36C26325Q0893 0002.pdf
PDF 101 KB Posted
- Attached to
- H259--Electrical Testing & Calibration Federal contract opportunity
- Solicitation number
- 36C26325Q0893
About this file
This document is a Solicitation Amendment (Standard Form 30) for Solicitation Number 36C26325Q0893, modifying a Request for Quotes (RFQ) for Electrical Testing and Calibration Services at the Black Hills VA Health Care System in Fort Meade, South Dakota. The amendment addresses vendor questions and clarifies specifications, with the solicitation period remaining unchanged at 12:00 pm on 07/24/2025. The procurement is a total small business set-aside under NAICS code 541380, with a size standard of $19 million.
Key details include a revised period of performance from 08/15/2025 to 10/31/2025, with the contract focusing on comprehensive electrical system testing and calibration. The amendment provides detailed responses to 13 vendor questions covering topics such as Professional Engineer licensing, testing requirements, circuit breaker specifications, and documentation. Specifically, all circuit breakers will need testing (except panelboards 225 amp or smaller), a Professional Engineer license from any state is acceptable, and attachments include test reports and arc flash study reports for Fort Meade and Hot Springs VA facilities. Quotes must be submitted via email to cameron.rick@va.gov, with the government anticipating a single Firm Fixed Price award.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Hot Springs VA Combined Test Report.pdf | ||
| Fort Meade VAMC Arc Flash Study Report.pdf | ||
| Fort Meade VA Combined Test Report.pdf | ||
| 36C26325Q0893 0002.docx | DOCX document | |
| 36C26325Q0893 0001.pdf | ||
| 36C26325Q0893.pdf | ||
| Wage Determination - Ft. Meade.pdf | ||
| Drawings.pdf | ||
| Specifications.pdf | ||
| Wage Determination - Hot Springs.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO. 1. CONTRACT ID CODE
FACILITY CODECODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30 PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243
(Type or print) (Type or print)
(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code)
(If other than Item 6)
(Specify type of modification and authority)
(such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer)
1 4
0002 07-21-2025
36C568
Department of Veterans Affairs Black Hills Health Care System
113 Comanche Rd.
Ft. Meade SD 57741
36C263
Department of Veterans Affairs
NETWORK 23 CONTRACTING OFFICE
316 Robert Street N. STE. 506 St. Paul MN 55101
To all Offerors/Bidders
36C26325Q0893
06-30-2025
X
X X
See CONTINUATION Page
X 1
The purpose of this modification is to answer vendor questions.
See below and attached.
The solicitation end date remains the same at 12:00pm on 07/24/2025. All bids must be received by this time in order to be considered.
Cameron Rick Contracting Officer
CONTINUATION PAGE
A.1 PRICE/COST SCHEDULE
ITEM INFORMATION
ITEM
NUMBE
R
DESCRIPTION OF
SUPPLIES/SERVIC
ES
QUANTIT
Y
UNI
T UNIT PRICE AMOUNT
0001 1.00 JB ________________
Electrical Testing and Calibration Contract Period: Base POP Begin: 08-15-2025 POP End: 10-31-2025 PRINCIPAL NAICS CODE: 541380 - Testing Laboratories and Services PRODUCT/SERVICE CODE: H259 - Equipment and Materials Testing - Electrical and Electronic Equipment Components
GRAND TOTAL ________________
Questions / Answers
1. Is it strictly required that the Professional Engineer (PE) license be registered in the state of South Dakota? If NO, is it possible to submit SD registered license after the award or is it acceptable for PE from other states?
A: A PE from another State is acceptable.
2. Is the primary and/or secondary injection testing required?
A: Please see Specification Section 16052 Electrical System Testing and Calibration for all required testing.
3. There presently are no states with provisions in electrician licensing examinations related to electrical testing and maintenance. Instead, the licensing relates to the National Electric Code (NEC) and related equipment installations. Can this statement be modified to say work under this SOW shall be performed by a certified test technician or Registered Professional Engineer?
A: Please see the Specifications- Section 16001 Qualifications for Electrical Switchgear and Distribution maintenance testing Service- 1.2 Field Service Requirements. If there are differences between the Drawings, Statement of Work (SOW), or Specifications the Specifications will take priority. There will be no adjustments made to the Specifications.
