This file is a Solicitation Questions and Answers document for a federal construction project at the San Francisco Veterans Affairs Medical Center. The document contains 50 questions and official government responses dated between August 3-10, 2026, addressing technical specifications, scheduling, work procedures, and compliance requirements for a roof replacement and building exterior improvement project (Project No. 438-22-600).

The project scope includes replacing roofing systems across multiple buildings, with thermoplastic polyolefin (TPO) specified as the preferred 60-mil flat roofing material, along with standing seam and copper lock seam metal roofs on designated buildings. The estimated award date has been clarified as September 30, 2026, with a 700-calendar-day performance period following Notice to Proceed. Key technical requirements include: removing and replacing pyrobar and insulation systems per drawings, reinstalling and recalibrating satellite dishes, re-certifying lightning protection systems, coordinating mechanical equipment outages with advance notification (2 weeks for small units, 4 weeks for large equipment serving sensitive inpatient areas), and complying with infection control risk assessment protocols. Past performance submissions will be evaluated based on project manager, site supervisor, safety manager, and quality manager experience, with contractors required to demonstrate a minimum of three to five completed projects totaling $10 million in total contract value over the past five years. Work hours are restricted to 8:00 AM to 4:30 PM Monday through Friday, with weekend and holiday work requiring Contracting Officer Representative approval. The bid due date was extended to August 28, 2026, and the NAICS code is 236220 (General Construction), requiring submission of a Certificate of Compliance for Services and Construction with all proposals. The project is a fixed-price contract with no allowances for temporary HVAC or heating/cooling systems.

View the file

Other files

File Type Posted
S06_Attachment 0_09113.01 - Addenda.pdf PDF
S06_36C26326R0027 0005_08.19.2026.docx DOCX document
36C26326R0027 0004.pdf PDF
36C26326R0027 0003.docx DOCX document
S06_Site Visit Sign in sheet_.pdf PDF
36C26326R0027 0002.docx DOCX document
36C26326R0027 0001.docx DOCX document
S02_WDOL_7 Pages.pdf PDF
S02_VA6500 Appendix C 1 - 1 page.pdf PDF
S02 TMS 20939 VA Privacy Training - 3 Pages.pdf PDF
S02_Drawings_133 Pages.pdf PDF
S02_Construction Documents_596 Pages.pdf PDF
36C26326R0027.docx DOCX document
S02_SOW_05.29.26.docx DOCX document
Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

