36C26123R0014_1.docx
DOCX document 268 KB Posted
- Attached to
- Z1LC-- 640A0-22-903 Repair Steamlines
- Solicitation number
- 36C26123R0014
About this file
This is a Request for Proposal (RFP) for a construction project to repair underground steamlines at a Veterans Affairs medical center campus in Menlo Park, California. The RFP requires removing and replacing approximately 500 linear feet of 2-inch condensate return piping and 100 linear feet of 3-inch high-pressure steam supply and 2-inch condensate piping between manholes at the site. The work must be completed within 180 days of receiving a notice to proceed and is set aside for a Service-Disabled Veteran-Owned Small Business (SDVOSB). Proposals are due by March 24, 2023. The RFP includes specifications for the construction work, contractor qualifications, and other requirements.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C26123R0014 Amendment 0002.docx | DOCX document | |
| SIte Walk Log Steam Lines.pdf | ||
| 36C26123R0014 0001.docx | DOCX document | |
| DIVISONAL COST BREAKOUT SHEET.docx | DOCX document | |
| S02 - RFI FORM.docx | DOCX document | |
| 640.000000.000.MPD-UTILITY EXHIBIT.201323.pdf | ||
| CONTRACTOR CERTIFICATION REGARDING SAFETY AND ENVIRONMENTAL.docx | DOCX document | |
| Previous RFI.docx | DOCX document | |
| mpd steam vault pics.pdf | ||
| VHA Supplemental Contract Requirements for Combatting COVID-19 02.docx | DOCX document | |
| P07 Wage Determination CA20220018 12.16.2022.pdf | ||
| Attachement A - mpd_utility_steam excerpt.pdf | ||
| SPEC 2023.01.30.pdf | ||
| VHA Supplemental Contract Requirements for Combatting COVID-19.docx | DOCX document |
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1. SOLICITATION NUMBER
2. TYPE OF SOLICITATION
3. DATE ISSUED
PAGE OF PAGES
4. CONTRACT NUMBER
5. REQUISITION/PURCHASE REQUEST NUMBER
6. PROJECT NUMBER
7. ISSUED BY
CODE
8. ADDRESS OFFER TO
a. NAME
b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date) 12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
12b. CALENDAR DAYS
13. ADDITIONAL SOLICITATION REQUIREMENTS:
STANDARD FORM 1442 (REV. 8/2014)
STANDARD FORM 1442
Prescribed by GSA-FAR (48 CFR) 52.236-1(d)
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
SOLICITATION
SOLICITATION
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR INFORMATION
CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
SEALED BID (IFB)
NEGOTIATED (RFP)
11. The Contractor shall begin performance within ____________ calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).
YES
NO
a.
Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.
b.
An offer guarantee is, is not required.
c.
All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d.
Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
36C26123R0014
X 02-22-2023
640-23-1-5281-0005
640A0-22-903
Department of Veterans Affairs VA Sierra Pacific Network (VISN 21) VA Sierra Nevada Health Care System 975 Kirman Avenue Reno NV 89502-2597 Proposals have been authorized to be sent electronically to Charee Harris as follows: charee.harris@va.gov and Nicole Renfrew:
nicole.renfrew@va.gov Charee Harris 775-788-5511 Project: 640A0-22-903, Repair Steamlines NAICS Code: 237990 - Other Heavy and Civil Engineer Construction Small Business Size Standard: $45M In accordance with 836.204, Magnitude of Construction is between $500,000 and $1,000,000.00
Project Description: This project is to repair steam tunnels at the Menlo Park Campus.
Place of Performance: VAPAHCS, 795 Willow Road, Menlo Park CA 940205.
A single organized site visit for this RFP is scheduled as follows:
-- Date: March 1, 2023 -- Time: 9:30 AM Pacific Time -- Location: VAPAHCS, 795 Willow Road, Building 334, Menlo Park, CA 94025.
Bid, payment and performance bonds are all required under the RFP and any result contract.
In accordance with established public law, all offerors are required to be registered and current in System for Award Management (SAM), the official website at https://sam.gov/SAM/.
This is a total Service-Disabled Veteran-Owned Small Business (SDVOSB) set-aside under public law 109-461.
Resultant contract will be awarded in accordance with FAR Part 15 -- Contracting by Negotiation.
Contractor shall comply with subcontracting limitations as defined in 13 CFR 125.6.
Wage Determination CA20220018 dated 12.16.2022 applies.
Period of Performance is 180 Days.
X X
52.211-10 X
(1) emailed 10:00
PDT
03-24-2023 X
14. NAME AND ADDRESS OF OFFEROR
15. TELEPHONE NUMBER
16. REMITTANCE ADDRESS
CODE
FACILITY CODE
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
AMENDMENT
NUMBER
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE
21. ITEMS ACCEPTED:
22. AMOUNT
23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
ITEM
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c)( 41 U.S.C. 3304(a) (
26. ADMINISTERED BY
27. PAYMENT WILL BE MADE BY
PHONE:
FAX:
28. NEGOTIATED AGREEMENT
29. AWARD
Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.
shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER
TO SIGN
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE
BY
OFFER
AWARD
STANDARD FORM 1442 (REV. 8/2014) BACK
(Include ZIP Code) (Include area code) (Include only if different than Item 14.)
(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each) (Type or print) (4 copies unless otherwise specified) (Type or print) (Type or print) (Contractor is required to sign this document and return _______ copies to issuing office.)
(Contractor is not required to sign this document.)
