618701_18116_Bid Clarification 012622.pdf

PDF 2 MB Posted

Attached to
Y1DA--EHRM Training and Admin Space Support Construction DBB Support Construction Minneapolis VAMC
Solicitation number
36C77622R0019
Issued by

About this file

This document package includes construction drawings and specifications for an infection control plan for renovation work at a Department of Veterans Affairs medical center, along with information on the related federal contract opportunity.

The construction drawings provide details on infection control requirements and protocols for work on the first and second floors, including barrier installation and removal procedures, material handling routes, and notes specifying wall types, ceiling work areas, and other scope items. The federal contract opportunity is a solicitation from the VA Technology Acquisition Center seeking bids for EHRM training and administrative space support construction at the Minneapolis VAMC, with responses due on January 26, 2022. The solicitation number is 36C77622R0019.

The documentation specifies the infection control protocols and barriers required during renovations to VA medical training spaces, as well as providing information on the competitive bidding process for the construction work through the Veterans Affairs solicitation.

View the file

Other files

Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MATERIAL DELIVERY/DEBRIS REMOVAL:

ROUTE FROM CONSTRUCTION

AREA TO SERVICE ELEVATORS

CONSTRUCTION BARRIER: REFER TO KEYNOTES

WALK-OFF MAT

TEMPORARY 1-HR BARRIER IN CORRIDOR: REFER TO

KEYNOTES

AREA OF CEILING WORK

1J-127

1J-127B

1J-127A

1J-128B

1J-128 1J-128A

1J-128C

1J-131

1J-132A

1J-132

1J-132B 1J-132C 1J-134

1J-134A

1J-134A

1J-135B1J-136B

1J-135 1J-136 1H-100

1J-137B

1J-136A

1P-375

1P-374 1P-374A

1P-99

1P-353 1P-3551P-3511P-349

1P-347

1P-345 1P-344

1P-3461P-348

1P-343 1P-3421P-341

1P-275

1P-276 1P-274 1P-2721P-270 1P-2681P-266 1P-264 1P-262 1P-260

1P-273 1P-2711P-269 1P-2671P-265 1P-263

1P-254

1P-251

1P-253

1P-250 1P-249

1P-252 1P-245

1P-247

1P-246

1P-248 1P-243

1P-241

1P-109

1P-107

1P-105

1P-240

1P-242

1P-244

1P-261

1P-242A

1P-340

C1P-93

C1P-88

C1P-91

1P-336 1P-331

1P-3291P-335

1P-334 1P-327

1P-3251P-333

C1P-90

1P-326

1P-328

1P-330

1P-332 1P-324

1P-322

1P-321

1P-320

C1P-94

C1P-103

C1P-100

CP-104

CP-103A

5K-101

CP-105

1P-323

1P-373

1P-372

1P-371

1P-370

1P-369

1P-368

1P-367

1P-366

1P-365

1P-364

1P-363

1P-362

1P-361

1P-360 1P-311 1P-309

1P-312

1P-310

1P-308

1P-314

1P-313

1P-220

1P-225

1P-218

1P-2231P-221

1P-216

1P-210

1P-208

1P-212

C1P-921P-300 C1P-98

1P-213

1P-211

1P-209

1P-204

1P-202

1P-200

C1P-102

1P-2061P-207

1P-1021P-203

1P-201

1P-103

C1P-101

1P-307 1P-305 1P-303 1P-219 1P-217 1P-215 1P-214

C1P-98A 1P-206

C1P-99C1P-97

C1P-95

C1P-86

1M-125

1M-122

1M-121

1M-120A

1M-120 C1-124

1M-117

C1-146C

1M-116A

