This document is a comprehensive technical specification for replacing Chiller #4 at the Minneapolis VA Health Care System's Energy Center. The project involves replacing the existing 1,100-ton York chiller with a new chiller, associated control components, and related infrastructure modifications. Key work includes demolishing and removing the existing chiller, installing a new chiller, replacing associated pumps and water filter, and updating control systems to integrate with the existing Engineering Control Center (ECC).
Specific tasks include removing existing equipment, installing a new chilled water pump (69-P18), replacing the water pump (69-P17), installing a new chemical water filter, and creating emergency chiller connection points on primary and condenser water lines. The project also requires installing a 1600A quick disconnect panel for temporary chiller connections. The controls work will be performed by Johnson Controls Inc., involving modifications to the existing control system, adding a new JCI DX-9100 controller, and integrating new control components with the existing Building Automation System. The project is part of VA Project Number 618-25-202 and is scheduled for completion in May 2025.
View the file
Other files for this federal contract opportunity
Show all 23
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF VETERANS AFFAIRS
SPECIFICATIONS
FACILITY: MINNEAPOLIS VA HEALTH CARE SYSTEM
1 VETERANS DRIVE
MINNEAPOLIS, MN 55417
PROJECT: REPLACE CHILLER 4 ENERGY CENTER
BUILDING 69
AND PROVIDE EMERGENCY POWER AND WATER
FOR EMERGENCY BACKUP CHILLER
VA PROJECT NO.: 618-25-202
100% CONSTRUCTION DOCUMENTS SUBMITTAL
MAY 02, 2025
Department of Veterans Affairs
Specifications
Table of Contents
Section 00 01 10
SECTION # DIVISION AND SECTION TITLES DATE
DIVISION 00 – SPECIAL SECTIONS
00 01 10 Table of Contents 06-24 00 01 15 List of Drawing Sheets 05-20
DIVISION 01 – General Requirements 01 00 00 General Requirements 11-21 01 33 23 Shop Drawings, Product Data, and Samples 11-23 01 35 26 Safety Requirements 05-24 01 42 19 Reference Standards 11-20 01 45 29 Testing Laboratory Services 11-18 01 74 19 Construction Waste Management 04-22 01 91 00 General Commissioning Requirements 04-22
DIVISION 2 – EXISTING CONDITIONS
02 41 00 Demolition 8-17
DIVISION 3 - CONCRETE
03 30 53 Cast-In-Place Concrete (Short Form) 01-21
DIVISION 9 - FINISHES
09 91 00 Painting 01-21
DIVISION 22 – PLUMBING
22 05 11 Common Work Results for Plumbing 03-23 22 11 00 Facility Water Distribution 05-21 22 08 00 Commissioning of Plumbing Systems 11-16
DIVISION 23 – HEATING, VENTILATION AND COOLING
23 05 11 Common work Results for HVAC and Steam Generation 03-23 23 05 12 General Motor Requirements for HVAC and Steam Generation
Equipment 01-23
23 05 41 Noise and Vibration Control for HVAC Piping and Equipment 03-23 23 05 93 Testing, Adjusting and Balancing for HVAC 03-23 23 07 11 HVAC, Plumbing, and Boiler Plant Insulation 02-20 23 08 00 Commissioning of HVAC Systems 03-23 23 09 23 Direct-Digital Control System for HVAC 03-23 23 21 13 Hydronic Piping 03-23
23 21 23 Hydronic Pumps 03-23 23 25 00 HVAC Water Treatment 03-23 23 64 00 Packaged Water Chillers 03-24
DIVISION 26 – ELECTRICAL
26 05 11 Requirements for Electrical Installation 11-22 26 05 19 Low-Voltage Electrical Power Conductors and Cables (600Volts and Below) 11-22
26 05 26 Grounding and Bonding for Electrical Systems 11-22 26 05 33 Raceways and Boxes for Electrical Systems 11-22 26 08 00 Commissioning of Electrical Systems 11-16 26 23 00 Low-Voltage Switchgears 11-22 26 27 26 Wiring Devices 11-22 26 29 11 Motor Controllers 11-22 26 29 21 Enclosed Switches and Circuit Breakers 11-22
05-01-20 618-25-202
Replace Chiller 4 Building 69
00 01 15 - 1
SECTION 00 01 15
LIST OF DRAWING SHEETS
The drawings listed below accompanying this specification form a part of the contract.
