102 – System Phasing Plans – Reissued.

a. Revised Systems Phasing Plan and revised telecommunications notes to correspond to the new phasing plans.

14. Sheet TD101 – Partial Level 1 Plan - Technology - Demo - Area A – Reissued.

a. Revised Technology Demo Plan indicating existing WAP and DAS devices and revised telecommunications notes to correspond to the changes.

15. Sheet TD102 – Partial Level 1 Plan - Technology - Demo - Area B – Reissued.

a. Revised Technology Demo Plan indicating existing WAP and DAS devices and revised telecommunications notes to correspond to the changes.

16. Sheet TN101 – Partial Level 1 Plan - Data/Access Control/CCTV - New Work - Area A –

Reissued.

a. Revised Technology New Work Plan indicating existing DAS devices and revised telecommunications notes to correspond to the changes.

17. Sheet TN102 – Partial Level 1 Plan - Data/Access Control/CCTV - New Work - Area B –

Reissued.

a. Revised Technology New Work Plan indicating existing DAS devices and revised telecommunications notes to correspond to the changes.

End of Addendum No.1

PHASE 1

PHASE 1

PHASE 2

Temporary Construction Barrier.

Existing Area not in project Scope

Construction Area included in current Phase

Construction Area completed in previous Phase(s)

Construction Area in future Phase(s)

Egress Path during Phase

Temporary Exit Signs

Existing Exit Signs

Temporary 2-Hour Fire Rated Egress Corridor with Emergency / Egress Lighting, Ceiling and Sprinklers

PHASING LEGEND

T

E

New East Building Expansion

New South Building Expansion

S T A

T E

OF FLO

R

I D A

R E G

IS

TERED ARC

H

IT

E C T

J A S

ON

H. RO

S S

AR101907

VA Project No.

RDC/JPA Project No.

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

FULLY SPRINKLERED

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANTS

321 4 5 6 7 8 9 10

Office of Construction and Facilities Management

03-07-2025

/2

/2

:5

:1

P

M

Create Cardiovascular Center at Lake Nona

03/07/2025

PHASING PLAN

GC101

NSCV

675-103

Orlando, Florida

Kevin Glover - COR

100% CONSTRUCTION

DOCUMENTS - BID SET

22040.00

N Scale: 1/16" = 1'-0"

Project Phasing Plan

A. Verify all conditions in the field prior to fabrication, erection and construction.

B. For temporay partition locations see Demolition Plans. Temporary partitions are suggested locations. Coordinate final location in field with COR.

C. All Temporary partitions to be 1 hour rated wall type T1.0 and shall extend to structural deck above unless noted otherwise. See dwg.

AE001 for temporary partition details.

D. Where temporary partitions are installed against existing walls, ceiling and / or wall finishes to remain, do not mechanically attached walls to prevent damage to those surfaces.

E. Temporary door locations and sizes are as required by the Contractor. Doors shall interfere with daily operations as little as possible. Confirm all locations with the COR. Construction doors are to use VA standard door hardware and to be keyed alike with VA standard locksets.

F. All Temporary doors installed in 1 hour rated construction partitions shall be 45 min. door unless otherwise noted.

G. Construct one section of temporary walls at a time to minimize congestion in corridor. Egress path must be maintained at all times.

H. Coordinate sequence construction with COR so that only one side of any corridor in use is obstructed at any one time.

I. Contractor to provide and install temporary wayfinding and egress signage during constuction. Coordinate sign depictions with COR and Physical Security.

J. Coordinate phase completion and start-up with requirements as set forth by the COR to maintain daily operations to near as normal as possible.

K. Coordinate location of job dumpster with the COR so as to disrupt daily operations as little as possible.

L. Coordinate access to all phases of construction, deliveries, and debris removal with the COR. See General Requirements.

M. Existing HVAC, medical gases, sprinklers and water supply to be maintained throughout as required during each phase of construction.Coordinate phasing with Mechanical and Plumbing contractor. Support and protect all lines during each phase of construction. See MEP Drawings.

N. Provide and maintain negative air pressure at all construction.

Coordinate with HVAC contractor. See HVAC plans for temporary venting requirements and duct locations.

O. Existing power must be maintained throughout as required during each phase of construction.Coordinate phasing with Electrical Contractor. Coordinate power turnover with requirements as dictated by the COR See Electrical Drawings.

P. Coordinate sequence construction with COR so that only one side of any corridor in use is obstructed at any one time.

R. Coordinate all work involving the generation of excessive noise so as to occur during non-peak operating hours, 1000 to 1600 daily.

Activities to occur during this time include, but are not limited to saw cutting, jack hammering, hammer drilling and core drilling. If there is any question as to whether an operation should occur during this time the Contractor will contact the COR.

S. Firestop all penetrations by the end of the shift. All Contractors shall have the Life Safety Plan that identifies each barrier. All Contractors shall be authorized and trained to perform firestopping.

T. All work requiring the use of a crane must be performed after hours.

U. Work to take place after hours shall be scheduled between 1700 to 600 Monday - Friday. Contractor shall coordinate and scheudule all after hours and weekend work with COR.

GENERAL PHASING NOTESPROJECT PHASING

524 Fernwood Drive, Altamonte Springs, Florida 32701 |www.rdcjpa.com| 800.362.1523 Revisions Date

1 Addendum No. 1 07/30/2025

N Scale: 1/16" = 1'-0"

Existing Plan

Note:

Refer to drawings FPC101 fire protection, PC101 plumbing, MC101 mechanical, EC101 electrical, TC101 technology & FAC101 fire alarm for additional phasing information and details.

Phase 1:

- Owner to vacate existing area defined in Phase 1.

- Construction fire rated temporary partitions.

- Demo & construct new interior renovation of Admin. & Holding rooms.

- Complete site work for new building expansion.

- Construct new East building expansion.

- Construction fire rated tempoary partitions including Stair and Interstitial Floor.

- Demo portion of existing exterior walls required for new construction.

- Construct recessed alcove in corridor wall for Police digital message board.

- Prior to commencing new building expansion shell construction adjacent to existing exterior Stair exit door, a tempoprary fire rated egress path back through the building must be completed.

- Construct temporary fire rated egress corridor walls & fire rated door with door swing oriented in the direction of egress from stair.

- Install ceiling along with emergency / egress lighting & directional exit signs along egress path.

- Install/modify suppression system to provide sprinklers in temporary corridor.

- Interior walls of temporary corridor shall be finished and painted.

- Remove & salvage existing interior exit door into Stair. Protect and store door to be reinstalled.

- Lock & install signage at existing exterior Stair exit door to prevent occupants from exiting into active construction area of building expansion.

- Upon completion of building expansion shell portion adjacent to the Stair exit door and approved by VA COR & Safety, reinstall interior stair exit door and reopen exterior stair exit discharge door.

- Temporary fencing to be in place to allow safe exiting from Stair door to beyond construction zone.

- Remove temporary fire rated egress corridor walls, fire rated door & ceiling.

- Remove temporary egress lighting & exit signs.

- Remove existing exterior exit door used for temporary stair egress & fill in with new pre-cast wall panel.

- Complete wall, floor & ceiling construction where temporary corridor was removed.

Phase 2:

- Owner to relocate existing Clinic operations into Phase 1 areas temporarily to maintain patient service & vacate Phase 2 area.

- Remove existing exit light, vestibule exit doors and install new doors to secure construction area.

- Construction fire rated temporary partitions.

- Demo & construct new interior renovation of Clinic rooms.

- Demo portion of existing exterior walls & interior vestibule required for new construction.

- Construct new South building expansion.

- Complete wall, floor & ceiling finishes in areas where temporary partitions were removed upon completion of Phase 2.

