Technical Question Tracking Sheet - Fresno Mech Syst - 5-2-22.pdf

PDF 289 KB Posted

Attached to
Y1DA--570-19-307 Replace Mechanical Systems Building 1 Construction - Fresno VAMC
Solicitation number
36C77622B0022
Issued by

About this file

This document contains a technical question tracking sheet and description for a federal construction contract to replace mechanical systems at the Fresno Veterans Affairs Medical Center in California. The contractor will provide all labor, equipment, and materials to complete the replacement of mechanical systems in Building 1, including ductwork, according to attached specifications and drawings. Key contact dates include questions received through April 2022 and answered on May 2, 2022. The contract will require work during daytime hours with potential HVAC and electrical outages scheduled early in the morning or on weekends. The VA will provide a reasonable laydown area and parking, as well as facility access. The project is solicited under solicitation number 36C77622B0022 for the Department of Veterans Affairs Technology Acquisition Center Austin.

View the file

Other files

File Type Posted
Pipe PDF Drawings Bldg 1.zip ZIP file
100 Percent PDF Drawings Bldg 1.zip ZIP file
VA Fresno ACM Survey - Asbestos Study Report Only.pdf PDF
Bldg 1 - Asbestos Bulk - Pt 1.pdf PDF
Bldg 1 - Asbestos Bulk - Pt 2.pdf PDF
Supporting Asbestos Bulk - Bldg 1 - Pt 2..zip ZIP file
HA PDF Drawings Bldg 1.zip ZIP file
36C77622B0022 0002.pdf PDF
Survey Documents.zip ZIP file
Asbestos Table - Final.xlsx XLSX spreadsheet
Supporting Asbestos Bulk - Bldg 1 - Pt 1..zip ZIP file
36C77622B0022 Amendment 0001.pdf PDF
Site Visit Attendance Sheet - IFB - Fresno.pdf PDF
Attachment 11 - DBA Rates - Fresno County - 4-1-22.pdf PDF
Attachment 5 - Plumbing Drawings.pdf PDF
Campus Map (Highlighted Parking).pdf PDF
Attachment 4 - Mechanical Drawings (Part II).zip ZIP file
Attachment 6 - Structural Drawings.pdf PDF
Attachment 10 - Contractor Safety - Environmental Form.docx DOCX document
Attachment 8 - COVID-19 Safety Protocols 12-14-21.pdf PDF
Attachment 3 - Architectural Drawings.pdf PDF
Attachment 4 - Mechanical Drawings (Part I).zip ZIP file
IFB Solicitation 36C77622B0022.pdf PDF
Attachment 2 - Cover Sheet.pdf PDF
Attachment 1 - 570-19-307 Issued for Construction - Specifications.pdf PDF
Attachment 9 - Limitations on Subcontracting - Construction.docx DOCX document
Attachment 7 - Electrical Plans.pdf PDF
Attachment 11 - DBA Rates - Fresno County - 3-25-22.pdf PDF
Site Visit Instructions - Fresno.pdf PDF
Show all 29

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

36C77622B0022 Fresno Mechanical Systems Construction: Technical Questions and VA Response Tracking Sheet

ITEM

NO.

DATE

QUESTION

RECEIVED

DATE

QUESTION

ANSWERED

QUESTION GOVERNMENT RESPONSE

1. 4-18-22 5-2-2022 Are their environmental hazards known to the government that need abated as part of this project?

If so, what are they?

As you are aware, this is an aging facility.

Constructed in the 1940’s. The facility had a comprehensive Asbestos study conducted in

2012. The intent would be if the contractor encounters potential environmental hazards such as Asbestos, lead etc. Contractor shall notify COR. COR will immediately have area(s) surveyed and if hazard material is found, VA will take care of abatement concerns. Also, all planed demolition must adhere to the local air board. Our jurisdiction is served by San Joaquin Valley Air

Pollution Control District. (BDM)

See Asbestos Attachments in Amendment 0002 for Bldg 1.