(Must be fully completed by offeror) (To be completed by Government)
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
Department of Veterans Affairs VA Sierra Pacific Network (VISN 21) VA Sierra Nevada HealthCare System 975Kirman Avenue Reno NV 89502
Department of Veteran Affairs FMS-VA-2(101) Financial Services Center
PO Box 149971 Austin TX 78714-9971
Charee Harris Contracting Officer NCO 21
Table of Contents
| PART I - THE SCHEDULE | 1 |
| SECTION A - SOLICITATION/CONTRACT FORM | 1 |
| A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair) | 1 |
| A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION, ALTERATION, OR REPAIR)– BACK | 2 |
| SECTION B - SUPPLIES OR SERVICES AND PRICE/COSTS | 15 |
| INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS | 16 |
| INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS | 16 |
| 2.1 52.216-1 TYPE OF CONTRACT (APR 1984) | 21 |
| 2.2 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014) | 21 |
| 2.3 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999) | 21 |
| 2.4 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014) | 23 |
| 2.5 52.228-1 BID GUARANTEE (SEP 1996) | 24 |
| 2.6 52.228-17 INDIVIDUAL SURETY—PLEDGE OF ASSETS (BID GUARANTEE) (FEB 2021) | 24 |
| 2.7 52.233-2 SERVICE OF PROTEST (SEP 2006) | 25 |
| 2.8 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995) | 25 |
| 2.9 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998) | 26 |
| 2.10 VAAR 852.228-72 ASSISTING SERVICE-DISABLED VETERAN-OWNED AND VETERAN-OWNED SMALL BUSINESSES IN OBTAINING BONDS (DEC 2009) | 26 |
| 2.11 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (OCT 2018) | 26 |
| 2.12 VAAR 852.233-70 PROTEST CONTENT/ALTERNATIVE DISPUTE RESOLUTION (OCT 2018) | 27 |
| REPRESENTATIONS AND CERTIFICATIONS | 28 |
| 3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (DEC 2022) | 28 |
| 3.2 52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS AND VIDEO SURVEILLANCE SERVICES OR EQUIPMENT (NOV 2021) | 32 |
| 3.3 52.209-13 VIOLATION OF ARMS CONTROL TREATIES OR AGREEMENTS—CERTIFICATION (NOV 2021) | 34 |
| GENERAL CONDITIONS | 37 |
| 4.1 52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND CERTIFICATIONS (DEC 2014) | 37 |
| 4.2 52.204-23 PROHIBITION ON CONTRACTING FOR HARDWARE, SOFTWARE, AND SERVICES DEVELOPED OR PROVIDED BY KASPERSKY LAB AND OTHER COVERED ENTITIES (NOV 2021) | 37 |
| 4.3 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) | 38 |
| 4.4 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (OCT 2022) | 38 |
| 4.5 52.222-35 EQUAL OPPORTUNITY FOR VETERANS (JUN 2020) | 41 |
| 4.6 52.222-40 NOTIFICATION OF EMPLOYEE RIGHTS UNDER THE NATIONAL LABOR RELATIONS ACT (DEC 2010) | 41 |
| 4.7 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (OCT 2022) | 43 |
| 4.8 SUPPLEMENTAL INSURANCE REQUIREMENTS | 48 |
| 4.9 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998) | 48 |
| 4.10 VAAR 852.201-70 CONTRACTING OFFICER'S REPRESENTATIVE (DEC 2022) | 51 |
| 4.11 VAAR 852.211-72 TECHNICAL INDUSTRY STANDARDS (NOV 2018) | 51 |
| 852.219-73 VA Notice of total set-aside for verified service-disabled veteran-owned small businessES (NOV 2022) | 52 |
| 4.12 VAAR 852.219-75 SUBCONTRACTING COMMITMENTS MONITORING AND COMPLIANCE (JUL 2018) | 56 |
| 4.13 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2018) | 57 |
| 4.14 VAAR 852.236-71 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (APR 2019) | 58 |
| 4.15 VAAR 852.236-79 CONTRACTOR PRODUCTION REPORT (APR 2019) | 59 |
| 4.16 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 2019) ALTERNATE I (APR 2019) | 59 |
| 4.17 VAAR 852.242-70 GOVERNMENT CONSTRUCTION CONTRACT ADMINISTRATION (OCT 2020) | 60 |
| 4.18 VAAR 852.242-71 ADMINISTRATIVE CONTRACTING OFFICER (OCT 2020) | 61 |
| 4.19 VAAR 852.243-70 CONSTRUCTION CONTRACT CHANGES—SUPPLEMENT (SEP 2019) | 62 |
| 4.20 IT CONTRACT SECURITY | 63 |
| 4.21 OTHER ATTACHMENTS | 73 |
| 4.22 VAAR 852.203-70 COMMERCIAL ADVERTISING (MAY 2018) | 74 |
| 4.23 VAAR 852.204-70 PERSONAL IDENTITY VERIFICATION OF CONTRACTOR PERSONNEL (MAY 2020) | 74 |
| 4.24 VAAR 852.228-70 BOND PREMIUM ADJUSTMENT (JAN 2008) | 74 |
| 4.25 VAAR 852.232-70 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (WITHOUT NAS– CPM) (NOV 2018) | 74 |
SCOPE OF WORK
PROJECT #640A0-22-903
“Replace Underground Steam Lines”
1. General Intent
1.1 The contractor shall provide all tools, materials, supervision, other items, and services necessary to provide a complete turnkey replacement of the outdated, leaking and energy deficient steam lines in two (2) separate locations at the VAPAHCS Menlo Park Division 795 Willow Road Menlo Park, CA 94025. (see attachments)
1.1. The contractor shall perform to the standards of this contract. This project shall take no longer than 180 days from the notice to proceed to complete.
1.2. This project encompasses underground work on the existing steam supply & condensate return system for building domestic hot water and space heating (HVAC) to direct patient care areas.
1.3. This project shall be coordinated with the appointed COR (Contracting Officers Representative) to ensure minimal interruption to DIRECT PATIENT CARE.