- Install casework in Providers office (Temp Waiting) once new Waiting Area is completed and in use.

T1.0

T1.0

T1.0

T1.0

T1.0

T1.0

Temporary Clinic Waiting & Check-in

Temporary Clinic Rooms for Echo, ECG, Holter & Stress

1.15

1.14

1.06

M in.

5'-0"

Common Path of Travel:

Max. Allowable = 100' Actual = 14'

Common Path of Travel:

Max. Allowable = 200' Actual = 55'

Common Path of Travel:

Max. Allowable = 100' Actual = 27'

Common Path of Travel:

Max. Allowable = 100' Actual = 41'

Travel Distance to Exit:

Max. Allowable = 200' Actual = 100'

Travel Distance to Exit:

Max. Allowable = 200' Actual = 98'

Travel Distance to Exit:

Max. Allowable = 200' Actual = 131'

Travel Distance to Exit:

Max. Allowable = 200' Actual = 153'

1.20

1.20

1.19

T .0

Travel Distance to Exit:

Max. Allowable = 200' Actual = 111'

Travel Distance to Exit:

Max. Allowable = 200' Actual = 98'

Common Path of Travel:

Max. Allowable = 100' Actual = 25'

Common Path of Travel:

Max. Allowable = 100' Actual = 97'

E

E

T E

EE

E

E

T1.0

T1.0

E E

E

E E

E

5'-0"

E

T1.0

5'-0"

T

T2.0

1.05

1.03

1.04

1.09

T2.0

T

TT

T T

T

1.10

Travel Distance to Exit:

Max. Allowable = 200' Actual = 94'

T2.0

1.06

1.12

1.12

T1.0

5'-0"

T2.0

T2.0

T2.0

T2.0

'-0

8'-0"

'-0

T2.0

1.17 1.10

1.11

1.13

Temporary Construction Barrier.

Existing Area not in project Scope

Construction Area included in current Phase

Construction Area completed in previous Phase(s)

Construction Area in future Phase(s)

Egress Path during Phase

Temporary Exit Signs

Existing Exit Signs

Temporary 2-Hour Fire Rated Egress Corridor with Emergency / Egress Lighting, Ceiling and Sprinklers

PHASING LEGEND

T

E

MECHANICAL

1E201

T1.0

T1.0

3'-0"

T1.0

1.16

New South Building Expansion

1.181.18

N Scale: 1/16" = 1'-0"1.2 Phase 1 Plan - Mechanical Floor

S T A

T E

OF FLO

R

I D A

R E G

IS

TERED ARC

H

IT

E C T

J A S

ON

H. RO

S S

AR101907

VA Project No.

RDC/JPA Project No.

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

FULLY SPRINKLERED

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANTS

321 4 5 6 7 8 9 10

Office of Construction and Facilities Management

03-07-2025

/2

/2

:4

:4

P

M

Create Cardiovascular Center at Lake Nona

03/07/2025

PHASING PLANS

GC102

DesignerApprover

675-103

Orlando, Florida

Kevin Glover - COR

100% CONSTRUCTION

DOCUMENTS - BID SET

22040.00

N Scale: 1/16" = 1'-0"2 Phase 2 Plan

N Scale: 1/16" = 1'-0"1.1 Phase 1 Plan

1.03 Remove and salvage existing door only, frame to remain.

Protect and store door to be reinstalled upon completion of adjacent building expansion.

1.04 VA to provide temporary signage to indicate existing exit door is not an exit and designate new exit through temporary egress pathway. Reopen exit door upon completion of building expansion shell at exit discharge and when deemed safe by

COR.

1.05 Provide 1-1/2 hour rated HM frame and door for temporary egress. Hardware shall be fail safe including closer, panic bar and gasketing around jambs & head.

1.06 Remove existing exit signs prior to start of construction.

1.09 Temporary 2-hr rated horizontal egress pathway to exit door.

Corridor inside walls to be painted and concrete floor sealed.

1.10 Ensure lighting along temporary egress pathway is connected to emergency power and lighting value provides a minimum of 1 ft-candle measured at the floor surface.

1.11 Remove temporary corridor after it is no longer required for building exit egress and complete room construction and finishes along temporary corridor area.

1.12 Do not install casework in Phase 1. All other room finishes shall be completed in Phase 1 to allow room to be temporarily used for another use during construction Phase 2.

1.13 Maintain access to Toilet Room for patient use during Phase 1.

1.14 Upon completion of Phase 2 and use of new Waiting room, install countertops and wall cabinets.

1.15 Apply temporary covering completely over storefront windows and doors on the inside face of the glazing.

1.16 Coordinate work for new opening in existing stair wall and installation of new door to minimize time for temporary partition in stair. Remove partition immediately upon completion of new door. Schedule work with COR.

1.17 Remove exit door and install new pre-cast panel in opening after temporary corridor is no longer required for building exit egress.

1.18 Demo existing walls and floor finishes as necessary to allow access for below slab work to connect new sanitary plumbing to existing sanitary lines in Phase 1 work. Interior renovations in this area to take place in Phase 2 work.

1.19 Install doors along construction barrier walls at end of Phase 2.

Install temporary barriers around doors or complete after hours to not interfere VA clinic operations during normal business hours.

1.20 Remove temporary construction barriers at end of Phase 2.

Path walls, floors, ceiling as required and complete installation of finishes.

A. Verify all conditions in the field prior to fabrication, erection and construction.

B. For temporay partition locations see Demolition Plans. Temporary partitions are suggested locations. Coordinate final location in field with COR.

C. All Temporary partitions to be 1 hour rated wall type T1.0 and shall extend to structural deck above unless noted otherwise. See dwg.

AE001 for temporary partition details.

D. Where temporary partitions are installed against existing walls, ceiling and / or wall finishes to remain, do not mechanically attached walls to prevent damage to those surfaces.

E. Temporary door locations and sizes are as required by the Contractor. Doors shall interfere with daily operations as little as possible. Confirm all locations with the COR. Construction doors are to use VA standard door hardware and to be keyed alike with VA standard locksets.

F. All Temporary doors installed in 1 hour rated construction partitions shall be 45 min. door unless otherwise noted.

G. Construct one section of temporary walls at a time to minimize congestion in corridor. Egress path must be maintained at all times.

H. Coordinate sequence construction with COR so that only one side of any corridor in use is obstructed at any one time.

I. Contractor to provide and install temporary wayfinding and egress signage during constuction. Coordinate sign depictions with COR and Physical Security.

J. Coordinate phase completion and start-up with requirements as set forth by the COR to maintain daily operations to near as normal as possible.

K. Coordinate location of job dumpster with the COR so as to disrupt daily operations as little as possible.

L. Coordinate access to all phases of construction, deliveries, and debris removal with the COR. See General Requirements.

M. Existing HVAC, medical gases, sprinklers and water supply to be maintained throughout as required during each phase of construction.Coordinate phasing with Mechanical and Plumbing contractor. Support and protect all lines during each phase of construction. See MEP Drawings.

N. Provide and maintain negative air pressure at all construction.

Coordinate with HVAC contractor. See HVAC plans for temporary venting requirements and duct locations.

O. Existing power must be maintained throughout as required during each phase of construction.Coordinate phasing with Electrical Contractor. Coordinate power turnover with requirements as dictated by the COR See Electrical Drawings.

P. Coordinate sequence construction with COR so that only one side of any corridor in use is obstructed at any one time.

R. Coordinate all work involving the generation of excessive noise so as to occur during non-peak operating hours, 1000 to 1600 daily.

Activities to occur during this time include, but are not limited to saw cutting, jack hammering, hammer drilling and core drilling. If there is any question as to whether an operation should occur during this time the Contractor will contact the COR.