1M-116 1M-115

5K-101

1M-115A

C1-126

C1-126A

M

-1 B

1M-106A

1M-118A

1M-124E1M-124F1M-124G

1M-123

1M-123A

1M-119

1M-119

1M-118

1M-124

1M-124A 1M-124B

1M-124C 1M-124D

1M-126 1M-127

M

-1

C1-123

C1-120

1M-105A 1M-105

1M-1141M-112

1M-112A 1M-107

C1-127

1Q-1041Q-103 1Q-1011Q-100A 1Q-100 1R-130

1J-156

1N-105

1N-106

1S-11

1N-104

C1-117A

C1-117

C1-117

G

C1-115

F 1S-8

C1-110

C1-110

1N-101

1S-10

C1-118

N

-1

1N-103

C1-111

M

-1 A 1S-7

M-3

1M-010

1M-102 1A-101

M-2

1A-103

C-9

C1-112

C1-125A

1M-103

1M-104

1M-108

1M-109

1M-110

2P-151

C1-148

1R-102

C1-149

2P-151

C1-125

2P-151

C1-196 1A-109

A

C1-199

A

A-105

C1-198

1S-5

1A-107

1A-106 1A-104

1G-112

1G-113

1G-109

1G-109A

C1-102 C1-201A

1G-1101G-1111G-114

1G-115

1G-115-a

1S-4

E

1P-111

1P-110

2P-151

1P-106

1P-104

1P-108

1P-100

1P-101

1G-116

1G-117

1G-121

1G-122 1G-121A

1G-121B

1G-119

1G-117A

1G-118

1G-120

1H-119

1H-120

1H-1021H-101

C1-76C1-75 C1-65

M-9 1M-114A

1Q-108A

C-10

1H-121

C-6

1G-106

1H-123

CP-107

C1-200

C1-109

C1P-109

1G-106A 1G-106B

1G-106C

1G-108

1A-108

1G-107

1G-109B

1A-111A

1A-110

1A-110C

1A-106A

1A-110B

1 2 3 4 5 6 7 8 9 10

1 2 3 4 5 6 7 8 9 10

A

B

C

D

E

F

A

B

C

D

E

F

CONSULTANT ARCHITECT/ENGINEER OF RECORD STAMP Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

Drawing Title

Approved: Project Director

Phase Project Title Project Number

Building Number

Drawing NumberLocation

Issue Date Checked Drawn

VA FORM 08-6231

FULLY SPRINKLERED

Bancroft Project No.

BUILDING 70 KEYPLAN

VA CONTRACT NO.

AREA K

AREAM70-139AREAA70-11770-121AREACAREAL70-13770-119AREAB70-123AREAD70-135AREAK70-127AREAF70-125AREAE70-133AREAJ 70-129AREAG70-131AREAH

AREA L

AREA B

AREA F

AREA J AREA G

AREA H

AREA E

AREA D

AREA C

AREA AAREA M

AREAM70-139AREAA70-11770-121AREACAREAL70-13770-119AREAB70-123AREAD70-135AREAK70-127AREAF70-125AREAE70-133AREAJ70-129AREAG70-131AREAH

N

I hereby certify that this plan, specification, or report was prepared by me or under my direct supervision and that I am a duly Licensed Architect / Professional Engineer under the laws of the state of Minnesota.

Signature: _____________________ Typed or Printed Name: __________ Date: _________________________ License Number: ________________

C U s e rs \l h o ff m a n

\D o c u m e n ts

\6

A rc h (C e n tr a l2 lh o ff m a n N

X Y

V .r v t

/2

/2

:3

:2

P

M

01/26/2022

GENERAL - INFECTION CONTROL PLAN -

FIRST FLOOR

EHRM Training and Admin Space Support

Minneapolis VA Healthcare System

DA LH

618-701

1384-GC401

ISSUE FOR BID

18-11636C26319D0022

N

1/16" = 1'-0"

INFECTION CONTROL PLAN - FIRST FLOOR

1. REFER TO SHEETS 1384-A001 & 1384-A002 FOR GENERAL NOTES AND MOUNTING HEIGHT

INFORMATION.

2. REVIEW THIS DRAWING IN CONJUNCTION WITH CORRESPONDING FIRE PROTECTION, PLUMBING, ELECTRICAL, MECHANICAL AND STRUCTURAL DRWAINGS FOR FULL SCOPE OF WORK.

