Logistics Mechanical Drawings-small.pdf

PDF 3 MB Posted

Attached to
R408--VASNHS-Las Vegas | Construction and Project Management Services 100% SDVOSB Set-Aside
Solicitation number
36C26122Q0743
Issued by

About this file

This solicitation is for construction and project management services at the Veterans Affairs Medical Center in Las Vegas, Nevada. The opportunity is set aside 100% for Service-Disabled Veteran-Owned Small Businesses. The work includes construction and renovation services at the Las Vegas VAMC. The period of performance is one base year with four one-year options. Proposals are due by June 26, 2022. The Veterans Health Administration and Veterans Integrated Service Network 21 are the agencies responsible for the contract. Pricing will be fixed price.

View the file

Other files

File Type Posted
230800 CxHVAC Systems.docx DOCX document
019100 Gen Cx Reqs .docx DOCX document
Assignment 2 - Logistics HVAC Commissioning.docx DOCX document
36C26122Q0743 0002.docx DOCX document
36C26122Q0743 0001.docx DOCX document
36C26122Q0743.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

F

SD

A/E ARCHITECT / ENGINEER

AAHX AIR TO AIR HEAT EXCHANGER

AB AIR BLENDER

AAV AUTOMATIC AIR VENT

ACC AIR-COOLED CONDENSER

ACCH AIR-COOLED CHILLER

ACCU AIR-COOLED CONDENSING UNIT

ACU AIR CONDITIONING UNIT

ACD AUTOMATIC CONTROL DAMPER,

MODULATING

ACD-TP AUTOMATIC CONTROL DAMPER,TWO

POSITION

AD ACCESS DOOR

AF AFTER FILTER

AFCV AIR FLOW CONTROL VALVE

AFF ABOVE FINISHED FLOOR

AFMD AIR FLOW MEASURING DEVICE

AFW AIR FOIL WHEEL (FAN)

AHU AIR-HANDLING UNIT

AMP AMPERGE

AP ACCESS PANEL

APD AIR PRESSURE DROP

ARI AIR CONDITIONING AND

REFRIGERATION INSTITUTE

AS AIR SEPARATOR

ASME AMERICAN SOCIETY OF MECHANICAL

ENGINEERS

AW AIR WASHER

AXF AXIAL FLOW

B BOILER

BD BUTTERFLY DAMPER

BDD BACKDRAFT DAMPER

BDR BASE BOARD RADIATOR

BFP BACKFLOW PREVENTER

BFT BOILER PLANT FIRE TUBE

BHP BRAKE HORSEPOWER

BHW HOT WATER HEATING BOILER

BHX BOILER BLOWDOWN HEAT

EXCHANGER

BIW BACKWARD INCLINED WHEEL (FAN)

BSC BIOLOGICAL SAFETY CABINETS

BT BUFFER TANK

BTU BRITISH THERMAL UNIT

BTUH BRITISH THERMAL UNIT PER HOUR

C CENTIGRADE (CELCIUS)

CC COOLING COIL

CCD COOLING COIL CONDENSATE DRAIN

CENT CENTRIFICAL

CFH CUBIC FEET PER HOUR

CFM CUBIC FEET PER MINUTE

CFT CUBIC FEET

CFP CHEMICAL FEED PUMP

CH CHILLER

CHWP CHILLED WATER PUMP

CHW CHILLER WATER

CHWR CHILLED WATER RETURN

CHWS CHILLED WATER SUPPLY

CI CAST IRON

CM CARBON MONOXIDE

CM CUBIC METER

CM/S CUBIC METER PER SECOND

CO CLEAN OUT

CO2 CARBON DIOXODE

COMP COMPRESSOR UNIT

COP COEFFICIENT OF PERFORMANCE

CP CONDENSATE PUMP

CU CONDENSING UNIT

CUH CABINET UNIT HEATER

CV CONSTANT VOLUME

CW COLD WATER (POTABLE)

CHWCC CHILLED WATER COOLING COIL

D DAMPER - AUTOMATIC

D-1 OUTDOOR AIR DAMPER

D-2 RETURN AIR DAMPER

D-3 RELIEF AIR DAMPER

D-4 ECONOMIZER OUTDOOR AIR

DAMPER

dB DECIBELS Db DRY-BULB TEMPERATURE

DDC DIRECT DIGITAL CONTROLS

DEG DEGREE

DF DIFFUSER

DIA DIAMETER

DIW DEIONIZED WATER

DP DEW POINT TEMPERATURE

DP DIFFUSER PLATE

DPA DIFFERENTIAL PRESSURE

ASSEMBLY

DPS DIFFERENTIAL PRESSURE SENSOR

DX DIRECT EXPANSION

DXCC DIRECT EXPANSION COOLING COIL

EA EXHAUST AIR

EAT ENTERING AIR TEMPERATURE

ECC ENGINEERING CONTROL CENTER

EER ENERGY EFFICIENCY RATIO

EF EXHAUST FAN

EG EXHAUST GRILLE

EGS EMERGENCY GAS SHUTOFF

EH EXHAUST HOOD

EJ EXPANSION JOINT

EMD END OF MAIN DRIP (STEAM)