Page Drawing No. Title
1 VAMC Chiller #1 and #2 Replacement
2 NR Network Riser Drawing
3 3.1.0 Chilled Water Flow Diagram
4 3.1.1 Condenser Water System
5 3.1.2 Sequence of Operations I
6 3.1.3 Sequence of Operations II
7 3.1.4 Chiller 1 Point Schedule
8 3.1.5 Chiller 3 Point Schedule
9 3.1.6 Chiller 1 Point Schedule Bldg. 69
10 3.1.7 Chiller MCC Control Panel Rewire
11 VS-1 Valve Schedule Chiller 1
12 VS-1 Valve Schedule Chiller 2
VA Chiller #3 Replacement
13 1127-E1 Electrical Title Sheet
14 1127-E4 Electrical Power Plan
15 1127-E6 Electrical One Line Base Bid and Alt. #4
16 1127-E7 Electrical One Line Alt. #5 & #6
17 1127-X1 Mechanical Title Sheet
18 1127-H1 Mechanical First Floor Demo Plan
19 1127-H2 Mechanical First Floor Revision Plan
20 1127-H3 Mechanical Second Floor Demo Plan
21 1127-H4 Mechanical Second Floor Revision Plan
22 1127-H6 Mechanical Details Sheet
23 1127-H7 Mechanical Flow Diagram/Temp Controls
24 1127-ME Mechanical/Electrical Schedules
05-01-20
Replace Chiller 4 Building 69
00 01 15 - 2
VA Chiller #4 Identifying Locations
25 1127 E4 Substation 2 and Quick disconnect locations
26 1127-H1 Chiller #4, Pumps, and water filter locations
27 Substation 2 One-Line Diagram
28 York-YK Model Product Drawing
- - - END - - -
11-01-21
Replace Chiller 4 Energy Center
01 00 00 -1
SECTION 01 00 00
GENERAL REQUIREMENTS
GENERAL
1.1 GENERAL INTENTION
A. The Contractor shall provide all labor; materials and equipment to accomplish the work required for the “Replace Chiller #4 at
Energy Center”, Project Number 618-25-202, located at the Energy
Center on the campus at the VA Medical Center, Minneapolis, Minnesota as required by drawings and specifications.
B. Prospective bidders are encouraged to tour job site to acquaint themselves with conditions, as they actually exist. Failure to tour the job site will not relieve the successful bidder to whom the contract is awarded from performing all work in accordance with project drawings and these specifications.
C. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.
D. Prior to commencing work, general contractor shall provide proof that an OSHA certified “Competent Person” (CP) (29 CFR
1926.20(b)(2) will maintain a presence at the work site whenever the general or subcontractors are present. The OSHA certified
CP shall have the 30-hour OSHA certified Construction Safety course and/or other relevant competency training, as determined by VA CP with input from the PCRA team.
E. The general contractor’s CP shall be part of a multi-disciplinary
VA team that will complete a pre-construction risk assessment consisting of a design review and site walk-through to determine health and safety requirements. The general contractor shall be responsible for implementing the measures prescribed by the team.
F. OSHA Training:
01 00 00 -2
1. All employees of the general contractor or subcontractors shall have the 10-hour OSHA certified Construction Safety course and /or other relevant competency training, as determined by Contracting Officer Representative.
2. Submit training records of all such employees for approval before the start of work.
1.2 STATEMENT OF BID ITEM(S)
A. Base Bid: The Contractor shall provide all labor, materials and equipment to accomplish:
a. Demolition consists of, but is not limited to, removal and disposal of the following: Existing 1,100 ton York chiller, equipment shall be removed to allow for the installation of the new chiller. Reconnect controls to the new chiller.
b. Contractor shall remove from the VA site and dispose of equipment slaved for parts as part of a prior chiller replacement. Equipment to be to be removed include: CE 126
Compressor, Discharge check valve, control panel, liquid line shutoff valve, expansion valve, oil coolers, oil pump, oil reservoir, lube box and compressor motor terminal box, chiller starter.
c. Provide all materials, labor and equipment to replace the existing chilled water pump, (69-P18), with a new chilled water pump of the same size and power requirements as the existing pump. Disconnecting the existing pump, relocation of power and piping should be included in the base bid.