3. REFER TO SHEETS 1384-A102 & 1384-A501 FOR PARITITION TYPES AND LOCATIONS.

GENERAL SHEET NOTES

KEYNOTES

BEFORE CONSTRUCTION PROJECTS BEGIN:

COMPLETE ALL CRITICAL BARRIERS TO SEAL CONSTRUCTION AREA FROM

NON WORK AREA (SEE WALL CONSTRUCTION TYPES ON GI404) OR

IMPLEMENT CONTROL CUBE METHOD (CART W/PLASTIC COVERING AND

SEALED CONNECTION TO WORK SITE WITH HEPA VACUUM FOR VACUUMING

PRIOR TO EXIT). WHERE THE CONSTRUCTION BOUNDARY UTILIZES EXISTING

WALLS CONTRACTOR TO VERIFY WALL RUNS TO THE UNDERSIDE OF THE

DECK AND ALL PENETRATIONS HAVE BEEN FIRESTOPPED. IF WALL IS

INCOMPLETE CONTRACTOR SHALL CONSTRUCT THE WALL TO THE

UNDERSIDE OF THE DECK USING WALL TYPE K ON 1384-A501.

ALL EXISTING WALLS AT CONSTRUCTION BOUNDARY THAT DO NOT HAVE

GYP. BD. GOING ALL THE WAY UP TO DECK ARE TO HAVE ADDITIONAL GYP.

BD. INSTALLED TO SEAL WALL AT DECK.

SEQUENCE WORK SO THAT SPRINKLER OUTAGES (INCLUDING

INOPERABILITY DUE TO MISSING CEILING SYSTEMS) ARE LIMITED TO 8

HOURS OR LESS PER DAY.

DURING CONSTRUCTION PROJECTS:

A. THE CONTRACTOR SHALL NOT BLOCK OR HINDER THE USE OF THE

BUILDINGS BY PATIENTS, STAFF & VISITORS.

B. ALL MATERIALS AND EQUIPMENT MUST BE PROPERLY STORED IN VA

DESIGNATED AREAS.

C. ALL NEW CONSTRUCTION MATERIALS, TOOLS AND EQUIPMENT

PASSING THROUGH NON-CONSTRUCTION AREAS TO BE COVERED

WITH 4 MIL. POLY SHEETS.

D. ALL DEBRIS AND GARBAGE THAT IS TO BE REMOVED THROUGH THE

NON-CONSTRUCTION AREAS MUST BE CONTAINED IN TIGHTLY

COVERED NONCOMBUSTIBLE CONTAINERS.

E. CONTRACTOR TO SUPPLY SPILL KIT, TO INCLUDE HEPA VAC, MULTI

PURPOSE SPILL CONTROL SORBENTS TO ABSORB NON AGGRESSIVE

LIQUIDS UP TO 30 GALLONS.

F. ALL CONSTRUCTION ENTRANCE POINTS SHALL CONTAIN THE

FOLLOWING (SEE CONSTRUCTION ENTRANCE POINT DETAIL ON

GC501):

F.1. TEMPORARY CONSTRUCTION DOOR. ALL TEMPORARY

CONSTRUCTION DOORS TO BE METAL (PAINTED PER

VA STANDARDS), 1 HR RATED, W/ METAL FRAMES, CLOSERS

AND SEALS.

F.2. PROPER LABEL COMPLYING WITH VA AND OSHA

REQUIREMENTS.

F.3. BEST KEYPAD EZ LOCK.

F.4. 24" X 36" WALK OFF MATTS. CHANGE THEM AS NEEDED.

F.5. HAND SANITIZER.

UPON COMPLETION OF CONSTRUCTION:

G. DO NOT REMOVE CONSTRUCTION BARRIERS FROM WORK AREA UNTIL

WORK IS COMPLETE IN DESIGNATED WORK AREA AND WORK IS

INSPECTED BY VA.

H. REMOVE BARRIER AND ALL ASSOCIATED MATERIALS CAREFULLY TO

MINIMIZE SPREADING OF DIRT AND DEBRIS ASSOCIATED WITH

CONSTRUCTION.

I. VACUUM WORK AREA WITH HEPA FILTERED VACUUMS.

J. WET MOP AREA WITH DISINFECTANT, WATER TO BE CHANGED AFTER

EACH USE.

SEE SHEET 1384-GC501 FOR CLASS IV BARRIER NOTES AND DETAILS

LEGEND

INFECTION CONTROL GENERAL NOTES

1 SUPPLY AND INSTALL WALK OFF MAT(S). SEE DETAILS ON SHEET

1384-GC501

2 CONSTRUCTION MATERIALS DELIVERY AND DEBRIS REMOVAL ROUTE.

3 SUPPLY AND INSTALL 6 MIL HEAVY DUTY, REINFORCED,

FIRE-RETARDANT, POLY SHEETING. PLASTIC SHEET SHALL BE FULLY

SEALED AT PERIMETER.