ENT ENTERING

ESP EXTERNAL STATIC PRESSURE

EWT ENTERING WATER TEMPERATURE

EX EXISTING

F FAHRENHEIT

F&T FLOAT AND THERMOSTATIC

F/SDPR COMBINATION FIRE SMOKE DAMPER

FA FREE AREA

FC FLEXIBLE CONNECTION

FCU FAN COIL UNIT (4 PIPE)

FCW FORWARD CURVED WHEEL (FAN)

FD FLOOR DRAIN

FD FIRE DAMPER

FF FINAL FILTER

FM FLOW METER

FPM FEET PER MINUTE

FPS FEET PER SECOND

FRP FIBER REINFORCED POLYESTER

FS FLOW SWITCH

FSTAT FREEZESTAT

FT FEET

FT-LB FOOT-POUND

FTR FIN TUBE RADIATION

FV FACE VELOCITY

GA GAUGE

GAL GALLONS

GH GRAVITY HOOD

GPD GALLONS PER DAY

GPH GALLONS PER HOUR

GPM GALLONS PER MINUTE

GS GALVANIZED STEEL

H HUMIDIFER

H&CW HOT & COLD WATER

HAC HOUSEKEEPING AID CLOSET

HB HOSE BIBB

HC HEATING COIL

HD HEAD

HD HOOD

HHW HEATING HOT WATER

HHWC HEATING HOT WATER COIL

HHWP HEATING HOT WATER PUMP

HHWR HEATING HOT WATER RETURN

HHWS HEATING HOT WATER SUPPLY

HOA HAND/OFF/AUTOMATIC

HP HEAT PUMP

HP HORSEPOWER

HPDT HIGH PRESSURE DRIP TRAP

HPR HIGH PRESSURE RETURN (STEAM

CONDENSATE)

HPS HIGH PRESSURE SUPPLY (STEAM)

HRC HEAT RECOVERY COIL

HRD HEAT RECOVERY DEVICE

HRP HYDRONIC RADIANT (CEILING) PANEL

HRW HEAT RECOVERY WHEEL

HSTAT HUMIDISTAT

HUM HUMIDIFIER UNIT MOUNTED

HVU HEATING AND VENTILATING UNIT

HW HOT WATER

HWC HOT WATER COIL

HWUH HOT WATER UNIT HEATER

HX HEAT EXCHANGER

Hz HERTZ

I/O INPUT/OUTPUT

IAQ INDOOR AIR QUALITY

IBT INVERTED BUCKET TRAP

ICF IN-LINE CENTRIFUGAL FAN

ICU INTENSIVE CARE UNIT

ID INSIDE DIAMETER

IFB INTEGRAL FACE AND BYPASS

IN INCHES

IN HG INCHES OF MERCURY

IN WC INCH WATER COLUMN

IN WG INCH WATER GAUGE

IN-LB INCH-POUND

IPLV INTERGRATED PART LOAD VALUE

IRH INTRARED HEATER

IS INSECT SCREEN

IV INLET VANES

kg KILOGRAM kg/HR KILOGRAM PER HOUR kPa KILOPASCAL kW KILOWATT kWh KILOWATT HOUR

L LITER

L/s LITERS PER SECOND

LAT LEAVING AIR TEMPERATURE

LBS/HR POUNDS PER HOUR

LF LINEAR FOOT (FEET)

LH LATENT HEAT

LPR LOW PRESSURE RETURN (STEAM

CONDENSATE)

LPRC LOW PRESSURE CLEAN RETURN

(STEAM CONDENSATE)

LPS LOW PRESSURE SUPPLY (STEAM)

LPSC LOW PRESSURE CLEAN SUPPLY

(STEAM)

LSD LINEAR SLOT DIFFUSER

LTCP LOCAL TEMPERATURE CONTROL

PANEL

LVG LEAVING

LVR LOUVER

LWT LEAVING WATER TEMPERATURE

M METER, SI UNIT

M/s METERS PER SECOND (OR

METERS/SECOND)

MA MIXED AIR

MAT MIXED AIR TEMPERATURE

MAV MANUAL AIR VENT

MAX MAXIMUM

MB MIXING BOX

MBH 1000 BTUH

MCA MINIMUM BRANCH CIRCUIT

AMPACITY

MER MECHANICAL EQUIPMENT ROOM

MERV MINIMUM EFFICIENCY REPORTING

VALUE

MHP MOTOR HORSEPOWER

MIN MINIMUM

MM MILLIMETER

MOV MOTOR OPERATED VALVE

MPR MEDIUM PRESSURE RETURN (STEAM

CONDENSATE)

MPS MEDIUM PRESSURE SUPPLY (STEAM)