d. Provide all materials, labor and equipment to replace existing water pump (69-P17), with a new water pump of the same size and power requirements. Disconnecting the power from the existing pump and reconnecting power to new pump should be included in the base bid.
e. Provide all materials, labor and equipment to replace Chem-
Aqua water filter adjacent to Chiller 4 with new water filter of same size and power requirements as existing
01 00 00 -3 filter. Disconnecting the existing Filter, relocation of power and piping should be included in the base bid.
f. Provide all materials, labor and equipment to install an emergency chiller connection point to the system on the primary water supply and return lines as well as the main condenser supply and return lines per VA specifications section 23-05-11.
1) Add “T” connections at condenser with shutoff valves.
a) CHW-S (2)
b) CHW-R (2)
c) Condenser supply (1)
d) Condenser return (1)
g. Provide all materials, labor and equipment to install a
1600A quick disconnect panel to the southern side of building 69 for a temporary connection point for an emergency chiller. Exterior electrical connection point to be fed from open space in substation 2. New connections shall include a 1600a disconnect, 1600a breaker, correct size conductors, conduit, and fittings and installed per VA specifications section 26-05-11.
h. Contractor shall remove from the VA site and dispose of equipment slaved for parts as part of the chiller replacement project.
i. The “Replace Chiller #4 and Pumps at the Energy Center” project shall be accomplished per reference drawings and specification number 618-25-202 and project number 618-25-
202.
1.3 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
A. AFTER AWARD OF CONTRACT, Reference drawings and specifications will be furnished electronically. Reference drawings and specification will be in Adobe PDF format.
01 00 00 -4
B. Hard Copy reference drawings and specifications may be made by the Contractor, at the Contractor’s expense, from electronic files furnished by the Issuing Contracting Officer.
1.4 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Plan:
1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.
2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.
B. Security Procedures:
1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.
2. For working outside the “regular hours” as defined in the contract, The General Contractor shall give 3 days notice to the VA Project Manager so that security arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.
3. No photography of VA premises is allowed without written permission of the Contracting Officer. Patients and staff are not to be photographed at any time.
4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the
Contracting Officer.
C. Key Control:
1. The General Contractor shall provide duplicate keys and lock combinations to the Contracting officers representative (COR)
01 00 00 -5 for the purpose of security inspections of every area of project including toolboxes and parked machines and take any emergency action.
D. Document Control:
1. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.
2. Before starting any work, the General Contractor/Sub
Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of “sensitive information”.
3. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.
4. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or
“Sensitive Unclassified”. Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the Contracting
Officer upon request.
5. These security documents shall not be removed or transmitted from the project site without the written approval of
Contracting Officer.
6. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the
VA.
7. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.
01 00 00 -6
8. All electronic information shall be stored in specified location following VA standards and procedures using an
Engineering Document Management Software (EDMS).
Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the EDMS system.
“Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.
E. Motor Vehicle Restrictions
1. General Contractor and Subcontractor vehicles are permitted to use the loading dock area for loading/unloading only. Once supplies and equipment have been unloaded, the contractor shall park their vehicle in general employee parking.
2. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted
24 hours before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies.
1.5 OPERATIONS AND STORAGE AREAS (FAR 52.236-10)
A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the
Contractor's performance.
B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the Contractor and shall be removed by the Contractor at its expense upon completion of the work. With
01 00 00 -7 the written consent of the Contracting Officer, the buildings and utilities may be abandoned and need not be removed.
C. The Contractor shall, under regulations prescribed by the
Contracting Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The
Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
D. Working space and space available for storing materials shall be as shown on the drawings, as determined by the COR.
E. Workers are subject to rules of Medical Center applicable to their conduct.
F. Execute work in such a manner as to interfere as little as possible with work being done by others. Keep roads clear of construction materials, debris, standing construction equipment and vehicles at all times.
G. Execute work so as to interfere as little as possible with normal functioning of Medical as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by
COR where required by limited working space.
1. Do not store materials and equipment in other than assigned areas.
01 00 00 -8
2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by
Department of Veterans Affairs in quantities sufficient for not more than two workdays. Provide unobstructed access to
Medical Center areas required to remain in operation.
3. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.
H. Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (except telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR. All such actions shall be coordinated with the COR or
Utility Company involved:
1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of VA
Project Manager. Electrical work shall be accomplished with all affected circuits or equipment de-energized. When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without the
Medical Center Director’s prior knowledge and written approval. Refer to specification Section 26 05 11 for additional requirements.
2. Contractor shall submit a request to interrupt any such services to VA Project Manager, in writing, 48 hours in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.
3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption
01 00 00 -9 will cause least inconvenience to operations of the VA Medical
Center. Interruption time approved by Medical Center may occur at other than Contractor's normal working hours.
4. Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the COR.
5. In case of a contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical.
6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.
I. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, which are to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.
J. To minimize interference of construction activities with flow of
Medical Center traffic, comply with the following:
1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles.
1.6 ALTERATIONS
A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR of the project site in which construction will occur and areas which are anticipated routes of access, and furnish a report, signed by both, to the
Contracting Officer.
01 00 00 -10
1. Shall note any discrepancies between drawings and existing conditions at site.
2. Shall designate areas for working space, materials storage and routes of access to the project site, which have been agreed upon by Contractor and Project Manager
3. Existing condition and types of resilient flooring, doors, windows, walls and other surfaces not required to be altered throughout affected areas of building.
4. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, etc., required by drawings to be either reused or relocated, or both.
5. Shall note any discrepancies between drawings and existing conditions at site.
6. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur, and which have been agreed upon by Contractor and COR.
B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of COR to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by
Contractor with new items in accordance with specifications which will be furnished by Government. Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled "DIFFERING SITE CONDITIONS" (FAR 52.236-2) and
"CHANGES" (FAR 52.243-4).
C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas of buildings involved. They shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls and other surfaces as compared
01 00 00 -11 with conditions of same as noted in first condition survey report:
1. Re-survey report shall also list any damage caused by
Contractor to such flooring and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of Contractor to restore damage caused by Contractor's workers in executing work of this contract.
D. Disposal & Retention: Materials and/or equipment salvaged during the demolition/construction work shall become the property of the Contractor and disposed of off station, except as noted on the drawings. Prior to removal, the Contractor will verify material/equipment disposal with the Project Manager and deliver to the Government any material/equipment as directed by the COR.
E. Protection: Provide the following protective measures:
1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.
2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.
3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.
1.7 DISPOSAL AND RETENTION
A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:
1. Reserved items which are to remain property of the Government are identified by attached tags or noted on drawings or in
01 00 00 -12 specifications as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by COR.
2. Items not reserved shall become property of the Contractor and be removed by Contractor from Medical Center.
3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government. When rooms and spaces are vacated by the Department of Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.
1.8 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT,
UTILITIES, AND IMPROVEMENTS (FAR 52.236-9)
A. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workers, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the
Contracting Officer.
B. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are
01 00 00 -13 made known to or should be known by the Contractor. The
Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the Contractor fails or refuses to repair the damage promptly, the Contracting Officer may have the necessary work performed and charge the cost to the Contractor.
1.10 RESTORATION
A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.
B. Upon completion of contract, deliver work complete and undamaged.
Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.)
disturbed or removed because of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.
C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workers to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.
01 00 00 -14
D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES" (FAR 52.243-4) and "DIFFERING SITE
CONDITIONS" (FAR 52.236-2).
1.11 PHYSICAL DATA
A. Data and information furnished or referred to below is for the
Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.
B. Government does not guarantee that other materials will not be encountered, nor that proportions, conditions or character of several materials will not vary from those indicated by explorations. Bidders are expected to examine site of work and logs of borings; and, after investigation, decide for themselves character of materials and make their bids accordingly.
1.12 PROFESSIONAL SURVEYING SERVICES (NOT USED)
1.13 LAYOUT OF WORK
A. Contractor shall layout work according to project drawings and specifications.
1.14 AS-BUILT DRAWINGS
A. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.
B. All variations shall be shown in the same general detail as used in the contract reference drawings. To ensure compliance, as-built drawings shall be made available for the COR review, as often as requested.
C. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) to the COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR.
01 00 00 -15
D. Paragraphs A, B, & C shall also apply to all shop drawings.
1.15 WARRANTY MANAGEMENT
A. Warranty Management Plan: Develop a warranty management plan which contains information relevant to FAR 52.246-21 Warranty of
Construction in at least 30 days before the planned pre-warranty conference, submit one set of the warranty management plan.