1.4. Contractor shall abide/ follow all current accepted/ applicable codes, standards, practices, and policies in use at the VAPAHCS at the time of the notice to proceed. In the event of overlapping or conflicting codes, standards etc. the COR is the authority having jurisdiction (AHJ) having the final decision, work shall continue at no additional cost to the government.
2. Summary of Major Tasks.
2.1. The contractor shall survey the existing condition of roadways, walkways, patios, landscaping, vegetation etc. in each work locations and provide pictures of the surveyed areas of work to the project COR before beginning work. Contractor shall restore all locations back to the original site condition and minimize excavation/ exposure. Due to patient privacy concerns no pictures shall be taken without the Contracting Officers written approval and taken in the COR’s presence.
2.2. Contractor shall provide a detailed and expanded contract schedule per specification 01 00 00 General Requirements to the CO as an evaluation factor and resubmit an updated copy after award to the COR.
2.3. Contractor provides all material submittals for prior approval to COR before actual purchase.
2.4. The contractor shall identify all existing underground utilities i.e., electrical, natural gas, water, Fire Protection, sewer, communications systems etc. before work begins in the work areas.
2.5. Contractor shall provide shop drawings of new steam pipe installations.
2.6. Contractor shall Saw-cut and remove existing asphalt/ pavement, concrete walkways/ patios and existing (old) steam piping etc. as needed. Disposal of materials is at the contractor’s expense.
2.7. Backfill trenches and compact the dirt to 95% compaction in roadways and 75% compaction in planter beds, reuse of dirt shall be permitted.
2.8. Contractor shall be responsible for maintaining safe work conditions to include but not limited to traffic control, trenching/ trenches, steam lines and manholes etc. Open trenches, welding etc. shall be protected from patients, staff, visitors, and vehicle traffic at all times.
2.9. Open trenches shall be covered with the appropriate material and area left in a clean safe condition at the end of each workday.
2.10. All manhole penetrations shall be sealed and watertight.
2.11. Contractor shall provide a weekly summary report of completed and projected tasks. Format to be approved by COR.
2.12. Contractor shall be required to attend the standard VAPAHCS shutdown safety meeting held at the Palo Alto Division Building 6 conference room number C-341 @ 1:00pm on the Friday before each and every shutdown.
2.13. Contractor is responsible for safely securing the work site during and after-hours, on-site security is not required.
2.14. Contractor shall provide traffic detour signage as required when closing roadway or walkways for each location, signage and posting plan shall be submitted to the COR for review and approval prior to posting.
3.0 Summary of the Scope of Work
3.1. Location #1 Remove and Replace approximately five hundred (500) linear feet of 2” condensate return piping between manholes 2-9 and 2-10. Work process is in the road between building 303 and 332 on Shoppe Lane. This section of steam line is beneath the existing road and will require road closure and pedestrian protection.
3.2. Location #2 Remove and Replace approximately one hundred (100) linear feet of 3” high pressure steam supply and 2 ½” condensate piping between manholes 2-1 and 2-0. NOTE Loading dock of Building 331 will be inaccessible.
3.3. Replace all excavated fill, base, road, and sidewalk removed for access to the lines per the applicable specifications and standards.
4.0 Quality Control
| 4.1. | The Contractor shall implement and maintain a complete quality control (QC) program so that all requirements are provided for as specified in all sections of this contract. The Contractor’s QCP shall include but not be limited to the following: |
| 4.1.1. | A statement describing how the Contractor will meet the basic requirements of this contract (including staffing levels, time of response) shall be provided to the COR fifteen (15) days after effective date of contract award and whenever there are major turnover of personnel. A major turn-over is two or more employees. |
| 4.1.2. | A method for identifying deficiencies in the quality of services performed before the performance deficiency becomes unacceptable. The QCP shall contain processes for corrective actions without dependence upon Government direction and shall maintain records of all Contractor QC inspections and corrective actions. |
| 4.1.3. | A method of recording or logging the activities of the Contractor, which would demonstrate the Contractor's ability to maintain the minimum requirements of this contract. |
| 4.1.4. | Three copies shall be submitted to the COR within 5 working days when changes are made thereafter. After acceptance of the quality control plan, the Contractor shall receive the COR’s approval in writing of any proposed change to the QAP. |
| 5.0 | Hours of Operation – Location – |
| 5.1. | The Contractor is responsible for conducting business during normal hours between 7:00 am to 6:00 pm, Monday thru Friday except on Federal holidays or when the Government facility is closed due to local or national emergencies, administrative closings, or similar Government directed facility closings. |
NOTE: Loud noise such as operating heavy equipment, vehicle traffic, asphalt/ concrete cutting etc. shall not be permitted between the hours 7:00am – 8:00am Monday thru Friday.