MTD MEAN TEMPERATURE DIFFERENCE

MVD MANUAL VOLUME DAMPER

NA NOT APPLICABLE

NC NOISE CRITERIA

NC NORMALLY CLOSED

NO NORMALLY OPEN

NOAA NATIONAL OCEANIC & ATMOSPHERIC

ADMINISTRATION

NOM NOMINAL

NPLV NON-STANDARD PART LOAD VALUE

NPSH NET POSITIVE SUCTION HEAD

NTS NOT TO SCALE

OA OUTSIDE AIR

OAI OUTSIDE AIR INTAKE

OD OUTSIDE DIAMETER

OR OPERATING ROOM

OSA OUTSIDE SUPPLY AIR

(CONDITIONED)

P PUMP

PC PUMPED CONDENSATE

PCF POUNDS PER CUBIC FOOT (FEET)

PD PRESSURE DROP

PF PRE-FILTER

PG PRESSURE GAGE

PHC PREHEAT COIL

PHCP PREHEAT COIL PUMP

PPM PARTS PER MILLION

PRV PRESSURE REGULATING VALVE

PSI POUNDS PER SQUARE INCH

PSIA POUNDS PER SQUARE INCH –

ABSOLUTE

PSIG POUNDS PER SQUARE INCH – GAGE

PSS PRIMARY SECONDARY SYSTEM

PSV PRESSURE SAFETY VALVE

R/E RETURN OR EXHAUST

RA RETURN AIR

RAT RETURN AIR TEMPERATURE

RDS ROOM DATA SHEETS

REA RELIEF AIR

RF RETURN FAN

RG RETURN GRILLE

RH RELATIVE HUMIDITY

RHC REHEAT COIL

RL REFRIGERANT LIQUID LINE

RLA RUN LOAD AMPERE

RPM REVOLUTIONS PER MINUTE

RS REFRIGERANT SUCTION

RTU ROOF TOP UNIT

RV RELIEF VALVE

SA SUPPLY AIR

SAD SOUND ATTENUATING DEVICE

SAT SUPPLY AIR TEMPERATURE

SC SHADING COEFFICIENT

SCFM STANDARD CUBIC FEET PER MINUTE

SCR SILICON CONTROLLED RECTIFIER

SD SMOKE DETECTOR

SD SUPPLY AIR DIFFUSER

SDPR SMOKE DAMPER

SDR SMOKE DAMPER (RETURN)

SDS SMOKE DAMPER (SUPPLY)

SEN SENSIBLE HEAT

SF SUPPLY FAN

SH STEAM HUMIDIFIER

SHC STEAM HEATING COIL

SI SQUARE INCHES

SP STATIC PRESSURE

SP GR SPECIFIC GRAVITY

SPD SUPPLY PROCESS AND

DISTRIBUTION

SPRV STEAM PRESSURE REDUCING VALVE

SPS STATIC PRESSURE SENSOR

SQ FT SQUARE FOOT (FEET)

SR SUPPLY AIR REGISTER

SS STAINLESS STEEL

SSR SOLID SEPARATOR

ST STEAM TRAP

SV STEAM SAFETY VALVE

SVS STEAM VENT SILENCER

T & PCV TEMPERATURE AND PRESSURE

CONTROL VALVE

TAB TESTING, ADJUSTING, BALANCE

TD TEMPERATURE DIFFERENCE

TDH TOTAL DYNAMIC HEAD

TDS TOTAL DISSOLVED SOLIDS

TP TRAP

TSP TOTAL STATIC PRESSURE

TSTAT THERMOSTAT

TU TERMINAL UNIT

UC UNDER CUT

UH UNIT HEATER

UL UNDERWRITERS LABORATORY

V VALVE

VAF VANE-AXIAL FAN

VAV VARIABLE AIR VOLUME

VD VOLUME DAMPER (MANUAL

OPPOSED BLADE)

VFD VARIABLE FREQUENCY DRIVE

VHA VETERANS HEALTH ADMINISTRATION

VI VIBRATION ISOLATOR

VP VACUUM PUMP

VPS VARIABLE PRIMARY SYSTEM

VR VACUUM (STEAM CONDENSATE)

RETURN

VSD VARIABLE SPEED DRIVE

VUH VERTICAL UNIT HEATER

W WATTS

Wb WET-BULB (TEMPERATURE)

WFCV WATER FLOW CONTROL VALVE

WFM WATER FLOWMETER

WFMD WATER FLOW MEASURING DEVICE

WG WATER GAGE

WPD WATER SIDE PRESSURE DROP

XT EXPANSION TANK

YR YEAR

MECHANICAL ABBREVIATIONS

1. WORK SHALL CONFORM TO APPLICABLE LOCAL, STATE, AND NATIONAL CODES AND APPLICABLE VA STANDARDS.

2. INSTALL EQUIPMENT IN ACCORDANCE WITH MANUFACTURER'S WRITTEN RECOMMENDATIONS.

3. OBTAIN AND PAY FOR PERMITS, FEES, AND INSPECTIONS REQUIRED FOR THIS WORK.

4. PROVIDE NEW MATERIALS, EQUIPMENT AND PRODUCTS INCORPORATED IN THE WORK, OF A SUITABLE GRADE FOR THE PURPOSES INTENDED.

