Technical Questions - Minneapolis EHRM_BAE Response.pdf

PDF 197 KB Posted

Attached to
Y1DA--EHRM Training and Admin Space Support Construction DBB Support Construction Minneapolis VAMC Federal contract opportunity
Solicitation number
36C77622R0019
Issued by
Department of Veterans Affairs Technology Acquisition Center Austin

About this file

This document contains technical questions and responses related to a solicitation for EHRM Training and Admin Space Support Construction at the Minneapolis VA Medical Center. The solicitation seeks construction services including installation of synthetic turf, automatic sliding doors, cabinetry and casework. Questions covered confirmation of products, specifications and COVID-19 safety protocols. Responses clarified allowable substitutions, design requirements and guidance to follow current CDC guidelines for testing and isolation of infected staff. The solicitation number is 36C77622R0019 and proposals were due on February 8th, 2022. The construction work is for the Department of Veterans Affairs Technology Acquisition Center Austin.

View the file

Other files for this federal contract opportunity

Other files attached to Y1DA--EHRM Training and Admin Space Support Construction DBB Support Construction Minneapolis VAMC, newest first.
File Type Posted
EP102103.pdf PDF
36C77622R0019 0006.pdf PDF
Structural Questions - Minneapolis EHRM_BAE Response.pdf PDF
P09 - Construction Wage Rates - Building - Hennepin County - 01.07.22.pdf PDF
36C77622R0019 0005.pdf PDF
Technical Questions - Minneapolis EHRM - FINAL.pdf PDF
618701_18116_Bid Clarification 012622.pdf PDF
36C77622R0019 0004.docx DOCX document
Minnepolis Sign In Sheet.pdf PDF
36C77622R0019 0003.pdf PDF
P09 - Construction Wage Rates - Hennepin County - 01.07.22.pdf PDF
36C77622R0019 0002.docx DOCX document
36C77622R0019 0001.docx DOCX document
Attachment 4 - Combined Drawings - 3 of 3.pdf PDF
Attachment 2 - Combined Drawings - 1 of 3.pdf PDF
Attachment 8 - Contractor Safety - Environmental Form.docx DOCX document
Attachment 7 - Limitations on Subcontracting - Construction.docx DOCX document
Attachment 6 - VHA Suppl. Contract Rqmnts for Combatting COVID-19 Updated 12-14-2021.pdf PDF
Attachment 5 - JA Brand Name Items - Minn TR Const.pdf PDF
Attachment 3 - Combined Drawings - 2 of 3.pdf PDF
Attachment 1 - Master Specifications - Final.pdf PDF
Attachment 9 - Construction Wage Rates - Hennepin County - 11.1.21.pdf PDF
36C77622R0019_1.docx DOCX document
Show all 23

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation # 36C77622R0019 EHRM Training and Admin Space Support Construction DBB Technical Questions and VA Response Tracking Sheet

ITEM

NO.

DATE

QUESTION

RECEIVED

DATE

QUESTION

ANSWERED

QUESTION GOVERNMENT RESPONSE

1. 1.11.22 1.27.22 Specs 32 18 16 are calling for golf green and chipping area with cups flagpoles etc, built on plywood and foam deck with undulations. The drawing 1384-A103 does not look like a golf green, asking for clarification. Is this a golf green, if not do you still want undulations?

This is not a golf green.

In specification Section 32 18 16:

Section 1.2, Part A: Strike references to indoor putting green and chipping Area.

Section 1.2, Part A to be revised to say: Section includes synthetic grass surfacing for installation as indicated on the Drawings and specified herein.

Section 1.3: Strike Part A from the project.

Section 1.6, Part C: Strike references to contour underlayment panels, cups and flagsticks from the project.

Section 3.3, Part C: Strike Item 1 from the project.

No contours, undulations or slopes are to be installed.

2. 1.11.22 1.27.22 Edge detail calls for a neoprene edging between turf.

Please confirm that edging is desired?

Neoprene Edging can be removed if proposed product substitutions can be seemed together cleanly. Contractor to provide a clean seam connection. If not, neoprene edge to remain to provide clean transition between turf systems

3. 1.11.22 1.27.22 Specs call for Synlawn Synblue949 and Synplay48 in gray. Just to clarify, Synblue is not blue it is green. Blue we believe is in reference to bluegrass.

Yes, the Blue in the product name is in reference to Bluegrass not the color blue.

4. 1.11.22 1.27.22 Can we use TXT48 which is the same product as Synplay 48 both made at STR.

Yes, TXT 48 is an acceptable substitution.