SFVAHCS Project No. 438-22-600-SFVAHCS Solicitation Questions
Item NumberPlans & Specs LocationDateSolicitation QuestionsDateVA/AE Response
1General8/3/26Will you accept past performance submissions that key individuals on the project worked on vs only the company / offeror as the past performance entity?8/4/26Past performance submissions will only be evealuated for the following roles: Project Manager, Site Supervisor, Safety Manager, and Quality Manager. Relevant listing of experience may be from previous projects worked on.
2General8/3/26Will you accept a combination of contracts at a single site as past performance to meet the $10M TCV?8/4/26A minimum of three (3) and a maximum of five (5) projects completed in the past 5 years can be used to meet the $10M TCV. The contracts may come from a single site or multiple sites.
3General8/3/26Amendment 1, Factor 1, states: “The period of performance for this project is 700 calendar days after the Notice to Proceed. For scheduling purposes, assume an estimated award date of 28 May 2026.” Would you please clarify the new estimated award date for this?8/4/26The new estimated award date for this project is September 30, 2026.
4General8/3/26Would you provide details about the underside of the roof assembly for each building detailed in the scope of work? Ie, any known obstacles or coordination items not shown on drawings, photos or visible during the site visit.8/4/26Known work that is required on the underside of each roof is indicated in the drawings.
504 01 008/3/26Is tuckpointing required as part of the scope of work?8/4/26Tuckpointing and replacement is indicated in the drawings.
607 54 238/3/26Will alternate single-ply materials that meet or exceed a 60 Mil reinforced roofing material be accepted?8/4/26Thermoplastic Polyolefin Roofing (TPO) is the preferred material for this project.
7Sheet 38.AE1218/3/26Bldg. 38 currently shows 1/8” per 1 foot specified for over half the roof. Would you accept a ¼” per 1 foot drop on all low slope roofs, which is consistent with International Building Code (IBC) Chapter 15 (1/4:12, or a 2% slope) for standard membrane and built-up roof systems?8/4/26NO – existing roof includes sloped structure – provide sloped insulation only as indicated in drawings. (slope of existing structure is indicated on sheet 38.AE121)
8General8/3/26When moving the satellite dishes and reinstalling them in specified locations, who is responsible for calibrations?8/4/26Contractor is responsible for calbrations of satellite dishes upon reinstallation.
9General8/3/26Are there existing core cuts for the flat roofs? If so, do we have access to the cores of the existing roofs to be replaced?8/4/26There are no existing core cuts for this project.
108/3/26What is the required average/minimum R value of the tapered iso?8/4/26Insulation thickness and slope is to be provided as indicated in drawings.
11General8/3/26Does the Government want the ballast from the roof?8/4/26No, the Government does not want ballast from the roof.
12General8/3/26Is there an infrared scan of the facilities that you would be willing to share?8/4/26No, there is not an infrared scan of the facilities available.
13General8/3/26Coping stone is shown to be removed and reinstalled. Due to the j-hook these are installed with, they often break during removal. Would the government like Contractors to carry an allowance or assumption for replacement of broken coping stone, or will this be treated as a change to the contract if/when required.8/4/26This is a matter of means & methods of the contractor. The Government will not be responsible for the cost to replace broken coping stone.
14General8/3/26Is there a staging area / access plan? Conversely, are there any areas that definitely cannot be used for staging/access?8/4/26Staging areas for the project will be avialable for a limited amount of time, agreed to by the COR, on a case-by-case basis. The area available will be dependent on the area of the campus the contractor is working in. There is no single long-term designated staging space for theproject.
15Sheet G-0018/6/26The drawings indicate removing pyrobar, installing 1.5" metal decking, but we couldn't find any specifics regarding the decking or plans for a nailing surface over it. We reviewed the specifications from division 5,6,7 and couldn't come up with an answer. I must be missing it somewhere.8/6/26Please reference roof type S2 on sheet G-001. Please also reference specification 07 22 00 - 2.4.D.
1607 54 238/10/26Is there a specified manufacturer the VA wishes to use to provide the 60mil TPO flat roofing?8/10/26No – There is no sole source specified material or manufacturer. Any product/manufacturer that meets 07 54 23 and other specification and bidding requirements is acceptable.