5. WHERE POSSIBLE, PROVIDE STANDARD PRODUCTS OF THE VARIOUS MANUFACTURERS EXCEPT WHERE SPECIAL CONSTRUCTION OR PERFORMANCE FEATURES ARE

REQUIRED.

6. EQUIPMENT OR MATERIAL DEVIATIONS FROM INDICATED CONTRACT REQUIREMENTS SHALL BE SUBJECT TO THE APPROVAL OF THE COR. SUBMIT PROPOSED EQUIPMENT DEVIATIONS THAT ARE SIMILAR BOTH IN QUALITY AND CAPACITY TO THAT EQUIPMENT SPECIFIED, AS SOLELY DETERMINED BY THE COR.

7. PROVIDE MECHANICAL EQUIPMENT THAT IS LISTED AND LABELED BY UNDERWRITERS LABORATORIES (U.L.).

8. INSTALL EQUIPMENT AS INDICATED, ALLOWING FOR SUFFICIENT ACCESS AND CLEARANCE SPACE FOR EQUIPMENT MAINTENANCE, REPAIRS, AND REPLACEMENT.

9. INSTALL EQUIPMENT WITH PROPER CLEARANCES FOR REQUIRED PIPING AND ELECTRICAL SERVICES AND CONNECTIONS. INSTALL EQUIPMENT WITH REQUIRED ACCESS AND CLEARANCES IN ACCORDANCE WITH MANUFACTURER'S WRITTEN RECOMMENDATIONS AND APPLICABLE CODES AND STANDARDS.

10. COORDINATE LOCATION, INSTALLATION, AND ROUTING OF DUCTWORK, PIPING, AND EQUIPMENT WITH WORK OF ALL OTHER TRADES.

11. PROVIDE SUPPORT FOR MECHANICAL EQUIPMENT. COORDINATE SUPPORT LOCATIONS WITH ALL CONTRACTORS PRIOR TO INSTALLATION.

12. PROVIDE POWER CONNECTIONS TO EQUIPMENT PROVIDED UNDER THIS CONTRACT AS WORK OF DIVISION 26.

13. PROVIDE CONTROL WIRING FOR MECHANICAL EQUIPMENT AS WORK OF DIVISION 23.

14. DUCTWORK AND PIPING LAYOUTS AND LOCATIONS ARE SCHEMATIC. DO NOT SCALE THESE DRAWINGS. COORDINATE AND DETERMINE EXACT ROUTING OF DUCTWORK AND

PIPING IN THE FIELD.

15. FIELD VERIFY DIMENSIONS BY ACTUAL MEASUREMENT AND OBSERVATION BEFORE ORDERING OR FABRICATING DUCTWORK, PIPING OR EQUIPMENT.

16. NOTIFY COR REGARDING DISCREPANCIES BETWEEN CONTRACT DOCUMENTS AND EXISTING CONDITIONS OR DIMENSIONS BEFORE PERFORMING WORK. FAILURE TO VERIFY AND REPORT SHALL CONSTITUTE CONTRACTOR'S ACCEPTANCE OF EXISTING CONDITIONS AS FIT FOR THE PROPER EXECUTION OF THE WORK.

17. SEE ARCHITECTURAL DRAWINGS FOR FINAL LOCATION OF CEILING INSTALLED EQUIPMENT.

18. INSTALL DUCTWORK AND PIPING AS HIGH AS POSSIBLE AND AS CLOSE AS POSSIBLE TO BUILDING WALLS, CEILING AND FLOOR AND ROOF STRUCTURE. PROVIDE OFFSETS, FITTINGS, AND DIMENSIONAL TRANSITIONS NOT SHOWN BUT REQUIRED TO MAINTAIN MINIMUM CLEAR SPACE TO BUILDING SURFACES AT NO ADDITIONAL COST.

19. PATCH, PAINT AND CLEAN SURFACES SUSTAINING DAMAGE ASSOCIATED WITH MECHANICAL WORK OF THIS CONTRACT, UNLESS NOTED OTHERWISE.

20. SUBMIT BOUND SET OF OPERATING AND MAINTENANCE INSTRUCTIONS FOR EQUIPMENT AT COMPLETION OF PROJECT.

21. INSTALL ESCUTCHEONS IN ALL PLACES WHERE PIPING PENETRATES A WALL IN AN EXPOSED LOCATION.

22. MAKE A COMPLETE REVIEW OF DRAWINGS, INCLUDING SCHEDULES AND DETAILS, PRIOR TO BEGINNING MECHANICAL SYSTEM INSTALLATION. RESOLVE CONFLICTS WITH

COR.

23. DRAWING PLANS, SCHEMATICS, AND DIAGRAMS INDICATE GENERAL LOCATION AND ARRANGEMENT OF PIPING SYSTEMS.

24. INSTALL PIPING INDICATED TO BE EXPOSED AND PIPING IN EQUIPMENT ROOMS AND SERVICE AREAS AT RIGHT ANGLES OR PARALLEL TO BUILDING WALLS. DIAGONAL RUNS

ARE NOT ACCEPTABLE UNLESS SPECIFICALLY INDICATED OTHERWISE.