5. 1.11.22 1.27.22 Is it acceptable to substitute ForeverLawn Dupont Select LX landscape grass for the Synblue 949

Substitution is acceptable. Please note response to item 2 above, if product is not able to be seemed with Synplay48 / TXT48 Neoprene edging is to be provided as the transition between turf types.

DATE

QUESTION

RECEIVED

DATE

QUESTION

ANSWERED

QUESTION GOVERNMENT RESPONSE

6. 1.11.22 1.27.22 Synblue 949 or DuPont Select LX would require infill.

Which product should we use for infill?

Utilize manufacturer recommended infill for product.

7. 1.13.22 1.27.22 Question on this, in the surgical waiting room it shows elevations on page A411 and A311. But does not show full height. It shows painting columns and P6 under windows on second story. How far up are we painting?

To deck? the whole wall and pillars?

All existing walls in the Atrium are to be painted to the bottom of deck. Refer to elevations on page A421, A422, A423 & A424 for wall areas above the elevations shown on sheets A411 & A412.

8. 1.17.22 1.27.22 For the automatic slide door 2P-150 detail 3/A601 shows our All-Glass slider. However, this is not mentioned in the spec and elevation 3/A411 shows the standard Dura- Glide with aluminum stiles. I attached product information on both types. Can you please help verify what it is they actually need? Let me know if you have any questions.

Basis of Design and Minneapolis Station Standard is the Stanley Dura Glide 2000.

9. 1.17.22 1.27.22 The same sliding door 2P-150 shows a B fire rating on the schedule. Neither of the attached door types have a fire rating. Are we able to install a non-rated door at this location?

Door must be NFPA 101 compliant. Basis of Design and Minneapolis Station Standard is the Stanley Dura Glide 2000.

10. 1.17.22 1.27.22 Please confirm that that Superintendent may also fulfill the role of SSHO.

Yes, per Specification 01 35 26, Section 1.7.C.

11. 1.17.22 1.27.22 In Section 01 45 00 it states, “The CQC System Manger is assigned as CQC System Manager but has duties as project superintendent in addition to quality control.”

Please confirm that it is the VA’s intent to only have 1 field person – that is fulfilling the duties of Superintendent, QC Manager, and SSHO – for a project magnitude and complexity of this size?

No, it is the intent that the CQC System manager is a separate person fulfilling the requirements set forth in Specification 01 45 00.

12. 1.17.22 1.27.22 If the VA does not want 1 field person fulfilling all duties, please confirm the exact field team the VA expects to be on site to ensure general conditions are priced accordingly.

Means and Methods. Specification sections provided outline the requirements put forth by the VA. Bidders shall fulfill these requirements and have reflected within their bid submittal.

DATE

QUESTION

RECEIVED

DATE

QUESTION

ANSWERED

QUESTION GOVERNMENT RESPONSE

13. 1.17.22 1.27.22 Please confirm the VA will hire the third-party commissioning agent?

AE Bancroft provides the commissioning, and the GC will provide commissioning support.

14. 1.17.22 1.27.22 Please confirm that offers are due by 1400 EST on 02- 02-2021.

The proposals are due 02/08/22 at 2:00 PM ET.

15. 1.17.22 1.27.22 Cabinet/casework specification section Refer to Specification Section 06 20 00.

16. 1.17.22 1.27.22 Can we get CAD Files? CAD files are not distributed as part of Bidding.

17. 1.17.22 1.27.22 Is this project going to be tax exempt? This project IS NOT tax exempt.

18. 1.17.22 1.27.22 Executive Order 14042/VHA Supplemental Contract

Requirements for Ensuring Adequate COVID-19 Safety Protocols for Federal Contractors

a. Will the VA COVID-19 screening tool change from what is currently presented today?

Unknown at this point. Follow current requirements. See Attachment 6.

19. 1.17.22 1.27.22 Executive Order 14042/VHA Supplemental Contract Requirements for Ensuring Adequate COVID-19 Safety Protocols for Federal Contractors

a. Are there any fines associated with employees not complying?

No current fines. Follow OSHA guidelines.

20. 1.17.22 1.27.22 Executive Order 14042/VHA Supplemental Contract Requirements for Ensuring Adequate COVID-19 Safety Protocols for Federal Contractors

a. If an employee is spot checked by a COR, and cannot provide a vaccination card or test, will the employee be asked to leave, or can they take a rapid test on site prior to returning to work?

Contractor shall follow current requirements without specific compliance checks from the VA.

See Attachment 6. Follow OSHA guidelines.