4 FREIGHT ELEVATOR ACCESS AT ELEVATOR G. DELIVERIES TO BE

MADE AFTER HOURS. CONTRACTOR TO PROVIDE MINIMUM 72-HR

NOTICE FOR WHEN ELEVATOR IS TO BE UTILIZED.

N

1/8" = 1'-0" 1A

INFECTION CONTROL PLAN - INTERSTITIAL SPACE ACCESS - TYPICAL

Revisions: Date:

95% Construction Documents Submittal 08/19/2021

ISSUE FOR BID 09/07/2021

Bidding Clarification 01/26/2022

MATERIAL DELIVERY/DEBRIS REMOVAL:

ROUTE FROM CONSTRUCTION

AREA TO SERVICE ELEVATORS

CONSTRUCTION BARRIER: REFER TO KEYNOTES

WALK-OFF MAT

TEMPORARY 1-HR BARRIER IN CORRIDOR: REFER TO

KEYNOTES

AREA OF CEILING WORK

3' - 8"

3' - 8 1/2"

5 11

10 10

44" MIN.

C2-111

2P-123A

2G-1212G-1202G-1172G-116

2G-122 2G-119 2G-118 2G-115 2G-114 2G-113

2G-1302G-1292G-1272G-1262G-1252G-124

2G-151

2G-150

2G-149

2G-148

2G-1452G-1442G-1432G-1412G-1402G-139

2G-142

2G-136

2G-128

2G-133

2G-135

2G-147

2G-146 2H-116

C2-115

C2-116A

C2-116

C2-118

C2-117

C2-119

2J-131 2J-121 2J-120 2J-119 2J-112 2J-111 2J-110 2J-109 2J-102 2J-101

2J-100

C2-80

2J-103

2J-104

2J-105

C2-81

2J-108

2J-107

2J-1062J-115

2J-114

2J-1132J-118

2J-117

2J-1162J-126

2J-125

2J-124

2J-131B 2J-131A2J-122

2J-123

2J-130

2J-130A

2J-129 2J-128 2J-127

C2-83 C2-82

C2-79

C2-95 C2-99 C2-100 C2-101 2P-111

C2-98C2-94

C2-93

C2-92

C2-91

C2-90

C2-89

C2-96

C2-87

2P-122

Room

C2-88

Room

2P-123B

2P-123 2P-122A

2P-123C

Room

2P-116

2P-112

2P-115

2P-114

Room

2P-119 2P-119A 2P-120 2P-120A2P-121 2P-124

C2-77B C2-77 C2-75D

C2-77A

C2-75

2J-155 2J-1452J-1472J-149

2J-150 2J-1512J-1412J-137

2J-139

C2-75A C2-75B

2J-133

2J-134

2J-142

C-8

C2-75C

2J-136 2J-138 2J-140A

2J-140 2J-143

2J-1432J-144A

2J-143B2J-144B

2J-144 2J-146

2J-146A

2J-148 2J-152

2J-152A

2J-153

2H-101

2S-6

E

C2-61

2H-102

2H-115

C-6

2H-114

2C-58

C2-60

2H-110

M-5 2H-113

2H-103

2H-103A

2H-108

C2-71BC2-71C

C2-71

C2-74

2H-104 2H-105

2H-106

2J-154A2J-154

2H-106A

2H-109

C2-72

C2-73

2K-137A 2H-107 2K-101

2H-111A

2H-111

2K-102A 2H-111C

2H-111B

2H-112

2K-137

2K-102

C2-57

C2-85

C2-86

2J-132C 2J-132D

2J-132

2J-132B

2J-132A

C2-84

2J-135

C2-102A

C2-102

2P-101

C2-104 2P-110

2P-1082P-109

C2-105

2P-106

2P-1052P-106A 2P-107

2P-106B

F 2S-8 C2-107

2P-104

2P-1032P-102 2M-113

C2-102B

2M-111

2M-112 2M-110

2M-107

2M-108

2M-109

2M-106

2M-105

2M-104

2M-103 2M-102C2-106

2M-114 2S-7 2M-115

M-3

2M-101 15

C-10

2A-101

2A-102

C9

M2