25. INSTALL PIPING FREE OF SAGS AND BENDS.

26. ALL INSTALLED SUPPLY AND RETURN DUCTWORK TO BE INSULATED.

27. INSTALL PIPING TO ALLOW APPLICATION OF INSULATION.

28. PIPING SHALL NOT BE ROUTED OVER TELECOM OR ELECTRICAL CLOSETS/ROOMS.

29. PREPARE DRAWINGS SHOWING MECHANICAL SYSTEMS AND EQUIPMENT FOR COORDINATION WITH WORK OF OTHER DIVISIONS AND WORK BY THE GOVERNMENT.

A. INCLUDE PLAN VIEWS, SECTIONS, AND ELEVATIONS, AS REQUIRED, TO FULLY COORDINATE ALL NEW WORK WITH ITSELF AND EXISTING CONDITIONS.

B. DRAWINGS SHALL SHOW, BUT NOT BE LIMITED TO, ALL DUCTWORK, AIR DISTRIBUTION, MECHANICAL EQUIPMENT, MECHANICAL PIPING, FIRE PROTECTION PIPING, PLUMBING PIPING, CABLE TRAYS, LIGHTING FIXTURES, CEILING GRID AND HEIGHT, BEAMS AND JOISTS (WITH ELEVATIONS MARKED), ELECTRICAL CONDUIT LARGER THAN 2 INCHES IN DIAMETER AND OTHER CEILING MOUNT DEVICES OR EQUIPMENT THAT PROTRUDE INTO THE CEILING CAVITY.

C. IF THERE ARE OUTSTANDING ISSUES THAT CANNOT BE RESOLVED, CONSULT WITH COR FOR GUIDANCE AND MAKE CORRECTIONS IN ACCORDANCE WITH DIRECTIONS

GIVEN.

D. DO NOT BEGIN FABRICATION OR PLACE EQUIPMENT ORDERS UNTIL COORDINATION DRAWINGS HAVE BEEN APPROVED.

30. INSTALLATION COMMENCED PRIOR TO COORDINATION DRAWING APPROVAL IS TAKEN AT THE CONTRACTORS OWN RISK. MODIFY, MOVE OR RECONFIGURE WORK LACKING

COORDINATION AT NO ADDITIONAL COST.

31. CONTRACTOR SHALL BE RESPONSIBLE FOR COORDINATING WITH GC AND EC TO ENSURE ALL OPENINGS ARE SEALED TO PREVENT ANY AIR LEAKAGE.

32. SITE ELEVATION IS 1900 FT ASL.

33. CONTRACTOR TO COORDINATE ANY WORK THAT REQUIRES A SHUTDOWN WITH THE VA AND GIVE MINIMUM 30 DAYS PRIOR NOTICE. SHUTDOWN IMPACTED WORK WILL HAVE

TO BE DONE AFTER HOURS.

MECHANICAL GENERAL NOTES

SEISMIC DESIGN CRITERIA

LAS VEGAS, NVLOCATION DSITE CLASSIFICATION

IVRISK CATEGORY DSEISMIC DESIGN CATEGORY

0.515

MAPPED SHORT PERIOD SPECTAL

RESPONSE (SS)

1.5SEISMIC IMPORTANCE FACTOR

0.169

MAPPED 1-SECOND SPECTRAL

RESPONSE (S1)

1.388SITE COEFFICIENT (Fa)

0.715

MAXIMUM SHORT PERIOD

SPECTRAL RESPONSE (SMS)

2.124SITE COEFFICIENT (Fv)

0.359

MAXIMUM 1-SECOND SPECTRAL

RESPONSE (SMS)

0.477

MAPPED SHORT PERIOD

SPECTRAL RESPONSE (S)

0.239

MAPPED 1-SECOND SPECTRAL

RESPONSE (SD1)

FOR FINAL VALUES REFER TO STRUCTURAL DRAWINGS.

PRESSURE SENSOR

THERMOSTAT

SUPPLY DIFFUSER

RETURN DIFFUSER/GRILLE

EXHAUST GRILLE

ROUND FLEX DUCT

EG-88 2000 DIFFUSER TAG | DIFFUSER CFM

LINEAR SLOT DIFFUSER

BALANCING DAMPER

(RECTANGULAR)

BALANCING DAMPER

(ROUND)

FIRE DAMPER

SMOKE DAMPER

D

R INCLINED RISE, IN

DIRECTION OF AIRFLOW

INCLINED DROP, IN DIRECTION

OF AIRFLOW

CONNECT NEW DUCT

TO EXISTING

LIMIT OF DEMOLITION

VANED ELBOW (PROVIDE ALL

SQUARE OR RECTANGULAR

ELBOWS WITH VANES EVEN IF

SYMBOL IS MISSING)

STANDARD RADIUS ELBOW

(LONG RADIUS)