DATE

QUESTION

RECEIVED

DATE

QUESTION

ANSWERED

QUESTION GOVERNMENT RESPONSE

21. 1.17.22 1.27.22 Executive Order 14042/VHA Supplemental Contract Requirements for Ensuring Adequate COVID-19 Safety Protocols for Federal Contractors

a. How long will the mandate be in place? Should we assume until the end of this contract?

Follow current requirements. See Attachment 6.

No future planning data is available at this time.

22. 1.17.22 1.27.22 VHA Supplemental Contract Requirements for Ensuring Adequate COVID-19 Safety Protocols for Federal Contractors

a. Do the VHA Supplemental Requirements apply to subcontracts under $250K?

Follow current requirements. See Attachment 6.

23. 1.17.22 1.27.22 52.223-99

a. Does 52.223-99 apply to subcontractors under $250K in contract value?

52.223-99 was not included in this project

24. 1.17.22 1.27.22 VHA Supplemental Contract Requirements for Ensuring Adequate COVID-19 Safety Protocols for Federal Contractors

a. Do the VHA Supplemental Requirements apply to all employees associated with the contract, or only employees traveling to and working at the VHA campus?

See Attachment 6. Applies to staff on site.

25. 1.17.22 1.27.22 52.223-99/EO 14042

a. Please confirm all employees on contracts and subcontracts above $250k are required to be vaccinated, even when not travelling to the VHA campus.

See Attachment 6. Applies to staff on site.

DATE

QUESTION

RECEIVED

DATE

QUESTION

ANSWERED

QUESTION GOVERNMENT RESPONSE

26. 1.17.22 1.27.22 Executive Order 14042/VHA Supplemental Contract Requirements for Ensuring Adequate COVID-19 Safety Protocols for Federal Contractors

a. Is testing required for exempt employees of covered contracts if the employee does not travel to or work at the VHA campus?

See Attachment 6. Applies to staff on site.

27. 1.17.22 1.27.22 Does 52.223-99 apply to subcontractors under the micro purchase threshold?

52.223-99 was not included in this project

28. 1.17.22 1.27.22 Do the VHA Supplemental Contract Requirements for COVID-19 apply to subcontractors under the micro purchase threshold?

Attachment 6 applies to all contractors.

29. 1.17.22 1.27.22 Executive Order 14042/VHA Supplemental Contract Requirements for Ensuring Adequate COVID-19 Safety Protocols for Federal Contractors

a. For subcontractors where 52.223-99 applies, will they need to test exempt employees that do not travel to or work at the VHA Campus?

52.223-99 was not included in this project

30. 1.17.22 1.27.22 VHA Supplemental Contract Requirements

a. The VHA Supplement Requirements requires testing for exempt employees but does not mention testing for employees that have been exposed to COVID 19 positive individuals. Are we to include costs for ancillary testing for unforeseen COVID 19 exposure, and if so what are the protocols?

Follow current CDC guidelines. Provide testing as directed. Costs to be included in the proposal.

31. 1.18.22 1.27.22 What are the protocols for contractor employees that test positive for COVID-19? If asked to leave the site, when can they return?

Follow current CDC guidelines.

DATE

QUESTION

RECEIVED

DATE

QUESTION

ANSWERED

QUESTION GOVERNMENT RESPONSE

32. 1.18.22 1.27.22 Can the project superintendent also be the CQC Systems Manager?

The project superintendent and the SSHO can be the same person, but they cannot fulfill both duties and be the CQC Manager.

33. 1.18.22 1.27.22 if there was going to be any AV upgrades for the project?

Please refer to solicitation drawings.

34. 1.18.22 Revised 02/03/22

What is the government intent for contractors to mobilize construction structural steel into the construction area?

Please refer to drawing 1384-GC402 and 1384- GC401 for material delivery intent for the project.

Entrance to the building is identified at corridor C1-117. Field splices to be provided as needed.

Field splices to be provided as needed based on delivery limitations based on material delivery route. Loading on floors to be limited to 100 PSF and a 2000# load over a 6.25 SF area.

35. 1.18.22 1.27.22 Would the government consider authorizing a 2nd site visit?

Due to COVID concerns, a 2nd site visit will not be granted at this time.

36. 1.18.22 1.27.22 Can Moderco Partitions be approved equal to Modernfold partitions – spec section 102243?

Substitution is acceptable. 02/03/22

37. 2.3.22 2.3.22 PLEASE SEE ATTACHMENT “Structural Questions - Minneapolis EHRM_BAE Response” FOR ADDITIONAL

TECHNICAL QUESTIONS AND ANSWERS

ITEM