S. Firestop all penetrations by the end of the shift. All Contractors shall have the Life Safety Plan that identifies each barrier. All Contractors shall be authorized and trained to perform firestopping.

T. All work requiring the use of a crane must be performed after hours.

U. Work to take place after hours shall be scheduled between 1700 to 600 Monday - Friday. Contractor shall coordinate and scheudule all after hours and weekend work with COR.

GENERAL PHASING NOTESPROJECT PHASING

Note:

Refer to drawings FPC101 fire protection, PC101 plumbing, MC101 mechanical, EC101 electrical, TC101 technology & FAC101 fire alarm for additional phasing information and details.

Phase 1:

- Owner to vacate existing area defined in Phase 1.

- Construction fire rated temporary partitions.

- Demo & construct new interior renovation of Admin. & Holding rooms.

- Complete site work for new building expansion.

- Construct new East building expansion.

- Construction fire rated tempoary partitions including Stair and Interstitial Floor.

- Demo portion of existing exterior walls required for new construction.

- Construct recessed alcove in corridor wall for Police digital message board.

- Prior to commencing new building expansion shell construction adjacent to existing exterior Stair exit door, a tempoprary fire rated egress path back through the building must be completed.

- Construct temporary fire rated egress corridor walls & fire rated door with door swing oriented in the direction of egress from stair.

- Install ceiling along with emergency / egress lighting & directional exit signs along egress path.

- Install/modify suppression system to provide sprinklers in temporary corridor.

- Interior walls of temporary corridor shall be finished and painted.

- Remove & salvage existing interior exit door into Stair. Protect and store door to be reinstalled.

- Lock & install signage at existing exterior Stair exit door to prevent occupants from exiting into active construction area of building expansion.

- Upon completion of building expansion shell portion adjacent to the Stair exit door and approved by VA COR & Safety, reinstall interior stair exit door and reopen exterior stair exit discharge door.

- Temporary fencing to be in place to allow safe exiting from Stair door to beyond construction zone.

- Remove temporary fire rated egress corridor walls, fire rated door & ceiling.

- Remove temporary egress lighting & exit signs.

- Remove existing exterior exit door used for temporary stair egress & fill in with new pre-cast wall panel.

- Complete wall, floor & ceiling construction where temporary corridor was removed.

Phase 2:

- Owner to relocate existing Clinic operations into Phase 1 areas temporarily to maintain patient service & vacate Phase 2 area.

- Remove existing exit light, vestibule exit doors and install new doors to secure construction area.

- Construction fire rated temporary partitions.

- Demo & construct new interior renovation of Clinic rooms.

- Demo portion of existing exterior walls & interior vestibule required for new construction.

- Construct new South building expansion.

- Complete wall, floor & ceiling finishes in areas where temporary partitions were removed upon completion of Phase 2.

- Install casework in Providers office (Temp Waiting) once new Waiting Area is completed and in use.

PLAN NOTES

524 Fernwood Drive, Altamonte Springs, Florida 32701 |www.rdcjpa.com| 800.362.1523 Revisions Date

1 Addendum No. 1 07/30/2025

Area - BArea - A

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT

321 4 5 6 7 8 9 10 www.abovegroupinc.com COA/CA Lic. No. 31120

FULLY SPRINKLERED305 East Dr., Suite H, Melbourne, Florida 32904

PH: 321.345.9026

A u to d e s k D o c s

/F lo ri d a

O rl a n d o

V A

/0

V A

L a k e N o n a C a rd io lo g y

R

M

E P

F P

F A

T .r v t

/2

/2

:5

:1

A

M

FPC101

FIRE PROTECTION PHASING PLANS Create Cardiovascular Center at Lake Nona

Orlando, Florida

675-103

Kevin Glover - COR

03/07/2025 JMC AJZ

100% CONSTRUCTION

DOCUMENTS - BID SET

ALLEN D. LANTZ, P.E.

FL License #98984

PHASING NOTES

1. REFER TO ARCHITECTURAL PHASING PLANS ON GC101 AND GC102 FOR MORE INFORMATION.

N 0 8' 16' 32' 48'

1/16" = 1'-0"

N.T.S.

Key Plan - Overall

524 Fernwood Drive, Altamonte Springs, Florida 32701 |www.rdcjpa.com| 800.362.1523 Revisions Date

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT

321 4 5 6 7 8 9 10 www.abovegroupinc.com COA/CA Lic. No. 31120

FULLY SPRINKLERED305 East Dr., Suite H, Melbourne, Florida 32904

PH: 321.345.9026

A u to d e s k D o c s

/F lo ri d a

O rl a n d o

V A

/0

V A

L a k e N o n a C a rd io lo g y

R

M

E P

F P

F A

T .r v t

/2

/2

:5

:1

A

M

FPC102

FIRE PROTECTION PHASING PLANS Create Cardiovascular Center at Lake Nona

Orlando, Florida

675-103

Kevin Glover - COR

03/07/2025 JMC AJZ

100% CONSTRUCTION

DOCUMENTS - BID SET

ALLEN D. LANTZ, P.E.

FL License #98984

PHASING NOTES

1. REFER TO ARCHITECTURAL PHASING PLANS ON GC101 AND GC102 FOR MORE INFORMATION.

PHASE 1:

FIRST FLOOR:

• PROVIDE SPRINKLERS ACCORDING TO FP111.

INTERSTITIAL:

• INSTALL NEW FIRE MAINS FROM EXISTING STANDPIPE AND EXTEND PIPING TO SPRINKLER ZONES.

• RECONNECT TO EXISTING FIRE MAINS TO SERVE AREAS TO BE RENOVATED IN FUTURE PHASES.

PHASE 2:

FIRST FLOOR:

• PROVIDE SPRINKLERS ACCORDING TO FP111.

INTERSTITIAL:

• CONNECT TO EXISTING FIRE MAIN AND EXTEND TO SERVE ZONE.

CODED NOTES:

INSTALL FIRE SPRINKLER DRAIN.

INSTALL FIRE MAIN AND FHV.

N 0 8' 16' 32' 48'

1/16" = 1'-0"

N.T.S.

Key Plan - Overall

524 Fernwood Drive, Altamonte Springs, Florida 32701 |www.rdcjpa.com| 800.362.1523 Revisions Date

1 Addendum No. 1 07/30/2025

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT

321 4 5 6 7 8 9 10 www.abovegroupinc.com COA/CA Lic. No. 31120

FULLY SPRINKLERED305 East Dr., Suite H, Melbourne, Florida 32904

PH: 321.345.9026

A u to d e s k D o c s

/F lo ri d a

O rl a n d o

V A

/0

V A

L a k e N o n a C a rd io lo g y

R

M

E P

F P

F A

T .r v t

/2

/2

:5

:2

A

M

PC101

PLUMBING PHASING PLANS Create Cardiovascular Center at Lake Nona

Orlando, Florida

675-103

Kevin Glover - COR

03/07/2025 JMC AJZ

100% CONSTRUCTION

DOCUMENTS - BID SET

ALLEN D. LANTZ, P.E.

FL License #98984

PHASING NOTES

1. REFER TO ARCHITECTURAL PHASING PLANS ON GC101 AND GC102 FOR MORE INFORMATION.

524 Fernwood Drive, Altamonte Springs, Florida 32701 |www.rdcjpa.com| 800.362.1523 Revisions Date

1 Addendum No. 1 07/30/2025

N 0 8' 16' 32' 48'

1/16" = 1'-0"

N.T.S.