| 5.1.2. | Contractor shall provide requests of critical tasks involving utility shutdowns a minimum of four weeks in advance to the COR. Utility shutdown shall not continue without the COR’s approval. |
| 5.1.3. | Federal Holidays. The Contractor shall not work on recognized holidays: New Year’s Day, Martin Luther King Day, President’s Day, Memorial Day, Independence Day, Labor Day, Columbus Day, Veterans Day, Thanksgiving Day, Christmas Day, and any other day designated by the President. |
| 5.1.4. | Place of Performance: The work shall be performed at the VA Menlo Park Medical Center located at 795 Willow Road Menlo Park, CA 94025 |
| 6.0 | Security Requirements |
| 6.1. | The Contractor shall wear and display temporary ID badges to be provided by the VA Police IAW Health Care System (HCS) Memorandum (Memo) No. 07-10-14, Attachment C. |
| 6.1.2. | Physical Security. The Contractor shall safeguard government equipment, information and property provided for Contractor’s use. The Contractor shall secure government facilities, equipment, and materials at the end of each work period. |
| 6.1.3. | Key Control. There shall be no government keys issued on this contract/ project. |
| 6.1.4. | Lock Combinations. The Contractor shall establish and implement methods of ensuring that all lock combinations are not revealed to unauthorized persons. The Contractor shall ensure that lock combinations are changed when personnel having access to the combinations no longer have a need to know such combinations. These procedures shall be included in the Contractor’s QAP. |
| 7. | Qualifications of Contractor Personnel |
| 7.1. | The Contractor shall be fully staffed on the first day of contract performance and prepared to maintain a fully trained staff through the life of the contract. The Contractor shall have sufficient and qualified staff to begin work on effective date of contract. |
| 7.1.2. | Project Manager. The Project Manager (PM) shall be physically on-site during normal work hours and shall be responsible for performance of all work. The PM shall possess a minimum of eight years’ experience within the last ten years. PM’s work experience should be similar to the size and magnitude of this contract and fully conversant in the English language. |
| 7.1.3. | Post Award Conference and Periodic Progress Meetings. The Contractor shall attend the post award conference and periodic progress meetings as scheduled by the COR. The CO, COR, and any other Government personnel, as appropriate, may meet periodically with the contractor to review the contractor's performance. |
| 7.1.4. | The Contractor shall submit a resume of qualifications to the COR for key personnel proposed for the project. All Contractor employees will be approved by the COR prior to start of work. If, at any time from date of award to the end of the contract, a non-key Contractor personnel is no longer available, the COR has the right to accept or reject new personnel. |
| 7.1.5. | Removal of Personnel. The Contractor shall remove any employee from the performance of this contract immediately upon receipt of CO notice. The Contractor employees shall be removed immediately when he/she is involved in a violation of the Terms and Conditions of the contract, criminal behavior, violation of VA security, confidentiality requirements and/or other disciplinary reasons. |
8.0 Contracting Officer Representative (COR)
| 8.1. | Designation of COR. Upon award of the contract the Contractor will receive a copy of the COR Delegation Letter. The letter will state the responsibilities and limitations of the COR, especially with regard to changes in cost or price, estimates or changes in delivery dates. The COR is not authorized to change any of the terms and conditions of the resulting order. |
| 8.1.2. | The COR will be authorized to perform the following functions |
| 8.1.3. | Monitor and inspect Contractor’s performance |
| 8.1.4. | Maintain written and oral communications with the Contractor concerning technical aspects of the contract |
| 8.1.5. | Issue written interpretations of technical requirements, including Government drawings, designs, and specifications |
| 8.1.6. | Communicate with the CO and the Contractor of any deficiencies |
| 8.1.7. | Coordinate availability of government furnished property |
| 8.1.8. | Provide site entry of Contractor personnel. |
9.0 Definitions and Acronyms used in SOW
| 9.1. | Contractor - A supplier or vendor awarded a contract to provide specific supplies or service to the government. The term used in this contract refers to the prime. |
| 9.2. | Contracting Officer (CO) - The person with the authority to enter into, administer, and or terminate contracts, and make related determinations and findings on behalf of the government. Note: The only individual who can legally bind the government. |
| 9.3. | Contracting Officer Representative (COR) – A VA employee delegated by the CO to administer the contract. The delegation will be in writing and will state the scope of authority and limitations. The COR will have the authority to provide technical direction to the Contractor as long as that direction is within the scope of the contract, does not constitute a change, and has no funding implications. The COR do not have the authority to change the terms and conditions of the contract. |
| 9.4. | Deliverable - Anything that can be physically delivered but may include non-manufactured things such as meeting minutes or reports. |
| 9.5. | Key Personnel – Those individuals identified to be important to the Contractor’s performance. |
| 9.6. | Physical Security - Actions that prevent the loss or damage of Government property. |
| 9.7. | Quality Assurance - The government procedures to verify that services being performed by the Contractor are performed according to acceptable standards. |
| 9.8. | Quality Assurance Surveillance Plan (QASP) - An organized written document specifying the surveillance methodology to be used for surveillance of contractor performance. |
| 9.9. | Quality Control Plan – The Contractor’s plan to ensure the necessary measures are taken to meet the terms and conditions of the contract. |
| 9.10. | Sub-contractor - One that enters into a contract with a prime contractor. The Government does not have “privity of contract” with the subcontractor. |
| 9.11. | Workday - The number of hours per day the Contractor provides services IAW with the contract. |
| 9.12. | Work week - Monday through Friday, unless specified otherwise. |
| 9.13. | Random Sampling – One of many methods used by the COR to monitor the Contractor’s work and performance. |
| 9.14. | 100% Inspection – This method will be used for tasks that occur infrequently. The COR or designated representative will inspect and evaluate performance. |