Include within the warranty management plan all required actions and documents to assure that the Government receives all warranties to which it is entitled. The plan must be in narrative form and contain sufficient detail to render it suitable for use by future maintenance and repair personnel, whether tradesman, or of engineering background, not necessarily familiar with this contract. The term “status” as indicated below must include due date and whether item has been submitted or was approved. Warranty information made available during the construction phase must be submitted to the Contracting Officer for approval prior to each monthly invoice for payment. Assemble approved information in a binder and turn over to the Government upon acceptance of the work. The construction warranty period will begin on the date of the project acceptance and continue for the product warranty period. A joint 4 month and 9 month warranty inspection will be conducted, measured from time of acceptance, by the Contactor and the Contracting Officer.
Include in the warranty management plan, but not limited to, the following:
1. Roles and responsibilities of all personnel associated with the warranty process, including points of contact and telephone numbers within the company of the Contractor, subcontractors, manufacturers or suppliers involved.
2. Furnish with each warranty the name, address and telephone number of each of the guarantor’s representatives nearest project location.
01 00 00 -16
3. Listing and status of delivery of all Certificates of Warranty for extended warranty items, to include roofs, HVAC balancing, pumps, motors, transformers and for all commissioned systems such as fire protection and alarm systems, sprinkler systems and lightning protection systems, etc.
4. A list for each warranted equipment item, feature of construction or system indicating:
a. Name of item.
b. Model and serial numbers.
c. Location where installed.
d. Name and phone numbers of manufacturers and suppliers.
e. Name and phone numbers of manufacturers or suppliers.
f. Names, addresses and phone numbers of sources of spare parts.
g. Warranties and terms of warranty. Include one-year overall warranty of construction, including the starting date of warranty of construction. Items which have extended warranties must be indicated with separate warranty expiration dates.
h. Starting point and duration of warranty period.
i. Summary of maintenance procedures required to continue the warranty in force.
j. Cross-reference to specific pertinent Operation and Maintenance manuals.
k. Organizations, names and phone numbers of persons to call for warranty service.
l. Typical response time and repair time expected for various warranted equipment.
5. The plans for attendance at the 4 and 9-month post construction warranty inspections conducted by the government.
6. Procedure and status of tagging of all equipment covered by extended warranties.
01 00 00 -17
7. Copies of instructions to be posted near selected pieces of equipment where operation is critical for warranty and/or safety reasons.
B. Performance & Payment Bonds: The Performance & Payment Bonds must remain effective throughout the construction period.
1. In the event the Contractor fails to commence and diligently pursue any construction warranty work required, the
Contracting Officer will have the work performed by others, and after completion of the work, will charge the remaining construction warranty funds of expenses incurred by the
Government while performing the work, including, but not limited to administrative expenses.
2. In the event sufficient funds are not available to cover the construction warranty work performed by the Government at the contractor’s expenses, the Contracting Officer will have the right to recoup expenses from the bonding company.
3. Following oral or written notification of required construction warranty repair work, the Contractor shall respond in a timely manner. Written verification will follow oral instructions. Failure to respond will be cause for the
Contracting Officer to proceed against the Contractor.
C. Pre-Warranty Conference: Prior to contract completion, and at a time designated by the Contracting Officer, the Contractor shall meet with the Contracting Officer to develop a mutual understanding with respect to the requirements of this section.
Communication procedures for Contractor notification of construction warranty defects, priorities with respect to the type of defect, reasonable time required for Contractor response, and other details deemed necessary by the Contracting
Officer for the execution of the construction warranty will be established/ reviewed at this meeting. In connection with these requirements and at the time of the Contractor’s quality control completion inspection, furnish the name, telephone number and
01 00 00 -18 address of a licensed and bonded company which is authorized to initiate and pursue construction warranty work action on behalf of the Contractor. This point of contract will be located within the local service area of the warranted construction, be continuously available and be responsive to Government inquiry on warranty work action and status. This requirement does not relieve the Contractor of any of its responsibilities in conjunction with other portions of this provision.