Key Plan - Overall

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT

321 4 5 6 7 8 9 10 www.abovegroupinc.com COA/CA Lic. No. 31120

FULLY SPRINKLERED305 East Dr., Suite H, Melbourne, Florida 32904

PH: 321.345.9026

A u to d e s k D o c s

/F lo ri d a

O rl a n d o

V A

/0

V A

L a k e N o n a C a rd io lo g y

R

M

E P

F P

F A

T .r v t

/2

/2

:5

:3

A

M

PC102

PLUMBING PHASING PLANS Create Cardiovascular Center at Lake Nona

Orlando, Florida

675-103

Kevin Glover - COR

03/07/2025 JMC AJZ

100% CONSTRUCTION

DOCUMENTS - BID SET

ALLEN D. LANTZ, P.E.

FL License #98984

PHASING NOTES

1. REFER TO ARCHITECTURAL PHASING PLANS ON GC101 AND GC102 FOR MORE INFORMATION.

FIRST FLOOR:

• INSTALL ALL UNDERGROUND SANITARY IN PHASE 1 AREA OF WORK AS SHOWN ON PS101 AND PS102.

• INSTALL ALL VENT, CW, HW, AND HWR PIPING SERVING NEW PLUMBING FIXTURES IN PHASE 1 AREA OF WORK.

INTERSTITIAL:

• INSTALL ALL VENT, CW, HW, AND HWR PIPING AND EXTEND DOWN TO FIRST FLOOR PLUMBING FIXTURES.

• CONNECT TO EXISTING O2, MV, MA, AND WAGD PIPING AND EXTEND NEW MAINS IN INTERSTITIAL AREA. PROVIDE

VALVES AND CAPS AT TAPS TO AREAS IN FUTURE PHASES.

PHASE 2:

FIRST FLOOR:

• INSTALL ALL UNDERGROUND SANITARY PIPING IN PHASE 2 AREA OF WORK.

• INSTALL ALL VENT, CW, HW, AND HWR PIPING SERVING NEW PLUMBING FIXTURES.

INTERSTITIAL:

• INSTALL ALL VENT, CW, HW, AND HWR PIPING AND EXTEND DOWN TO FIRST FLOOR PLUMBING FIXTURES.

• CONNECT TO EXISTING O2, MV, MA, AND WAGD PIPING TAPS AND EXTEND TO SERVE ROOMS IN PHASE 2 AREA OF

WORK.

524 Fernwood Drive, Altamonte Springs, Florida 32701 |www.rdcjpa.com| 800.362.1523 Revisions Date

1 Addendum No. 1 07/30/2025

CODED NOTES:

CONNECT NEW SANITARY PIPING INTO EXISTING UNDERSLAB SANITARY PIPING AT THIS LOCATION AS SHOWN ON PS101.1

N 0 8' 16' 32' 48'

1/16" = 1'-0"N.T.S.

Key Plan - Overall

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT

321 4 5 6 7 8 9 10 www.abovegroupinc.com COA/CA Lic. No. 31120

FULLY SPRINKLERED305 East Dr., Suite H, Melbourne, Florida 32904

PH: 321.345.9026

A u to d e s k D o c s

/F lo ri d a

O rl a n d o

V A

/0

V A

L a k e N o n a C a rd io lo g y

R

M

E P

F P

F A

T .r v t

/2

/2

:4

:2

A

M

MC101

MECHANICAL PHASING PLANS Create Cardiovascular Center at Lake Nona

Orlando, Florida

675-103

Kevin Glover - COR

03/07/2025 JMC AJZ

100% CONSTRUCTION

DOCUMENTS - BID SET

ALLEN D. LANTZ, P.E.

FL License #98984

PHASING NOTES

1. REFER TO ARCHITECTURAL PHASING PLANS ON GC101 AND GC102 FOR MORE INFORMATION.

N 0 8' 16' 32' 48'

1/16" = 1'-0"

N.T.S.

Key Plan - Overall

524 Fernwood Drive, Altamonte Springs, Florida 32701 |www.rdcjpa.com| 800.362.1523 Revisions Date

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT

321 4 5 6 7 8 9 10 www.abovegroupinc.com COA/CA Lic. No. 31120

FULLY SPRINKLERED305 East Dr., Suite H, Melbourne, Florida 32904

PH: 321.345.9026

A u to d e s k D o c s

/F lo ri d a

O rl a n d o

V A

/0

V A

L a k e N o n a C a rd io lo g y

R

M

E P

F P

F A

T .r v t

/2

/2

:4

:3

A

M

MC102

MECHANICAL PHASING PLANS Create Cardiovascular Center at Lake Nona

Orlando, Florida

675-103

Kevin Glover - COR

03/07/2025 JMC AJZ

100% CONSTRUCTION

DOCUMENTS - BID SET

ALLEN D. LANTZ, P.E.

FL License #98984

PHASING NOTES

1. REFER TO ARCHITECTURAL PHASING PLANS ON GC101 AND GC102 FOR MORE INFORMATION.

FIRST FLOOR:

• PROVIDE ALL DIFFUSERS, GRILLES, AND THERMOSTATS FOR SPACES SERVED BY H-AHU-1 FOR SPACES WITHIN

THE PHASE 1 AREA OF WORK.

• PROVIDE ALL DIFFUSERS, GRILLES, AND THERMOSTATS FOR SPACES SERVED BY H-AHU-31 AND H-AHU-32.

• BALANCE H-AHU-31 AND H-AHU-32

• REBALANCE H-AHU-1 TO PHASE 1 CFMS.

INTERSTITIAL:

• PROVIDE H-AHU-31 AND H-AHU-32 AND ALL ASSOCIATED DUCTWORK, PIPING, AND CONTROLS. PROVIDE ALL

TERMINAL UNITS, HHWS/R PIPING, CHWS/R PIPING, CONTROLS, AND DUCTWORK AS SHOWN ON MH121, MH122, MP121, AND MP122 FOR THE PHASE 1 AREA OF WORK.

• PROVIDE VALVES AND CAPS FOR ALL PIPING BRANCHES TO SERVE FUTURE PHASES.

PHASE 2:

FIRST FLOOR:

• PROVIDE ALL DIFFUSERS, GRILLES, AND THERMOSTATS FOR SPACES SERVED BY H-AHU-1 IN PHASE 2 AREA OF

WORK.

• REBALANCE H-AHU-1 TO PHASE 2 CFMS.

INTERSTITIAL:

• PROVIDE ALL TERMINAL UNITS, HHWS/R PIPING, CHWS/R PIPING, CONTROLS, AND DUCTWORK AS SHOWN ON

MH121, MH122, MP121, AND MP122 FOR THE PHASE 2 AREA OF WORK.

N 0 8' 16' 32' 48'

1/16" = 1'-0"N.T.S.

Key Plan - Overall

524 Fernwood Drive, Altamonte Springs, Florida 32701 |www.rdcjpa.com| 800.362.1523 Revisions Date

A7 32.4

H1E2LS2

H1E2LN3

H1E2LN4

H1E2LC3

H1E2LC4

H1E2HC2

H1E2HN2

H1E2HS2

T-H1E2LS2

ELECTRIC

1C102C

ECB-H1E2HS2

T-H1E2LC3

T-H1E2LN3

ECB-H1E2HN2

ECB-H1E2HC2

B.1

C.1

3.7

H1E3HN1

T-H1E3LN1

H1E3LC1

H1E3HC1

H1E3LN1

H1E3LN2

ELECTRIC

1C924

T-H1E3LC1

H1E3HS1

H1E3LN1-14

H1E3LN1-14

ECB-H1E3HN1

ECB-H1E3HC1

LIGHTING CONTROL PANEL

EXISTING 15kV

CONDUITS

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT

321 4 5 6 7 8 9 10 www.abovegroupinc.com COA/CA Lic. No. 31120

FULLY SPRINKLERED305 East Dr., Suite H, Melbourne, Florida 32904

PH: 321.345.9026

A u to d e s k D o c s

/F lo ri d a O rl a n d o V

A /0

V

A L a k e N o n a C a rd io lo g y

R

M E

P F

P F

A T

.r v t

/2

/2

:3

:2

P

M

EC101

ELECTRICAL PHASING PLANS Create Cardiovascular Center at Lake Nona

Orlando, Florida

675-103

Kevin Glover - COR

03/07/2025 CJM IMW

100% CONSTRUCTION

DOCUMENTS - BID SET

BRANDON M. SARGENT, P.E.