| 9.15. | Periodic Surveillance – This method is used to evaluate on a periodic basis such as monthly, quarterly, or semi-annually. |
| 9.16. | Acronyms commonly used |
| ACOR | Alternate Contracting Officer's Representative |
| CCE | Contracting Center of Excellence |
| CFR | Code of Federal Regulations |
| CONUS | Continental United States (excludes Alaska and Hawaii) |
| CO | Contracting Officer |
| COR | Contracting Officer Representative |
| COTS | Commercial-Off-the-Shelf |
| FAR | Federal Acquisition Regulation |
| HIPAA | Health Insurance Portability and Accountability Act of 1996 |
| IAW | In Accordance With |
| OCI | Organizational Conflict of Interest |
| PIPO | Phase In/Phase Out |
| POC | Point of Contact |
| PRS | Performance Requirements Summary |
| SOW | Performance Work Statement |
| QA | Quality Assurance |
| QAP | Quality Assurance Program |
| QASP | Quality Assurance Surveillance Plan |
| QC | Quality Control |
| QCP | Quality Control Program |
| SOW | Statement of Work |
TBD To Be Determined
| TE | Technical Exhibit |
| VAPAHCS | VA Palo Alto Health Care System |
| 10. | Government Property, Facilities, Equipment and Other Services |
| 10.1. | Shut-Down Utility Services. The Government will provide manpower to assist in the shutdown of utility systems where the Contractor is required to service only through approved utility shutdown request. Shutdown requests shall be submitted to the COR no later than 4 weeks in advance and approved by the COR before work will commence. Shutdowns will not be authorized on holiday weekends (usually 3 days in length). |
| 10.2. | Using Government facilities during performance: |
| 10.2.1. | The Contractor shall be in proper attire (shirt and shoes required). The Contractor shall make every effort to keep the areas clean and tidy. The Contractor shall clean-up areas after each day’s work. NOTE Access to patient areas is prohibited. |
| 10.2.2. | Latrines Usage. The Contractor is permitted to use the VA toilet facilities within building 370 (maintenance shop), however, the Contractor will ensure that the facilities are kept clean and will be responsible for any damage done by the Contractor’s workers. |
| 10.2.3. | Parking. The Contractor shall adhere to the rules and regulations of the station when parking within the facility. |
| 10.2.4. | Specific parking areas may be assigned to the Contractor. Violators will be ticketed. The Contractor shall not use parking spaces reserved for engineering vehicles or lawn areas or “back in” into a parking space. |
| 10.2.5. | Contractor Deliveries. The COR will assign routes for the delivery of materials and supplies to the job site. The Contractor or construction traffic will not block any road or street, walk or building egress without requesting approval in a timely manner. |
| 10.2.6. | Loading and unloading. Building loading docks and landings may be used to load or unload construction materials when approved by the COR. However, any vehicle left unattended for more than a few minutes may be cited by the VA Police. Some areas may be reserved for VA operations only during certain hours. |
| 10.2.7. | VA Police. The VA Police are Federal Police Officers with full authority to make arrests, investigate crime, and to issue citations. Citations issued for driving, parking violations or other offenses may require an appearance in the Federal District Court and/or payment of a fine. |
| 10.2.8. | Speed Limits. For the safety of patients, speed limits and other driving and parking codes will be strictly enforced. The speed limit on VA roads is 15 MPH under ideal conditions. In parking lots, the speed limit is 5 MPH. |
| 10.2.9. | Locked Areas. The Contractor is to coordinate access to locked areas with the COR, including obtaining keys required for access to work sites. All buildings at the VAMC are locked during other than normal work hours. When the Contractor has approval to work other than normal work hours, he will need to make arrangements for his workers to have access to job sites. |
10.2.10. Operations and Storage Areas will be confined to areas designated by the COR or approved in writing by the COR. The Government will not be responsible for tools, equipment or other materials left or stored on Government facilities, unless exceptions are provided in the contract.
10.2.11. Utilities. The VA will provide utilities in the facility and will be available for the Contractor to use in the performance of the contract. The Contractor shall exercise conservation practices. The Contractor is expected to turn off water faucets or valves after use. The Contractor is required to utilize GFCI protectors with all plugged in equipment. The Contractor is required to hardwire temporary power distribution boxes when large electrical loads are required to prevent tripping breakers and interrupting service.
| 10.3. | The Contractor shall NOT turn-on or turn-off any utility service such as water, gas, medical air and gas, steam, sewer, electric, fire protection or communication without prior approval of the Chief of Engineering, VAPAHCS. This includes those interruptions required by the contract. |
| 10.4. | Shutdowns. Written requests for utility shutdowns shall be completed by the Contractor and submitted to the COR at least four weeks before the scheduled work. Lock-out / tag-out (LOTO) shall be strictly adhered to on any disruption or shut-down of any energy source. Any emergency requiring an immediate shutdown shall be reported to the COR. The COR will notify the engineering office and the appropriate Chief, Maintenance and Repair or site designee. The Contractor shall prepare and forward to the COR or designated representative, a written report of the situation, why it happened, a schedule of any further corrective work needed, and what, if any steps will be taken to prevent a recurrence. |
| 10.5. | Government Furnished Equipment (GFE). The VA will not provide any equipment or materials to be used in this contract. |
| 11. | Contractor Furnished Equipment (CFE) and Responsibilities |
| 11.1. | Secured worksites. The Contractor shall secure the worksite and provide construction safety and infection control barriers, including but not limited to temporary fencing, trench covers, etc. or wherever work may cause injury to workers, patients, visitors, and VA personnel. |
| 11.1.1. | The Contractor shall conform to the rules and regulations as set forth by OSHA Safety and Health Standards, 29 CFR Part 1926 - Safety and Health Regulations for Construction and Title 8, California Administrative Code - Construction Standards. When the standards differ, the more restrictive standard shall apply, COR shall make the final determination. Construction site signage is required. Construction sites outside of existing structures shall be enclosed by 6 feet tall metal fencing. |