D. Contractor’s Response to Construction Warranty Service
Requirements:
E. Following oral or written notification by the Contracting
Officer, the Contractor shall respond to construction warranty service requirements in accordance with the “Construction
Warranty Service Priority List” and the three categories of priorities listed below. Submit a report on any warranty item that has been repaired during the warranty period. Include within the report the cause of the problem, date reported, corrective action taken, and when the repair was completed. If the Contractor does not perform the construction warranty within the timeframe specified, the Government will perform the work and back charge the construction warranty payment item established.
F. Warranty Tags: At the time of installation, tag each warranted item with a durable, oil and water-resistant tag approved by the
Contracting Officer. Attach each tag with a copper wire and spray with a silicone waterproof coating. Also submit two record copies of the warranty tags showing the layout and design. The date of acceptance and the QC signature must remain blank until the project is accepted for beneficial occupancy. Show the following information on the tag.
Warranty Tags
Type of product/material
01 00 00 -19
Warranty Tags
Model number
Serial number
Contract number
Warranty period from/to
Inspector’s signature
Construction Contractor
Address
Telephone number
Warranty Contact
Address
Telephone number
Warranty response time priority code
SPEC WRITER NOTE: Determine necessary paragraphs from below and delete non-applicable portions.
1.16 USE OF ROADWAYS
A. For hauling, use only established public roads and roads on
Medical Center property and, when authorized by the COR, such temporary roads which are necessary in the performance of contract work. Temporary roads shall be constructed and restoration performed by the Contractor at Contractor's expense.
When necessary to cross curbing, sidewalks, or similar construction, they must be protected by well-constructed bridges.
1.17 RESIDENT ENGINEER'S FIELD OFFICE (NOT USED)
1.18 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT
A. Use of new installed mechanical and electrical equipment to provide heat, ventilation, plumbing, light and power will be permitted subject to written approval and compliance with the following provisions:
01 00 00 -20
1. Permission to use each unit or system must be given by COR in writing. If the equipment is not installed and maintained in accordance with the written agreement and following provisions, the COR will withdraw permission for use of the equipment.
2. Electrical installations used by the equipment shall be completed in accordance with the drawings and specifications to prevent damage to the equipment and the electrical systems, i.e. transformers, relays, circuit breakers, fuses, conductors, motor controllers and their overload elements shall be properly sized, coordinated and adjusted.
Installation of temporary electrical equipment or devices shall be in accordance with NFPA 70, National Electrical Code, (2014 Edition), Article 590, Temporary Installations. Voltage supplied to each item of equipment shall be verified to be correct and it shall be determined that motors are not overloaded. The electrical equipment shall be thoroughly cleaned before using it and again immediately before final inspection including vacuum cleaning and wiping clean interior and exterior surfaces.
3. Units shall be properly lubricated, balanced, and aligned.
Vibrations must be eliminated.
4. Automatic temperature control systems for preheat coils shall function properly and all safety controls shall function to prevent coil freeze-up damage.
5. The air filtering system utilized shall be that which is designed for the system when complete, and all filter elements shall be replaced at completion of construction and prior to testing and balancing of system.
6. All components of heat production and distribution system, metering equipment, condensate returns, and other auxiliary facilities used in temporary service shall be cleaned prior to use; maintained to prevent corrosion internally and externally
01 00 00 -21 during use; and cleaned, maintained and inspected prior to acceptance by the Government. Pumps and auxiliary equipment must be operated as a complete system and be fully maintained by operating personnel. Boiler water must be given complete and continuous chemical treatment.
B. Prior to final inspection, the equipment or parts used which show wear and tear beyond normal, shall be replaced with identical replacements, at no additional cost to the Government.
C. This paragraph shall not reduce the requirements of the mechanical and electrical specifications sections.
D. Any damage to the equipment or excessive wear due to prolonged use will be repaired replaced by the contractor at the contractor’s expense.
1.19 TEMPORARY USE OF EXISTING ELEVATORS (NOT USED)
1.20 TEMPORARY USE OF NEW ELEVATORS (NOT USED)
1.21 TEMPORARY TOILETS
A. Provide where directed, (for use of all Contractor's workers) ample temporary sanitary toilet accommodations with suitable sewer and water connections; or, when approved by COR, provide suitable dry closets where directed. Keep such places clean and free from flies and all connections and appliances connected therewith are to be removed prior to completion of contract, and premises left perfectly clean.