FL License #92822524 Fernwood Drive, Altamonte Springs, Florida 32701 |www.rdcjpa.com| 800.362.1523 Revisions Date

1 Addendum No. 1 07/30/2025

N 0 8' 16' 32' 48'

1/16" = 1'-0"

ELECTRICAL ROOM 1C102C

ELECTRICAL ROOM 1C924

1/4" = 1'-0"

1 ELECTRIC 1C102C ENLARGED ELECTRICAL EQUIPMENT

0 2' 4' 8' 12'

1/4" = 1'-0"

1/4" = 1'-0"

2 ELECTRIC 1C924 ENLARGED ELECTRICAL EQUIPMENT

1REVISED PHASING

A7 32.4

H1E2LS2

H1E2LN3

H1E2LN4

H1E2LC3

H1E2LC4

H1E2HC2

H1E2HN2

H1E2HS2

T-H1E2LS2

ELECTRIC

1C102C

ECB-H1E2HS2

T-H1E2LC3

T-H1E2LN3

ECB-H1E2HN2

ECB-H1E2HC2

B.1

C.1

3.7

H1E3HN1

T-H1E3LN1

H1E3LC1

H1E3HC1

H1E3LN1

H1E3LN2

ELECTRIC

1C924

T-H1E3LC1

H1E3HS1

H1E3LN1-14

H1E3LN1-14

ECB-H1E3HN1

ECB-H1E3HC1

LIGHTING CONTROL PANEL

EXISTING 15kV

CONDUITS

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT

321 4 5 6 7 8 9 10 www.abovegroupinc.com COA/CA Lic. No. 31120

FULLY SPRINKLERED305 East Dr., Suite H, Melbourne, Florida 32904

PH: 321.345.9026

A u to d e s k D o c s

/F lo ri d a O rl a n d o V

A /0

V

A L a k e N o n a C a rd io lo g y

R

M E

P F

P F

A T

.r v t

/2

/2

:3

:2

P

M

EC102

ELECTRICAL PHASING PLANS Create Cardiovascular Center at Lake Nona

Orlando, Florida

675-103

Kevin Glover - COR

03/07/2025 CJM IMW

100% CONSTRUCTION

DOCUMENTS - BID SET

BRANDON M. SARGENT, P.E.

FL License #92822524 Fernwood Drive, Altamonte Springs, Florida 32701 |www.rdcjpa.com| 800.362.1523 Revisions Date

1 Addendum No. 1 07/30/2025

N 0 8' 16' 32' 48'

1/16" = 1'-0"

1/4" = 1'-0"

1 ELECTRIC 1C102C ENLARGED ELECTRICAL EQUIPMENT

1/4" = 1'-0"

2 ELECTRIC 1C924 ENLARGED ELECTRICAL EQUIPMENT

ELECTRICAL ROOM 1C102C

ELECTRICAL ROOM 1C924

ELECTRICAL NOTES:

- INSTALL AND CONNECT ALL NEW ELECTRICAL EQUIPMENT IN ELECTRICAL ROOM 1C924 AS REQUIRED. EXTEND THE EXISTING 800A BUS DUCT FROM ELECTRICAL ROOM 1C924 TO COMPLETE THE INSTALLATION OF ECB-H1E3HC1. COORDINATE AND MINIMIZE ANY REQUIRED POWER SHUTDOWNS AND OUTAGES REQUIRED WITH THE VA (4) WEEKS IN ADVANCE.

- PROVIDE LOW VOLTAGE SWITCHES AT EITHER END OF THE TEMPORARY CORRIDOR AND OCCUPANCY SENSORS SPACED AT 20 FEET FOR LIGHTING CONTROLS. LIGHTING SHALL BE AUTOMATIC ON TO 50% LIGHT LEVEL UPON OCCUPANCY, AND 100% MANUAL ON. VACANCY SENSOR TIMEOUT DELAY SHALL BE 20 MINUTES.

- PROVIDE (9) TYPE 'C1' LIGHTING FIXTURES AND (5) TYPE 'X' EXIT SIGNS (PER THE LIFE SAFETY PLAN) MOUNTED TO THE CEILING OF THE TEMPORARY CORRIDOR. ALL LIGHTING FIXTURES SHALL BE CIRCUITED TO A SPARE CIRCUIT IN THE NEW LIFE SAFETY PANELBOARD H1E3HS1 LOCATED IN ELECTRICAL ROOM 1C924 (AS PART OF PHASE 1).

- PROVIDE (1) TYPE 'W' FIXTURE MOUNTED AT 8 FEET AFG ON THE EXTERIOR OF THE BUILDING FOR EMERGENCY EGRESS LIGHTING. THIS LIGHTING FIXTURE SHALL BE CIRCUITED TO A SPARE CIRCUIT IN THE NEW LIFE SAFETY PANELBOARD H1E3HS1 LOCATED IN ELECTRICAL ROOM 1C924 (AS PART OF PHASE 1). COORDINATE AND MINIMIZE ANY REQUIRED

POWER SHUTDOWNS AND OUTAGES REQUIRED WITH THE VA (4) WEEKS IN ADVANCE.

- PROVIDE LIGHTING AND POWER LAYOUTS IN MECHANICAL ROOM 1E201 PER ELECTRICAL SHEETS EL102.D AND EP102.D. PROVIDE CIRCUITING PER ELECTRICAL SHEETS EL102.D AND EP102.D. COORDINATE AND MINIMIZE ANY REQUIRED POWER SHUTDOWNS AND OUTAGES REQUIRED WITH THE VA (4) WEEKS IN ADVANCE.

- AT THE END OF PHASE 1, ALL WORK LOCATED WITHIN THE TEMPORARY CORRIDOR SHALL BE REMOVED IN ITS ENTIRETY TO PREPARE FOR WORK DONE IN PHASE 2.

ELECTRICAL NOTES:

- CONNECT ALL ELECTRICAL DEVICES TO THE PANELS LOCATED IN ELECTRICAL ROOM 1C102C

AND ELECTRICAL ROOM 1C924 AS REQUIRED. COORDINATE AND MINIMIZE ANY REQUIRED

POWER SHUTDOWNS AND OUTAGES REQUIRED WITH THE VA (4) WEEKS IN ADVANCE.

ELECTRICAL ROOM 1C102C

ELECTRICAL ROOM 1C924

1REVISED PHASING

0 2' 4' 8' 12'

1/4" = 1'-0"

37-PIN CONNECTOR FOR PATIENT BED CONTROLS (NURSE CALL/CODE

BLUE/TV/LIGHTS/PHONE

N

TELEPHONE BACKBOARD (WALL MOUNTED)

TELEPHONE TERMINAL CABINET

DEVICE MOUNTING LOCATION AND HEIGHT NOTES:

1. FOR WHEELCHAIR PATIENT USE MOUNT TELEPHONE OUTLET 36" AFF TO BOTTOM OF OUTLET

BOX.