| 11.2. | CFE Equipment, Supplies and Materials: The Contractor shall furnish materials, supplies, and equipment necessary to meet the requirements under this SOW. |
| 11.2.1. | Protective Clothing/Equipment. The Contractor shall wear and use protective clothing and gear when required. This includes hard hats, goggles, protective shoes, gloves, harnesses, masks or breathing apparatus, etc. |
| 11.2.2. | Telephones. The VA will not provide phones to the Contractor. However, the Contractor may use the VA telephone lines to contact the COR, the Engineering Service office, or when authorized by the COR, to call their office concerning contract matters. Telephone calls for the Contractor will not be accepted by the VA. |
| 11.3. | Waste and Debris. The Contractor shall remove any waste and debris created in executing the contract and shall dispose the waste outside of the VAMC. The Contractor may bring in a bin or dumpster for waste, however, must have the COR’s written approval prior to locating the bin at a specific location. Contractor’s debris shall be covered when taken from work sites to dump area. This is critical when carried through patient care areas. |
| 12. | Specific Tasks to the Major Tasks in SOW 2.0 |
| 12.1. | Mobilization-The Contractor shall provide the COR with a request for laydown area to include but not be limited to area and description of what will be placed. The COR shall identify Contractor Laydown and parking location after the request is reviewed and accepted. |
| 12.1.1. | The contractor shall install temporary fencing per Specs 01-00-00-6 section 1.6. (F) Operations and Storage areas |
| 12.2. | Storage- Contractor shall determine storage requirements and install in designated laydown area identified by COR. |
| 12.3. | Contractor shall gather all tools, machinery, and equipment to perform required services within this SOW securing in storage container/area. |
| 12.4. | Provide required documents as stated in section 3.0 of the SOW. |
| 12.5. | Install Safety signage per specification 10-00-00-21 section 1.30 Safety sign(s). |
| 12.6. | Site Preparation |
| 12.6.1. | The COR shall identify the work zone, new equipment location and location restraints. |
| 12.6.2. | The Contractor shall identify work hazards IAW OSHA Hazard communication standard (29 CFR 1910.1200). |
| 12.6.3. | The Contractor shall protect existing vegetation, structures, equipment, utilities, and improvements per specification 01 00 00.1.10. |
| 12.7. | Demobilization Activities |
| 12.7.1. | Clean Up Responsibility. The Contractor shall clean and remove all debris, trash, supplies, equipment and CFE property upon completion of project. Clean up activities includes the disassembly, removal, and site cleanup of offices, buildings, and other facilities assembled on the site. The Contractor shall NOT dispose the waste and debris on VA property to include the VA trash containers or dumpsters. The Contractor may provide its own trash bin or dumpster with prior approval from the COR. Location of Contractor’s bin will be decided by the COR. |
| 12.7.2. | Clean-Up. The Contractor shall not allow waste or debris to accumulate in facility corridors or any other building areas where it may pose a safety hazard. Debris and trash shall be covered when it is transported through patient care areas. Contractor shall adhere to up IAW Section 01 00 00.1.8 Infection Prevention Measures and clean up sections of related work specifications. |
| 12.7.3. | The Contractor shall restore any damage to vegetation, structures, equipment, utilities, and improvements per Section 01 00 00.1.11 |
| 12.8. | Documentation |
| 12.8.1. | Work plan. The Contractor shall submit a work plan outlining the company plans to complete a quality project within a given amount of time and in compliance with this firm fixed price contract. |
| 12.8.2. | Schedule. The Contractor shall submit project schedule IAW Section 01 32 13 16.15 Project Schedules and simplified three-week look-ahead schedule. |
| 12.8.3. | Submittals. The Contractor shall submit project submittals per Section 01 03 23 Shop Drawings, Product Data, and Samples for COR approval. |
| 12.8.4. | Quality Control Plan. The Contractor shall outline the procedures that the contractor will use to ensure that a high-quality product is produced for this contract. See SOW 3.0. |
| 12.8.5. | Safety Plan. The Contractor shall outline the safety procedures that comply with applicable federal, state, and local laws, the Occupational, Safety and Health Act (OSHA) (Public Law 91-596) and the resulting standards, OSHA Standards 29 CFR 1910 and 1926, as applicable, and the protection of their employees. Additionally, the Contractor is responsible for the safety and health of all subcontractor employees. |
| 12.8.6. | Meeting minutes. The Contractor shall record and track meeting minuets and submit to COR for editing and approval. |
| 12.8.7. | Inspection records. The Contractor shall submit weekly inspection testing and reports to COR. |
| 13. | Applicable Publications |
| 13.1. | The Contractor shall abide by the applicable regulations, publications, manuals, and local policies and procedures as set forth in the Terms and Conditions of this contract. |
14.0 Deliverable Schedule
| Deliverable |
| Frequency |
| Format |
| Submit To |
| Work plan |
| Updated weekly submissions |
| Electronic |
| COR |
| Schedule |
| Updated weekly submissions |
| Electronic |
| COR |
| Submittals |
| Daily |
| Electronic |
| COR |
| Quality control plan |
| 15 days post award, updated as needed/changes occur |
| Electronic |
| COR |
| Safety plan |
| 15 days post award |
| Electronic |
| COR |
| Meeting minutes |
| Weekly |
| Electronic |
| COR |
| Inspection records |
| Weekly |
| Electronic |
| COR |
| Shutdown request |
| 28 Days prior to shutdown date requested |
| Electronic |
| COR |
Page 1 of Page 1 of
SECTION B - SUPPLIES OR SERVICES AND PRICE/COSTS
SECTION B PRICE SCHEDULE
CLIN 0001 – Project Replace Steam Tunnels $____________________________
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS
PROPOSAL SUBMISSION:
The following documents are to be included in the Request for Proposal (RFP) submission:
One (1) original completed Proposal amount entered in block 17 of the SF1442 Offer page.
One (1) fully completed Supplemental Price Breakdown by Division Sheet
One (1) fully completed and signed SF 1442 Offer page, acknowledgment of all amendments either via entering data in block 19 of the SF1442 or completing blocks 15a, b, and c of the Amendment and attaching to the SF 1442 Offer page.
One (1) original completed/signed SF 24 Bid Bond (scanned PDF is acceptable for email, with original wet signature original due to the Contracting Officer within 3 calendar days after closing).