2. 4-18-22 5-2-2022 Please provide the project specific Environmental

Survey

Please see attached in Amendment 002 the facility’s most recent Asbestos Report Bldg

1. (BDM)

3. 4-18-22 5-2-2022 What are the live loads and dead load capacities of the lower roof areas?

This information is not required for Building 1 work and would not impact pricing of bids.

In regard to the Pharmacy, it will be a 1:1 swap and not relevant to bids. (BDM)

NO.

DATE

QUESTION

RECEIVED

DATE

QUESTION

ANSWERED

QUESTION GOVERNMENT RESPONSE

4. 4-18-22 5-2-2022 Please confirm the times HVAC/Electrical change overs and outages can occur?

Most HVAC (Mechanical) outages occur based on either the cooling demand or heating demand of the spaces being impacted.

Temporary HVAC outages in the summer are normally conducted during the early morning hours (i.e., 0001-0600). Planned Electrical outages should be accompanied with temporary generators/transformers and are preferred on the weekends. (BDM)

5. 4-18-22 5-2-2022 Please confirm work hours 0600 – 1700 (BDM)

6. 4-18-22 5-2-2022 Will a reasonable contractor lay down yard be provided?

Lay down area space is very limited here at the facility. However, every effort will be made to provide reasonable Lay Down for this project. Winning contractor should immediately start Laydown Yard conversation with VA’s COR & CO. (BDM)

7. 4-18-22 5-2-2022 Please confirm the VA will provide the contractor a reasonable number of keys such that the contractor and their crews can access the work site

Work should predominately occur during hospital working hours. Contractor will have reasonable access to any area needed to successfully complete the contract. (BDM)

DATE

QUESTION

RECEIVED

DATE

QUESTION

ANSWERED

QUESTION GOVERNMENT RESPONSE

8. 4-18-22 5-2-2022 Where will the contractor’s lay down yard be located?

Actual Laydown Yard is TBD. However, the likely area will be at Parking Lot “C.”

Currently we have several Contractors from various project utilizing some of Parking Lot

“C.” Winning Contractor should have some idea as to required square footage and VA can coordinate from that point moving forward.

(BDM)

9. 4-18-22 5-2-2022 Please confirm the contractor will be provided parking on-site

Parking is at a premium. However, the winning Contractor will have access to On-site Parking in their Laydown Area. (BDM)

10. 4-19-22 5-2-2022 Does the VA have an Environmental Survey for lead paint and asbestos, from the rooms for AHU 9

& 10?

Particularly for lead in the paint since the plans are calling for epoxy on walls and ceilings.

The existing paint will need to be disturbed /scuffed for epoxy paint adhesion

Survey was conducted in 2012. Please see amendment 002 Bldg 1 attachments. Please refer to Question/Item No.1 above.

Potential “Hot” area shall be surveyed prior to the commencement of demo/disturbances, SJVAPCD, San Joaquin Valley Air Pollution

Control District. (BDM)

DATE

QUESTION

RECEIVED

DATE

QUESTION

ANSWERED

QUESTION GOVERNMENT RESPONSE

11. 4-20-22 5-2-2022 Plan page 32-M-131.1 shows an Existing rental chiller, existing flex ducts, existing temporary air handler, temporary chiller and temporary water hoses.

Keynote 9 shows existing ductwork.

None of the existing conditions noted on the plans is currently in place.

Is this equipment to be installed by others prior to this contract?

Does this contract start at Keynote 3 on plan page

32-M-131.1?

Yes, all the existing equipment etc. will be on station prior to the commencement of the winning contractor’s work.

Yes, Keynote #3 signifies the point of connection to the (2) existing 24x48 duct.

Again, the VA is working on several projects concurrently and the existing duct will be a relic from our Sub-basement AHU replacement.

File details come from the government source that posted it. Updated .