2. DESK PHONES - MOUNT OUTLET 1'-6" AFF.

3. PAY PHONES - MOUNT OUTLET 4'-0" AFF

4. HEIGHT OF TELECART OUTLETS SHALL BE AS INDICATED ON BEDWALLS OR PBPU DETAILS.

5. SEE VA BARRIER FREE DESIGN GUIDE PG-18-13.

NURSE CALL CORRIDOR DOME LIGHT WITH SOUNDER:

2 = NURSE'S CALL DOME LIGHT (SUFFIX INDICATES NUMBER OF LAMP) MTD 6" ABOVE DOOR.

Z = AUXILIARY INTERSECTIONAL DOME LIGHT.

NURSE CALL STATION:

2 = DUPLICATE FACILITIES FOR TWO BEDS (SEPARATE INDICATORS AT

MASTER STATION) MTD 5'-0" AFF UNLESS OTHERWISE NOTED

D = DUTY STATION. MTD 5'-0" AFF UNLESS NOTED NOTED.

T = PULL CORD MTD 6'-0" AFF FOR SHOWER LOCATION, MTD 4'-6" AFF FOR TUB LOCATION, & MTD

3'-0" AFF FOR TOILET LOCATION.

E = STAFF ASSISTANCE MTD 5'-0" AFF.

B = CODE BLUE

P = PATIENT BED STATION

S = AUDIO VISUAL WALL STATION (STAFF) MTD 5'-0" AFF UNLESS OTHERWISE NOTED.

U = UTILITY CALL STATION, MTD 5'-0" AFF UNLESS OTHERWISE NOTED.

NURSE CALL TERMINAL CABINET.

NURSE'S CALL MASTER STATION MTD ON NURSE'S COUNTER TOP, UNLESS

OTHERWISE NOTED.

OUTLET; LETTER INDICATES AS FOLLOWS:

V = VIDEO CONNECTION (1) RG6 COAXIAL CABLE

OUTLET DATA ONLY - (1) CAT6A CABLE PER PORT.

# = NUMBER OF PORTS, CH = COUNTER HEIGHT,

MF = MODULAR FURNITURE CONNECTION

OUTLET (VOIP) TELEPHONE, (1) PORT; (1) CAT6A CABLE. LETTER INDICATES

AS FOLLOWS:

J = JACK TYPE 18" AFF W = WALL TYPE 48" AFF WITH MOUNTING POSTS

FLOOR RECEPTACLE, (VOIP) TELEPHONE

FIBEROPTICS LINE = FO

WORK AREA TCO, COMBINATION TELEPHONE/DATA COMMUNICATION OUTLET - 4 DATA PORT FACE

PLATE WITH 4 DATA PORTS - (1) CAT6A CABLE PER PORT.

NCS

NCT

TTB

V

J

N

FO

COMMUNICATION SYMBOLS

SYMBOL DESCRIPTION

CH = COUNTER HEIGHT

MF = MODULAR FURNITURE CONNECTION

CH

GENERAL NOTES

1. PRODUCTS SHALL BE OF MATERIALS THAT ARE SUITABLE FOR THE ENVIRONMENT IN WHICH THEY ARE TO BE INSTALLED.

2. WORKING CLEARANCES AROUND ELECTRICAL EQUIPMENT SHALL BE MAINTAINED IN COMPLIANCE WITH THE NATIONAL ELECTRICAL CODE ARTICLE 110, COORDINATE

EQUIPMENT INSTALLATION TO MAINTAIN REQUIRED CLEARANCES.

3. IF AN OUTLET BOX IS REQUIRED TO BE LOCATED IN AN ASSEMBLY OR PARTITION RATED AS "FIRE/SMOKE" OR "SMOKE" OR IDENTIFIED AS EITHER "FIRE/SMOKE" OR "SMOKE", THEN ALL OF THE FOLLOWING CONDITIONS SHALL BE MET:

A. THE OUTLET BOX SHALL BE METALLIC.

B. THE OUTLET BOX OPENINGS SHALL OCCUR ONLY ON ONE SIDE OF THE FRAMING SPACE.

C. THE OUTLET BOX OPENINGS SHALL NOT EXCEED 16 SQUARE INCHES.

D. ALL CLEARANCES BETWEEN THE OUTLET BOX AND THE WALL BOARD MATERIAL SHALL BE COMPLETELY SEALED WITH APPROVED MATERIALS IN ACCORDANCE WITH THE

APPLICABLE CODES AND STANDARDS FOR THE PROJECT.

E. PROVIDE A SUPPLEMENTAL BARRIER AROUND OUTLETS LARGER THAN 16 INCHES SO THAT THE ORIGINAL RATING OF THE PENETRATION IS MAINTAINED.

F. THE TOTAL AGGREGATE SURFACE AREA OF THE OUTLET BOX SHALL NOT EXCEED 100 SQUARE INCHES PER 100 SQUARE FEET.

G. THE OUTLET BOX SHALL BE SEPARATED FROM OPENINGS ON THE OPPOSITE SIDE OF THE RATED PARTITION BY A MINIMUM HORIZONTAL DISTANCE OF 24 INCHES.

H. THE OUTLET BOX SHALL BE SECURELY FASTENED TO A PARTITION FRAMING MEMBER BY MEANS OF AN APPROVED ATTACHMENT METHOD.

I. OPENINGS CUT INTO THE WALL BOARD MATERIAL SHALL NOT EXCEED 1/8 INCH BETWEEN THE EDGES OF THE OUTLET BOX AND THE EDGES OF THE OPENING.

4. LOCATIONS OF EQUIPMENT SHOWN ON THE DRAWINGS ARE APPROXIMATE, COORDINATE EXACT EQUIPMENT LOCATION AND CONNECTION REQUIREMENTS WITH THE

APPROPRIATE TRADE PRIOR TO INSTALLATION.

5. FOR EXACT LOCATION OF CEILING MOUNTED EQUIPMENT REFER TO THE ARCHITECTURAL REFLECTED CEILING PLAN. LOCATIONS OF EQUIPMENT NOT INCLUDED ON THE REFLECTED CEILING PLAN SHALL BE COORDINATED WITH THOSE ITEMS SHOWN. COORDINATION OF CEILING MOUNTED EQUIPMENT SHALL BE PRIOR TO ANY ROUGH-IN.

NOTIFY ARCHITECT OF ANY DISCREPANCY.

6. PROVIDE FINAL CONNECTIONS TO OWNER PROVIDED EQUIPMENT WHERE INDICATED ON THE PLAN DRAWINGS.

7. PRIOR TO ROUGH-IN AND INSTALLATION OF ANY FLOOR MOUNTED DEVICE, VERIFY LOCATION WITH THE ARCHITECT.

8. VERIFY AND COORDINATE THE LOCATION OF REQUIRED DIVISION 27 OUTLETS WITH OTHER TRADE DRAWINGS AND OWNER PROVIDED EQUIPMENT.

PULL SCHEDULE REQUIREMENTS

CONTRACTOR SHALL PROVIDE PULL SCHEDULE WITH TELECOM SHOP DRAWINGS. TELECOM SHOP DRAWINGS WILL NOT BE REVIEWED UNLESS THEY INCLUDE PULL

SCHEDULES.

STRUCTURED CABLING SYSTEM (SCS):

THE SCS CONTRACTOR (SCSC) SHALL PROVIDE ALL BACKBONE AND HORIZONTAL CABLING, COMPONENTS AND TERMINATIONS AS REQUIRED FOR A COMPLETE AND OPERATIONAL CABLING

SYSTEM PER INDUSTRY BEST PRACTICES AS PRESCRIBED BY BICSI AND NEC.

THE SCSC SHALL BE RESPONSIBLE FOR COORDINATION WITH THE ELECTRICAL CONTRACTOR (EC) FOR SPECIFIC LOCATIONS OF ALL TELECOMMUNICATIONS SYSTEM DEVICES, INCLUDING

ANCILLARY SYSTEM COMPONENTS AND ASSOCIATED CONDUITS PROVIDED BY THE EC.