One (1) Documentation of Safety & Environmental Record and Documentation of Experience Modification Rate (EMR) (See below instructions).
Offerors are responsible for ensuring and verifying their price and all required documents are received at the email address designated in block 8 of the SF 1442 Solicitation and by the date and time specified in block 13A of the SF 1442 Solicitation (subject to amendment). Any exception to the terms and conditions of this request for quotation will result in a nonresponsive quotation.
PROPOSALS ARE TO BE SENT TO:
One (1) electronic copy via email of the price proposal are to be sent to arrive on or before the due date/time at the following email address:
Proposals have been authorized and are to be sent by email to Charee Harris, charee.harris@va.gov Solicitation number and title must be in the title of the email. Faxed quotations are not permitted.
REQUESTS FOR INFORMATION (RFI):
To obtain clarifications and/or additional information concerning the contract requirements or specifications, submit a written Request for Information (RFI) utilizing the RFI Form included in this RFP, which is to be sent via email to charee.harris@va.gov. See RFI form for specifics.
RFI responses will be responded to as necessary in amendment format, which will posted/e-mailed to all concerned.
Deadline for submission of RFIs for this solicitation is March 15, 2023, at 10:00 AM PDT. No questions will be answered after this date/time unless determined to be in the best interest of the Government as determined by the Contracting Officer. Telephone requests for information will not be accepted or returned.
PROPOSAL DUE DATE SCHEDULE:
Proposal volumes and the electronic copy are due by the date and time set for the receipt of quotations shown in Block 13 of the SF 1442.
INSTRUCTIONS TO OFFERORS:
Proposals received after March 24, 2023, at 10:00 AM PDT may be rejected.
Any exception to the terms and conditions of this RFP will result in a nonresponsive quotation.
Failure to provide a definitive price or conditioned price will result in a nonresponsive quotation. Receipt of a Price Quotation must be in accordance with terms and conditions of this RFP. Offerors must acknowledge (in writing only) amendments to this solicitation, otherwise a quotation may be determined nonresponsive.
The apparent successful offeror must be determined as “responsible” by the Contracting Officer in accordance with FAR Part 9, Contractor Qualifications.
SITE VISIT:
Potential Offerors are strongly urged and expected to inspect the site where services are to be performed and to satisfy themselves regarding all general and local conditions that may affect the cost of performing construction services. Failure to inspect the site shall not constitute grounds for a claim after contract award.
See Provision 52.236-27 for specific information regarding the project pre-offer site visit, which will be the only opportunity for potential Offerors to visit the site. All potential Offerors, subcontractors, and suppliers are strongly encouraged and expected to attend the pre-offer site visit.
BID GUARANTEE:
A bid guarantee is required in an amount not less than 20 percent of the bid price but shall not exceed $3,000,000.00. Failure to furnish the required bid guarantee in the proper form and amount, by the time set for the opening of bids, will require rejection of the bid in all cases except those listed in FAR 28.101-4, and may be cause for rejection even then.
PERFORMANCE & PAYMENT BONDS:
In accordance with FAR 28.102-1 and Contract Clause 52.228-15, offerors are reminded that any award amount over $35,000 shall require a Payment Bond (or other acceptable protection – see clause FAR 52.228-13), and awards exceeding $150,000 shall require both Payment and Performance Bonds. All bonds are due no later than 10 calendar days after award.
LIQUIDATED DAMAGES: N/A
WAGE DETERMINATION APPLICABLE TO THIS PROJECT:
General Decision Number: CA20200018 12/16/2022 PER VHA DIRECTIVE 7715 (06 April 2017) SAFETY & ENVIRONMENTAL RECORD AND EXPERIENCE MODIFICATION RATE (EMR):
To be eligible for consideration and award, the contractor shall have no more than three serious, or one repeat, or one willful OSHA or EPA violation(s) in the past 3 years and have an EMR of equal to or less than 1.0.
All contractors shall submit the following information pertaining to their past Safety & Environmental Record and EMR with their quotation.
1. SAFETY & ENVIRONMENTAL RECORD: A self-certification on company letterhead that the contractor has no more than three (3) serious, or one (1) repeat or one (1) willful OSHA or any EPA violation(s) in the past three years.
1. EMR: All contractors shall submit information regarding their current EMR. This information shall be obtained from the contractor’s insurance carrier and be furnished on the insurance carrier’s letterhead. Must have an EMR of equal to or less than 1.0.
PRIVACY TRAINING:
All workers regardless of project length must take VA Privacy Training which will be coordinated after project award with the Contracting Officer’s Representative (COR).
TRAINING:
All employees of the general contractor and subcontractors shall have the 10-hour OSHA certified construction safety course and/or other relevant competency training, as determined by the COR with input from the ICRA (Infection Control Risk Assessment) team. The General Contractor’s Competent Person/Superintendent shall have completed the 30-hour OSHA certified construction safety course. Documentation of training shall be submitted to the Contracting Officer for review and approval prior to any work being performed. No ID badge will be issued to an employee who does not provide this documentation. There shall be no exceptions to this requirement.
PRIVACY AND CONFIDENTIALITY:
Contractors to the Department of Veteran Affairs may be unintentionally exposed to sensitive information. Information may be overheard, seen on documents or electronic devices, or observed that could potentially violate the privacy and confidentiality of our veterans, employees, volunteers, and their families. Regulations such as, but not limited to the Health Insurance Portability and Accountability Act of 1996 (HIPAA), Freedom of Information Act (FOIA) and Privacy Act of 1974 have been enacted to protect sensitive information from being improperly disclosed. Information should not be divulged or released to anyone unless specifically authorized by this contract or its’ attached documents in accordance with the contracted services. Failure to comply with applicable statutes and regulation can result in the termination of this contract and civil and criminal penalties, including fines and imprisonment. All suspected or actual breeches of privacy and confidentiality should be reported immediately to the Contracting Officer, Contracting Officer’s Representative (COR) or the Facility Privacy Officer.
