Amendment 0001 Attachment 1 RFI Log.pdf
PDF 76 KB Posted
- Attached to
- Install Dedicated Fire Suppression Water Distribution System & Replace Potable Water Lines for North Campus Federal contract opportunity
- Solicitation number
- 36C26222B0007
About this file
This document contains a request for information log and related federal contract solicitation for a project to install a dedicated fire suppression water distribution system and replace potable water lines at a Veterans Affairs medical center campus in Los Angeles, California. Key details include that the solicitation is for general construction, alterations, mechanical and electrical work, and utility system installation and replacement to support occupied hospital operations. The project includes demolition, excavation, and tie-ins to existing buildings. The response log addresses contractor questions on the project schedule and timeline, archeological and security monitoring requirements, utility mapping access, and clarifications to bid items and specifications.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment 0003 Solicitation 36C26222B0007.pdf | ||
| Amendment 0002 Solicitation 36C26222B0007.pdf | ||
| Amendment 0002 Attachment 1 RFI Log.pdf | ||
| Amendment 0001 Attachment 2 Traffic Control Plan.pdf | ||
| Amendment 0001 Attachment 3 Revised Plans.pdf | ||
| Amendment 0001 Solicitation 36C26222B0007.pdf | ||
| S02 Solicitation Attachment E GLA Specific Requirements.pdf | ||
| S02 Solicitation Attachment A Specifications.pdf | ||
| S02 Solicitation Attachment E GLA Specific Requirements.pdf | ||
| S02 Solicitation 36C26222B0007.pdf | ||
| S02 Solicitation Attachment C Wage Determination.pdf | ||
| S02 Solicitation Attachment D Temporary Traffic Control Standards.pdf | ||
| S02 Solicitation Attachment B Drawings.pdf |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFI # Description Notes
Is FAR Clause 16.203-2 incorporated in the contract? If not would the government consider adding FAR Clause 16.203-2 or another economic price adjustment clause to the contract to address inflation, rising material costs, rising labor costs, rising delivery and other supply-chain related costs?
No
In the Solicitation under Basis for Award section found on page 8 of 66 it is noted, “A single award will be made to the responsible bidder whose bid, conforming to the solicitation, bids the lowest price on the MAIN ITEM, provided that price is reasonable and does not exceed the funding available for the project.” Can the VA advise on the funding amount currently available for the project?
No. The price range has been disclosed in the soliciation IAW VAAR 836.204- Disclosure of the magnitude for construction projects.
Please confirm the CLINs/Bid Items for this project. The Statement of Bid Items in the solicitation (Section 4.1, page 33 of 66) conflicts with the Statement of Bid Items in specification section 01 00 00 (Section 1.3, starting on page 1 of 564).
The Satement of Bid Items in Section 4.1 page 33 is a generic description while the Statement of Bid Items in Spec Section 01 00 00, page 1, paragraph 1.3 further describes some but not all of the significant tasks required within the scope.
The specifications state that the contractor is to provide security guards at the project site during non-construction hours. Will this project require security guards?
No
Bid item 12 states the need for one archeological monitor and one native American monitor for 9 hours per day. Spec section 01 00 00 sub section
1.26 states a requirement for 2 archeological monitors and 1 native American monitor. What is the requirement for archeological and native American monitors?
One archeological monitoring per excavation/trench. If multiple trenching is happening simultaneously then archeological monitoring is required per each.
We feel the project POP of 365 days is a shorter duration than needed to facilitate this project. Would the VA be willing to outline the project into phases such as 45 days between award and NTP for preconstruction activities (i.e. submittals & government review), 365 days for installation, commissioning and turnover of the new dedicated water lines, and 60 days after BOD for closeout?
Please refer to response for RFI #7.
Is the CCD for this project actually 365 calendar days? With the size of the project and the amount of road closures and building tie-ins to be done we do not see this a feasible. We understand from conversations on the job walk that there are deadlines for certain buildings to be occupied and this is the reason for this schedule but can the project timeline be 500 Calendar days?
It is acceptable to VA.
8 Are meters being provided by the utility companies?
DWP will provide meter at service connection points.
The contractor shall provide meters for existing VA buildings.
Developers shall provide meter for existing and future EUL buildings.
Do we know what the existing piping is made of? If not, we have to assume it is of a material that is lead or asbestos containing.
The complete limits of the ACM are unknown. The pipelines we know are ACM are marked in sheet CD-101 along with limits of removal vs abandonment in place.
10 Is soil sampling for contaminants part of this scope?
Typically ACM pipe removal, or any work associated with package 1, does not require soil sampling for contaminants.
Is the Archeological monitors the only one we need to have on site while digging is performed? Do we need to have native American and biological monitors as well?
Refer to question #5
Can we have access to the GIS mapping for the existing utilities on the project?
DWG drawings will be provided after award.
13 Temporary Traffic Control Plan Plan is provided as attachment to this RFI
14 Updated drawings Updated drawings are MD-101, CI-101, MP-102, MP-106 as attached.