1.22 AVAILABILITY AND USE OF UTILITY SERVICES
A. The Government shall make all reasonably required amounts of utilities available to the Contractor from existing outlets and supplies, as specified in the contract. The amount to be paid by the Contractor for chargeable electrical services shall be the prevailing rates charged to the Government. The Contractor shall carefully conserve any utilities furnished without charge.
B. The Contractor, at Contractor's expense and in a workmanlike manner, in compliance with code and as satisfactory to the
Contracting Officer, shall install and maintain all necessary
01 00 00 -22 temporary connections and distribution lines, and all meters required to measure the amount of electricity used for the purpose of determining charges. Before final acceptance of the work by the Government, the Contractor shall remove all the temporary connections, distribution lines, meters, and associated paraphernalia and repair restore the infrastructure as required.
C. Contractor shall install meters at Contractor's expense and furnish the Medical Center a monthly record of the Contractor's usage of electricity as hereinafter specified.
D. Electricity (for Construction and Testing): Furnish all temporary electric services.
1. Obtain electricity by connecting to the Medical Center electrical distribution system. The Contractor shall meter and pay for electricity required for electric cranes and hoisting devices, electrical welding devices and any electrical heating devices providing temporary heat. Electricity for all other uses is available at no cost to the Contractor.
E. Water (for Construction and Testing): Furnish temporary water service.
1. Obtain water by connecting to the Medical Center water distribution system. Provide reduced pressure backflow preventer at each connection as per code. Water is available at no cost to the Contractor.
2. Maintain connections, pipe, fittings and fixtures and conserve water-use so none is wasted. Failure to stop leakage or other wastes will be cause for revocation (at COR discretion) of use of water from Medical Center system.
1.23 NEW TELEPHONE EQUIPMENT (NOT USED)
1.24 TESTS
A. As per specification section 23 05 93 the contractor shall provide a written testing and commissioning plan complete with component level, equipment level, sub-system level and system
01 00 00 -23 level breakdowns. The plan will provide a schedule and a written sequence of what will be tested, how and what the expected outcome will be. This document will be submitted for approval prior to commencing work. The contractor shall document the results of the approved plan and submit for approval with the as built documentation.
B. Pre-test mechanical and electrical equipment and systems and make corrections required for proper operation of such systems before requesting final tests. Final test will not be conducted unless pre-tested.
C. Conduct final tests required in various sections of specifications in presence of an authorized representative of the Contracting Officer. Contractor shall furnish all labor, materials, equipment, instruments, and forms, to conduct and record such tests.
D. Mechanical and electrical systems shall be balanced, controlled and coordinated. A system is defined as the entire system which must be coordinated to work together during normal operation to produce results for which the system is designed. For example, air conditioning supply air is only one part of entire system which provides comfort conditions for a building. Other related components are return air, exhaust air, steam, chilled water, refrigerant, hot water, controls and electricity, etc. Another example of a system which involves several components of different disciplines is a boiler installation. Efficient and acceptable boiler operation depends upon the coordination and proper operation of fuel, combustion air, controls, steam, feedwater, condensate and other related components.
E. All related components as defined above shall be functioning when any system component is tested. Tests shall be completed within a reasonably period of time during which operating and environmental conditions remain reasonably constant and are typical of the design conditions.
01 00 00 -24
F. Individual test result of any component, where required, will only be accepted when submitted with the test results of related components and of the entire system.
1.25 INSTRUCTIONS
A. Contractor shall furnish Maintenance and Operating manuals (hard copies and electronic) and verbal instructions when required by the various sections of the specifications and as hereinafter specified.
B. Manuals: Maintenance and operating manuals (four hard copies and one electronic copy each) for each separate piece of equipment shall be delivered to the COR coincidental with the delivery of the equipment to the job site. Manuals shall be complete, detailed guides for the maintenance and operation of equipment.
They shall include complete information necessary for starting, adjusting, maintaining in continuous operation for long periods of time and dismantling and reassembling of the complete units and sub-assembly components. Manuals shall include an index covering all component parts clearly cross-referenced to diagrams and illustrations. Illustrations shall include
"exploded" views showing and identifying each separate item.
Emphasis shall be placed on the use of special tools and instruments. The function of each piece of equipment, component, accessory and control shall be clearly and thoroughly explained.
All necessary precautions for the operation of the equipment and the reason for each precaution shall be clearly set forth.