THE ELECTRICAL CONTRACTOR (EC) SHALL BE RESPONSIBLE FOR PROVIDING AND INSTALLING ALL ROUGH-IN COMPONENTS ASSOCIATED WITH THE TELECOMMUNICATIONS SYSTEM COMPONENTS AS NOTED ON THE DRAWINGS AND SPECIFICATIONS, INCLUDING BUT NOT LIMITED TO, CONDUIT AND BACK-BOXES. THE EC SHALL COORDINATE ALL REQUIREMENTS WITH THE

SCS CONTRACTOR.

TELECOM ROOM (TR) EQUIPMENT RACKS:

THE SCS CONTRACTOR (SCS) SHALL FURNISH AND INSTALL ALL EQUIPMENT RACKS. THE SCS CONTRACTOR SHALL FURNISH AND INSTALL ALL CABLING PATCH PANELS (COPPER AND FIBER) WITH RACK, AND SHALL BE RESPONSIBLE FOR ALL CABLE TERMINATIONS AT THE PATCH PANELS.

THE VA SHALL BE RESPONSIBLE FOR FURNISHING AND INSTALLING ALL ACTIVE EQUIPMENT, CONTROLLERS, SWITCHES, ETC. THAT RESIDE WITHIN THESE RACKS.

ACCESS CONTROL:

THE SCS CONTRACTOR (SCS) SHALL BE RESPONSIBLE FOR INSTALLING ALL CABLING AND DEVICES TO SUPPORT THE VA PROVIDED SECURITY HEAD END EQUIPMENT. VA SHALL INSTALL, CONNECT AND CONFIGURE FINAL SECURITY HEAD END EQUIPMENT.

THE ELECTRICAL CONTRACTOR (EC) SHALL BE RESPONSIBLE FOR PROVIDING AND INSTALLING ALL ROUGH-IN COMPONENTS ASSOCIATED WITH THE SECURITY SYSTEM AS NOTED ON THE DRAWINGS AND SPECIFICATIONS, INCLUDING BUT NOT LIMITED TO, CONDUIT AND BACK-BOXES. THE EC SHALL COORDINATE WITH THE SCS CONTRACTORS.

GROUNDING AND BONDING:

THE EC SHALL BE RESPONSIBLE FOR INSTALLING THE GROUNDING BUSBAR(S) AS ILLUSTRATED ON THE DRAWINGS AND SPECIFICATIONS, AND CONNECTING IT TO THE BUILDING MAIN ELECTRICAL SERVICE GROUND. THE EC SHALL BE RESPONSIBLE FOR GROUNDING ALL BACKBONE CONDUIT AND CABLE TRAY.

THE SCSC SHALL BE RESPONSIBLE FOR GROUNDING ALL RACKS, CABINETS, ENCLOSURES, PROTECTOR BLOCKS AND CABLE LADDER-RACK INSIDE TELECOMMUNICATIONS ROOMS.

FIRESTOPPING:

THE EC SHALL BE RESPONSIBLE FOR FIRE-STOPPING SLEEVE ASSEMBLIES TO OBTAIN A UL RATING.

THE SCSC SHALL BE RESPONSIBLE FOR FIRE-STOPPING INSIDE THE SLEEVES AFTER CABLE INSTALLATION IS COMPLETE.

CASEWORK / MILLWORK:

THE SCSC SHALL BE RESPONSIBLE FOR INSTALLING TELECOMMUNICATIONS OUTLETS IN CASEWORK, AS REQUIRED. CABLES SHALL BE CONCEALED IN CASEWORK.

THE EC SHALL BE RESPONSIBLE FOR INSTALLING ASSOCIATED CONDUIT AND BACK-BOXES.

CONDUIT:

THE EC SHALL BE RESPONSIBLE TO PROVIDE AND INSTALL ALL BACKBONE AND HORIZONTAL CABLING PATHWAYS. THIS SHALL INCLUDE ALL INTERIOR CONDUITS, PATHWAY COMPONENTS SUCH AS JUNCTION BOXES, PULL BOXES, WALL/CEILING PENETRATIONS AND CONDUIT SLEEVES, WHETHER SHOWN ON THE DRAWINGS OR AS REQUIRED TO PENETRATE FULL-HEIGHT PARTITIONS AS SHOWN ON THE DRAWINGS. THE EC SHALL PROVIDE AND INSTALL ALL BUSHINGS ON TELECOMMUNICATIONS

CONDUITS PRIOR TO INSTALLATION OF CABLING.

THE SCSC SHALL BE RESPONSIBLE FOR ALL WIRE RACEWAYS, CABLE RUNWAY (LADDER RACK) AND OTHER REQUIREMENTS FOR ROUTING AND SECURING CABLE INSIDE

THE MAIN TELECOMMUNICATIONS ROOM (MTR) AND ALL TR'S.

TELECOMMUNICATIONS COMMUNICATIONS OUTLETS (C.O.'S) AND DEVICES:

THE EC SHALL BE RESPONSIBLE FOR PROVIDING AND INSTALLING ALL CONDUIT AND BACK-BOXES ASSOCIATED WITH THE TELECOMMUNICATIONS C.O.'S AND DEVICES.

THE SCSC SHALL BE RESPONSIBLE FOR INSTALLATION OF ALL STRUCTURED CABLING, JACKS, FACEPLATES AND JUMPER/PATCH CORDS.

BACKBOARDS:

THE EC SHALL BE RESPONSIBLE FOR PROVIDING AND INSTALLING ALL BACKBOARDS AS ILLUSTRATED ON THE DRAWINGS AND AS REQUIRED FOR A COMPLETE SYSTEM AS ILLUSTRATED IN THE SPECIFICATIONS. THE EC SHALL BE RESPONSIBLE FOR ROUGH-IN OF ALL CONDUIT AND BACK-BOXES. POWER CONDUITS SHALL BE CONCEALED BEHIND ALL BACKBOARDS. BACKBONE CONDUIT SHALL BE EXPOSED AS ILLUSTRATED ON THE DRAWINGS (TR WALL ELEVATIONS).

COORDINATION NOTES:

SYMBOL DESCRIPTION

CEILING MOUNTED WIRELESS ACCESS POINT (WAP) - (2) CAT6A CABLES

PROXIMITY CARD READER, MTD. 4'-0" AFF UNLESS OTHERWISE NOTED.CR

FLOOR RECEPTACLE, COMBINATION TELEPHONE/DATA COMMUNICATION OUTLET - 4 DATA PORTS -

(1) CAT6A CABLE PER PORT.

NUMERIC KEYPAD, MTD. 4'-0" AFF UNLESS OTHERWISE NOTED.KP

REQUEST TO EXIT DEVICE IN DOOR HARDWARE. RE

FIX

SECURITY ACCESS, VIDEO CAMERA WITH LENS

ML = MULTI LENS

FIX = FIXED WITH MOTION DETECTOR

PZ = MOTION DETECTOR WITH PAN AND ZOOM

PTZ= MOTION DETECTOR WITH PAN, TILT, AND ZOOM

CEILING MOUNTED PUBLIC ADDRESS SYSTEM SPEAKERS

SECURITY DURESS BUTTON

D = DURESS

P = PANIC

D

FIX

CEILING MOUNTED

WALL MOUNTED

REQUEST TO EXIT DEVICE MOUNTED ABOVE DOOR.RE

TELECOMM GROUND BUS BAR, COPPER

INTERCOM CALL STATIONICS

ADMINISTRATIVE PHONEAP

INTERCOM/VOIP HANDSETIHS

COMBINATION CARD READER/NUMERIC KEYPAD, MTD. 4'-0" AFF UNLESS

OTHERWISE NOTED.