10x8 NEW DUCT (INSIDE

DIMENSIONS: WIDTH X DEPTH)

EXISTING DUCT TO REMAIN

EXISTING DUCT TO BE

DEMOLISHED

DUCT TRANSITION

SIDE MOUNTED GRILLE

SUPPLY

RETURN45°

45°

DN

DN

UP

UP

DNUP

STANDARD BRANCH SUPPLY OR

RETURN, NO SPLITTER (45° TAP)

SUPPLY DUCT (UP & DOWN)

EXHAUST DUCT (UP & DOWN)

RETURN DUCT (UP & DOWN)

MECHANICAL LEGEND

S-60

S-15

CR-15

CHWS

CHWR

HIGH PRESSURE STEAM (60

PSI AND ABOVE)

LOW PRESSURE STEAM (15 PSI

AND BELOW)

LOW PRESSURE STEAM

CONDENSATE RETURN

CHILLED WATER SUPPLY PIPING

CHILLED WATER RETURN PIPING

PIPE UP

PIPE DOWN

BOTTOM CONNECTION

TOP CONNECTION

CAPPED OUTLET

GLOBE VALVE

GATE VALVE

BALL VALVE

STEAM SAFETY VALVE

PRESSURE REGULATING VALVE

WYE STRAINER VALVE

BALANCING VALVE

MOTORIZED CONTROL VALVE

STEAM TRAP

COND CONDENSATE DRAIN LINE

CR-60 HIGH PRESSURE STEAM

CONDENSATE RETURN

HWS

HWR

HEATING HOT WATER SUPPLY

PIPING

HEATING HOT WATER RETURN PIPING

RLS REFRIGERANT LINE SET (LIQUID

AND SUCTION)

CONNECT TO EXISTING PIPE

LIMITS OF DEMOLITION

INLINE CENTRIFUGAL PUMP

TANGENTIAL AIR SEPARATOR

EXPANSION TANK

WALL-MOUNTED INDOOR

SPLIT-SYSTEM

SPLIT-SYSTEM CONDENSING UNIT

UTILITY SET EXHAUST FAN

STEAM PRESSURE

REDUCING STATION

DRAIN VALVE

TEST PLUG

SUPPLY

TERMINAL UNIT SUPPLY

DUCT BRANCH (CONICAL

TAP)

TERMINAL UNIT

CHECK VALVE

S-30

CR-30

MEDIUM PRESSURE STEAM (16

PSI THROUGH 59 PSI)

MEDIUM PRESSURE STEAM

CONDENSATE RETURN

P

T

TERMINAL UNITSD

Engineers Architects

Revisions: Date

Drawing Title

Approved: Project Director

Project Title

Location

VA PROJECT NUMBER

Building Number

Drawing Number

Dwg of

VA FORM 08-6231

VA Southern Nevada Health

System (VASNHS)

CONSULTANTS: PROJECT MANAGER

Date Checked Drawn

FULLY SPRINKLERED

ACG Project Number

Headquarters:

Apogee Consulting Group, P.A.

1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.

/1

/2

:1

:0

P M

M-001

MECHANICAL GENERAL INFORMATION

1 15

Tikisha Slan

PA, NAS

Renovate Logistics Space Design

6900 N. Pecos Road North Las Vegas, NV 89086

04/03/2020

100% CONSTRUCTION DOCUMENTS

593-18-30218-352

RBK

DocuSign Envelope ID: C8DBEC4A-B8ED-4DC5-B48D-F1193BC67E5F

4/3/2020

W11W10W9W8W7W6W5W4W3

N.8

WD

WD1

WC

WB

WA

N.2

N

SUPPLY SERVICE

WAREHOUSE

BG115

10106 SF

CORRIDOR

CB-8

993 SF

PIPING ROOM

CB-7

1163 SF

CORRIDOR

CB-9

2046 SF

GAS STORAGE

BG113

66 SF

GAS STORAGE

BG114

57 SF

STOREKEEPER

BG110

160 SF

UTILITY TRENCH ACCESS

ROOM

BE103

378 SF

REPRODUCTION CENTER

BG101

474 SF

MAIL

BG102

336 SF

EQUIPMENT CHARGING

BG109

423 SF

GAS MANIFOLD ROOM

BG109A

198 SF

STAFF TOILET

BG108

66 SF

STAFF TOILET

BG107

58 SF

REF AND SECURE STORES

BG116

118 SF

1 11

Engineers Architects

## KEY NOTES:

Revisions: Date

Drawing Title

Approved: Project Director

Project Title

Location

VA PROJECT NUMBER

Building Number

Drawing Number

Dwg of

VA FORM 08-6231

VA Southern Nevada Health

System (VASNHS)

CONSULTANTS: PROJECT MANAGER

SHEET NOTES:

Date Checked Drawn

FULLY SPRINKLERED

ACG Project Number

Headquarters:

Apogee Consulting Group, P.A.

1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.