Manuals must reference the exact model, style and size of the piece of equipment and system being furnished. Manuals referencing equipment similar to but of a different model, style, and size than that furnished will not be accepted.
C. Instructions: Contractor shall provide qualified, factory-trained manufacturers' representatives to give detailed training to assigned Department of Veterans Affairs personnel in the operation and complete maintenance for each piece of equipment.
01 00 00 -25
All such training will be at the job site. These requirements are more specifically detailed in the various technical sections. Instructions for different items of equipment that are component parts of a complete system, shall be given in an integrated, progressive manner. All instructors for every piece of component equipment in a system shall be available until instructions for all items included in the system have been completed. This is to assure proper instruction in the operation of inter-related systems. All instruction periods shall be at such times as scheduled by the COR and shall be considered concluded only when the COR is satisfied in regard to complete and thorough coverage. The contractor shall submit a course outline with associated material to the COR for review and approval prior to scheduling training to ensure the subject matter covers the expectations of the VA and the contractual requirements. The Department of Veterans Affairs reserves the right to request the removal of, and substitution for, any instructor who, in the opinion of the COR, does not demonstrate sufficient qualifications in accordance with requirements for instructors above.
1.26 GOVERNMENT-FURNISHED PROPERTY (NOT USED)
1.27 RELOCATED EQUIPMENT ITEMS
A. All items not used in new construction of space should be returned to owner or disposed of according to instructions on the project drawings.
1.28 STORAGE SPACE FOR DEPARTMENT OF VETERANS AFFAIRS EQUIPMENT (NOT
USED)
1.29 CONSTRUCTION SIGN
A. Provide a Construction Sign where directed by the COR.
B. Maintain sign and remove it when directed by the COR.
01 00 00 -26
1.30 SAFETY SIGN (NOT USED)
1.31 PHOTOGRAPHIC DOCUMENTATION
A. During the construction period through completion, provide photographic documentation of construction progress and at selected milestones including electronic indexing, navigation, storage and remote access to the documentation, as per these specifications. The commercial photographer or the subcontractor used for this work shall meet the following qualifications:
1. Demonstrable minimum experience of three (3) years in operation providing documentation and advanced indexing/navigation systems including a representative portfolio of construction projects of similar type, size, duration and complexity as the Project.
2. Demonstrable ability to service projects throughout North
America, which shall be demonstrated by a representative portfolio of active projects of similar type, size, duration and complexity as the Project.
B. Photographic documentation elements:
1. Each digital image shall be taken with a professional grade camera with minimum size of 6 megapixels (MP) capable of producing 200x250mm (8 x 10 inch) prints with a minimum of
2272 x 1704 pixels and 400x500mm (16 x 20 inch) prints with a minimum 2592 x 1944 pixels.
2. Indexing and navigation system shall utilize actual AUTOCAD construction drawings, making such drawings interactive on an on-line interface. For all documentation referenced herein, indexing and navigation must be organized by both time (date-stamped) and location throughout the project.
3. Documentation shall combine indexing and navigation system with inspection-grade digital photography designed to capture actual conditions throughout construction and at critical milestones. Documentation shall be accessible on-line through
01 00 00 -27 use of an internet connection. Documentation shall allow for secure multiple-user access, simultaneously, on-line.
4. Before construction, the building pad, adjacent streets, roadways, parkways, driveways, curbs, sidewalks, landscaping, adjacent utilities and adjacent structures surrounding the building pad and site shall be documented. Overlapping photographic techniques shall be used to ensure maximum coverage. Indexing and navigation accomplished through interactive architectural drawings. If site work or pad preparation is extensive, this documentation may be required immediately before construction and at several pre-determined intervals before building work commences.
5. Construction progress for all trades shall be tracked at pre-determined intervals, but not less than once every thirty (30) calendar days (“Progressions”). Progression documentation shall track both the exterior and interior construction of the building. Exterior Progressions shall track 360 degrees around the site and each building. Interior Progressions shall track interior improvements beginning when stud work commences and continuing until Project completion.
6. As-built condition of pre-foundation utilities and site utilities shall be documented prior to pouring footers, placing concrete and/or backfilling. This process shall include all underground and in-slab utilities within the building(s) envelope(s) and utility runs in the immediate vicinity of the building(s) envelope(s).