CP

4-POST NETWORK EQUIPMENT RACK.

LADDER TYPE CABLE TRAY; SIZE AND MOUNTING HEIGHT AS INDICATED ON PLANS.

BASKET/SOLID BOTTOM/CHANNEL TYPE CABLE TRAY; SIZE, TYPE AND MOUNTING HEIGHT AS

INDICATED ON PLANS.

VERTICAL CABLE MANAGEMENT.

TELECOMMUNICATIONS ABBREVIATIONS

A/C UNIT AIR CONDITIONING UNIT

A/E ARCHITECT/ENGINEER

AAP ALARM ANNUNCIATOR PANEL

AC ALTERNATING CURRENT OR ARMORED CABLE

ACC ACCESSIBLE

ADDL ADDITIONAL

ADJ ADJACENT, ADJOINING

ADO AUTOMATIC DOOR OPENER

AFC ABOVE FINISHED COUNTER

AFF ABOVE FINISHED FLOOR

AFG ABOVE FINISHED GRADE

AHJ AUTHORITY HAVING JURISDICTION

ALT ALTERNATE

AMB OR A AMBIENT

ARCH ARCHITECT

ATS AUTOMATIC TRANSFER SWITCH

AUTO AUTOMATIC

AV AUDIO VISUAL

BAT BATTERY

BBC BONDING BACKBONE CONDUCTOR

BC BARE COPPER

BD BOARD

BFF BELOW FINISH FLOOR

BLDG BUILDING

BPIP BOILER PLANT INSTRUMENTATION PANEL

BYP BY PASS

C CONDUIT

CAB CABINET

CALC CALCULATE

CAP CAPACITY

CAT CATALOG

CATV COMMUNITY ANTENNA TELEVISION

CCR CONTROL CONTACTOR

CCTV CLOSED CIRCUIT TELEVISION

CD CONSTRUCTION DOCUMENTS

CF CONTRACTOR FURNISHED

CF/CI CONTRACTOR FURNISHED/CONTRACTOR INSTALLED

CF/OI CONTRACTOR FURNISHED/OWNER INSTALLED

CFE CONTRACTOR FURNISHED EQUIPMENT

CLG CEILING

CMU CONCRETE MASONRY UNIT

COAX COAX CABLE

COMM COMMUNICATION

COMPT COMPARTMENT

CONC CONCRETE

CONT CONTINUE

CONTR CONTRACTOR

COORD COORDINATE

CTV CABLE TELEVISION

CU COPPER

CU FT CUBIC FEET

CUR CURRENT

DAS DISTRIBUTED ANTENNA SYSTEM

DB DECIBEL OR DIRECT BURIAL

DC DIRECT CURRENT

DEG C DEGREES CELSIUS

DEG F DEGREES FAHRENHEIT

DEMO DEMOLITION

DIAG DIAGRAM

DISTR DISTRIBUTION

DN DOWN

DRSW DOOR SWITCH

DWG DRAWING

EC EMPTY CONDUIT

EG EQUIPMENT GROUND

EL ELEVATION

ELEC ELECTRIC OR ELECTRICAL

ELEV ELEVATOR

EMER EMERGENCY

EMI ELECTROMAGNETIC INTERFERENCE

EMT ELECTRICAL METALLIC TUBING

ENCL ENCLOSURE

EPO EMERGENCY POWER OFF

ESMT EASEMENT

EXIST EXISTING

FLEX FLEXIBLE METALLIC CONDUIT

FOUTT TELEPHONE FLOOR OUTLET

FP FIRE PROTECTION

FT FEET OR FOOT

G OR GND GROUND OR GENERATOR

GEN GENERATOR

GTB GROUND TERMINAL BOX

HT HEIGHT

HZ HERTZ

IMC INTERMEDIATE METAL CONDUIT

IR INFRARED

J-BOX JUNCTION BOX

LF LINEAR FEET (FOOT)

LTNG LIGHTNING

LV LOW VOLTAGE

MATV MASTER ANTENNA TELEVISION SYSTEM

MAX MAXIMUM

MECH MECHANICAL

MH MANHOLE

MIN MINIMUM

MT MOUNT

MTD MOUNTED

MTG MOUNTING

NA NOT APPLICABLE

NEC NATIONAL ELECTRICAL CODE

NEUT OR N NEUTRAL

NIC NOT IN CONTRACT

NS NO SCALE

NTS NOT TO SCALE

OC ON CENTER

OD OUTSIDE DIAMETER

P POLE

PA PUBLIC ADDRESS

PB PANELBOARD, PULL BOX, OR PUSHBUTTON

PBB PRIMARY BONDING BUSBAR

PBPU PREFABRICATED BEDSIDE PATIENT UNIT

PED PEDESTAL

PEND PENDANT

PF POWER FACTOR

PH PHASE

PNL PANEL

PVC POLYVINYL CHLORIDE (PLASTIC)

PWR POWER

RCP REFLECTED CEILING PLAN

REC RECESSED

RECPT RECEPTACLE

RGS RIGID GALVANIZED STEEL

RM ROOM

REQD REQUIRED

SF SQUARE FOOT (FEET)

SHT SHEET

SI INTERNATIONAL SYSTEM OF UNITS

SPEC SPECIFICATION

SURF SURFACE

SW SWITCH

TBC TELECOMMUNICATIONS BONDING BUSBAR

TEL TELEPHONE

TP TWISTED PAIR

TPS TWISTED PAIR SHIELDED

TTB TELEPHONE TERMINAL BOARD

TV TELEVISION

TYP TYPICAL

MSB MAIN SWITCH BOARD

UFD UNDERFLOOR DUCT

UGND UNDERGROUND

UL UNDERWRITERS LABORATORY

UON UNLESS OTHERWISE NOTED

UPS UNINTERRUPTIBLE POWER SUPPLY

UTIL UTILITY

V VOLT

WP WEATHERPROOF

9. ALL RACEWAY SYSTEMS SHOWN TO SUPPORT THE INSTALLATION OF THE DIVISION 27 EQUIPMENT SHALL BE PROVIDED BY THE ELECTRICAL CONTRACTOR. PROVIDE COORDINATION FOR THE INSTALLATION OF THIS RACEWAY SYSTEM WITH THE ELECTRICAL CONTRACTOR.

10. EACH VOICE/DATA OUTLET LOCATION SHOWN, SHALL HAVE A DOUBLE GANG OUTLET BOX WITH A SINGLE GANG PLASTER RING AND (1) 1-1/2" CONDUIT TO TR. WORK BY

ELECTRICAL CONTRACTOR PER SPECS.

11. ALL BONDING AND GROUNDING ELEMENTS UTILIZED FOR STRUCTURED CABLING SYSTEM SHALL BE IN COMPLIANCE WITH SPECIFICATION SECTION 262000.

12. PROVIDE ALL SLEEVES AS REQUIRED FOR ALL LOW VOLTAGE CABLE PATHWAYS. RESTORE THE FIRE RATING OF THE SURFACE.

13. CABLE INSTALLED BELOW SLAB SHALL HAVE INDOOR/OUTDOOR RATED JACKET FOR PROTECTION OF STRUCTURED CABLE.

14. TELECOMMUNICATIONS ROOM SHALL BE BONDED AND GROUNDED IN ACCORDANCE WITH TIA-607D.

15. ALL TELECOMMUNICATIONS CONDUITS SHALL BE PROVIDED WITH BUSHINGS AT EACH END FOR PROTECTION OF…

This is the start of the file's text. The full file is on GovTribe.