/1

/2

:1

:2

P M

MD101

BASEMENT LEVEL MECHANICAL

DEMOLITION PLAN

2 15

Tikisha Slan

PA, NAS

Renovate Logistics Space Design

6900 N. Pecos Road North Las Vegas, NV 89086

04/03/2020

100% CONSTRUCTION DOCUMENTS

593-18-30218-352

RBK

0 4 8 16

NORTH

PLAN

1 DEMOLISH ALL SA DIFFUSERS AND RA

GRILLES IN THIS AREA. DEMOLISH ALL

DUCTWORK AND VAV TERMINAL UNITS

BACK TO LIMITS OF DEMOLITION AND CAP.

2 DEMOLISH EXHAUST DIFFUSER. DEMOLISH

EXHAUST DUCT BACK TO LIMITS OF

DEMOLITION AND CAP.

3 8" EXHAUST UP THROUGH ROOF EXISTING

TO REMAIN.

4 REBALANCE EXHAUST AIRFLOWS FOR THE

RESTROOMS. EXHAUST RATE IS TO BE 100

CFM IN EACH RESTROOM. FAN

BELTS/SHEAVES REPLACEMENT SHALL BE

INCLUDED IN THE SCOPE.

N

AREA OF WORK

SCOPE OUTLINE

KEY PLAN

SCALE: NO SCALE

Scale: 1/8" = 1'-0"

BASEMENT LEVEL MECHANICAL DEMOLITION PLAN

1. DEMOLITION WORK IN THE OFFICE AREA

SHALL BE PERFORMED DURING OFF

HOURS OR WEEKENDS AS DIRECTED BY

THE VA.

WD

WD1

WC

WB

WA

N.2

N

3/4" CR-15

1 1/4" S-15

2 1/2" CHWS

2 1/2" CHWR

1 1/2" HWS

1 1/2" HWR

3/4" CR-15

1" S-15

1 1/4" HWR

1 1/4" HWS

2" CHWR

2" CHWS

3/4" CR-15

1" S-15

2" CHWR

2" CHWS

1 1/2" HWR

1 1/2" HWS

1 1/4" HWR

1 1/4" HWS

2" CHWR

2" CHWS

1 1/4" HWS

1 1/4" HWR

1 1/2" HWR

1 1/2" HWS

2 1/2" CHWR

2 1/2" CHWS

1 1/4" S-15

3/4" CR-15

1 1/2" HWR

1 1/2" HWS

1" HWR

1" HWS

1" CHWR

1" CHWS

2" HWR

2" HWS

1" CR-15

2" S-15

3" CHWR

3" CHWS

1 1/2" S-15

1" CR-15

3" CHWR

3" CHWS

2" HWR

2" HWS

SUPPLY SERVICE

WAREHOUSE

BG115

10106 SF

CORRIDOR

CB-8

993 SF

PIPING ROOM

CB-7

1163 SF

CORRIDOR

CB-9

2046 SF

GAS STORAGE

BG113

66 SF

GAS STORAGE

BG114

57 SF

STOREKEEPER

BG110

160 SF

UTILITY TRENCH ACCESS

ROOM

BE103

378 SF

REPRODUCTION CENTER

BG101

474 SF

MAIL

BG102

336 SF

EQUIPMENT CHARGING

BG109

423 SF

GAS MANIFOLD ROOM

BG109A

198 SF

STAFF TOILET

BG108

66 SF

STAFF TOILET

BG107

58 SF

REF AND SECURE STORES

BG116

118 SF

2" D co coco

2" D

2" D

2" D

2" D

2" D

2" D

2" D

2" D

Engineers Architects

## KEY NOTES:

Revisions: Date

Drawing Title

Approved: Project Director

Project Title

Location

VA PROJECT NUMBER

Building Number

Drawing Number

Dwg of

VA FORM 08-6231

VA Southern Nevada Health

System (VASNHS)

CONSULTANTS: PROJECT MANAGER

SHEET NOTES:

Date Checked Drawn

FULLY SPRINKLERED

ACG Project Number

Headquarters:

Apogee Consulting Group, P.A.

1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.

/1

/2

:1

:3

P M

MD102

BASEMENT LEVEL MECHANICAL PIPING

DEMOLITION PLAN

3 15

Tikisha Slan

PA, NAS

Renovate Logistics Space Design

6900 N. Pecos Road North Las Vegas, NV 89086

04/03/2020

100% CONSTRUCTION DOCUMENTS

593-18-30218-352

RBK

N

AREA OF WORK

SCOPE OUTLINE

KEY PLAN

SCALE: NO SCALE

Scale: 1/8" = 1'-0"

BASEMENT LEVEL MECHANICAL PIPING DEMOLITION PLAN 0 4 8 16

NORTH

PLAN

1 EXISTING 1-1/4" HWS & HWR UP TO

RTU-WH-2 TO REMAIN. SEE MD103 FOR

CONTINUATION.

2 EXISTING 2" CHWS & CHWR UP TO

RTU-WH-2 TO REMAIN. SEE MD103 FOR

CONTINUATION.