2A-103

C2-110 C2-112

2C-113

C2-114

2G-131

2G-112

2C-120 2C-120

2C-122 2G-108

2G-1102G-106

2G-105

2C-121

2G-102

2G-105

2A-104

2G-101

2G-103

2G-104

C2-123

C2-125

C2-124

2B-105

C2-60

C2-126A

2A-107 2A-106

2S-5

2B-105B

2B-105C

2A-105

A

C2-127

A

2A-108C2-153

B

2R-1002R-102

2R-103A2R-103B

2R-103

2R-104A

2R-108

2R-109 2T-101M4

2R-101

2R-163

2R-149A

2R-161

2R-162

2R-1132R-114

C2-158

2R-160

C2-178

C2-180

2Q-133

2Q-134

M42Q-136

2Q-135

2Q-135A

C2-193

2Q-105A2Q-105

2Q-104

2Q-101

2Q-106

C2-108

C2-109

C2-194

2N-101G

C2-196

2Q-1032Q-102

2Q-108

2Q-107A

2S-10

C2-192

C2-189

C2-155

C2-157

1 HOUR FIRE & SMOKE SEPARATION

NON-RATED SMOKE PARTITION

2 HOUR FIRE & SMOKE SEPARATION

1 2 3 4 5 6 7 8 9 10

1 2 3 4 5 6 7 8 9 10

A

B

C

D

E

F

A

B

C

D

E

F

CONSULTANT ARCHITECT/ENGINEER OF RECORD STAMP Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

Drawing Title

Approved: Project Director

Phase Project Title Project Number

Building Number

Drawing NumberLocation

Issue Date Checked Drawn

VA FORM 08-6231

FULLY SPRINKLERED

Bancroft Project No.

BUILDING 70 KEYPLAN

VA CONTRACT NO.

AREA K

AREAM70-139AREAA70-11770-121AREACAREAL70-13770-119AREAB70-123AREAD70-135AREAK70-127AREAF70-125AREAE70-133AREAJ 70-129AREAG70-131AREAH

AREA L

AREA B

AREA F

AREA J AREA G

AREA H

AREA E

AREA D

AREA C

AREA AAREA M

AREAM70-139AREAA70-11770-121AREACAREAL70-13770-119AREAB70-123AREAD70-135AREAK70-127AREAF70-125AREAE70-133AREAJ70-129AREAG70-131AREAH

N

I hereby certify that this plan, specification, or report was prepared by me or under my direct supervision and that I am a duly Licensed Architect / Professional Engineer under the laws of the state of Minnesota.

Signature: _____________________ Typed or Printed Name: __________ Date: _________________________ License Number: ________________

C U s e rs \l h o ff m a n

\D o c u m e n ts

\6

A rc h (C e n tr a l2 lh o ff m a n N

X Y

V .r v t

/2

/2

:3

:3

P

M

01/26/2022

GENERAL - INFECTION CONTROL PLAN -

SECOND FLOOR

EHRM Training and Admin Space Support

Minneapolis VA Healthcare System

DA LH

618-701

1384-GC402

ISSUE FOR BID

18-11636C26319D0022

1. REFER TO SHEETS 1384-A001 & 1384-A002 FOR GENERAL NOTES AND MOUNTING HEIGHT

INFORMATION.

2. REVIEW THIS DRAWING IN CONJUNCTION WITH CORRESPONDING FIRE PROTECTION, PLUMBING, ELECTRICAL, MECHANICAL AND STRUCTURAL DRWAINGS FOR FULL SCOPE OF WORK.