1701 00 008/10/26Does all material for the project need to be stored in indoor units such as quadcons?8/10/26Storage containers for all materials is not a requirement of 01 00 00. Storage and protection of materials is the responsibility (means and methods) of the contractor
18General8/10/26What are the specified working hours on this project?8/10/26Working hours are from 8:00am to 4:30pm, Monday through Friday. Working outside of these hours may be allowed by permission of the COR.
19General8/10/26Is weekend and holiday work allowed?8/10/26Working hours are from 8:00am to 4:30pm, Monday through Friday. Work shall not take place on Federal holidays or weekends without prior approval from the COR.
20General8/10/26What are the quiet hours for the VA where work cannot be performed?8/10/26Working hours are from 8:00am to 4:30pm, Monday through Friday. Working outside of these hours may be allowed by permission of the COR.
21General8/10/26Does the VA have a specified access location for a crane to lift roofing materials onto the roof?8/10/26Construction work areas (including locations for cranes) and storage areas are to be coordinated with and determined by the COR per 01 00 00.
228/10/26Per the drawings, is there no flat layer of insulation to be added to roof 5A, just one layer of tapered insulation?8/10/26The roof on 5A is above an unconditioned space below and insulation is only required to achieve the required drainage slope.
23Addendum 018/10/26Per the drawings, building 52 is just showing the new roof to be comprised of 60mil TPO fully adhered directly to the existing wood deck. I believe this system applied the way it is designed in the drawings will not offer a warranty, can the VA advise on this area?8/10/26The existing roof of building 52 is currently EPDM adhered directly to 7/16 OSB wood deck. A cover board has been added to this roof system in Addendum 01 as the OSB will likely have damage after removal of the EPDM.
24Sheet G-0018/10/26How would the VA like the GC to coordinate which buildings will be under construction in the phasing plan?8/10/26Phasing schedule is noted on sheet G-001. Reference specification section 01 00 00 – 1.6.H for other coordination requirements.
25Sheet 05.AE5008/10/26On buildings 5H, 5G, 5E, and 5F the current TPO membrane is installed under the current side ACM metal wall panels. How does the VA want us to address the replacement of these membrane areas? Are we to remove the current metal flashing at the bottom of the ACM panels to reach the TPO membrane?8/10/26Wall tie-in and flashing details for each roof area are in 05.AE500 series detail drawings.
2626 41 008/10/26With the installation of the new roof, does the VA want the current lightning protection system to be re-certified with re-installation?8/10/26Yes - Certification that lightning protection has been inspected by a UL representative and has been approved by UL required.
2701 00 008/10/26For the raising of mechanical equipment, how does the VA wish for the GC to coordinate the temporary shutting down of said units?8/10/26Submit a formal outage request form showing the system/equipment and areas affected to the VA COR to give them enough advance notice to coordinate with facilities and infection control risk assessment (where applicable). Also reference specification section 01 00 00.
2801 00 008/10/26What is the lead time that the GC needs to give to let the VA know that equipment needs to be temporarily shut down for movement?8/10/26For smaller fans and condensing units serving outpatient areas, a two(2) week advance notification should be adequate. But for larger equipment that requires crane assistance, or for equipment serving sensitive inpatient services, there should be at least a four(4) week advance notification per key note ‘I’ shown on every MEP drawing that reads as follows, “CONTRACTOR TO PROVIDE CRANE RIGGING/PICK PLANS AT LEAST FOUR(4) WEEKS PRIOR TO SCHEDULED DATE. SUBMIT PLANS TO VA COR TO DISTRIBUTE TO APPROPRIATE SAFETY OFFICERS FOR DISRUPTION PLANNING. ALL DATES ARE TENTATIVE UNTIL APPROVED.” Also reference specification section 01 00 00.
29Sheet G-0018/10/26How does the VA wish for the GC to coordinate phasing operations for construction?8/10/26Phasing schedule is noted on sheet G-001. Reference specification section 01 00 00 – 1.6.H for other coordination requirements.
30Sheet G-0018/10/26Is the standing seam metal roof on building 11 to be replaced with a copper metal roof, or another metal specification?8/10/26Metal roof types M1( Buildings 16 and 17) are copper lock seam as noted on sheet G-001.