4. If so, Section 16001, Qualifications for Electrical Switchgear and Distribution Maintenance Testing Service should then be modified to include a new section 1.2B and 1.2C to read:
a. “Field service work shall be performed directly by field service engineers who have successfully demonstrated their knowledge and experience in the field of Electrical Power Distribution Systems Testing. The field service engineer shall be capable of: 1) testing assessing, evaluation, servicing, and reconditioning components, 2) assuring that the equipment on which work has been performed is safe, reliable and acceptable for its intended purpose, and 3) identifying defective equipment, and potential safety problems, environmental hazards, or code violations.
b. The lead Field Service Engineer/Technician must have minimum qualifications as follows:
i. Current certification by the National Institute for Certification in Engineering Technologies (NICET) or the National Electrical Testing Association (NETA), plus at least five (5) years experience in electrical switchgear and power distribution systems testing; or
ii. Persons who, by their education, training, and specialized experience can qualify for certification buy who have not yet applied or taken the certification exams. These people must submit three (3) references on projects of similar size and complexity and demonstrate that they have the required specialized knowledge and five (5) years experienced in electrical switchgear and power distribution systems testing; or
iii. Persons with higher qualifications, such as a BS degree in Engineering, provided that they submit three (3) references on projects of similar size and complexity and demonstrate that they have the acquired specialized knowledge and five (5) years experience in electrical switchgear and power distribution systems testing.”
Is this acceptable?
A: Please see the Specifications- Section 16001 Qualifications for Electrical Switchgear and Distribution maintenance testing Service- 1.2 Field Service Requirements. If there are differences between the Drawings, Statement of Work (SOW), or Specifications the Specifications will take priority. There will be no adjustments made to the Specifications.
5. Section 16001, Qualifications for Electrical Switchgear and Distribution Maintenance Testing Service section 1.1C states the following: “The contractor shall meet OSHA criteria for accreditation of testing laboratories, Title 29, Part a907.” This statement applies to testing laboratories such as Underwriters Laboratories (UL) in evaluating safety of products for sale to the public. It does not apply to testing companies performing field testing after equipment has been installed as called for in this solicitation. Can this statement be removed from section 16001?
A: There will be no adjustments made to the Specifications.
6. Page 8, section B.2, Price/Cost Schedule outlines a performance period of September 1, 2025 to October 31, 2025. This is typically peak season for most testing companies providing limited flexibility in completing work with this performance period due to existing project schedules. Can the period of performance be increased to 90 days, 9/1/25-11/30/25?
A: Due to the location in South Dakota and the unpredictable weather we cannot push the POP out after 10/31/25. The start of the project could be advanced to start August 15th- October 31st 2025 to extend the POP to 75 days. Please keep in mind the 12KV Feeders at Fort Meade may be removed from service during the non-cooling season of (September 1st- October 31st). The Price/Cost Schedule has been adjusted for a 08/15/25 start date.
7. What should be included in generator testing? Is load bank testing required?
A: We have a separate contract for Load bank testing and Load Bank Testing is not required.
8. Can you please provide the latest test report?
A: Yes, see attached. Please keep in mind the last test report did not include everything in this solicitation.
9. Can you provide the latest AF study report?
A: Yes, see attached. Please keep in mind the last test report did not include everything in this solicitation.
10. How many medium voltage cables should be inspected? All those identified in the drawings?
A: Correct, all identified in the drawings.
11. Are contact resistance and insulation resistance tests sufficient for low voltage circuit breakers?
A: Please see Specification Section 16052 Electrical System Testing and Calibration- Sections 1.12 and 1.13.
12. Some one-line drawings allow us to see the devices installed within each switchboard/panel/MCC, such as drawing E-4 on page 5, but riser diagrams, such as E- 3 on page 4, don't allow us to know which and how many breakers are installed within each switchboard/panel/MCC. Should we consider in the proposal only the devices we can identify in the drawings, or can the government provide an estimate of quantities/inventory?
A: Panelboards 225 amp or smaller are excluded.
13. What size circuit breaker needs to be tested? (Example: 250A or larger/600A or larger.)
A: All Circuit breakers will need to be tested. Panelboards 225 amp or smaller are excluded.
See attached document: Fort Meade VA Combined Test Report.
See attached document: Fort Meade VAMC Arc Flash Study Report.
See attached document: Hot Springs VA Combined Test Report.
| A.1 PRICE/COST SCHEDULE |
| ITEM INFORMATION |
File details come from the government source that posted it. Updated .