3. REFER TO SHEETS 1384-A102 & 1384-A501 FOR PARITITION TYPES AND LOCATIONS.

GENERAL SHEET NOTES

KEYNOTES

N

1/16" = 1'-0"

INFECTION CONTROL PLAN - SECOND FLOOR

BEFORE CONSTRUCTION PROJECTS BEGIN:

COMPLETE ALL CRITICAL BARRIERS TO SEAL CONSTRUCTION AREA FROM

NON WORK AREA (SEE WALL CONSTRUCTION TYPES ON GI404) OR

IMPLEMENT CONTROL CUBE METHOD (CART W/PLASTIC COVERING AND

SEALED CONNECTION TO WORK SITE WITH HEPA VACUUM FOR VACUUMING

PRIOR TO EXIT). WHERE THE CONSTRUCTION BOUNDARY UTILIZES EXISTING

WALLS CONTRACTOR TO VERIFY WALL RUNS TO THE UNDERSIDE OF THE

DECK AND ALL PENETRATIONS HAVE BEEN FIRESTOPPED. IF WALL IS

INCOMPLETE CONTRACTOR SHALL CONSTRUCT THE WALL TO THE

UNDERSIDE OF THE DECK USING WALL TYPE K ON A501.

ALL EXISTING WALLS AT CONSTRUCTION BOUNDARY THAT DO NOT HAVE

GYP. BD. GOING ALL THE WAY UP TO DECK ARE TO HAVE ADDITIONAL GYP.

BD. INSTALLED TO SEAL WALL AT DECK.

SEQUENCE WORK SO THAT SPRINKLER OUTAGES (INCLUDING

INOPERABILITY DUE TO MISSING CEILING SYSTEMS) ARE LIMITED TO 8

HOURS OR LESS PER DAY.

DURING CONSTRUCTION PROJECTS:

A. THE CONTRACTOR SHALL NOT BLOCK OR HINDER THE USE OF THE

BUILDINGS BY PATIENTS, STAFF & VISITORS.

B. ALL MATERIALS AND EQUIPMENT MUST BE PROPERLY STORED IN VA

DESIGNATED AREAS.

C. ALL NEW CONSTRUCTION MATERIALS, TOOLS AND EQUIPMENT

PASSING THROUGH NON-CONSTRUCTION AREAS TO BE COVERED

WITH 4 MIL. POLY SHEETS.

D. ALL DEBRIS AND GARBAGE THAT IS TO BE REMOVED THROUGH THE

NON-CONSTRUCTION AREAS MUST BE CONTAINED IN TIGHTLY

COVERED NONCOMBUSTIBLE CONTAINERS.

E. CONTRACTOR TO SUPPLY SPILL KIT, TO INCLUDE HEPA VAC, MULTI

PURPOSE SPILL CONTROL SORBENTS TO ABSORB NON AGGRESSIVE

LIQUIDS UP TO 30 GALLONS.

F. ALL CONSTRUCTION ENTRANCE POINTS SHALL CONTAIN THE

FOLLOWING (SEE CONSTRUCTION ENTRANCE POINT DETAIL ON

1384-GC501):

F.1. TEMPORARY CONSTRUCTION DOOR. ALL TEMPORARY

CONSTRUCTION DOORS TO BE METAL (PAINTED PER

VA STANDARDS), 1 HR RATED, W/ METAL FRAMES, CLOSERS

AND SEALS.

F.2. PROPER LABEL COMPLYING WITH VA AND OSHA

REQUIREMENTS.

F.3. LOCKSET.

F.4. 24" X 36" WALK OFF MATTS. CHANGE THEM AS NEEDED.

F.5. HAND SANITIZER.

UPON COMPLETION OF CONSTRUCTION:

G. DO NOT REMOVE CONSTRUCTION BARRIERS FROM WORK AREA UNTIL

WORK IS COMPLETE IN DESIGNATED WORK AREA AND WORK IS

INSPECTED BY VA.

H. REMOVE BARRIER AND ALL ASSOCIATED MATERIALS CAREFULLY TO

MINIMIZE SPREADING OF DIRT AND DEBRIS ASSOCIATED WITH

CONSTRUCTION.

I. VACUUM WORK AREA WITH HEPA FILTERED VACUUMS.

J. WET MOP AREA WITH DISINFECTANT, WATER TO BE CHANGED AFTER

EACH USE.

SEE SHEET 1384-GC501 FOR CLASS IV BARRIER NOTES AND DETAILS

LEGEND

INFECTION CONTROL GENERAL NOTES

1 CONSTRUCTION WALL FOR ANTE ROOM TO REMAIN AS PART OF NEW

CONSTRUCTION. TEMPORARY DOOR TO BE REMOVED AT COMPLETION

OF WORK. NEW DOOR TO BE INSTALLED PRIOR TO REMOVAL OF ALL

TEMPORARY CONSTRUCTION WALLS. CONTRACTOR TO REPAIR

DAMAGE DONE DURING CONSTRUCTION TO ALL WALLS INDICATED AS

PERMANENT PRIOR TO APPLICATIONS OF FINISHES.

