Addendum 001 List of Changes.pdf
PDF 188 KB Posted
- Solicitation number
- 36C26224B0012
About this file
This document is an Addendum that describes revisions to the drawings and specifications for the Building 80 Upgrade (Covid-19) project at the VA New Mexico Healthcare System in Albuquerque, NM. The key revisions include:
- Changes to the site plan, floor plans, reflected ceiling plan, demolition plans, and renovation plans to highlight areas of work and add/relocate details and notes.
- Revisions to the door schedule, hardware schedule, ceiling details, and structural plans.
- Removal of several plumbing and process/instrumentation drawings related to the oxygen storage equipment.
The related federal contract opportunity is Solicitation Number 36C26224B0012 for the Building 80 Upgrade project. The work includes general construction, mechanical and electrical work, utility systems, demolition, and other tasks to reconfigure the existing Great Room, Bathing Suite, Oxygen Storage room, and trash enclosure. All work must be performed in accordance with the solicitation terms, drawings, and applicable codes.
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MA|Architects, Inc.
Planning - Architecture - Interiors
385 Van Ness Ave., Suite 110, Torrance, CA 90501 www.ma-architects.net
NMVAHCS Building 80 Upgrade (Covid-19) pg. 1
Addendum #: 001 Date: 8/16/2024
The Work shall be carried out in accordance with the following instructions issued in accordance with the Contract Documents without change in the Contract Sum or Contract Time. Proceeding with the Work in accordance with these instructions indicates your acknowledgement that there will be no change in the Contract Sum nor Contract Time.
Description:
GI-000 – Cover Sheet Revisions to site plan scale to include more site components throughout the VA New Mexico Healthcare System and Building Key.
GI-001 – Sheet Index, Applicable Standards & General Notes Revisions to Sheet Index.
GI-101 – Fire Life Safety & Reference Floor Plan Revisions to plan to highlight areas of work with grey highlight and the addition of Fire Life Safety notes including exit and fire extinguisher cabinet locations and path of travel.
GI-102 - Reference Reflected Ceiling Plan Revisions to plan to highlight areas of work with grey highlight.
C-100 – Overall Grading Plan Revisions to plan to include Pavement Sections for Heavy Duty Pavement and Concrete.
ASD-100 – Overall Demolition Site Plan Revisions to plan AD-100 to include an enlarged plan callout, relocation of keyed notes to ASD-101, and addition of keyed note 135.
ASD-101 – Enlarged Demolition Site Plan New sheet to provide an enlarged view of demolition work at Old Quarter’s Road.
Project # 501-22-101
Project:
Building 80 Upgrade (Covid-19) VA New Mexico Healthcare System 1501 San Pedro Dr. SE.
Albuquerque, NM 87108
To: Cliff Bourque http://www.ma-architects.net/
NMVAHCS Building 80 Upgrade (Covid-19) pg. 2
AS-100 – Overall Renovation Site Plan Revisions to sheet to include an enlarged plan callout, relocation of keyed notes to AS-101, and the addition of keyed notes 502, 505, 512.
AS-101 – Enlarged Renovation Site Plan New sheet to provide an enlarged view of renovation work at Old Quarter’s Road.
AS-102 – Enlarged Site Plans – Oxygen Storage & New Trash Enclosure New sheet to provide an enlarged views of demolition and renovation work at the Oxygen tank and new trash enclosure.
AE-211 – Enlarged Plans – Patient Conference Room B103 Addition of section detail callout on view 2/AE-211.
AE-212 – Enlarged Plans – Clean Storage A147 Addition of ceiling plan 2/AE-212.
AE-800 – Door, Window & Finish Schedules Revisions to door schedule and hardware schedule.
AE-1002 – Ceiling Details New sheet to provide ceiling details for Rooms A147 & B103.
AE-800 – Door, Window & Finish Schedules Revisions to door schedule and hardware schedule.
S1.0 – General Notes & Plans Revisions to Enclosure Plans 1/S1.0 and 2/S1.0.
S2.0 – General Notes & Plans Revisions to Enclosure Plans 9/S2.0.
PS-202 – Partial Site – Bulk O2 Enclosure, Drive Pad Plan and Details Removal of sheet.
P-701 – Plumbing Site Plan – O2 Equipment & Piping Schematic Removal of sheet.
P-702 – Plumbing Site Plan – O2 Equipment & Piping Schematic Removal of sheet.
PID-401 – Process & Instrument Diagram Removal of sheet.
NMVAHCS Building 80 Upgrade (Covid-19) pg. 3
Issued by the Architect:
Steven A. McCaslin | Architect
Date: 8.16.2024