Metal roof types M2 (Building 17) are standing seam metal roof as noted on sheet G-001 and specified in section 07 41 13.16.

Metal roof types M2 (Building 11) are standing seam metal roof as noted on sheet G-001 and specified in section 07 41 13.16.

3101 35 268/10/26Can crane operations take place during the day for the project? I.e. Lifting materials to the roof and removing trash?8/10/26Crane operation days/times fall under normal dates/times for construction activities as specified in 01 00 00.
3201 35 268/10/26What special requirements does the VA have for conducting crane operations?8/10/26Crane operation days/times fall under normal dates/times for construction activities as specified in 01 00 00.
3301 35 268/10/26What must the crane operators and company provide before operations commence?8/10/26Construction safety and security requirements are addressed in specification section 01 00 00
3401 35 268/10/26Does the VA require any class-style training for workers before work commences on the project?8/10/26Construction safety and security requirements are addressed in specification section 01 00 00
35General8/10/26Does the government intend to use automation for any of the scoring and/or evaluation of the submitted proposals? If so, what type of automation will be used, for which sections, and what are the scoring/evaluation parameters?8/10/26No, the government does not intend to use automation for any of the scoring/evaluation of the submitted proposals.
36General8/10/26Does the VA have any requirements for temporary air control systems to be utilized while current HVAC units need to be disconnected and connected?8/10/26Filtration and airflow/pressurization requirements would be dictated by ICRA report based on area(s) served.
37General8/10/26Is a temporary air control system required during the project?8/10/26If area served is an outpatient space and outage duration is less than 8 hours on a moderate weather day, it could potentially be omitted. All other instances will require temporary ventilation
3801 00 008/10/26What type of notice must be given before disconnecting any current HVAC units?8/10/26For smaller fans and condensing units serving outpatient areas, a two(2) week advance notification should be adequate. But for larger equipment that requires crane assistance, or for equipment serving sensitive inpatient services, there should be at least a four(4) week advance notification per key note ‘I’ shown on every MEP drawing that reads as follows, “CONTRACTOR TO PROVIDE CRANE RIGGING/PICK PLANS AT LEAST FOUR(4) WEEKS PRIOR TO SCHEDULED DATE. SUBMIT PLANS TO VA COR TO DISTRIBUTE TO APPROPRIATE SAFETY OFFICERS FOR DISRUPTION PLANNING. ALL DATES ARE TENTATIVE UNTIL APPROVED.” Also reference specification section 01 00 00.
39General8/10/26Is an allowance for temporary heat/AC acceptable?8/10/26No this is a fixed-price contract.
4022 14 008/10/26Is insulated PVC acceptable for new storm drain piping?8/10/26No. Provide cast iron storm drain piping per specification 22 14 00 (para 2.1.A). Insulate per specification 22 07 11 along with drawing key note requirements.
41General8/10/26Are there any working hours restrictions on the jobsite?8/10/26Working hours are from 8:00am to 4:30pm, Monday through Friday. Working outside of these hours may be allowed by permission of the COR.
4226 05 338/10/26Are there restrictions on electrical conduit types inside the building?8/10/26Install electrical conduit per specifications.
43General8/10/26If circuits need to be extended for electrical reconnection of rooftop equipment, are NEMA 3R junction boxes and rated splice kits acceptable?8/10/26Splices are not allowed to extend circuit for reconnection.
44General8/10/26Section 5, TECHNICAL PROPOSAL PREPARATION INSTRUCTIONS, Volume I (f) of Amendment 001 for requisition 438-26-4-3916-0018 states: "Per VAAR 819.7004, VAAR 852.219-75 VA Notice of Limitations on Subcontracting – Certificate of Compliance for Services and Construction must be completed, signed, and returned with the offeror’s Bid/quotation/proposal. The Government will not consider offers for award from offerors that do not provide the certification with their bid/quotation/proposal, and all such responses will be deemed ineligible for evaluation and award". However, the FAR Part 19.102 states, "Contracting Officer check{s} the appropriate box based on the predominant NAICS code assigned to the acquisition". Could the government clarify if Offerors should submit their own VAAR or will the Certificate of Compliance for Services and Construction be provided with the appropriate box and NAICS code checked by the CO?8/10/26The NAICS code for this project is 236220, Seection a (1) ii , General Construction should be be checked. The documents requested in the RFP must be adhred to: Certificate of Compliance for Services and Construction must be completed, signed, and returned with the offeror’s Bid/quotation/proposal. The Government will not consider offers for award from offerors that do not provide the certification with their bid/quotation/proposal, and all such responses will be deemed ineligible for evaluation and award".
45General8/10/26Request for Extension of Bid Due Date: Given the magnitude and complexity of this project, would the Government consider extending the August 18, 2026 bid due date? The limited timeframe between the anticipated release of RFI responses and the current bid deadline may not allow sufficient time to review and incorporate those responses into our estimate and proposal. An extension would allow offerors adequate time to prepare an accurate and complete bid.8/10/26The Bid Due Date has been extended to August 28, 2026.
46General8/10/26Insurance Requirements: Please identify any specific insurance coverage requirements applicable to this solicitation, including minimum policy limits, umbrella or excess liability coverage, required clauses, endorsements, additional insured requirements, or any other insurance-related provisions required of the successful contractor and any subcontractors.8/10/26Please to follow the information in the RFP.This is business decision your company will have to determine in accordance with provision and clauses within the solcitation.
47General8/10/26Do you have any context for why they are removing the Pryobar? For that single building alone, this is roughly 350 Tons of material and its removal is problematic.8/10/26Pyrobar is being removed for several reasons, some pieces are already cracked/damaged, due to the difficulty of removing existing fasteners without cracking/damaging the pyrobar, and due to the difficulty of installing new slate fasteners without cracking/damaging the pyrobar.
48Sheet 05.AE5008/10/26Is the entire parapet intended to be wrapped with membrane or should Contractors go back with like counter flashing?8/10/26This question does not contain adequate information to address specifically (no specific building identified). Wall tie-in and flashing details for each roof area are in 05.AE500 series detail drawings.
49General8/10/26Building 19 is not called out on the drawing – is this building/roof to be included?8/10/26There is no Building 19 that is called out in this project.
50Sheet 05.AE 1258/10/26Is roof section 5-0.North to be included? It calls out on the overall map but is X’d out on drawings 05.AE125 – Please clarify which part of these roof sections is or isn’t included.8/10/26Roof Section 5-O. North is not to be included. This roof was recently replaced in 2024 and does not require a new roof.