2 SEAL OFF DOOR DURING CONSTRUCTION. SUPPLY AND INSTALL 6 MIL

HEAVY DUTY, REINFORCED, FIRE-RETARDANT, POLY SHEETING.

PLASTIC SHEET SHALL BE FULLY SEALED AT PERIMETER.

3 COVER ALL WINDOWS WITH PAPER AND PROTECT GLASS DURING

CONSTRUCTION.

4 CONSTRUCTION MATERIALS DELIVERY AND DEBRIS REMOVAL ROUTE.

5 SUPPLY AND INSTALL WALK OFF MAT(S). SEE DETAILS ON SHEET

1384-GC501

6 TEMPORARY 45MIN DOOR AND ASSOCIATED HARDWARE

7 CORRIDOR CEILING WORK TO BE DONE AFTER HOURS WITH MOBILE

ICRA CART. CONTRACTOR TO PROVIDE VA WITH 24 HOUR NOTICE

PRIOR TO THE START OF ANY CORRIDOR WORK. TEMPORARY

SUSPENDED PLASTIC BARRIER TO BE ERECTED AROUND AREA OF

CEILING WORK TO BE COMPLETED WITHIN ONE SHIFT AND REMOVED

AT THE END OF SHIFT.

8 FREIGHT ELEVATOR ACCESS AT ELEVATOR G. DELIVERIES TO BE

MADE AFTER HOURS. CONTRACTOR TO PROVIDE MINIMUM 72-HR

NOTICE FOR WHEN ELEVATOR IS TO BE UTILIZED.

9 TEMPORARY CONSTRUCTION BARRIER WALL TYPE A ON SHEET

1384-GC501.

10 TEMPORARY 1-HR BARRIER. TYPE A WALL SEE DETAIL 5/1384-GC501.

11 NEW WALL CONSTRUCTION IDENTIFIED ON THE CONSTRUCTION

DRAWINGS. WALL TYPE IDENTIFIED ON SHEET 1384-A102 AND WALL

TYPE CONSTRUCTION LOCATED ON SHEET 1384-A501.

12 ANY ELECTRICAL FIXTURES AND DEVICES THAT ARE NOT IDENTIFIED

ON THESE DRAWINGS IN THE AREAS OF CEILING WORK ARE TO BE

CAREFULLY REMOVED FROM THE CEILING, PROTECTED,

TEMPORARILY HUNG AND THEN REATTACHED IN THE SAME

LOCATIONS AS THEY WERE FOUND PRIOR TO DEMOLITION.

13 REMOVE AND STORE CEILING TILES IN THIS AREA AS REQUIRED FOR

THE INSTALLATION OF ALL REQUIRED CONDUIT AND ELECTRICAL

EQUIPMENT PER ELECTRICAL DRAWINGS. WHEN ELECTRICAL WORK IS

COMPLETED CONTRACTOR SHALL REINSTALL TILES AND GRID.

CONTRACTOR TO REPLACE ANY DAMAGED TILES AND GRIDS TO

MATCH EXISTING. REFER TO ELECTRICAL SHEETS FOR ADDITIONAL

INFORMATION.

14 WORK AREA TO BE MOPPED, CLEANED AND AVAILABLE TO THE VA

HALD HOUR PRIOR TO THE START OF NORMAL WORKING HOURS.

15 SUPPLY AND INSTALL 6 MIL HEAVY DUTY, REINFORCED,

FIRE-RETARDANT, POLY SHEETING. PLASTIC SHEET SHALL BE FULLY

SEALED AT PERIMETER.

Revisions: Date:

65% Design Development Submittal 07/15/2021

95% Construction Documents Submittal 08/19/2021

ISSUE FOR BID 09/07/2021

Bidding Clarification 01/26/2022

Sheets
1384-GC401 - GENERAL - INFECTION CONTROL PLAN - FIRST FLOOR
1384-GC402 - GENERAL - INFECTION CONTROL PLAN - SECOND FLOOR

File details come from the government source that posted it. Updated .