The C&A requirements do not apply, and a Security Accreditation Package is not required. If the contractor opts to use a computer or computer system for processing contract documents, the requirements of FIPS 140-2 for encryption of contract documents must be met.
PLANS/SPECIFICATIONS/DRAWINGS:
Drawings and specifications are attached in electronic format to this solicitation. Contractors are responsible for downloading and printing their own plan sets. The VA will not provide hard copies of the drawings and specifications to any Contractor. Contractors are responsible for ensuring that any construction document package used for their quotation or construction is complete and up to date.
BRAND NAME OR EQUAL:
The RFQ may include the salient characteristics of the “or equal” aspect for determination of what is equal to any cited brand name. See FAR 52.211-6 for “brand name or equal” information. This is an extremely long, detailed, and comprehensive RFQ, including all specifications and drawings. Please note that, wherever a brand name is cited, contractor shall ensure, in any resultant contract, that any equal has the salient characteristics of the brand name. Lack of confirmation shall be grounds for Government inspection at any time and Government direction for replacement of materials or equipment by the Contractor at no increase in contract price or time.
SYSTEM FOR AWARD MANAGEMENT (SAM):
Federal Acquisition Regulations require that federal contractors register in the System for Award Management (SAM) database at http://www.sam.gov and enter all mandatory information into the system. Award cannot be made unless the contractor is registered. Contractors are encouraged to ensure that they are registered in SAM prior to submitting their quotation.
ADDITIONAL VETBIZ INFORMATION:
1. Eligibility of SDVOSBs continues to be governed by the Small Business Administration regulations, 13 CFR subparts 125.8 through 125.13, as well as the FAR, except where expressly directed otherwise by the VAAR, and 38 CFR verification regulations for SDVOSBs.
2. At the time of submission of offer, the offeror must represent to the contracting officer that it is a—
a. SDVOSB concern
b. Small business concern under the North American Industry Classification System (NAICS) code assigned to the acquisition; and
c. Verified for eligibility in the VIP database.
3. A joint venture may be considered an SDVOSB or VOSB concern if,
a. At least one member of the joint venture is an SDVOSB or VOSB concern and makes the representations in paragraph (b) of this section.
b. Each other concern is small under the size standard corresponding to the NAICS code assigned to the procurement.
c. The joint venture meets the requirements of paragraph 7 of the size standard explanation of affiliates in FAR 19.101; and
d. The joint venture meets the requirements of 13 CFR 125.15(b), modified to include Veteran-owned small businesses where this CFR section refers to SDVOSB concerns.
4. Any SDVOSB or VOSB concern (nonmanufacturer) must meet the requirements in FAR 19.102(f) to receive a benefit under this program.
JOINT VENTURES: See 13 C.F.R. § 121.103 Affiliation based on joint ventures: A joint venture is an association of individuals and/or concerns with interests in any degree or proportion consorting to engage in and carry out no more than three specific or limited-purpose business ventures for joint profit over a two-year period, for which purpose they combine their efforts, property, money, skill, or knowledge, but not on a continuing or permanent basis for conducting business generally.
This means that a specific joint venture entity generally may not be awarded more than three contracts over a two-year period, starting from the date of the award of the first contract, without the partners to the joint venture being deemed affiliated for all purposes. Once a joint venture receives one contract, SBA will determine compliance with the three awards in two years rule for future awards as of the date of initial offer including price.
As such, an individual joint venture may be awarded more than three contracts without SBA finding general affiliation between the joint venture partners where the joint venture had received two or fewer contracts as of the date it submitted one or more additional offers which thereafter result in one or more additional contract awards. The same two (or more) entities may create additional joint ventures, and each new joint venture entity may be awarded up to three contracts in accordance with this section. At some point, however, such a longstanding inter-relationship or contractual dependence between the same joint venture partners will lead to a finding of general affiliation between and among them.
For purposes of this provision and in order to facilitate tracking of the number of contract awards made to a joint venture, a joint venture must be in writing and must do business under its own name, and it may (but need not) be in the form of a separate legal entity, and if it is a separate legal entity it may (but need not) be populated (i.e., have its own separate employees). SBA may also determine that the relationship between a prime contractor and its subcontractor is a joint venture, and that affiliation between the two exists, pursuant to paragraph (h)(4) of this section.
RESPONSIBILITY REQUIREMENTS:
A responsibility check will be accomplished for the apparent awardee prior to award. Checks of the VIP database (to insure apparently successful offeror is a verified Service-Disabled Veteran Owned Small Business), System for Award Management (SAM) database (Central Contractor Registration, Online Representations and Certifications, and Excluded Parties List System to ensure registrations are current, valid, and no debarment records exist). Any information retrieved or received by the Government that would be cause for negative or unsatisfactory responsibility rating may result in the offeror being determined ineligible for award.
CONFORMANCE WITH ENVIRONMENTAL MANAGEMENT SYSTEMS:
The Contractor shall perform work under this contract consistent with the relevant policy and objectives identified in the agency, organizational, or facility Green Environmental Management System (GEMS) applicable for your contract. The Contractor shall perform work in a manner that conforms to all appropriate Environmental Management Programs and Operational Controls identified by the agency, organizational, or facility GEMS, and provide monitoring and measurement information as necessary for the organization to address environmental performance relative to the environmental, energy, and transportation management goals. In the event an environmental nonconformance or noncompliance associated with the contracted services is identified, the contractor shall take corrective and/or preventative actions. In the case of a noncompliance, the Contractor shall respond and take corrective action immediately.