3 DEMOLISH EXISTING HWS & HWR

BRANCHES BACK TO MAIN AND CAP.

4 DEMOLISH EXISTING 1" STEAM PIPING (S-15)

SUPPLY BACK TO MAIN AS INDICATED.

5 DEMOLISH EXISTING 3/4" STEAM

CONDENSATE RETURN (CR-15) SUPPLY

BACK TO MAIN AS INDICATED.

6 ALL EXISTING PIPING SERVING

WAREHOUSE EQUIPMENT & OTHER AREAS

SHALL REMAIN.

1. DEMOLITION WORK SHALL BE PERFORMED

DURING OFF HOURS OR WEEKENDS AS

DIRECTED BY THE VA.

2. ISOLATION VALVES SHALL BE PROVIDED

FOR ALL BRANCH PIPING NEAR THE MAINS.

WD

WD1

WC

WB

WA

N.2

N

RTU-WH-3 (EX.) RTU-WH-4 (EX.)

RTU-WH-2

RTU-WH-1 (EX.)

Engineers Architects

## KEY NOTES:

Revisions: Date

Drawing Title

Approved: Project Director

Project Title

Location

VA PROJECT NUMBER

Building Number

Drawing Number

Dwg of

VA FORM 08-6231

VA Southern Nevada Health

System (VASNHS)

CONSULTANTS: PROJECT MANAGER

SHEET NOTES:

Date Checked Drawn

FULLY SPRINKLERED

ACG Project Number

Headquarters:

Apogee Consulting Group, P.A.

1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.

/1

/2

:1

:3

P M

MD103

ROOF MECHANICAL DEMOLITION PLAN

4 15

Tikisha Slan

PA, NAS

Renovate Logistics Space Design

6900 N. Pecos Road North Las Vegas, NV 89086

04/03/2020

100% CONSTRUCTION DOCUMENTS

593-18-30218-352

RBK

N

AREA OF WORK

SCOPE OUTLINE

KEY PLAN

SCALE: NO SCALE

Scale: 1/8" = 1'-0"

ROOF MECHANICAL DEMOLITION PLAN 0 4 8 16

NORTH

PLAN

1 DISCONNECT CHS/R, HWS/R, LPS SUPPLY &

CONDENSATE PIPING CONNECTED TO

EXISTING RTU.

2 DEMOLISH SUPPLY AND RETURN AIR

DUCTWORK CONNECTED TO RTU &

LOCATED BELOW CEILING WITHIN

WAREHOUSE AND DISPOSE.

3 DISCONNECT CONTROLS SERVING

RTU-WH-2, INCLUDING WIRING AND

CONDUITS.

4 REMOVE & DISPOSE OF THE EXISTING RTU.

5 DEMOLISH EXISTING STEAM PIPING (S-15)

SUPPLY & CONDENSATE PIPING BACK TO

MAIN. SEE SHEET MD102 FOR EXTENT OF

DEMOLITION.

6 DEMOLISH CONDENSATE DRAIN PIPING FOR

EXISTING RTU.

7 DEMOLISH EXISTING RTU ROOF CURB.

1. DEMOLITION WORK SHALL BE PERFORMED

DURING OFF HOURS OR WEEKENDS AS

DIRECTED BY THE VA.

2. REMOVAL OF DUCTWORK WITHIN

WAREHOUSE SHALL BE COORDINATED

WITH THE VA.

3. TEMPORARY PROTECTION OF OPENINGS

AFTER REMOVAL OF RTU IF REQUIRED

SHALL BE PROVIDED BY MECHANICAL

CONTRACTOR. PROTECTION SHALL

INCLUDE WATERPROOFING & SECURITY.

4. UTILITY SHUTDOWN, IF REQUIRED, SHALL

BE COORDINATED WITH VA.

Scale: No Scale

EXISTING RTU ON ROOF

Scale: No Scale

PIPING & DUCTWORK TO EXISTING RTU

WD

WD1

WC

WB

WA

N.2

N

SUPPLY SERVICE

WAREHOUSE

BG115

CLEAN STORAGE

BG105

DELIVERY PREP

BG104

PIPING ROOM

CB-7

CORRIDOR

CB-8

CORRIDOR

CB-9

M-301 x x x x

12x12

12x12

12ø8ø

10ø

12x12

RG-24 440

SD-13 330

SD-13 330

RG-24 440

SD-13 310

SD-13 310

SD-13 310SD-13 310 RG-24 435

RG-24 435

RG-24 435 SD-13 310SD-13 310

SD-13 310 SD-13 310

RG-24 435

SD-14 420 RG-24 530

SD-14 420 RG-24 530

10ø

10ø

12ø 12x10 x

10ø

BREAK OUT ROOM

BG106

16x1216x12

CORRIDOR

CB-9

GAS STORAGE

BG113

GAS STORAGE

BG114

STOREKEEPER

BG110

UTILITY TRENCH ACCESS

ROOM

BE103

REPRODUCTION CENTER

BG101

MAIL

BG102

EQUIPMENT CHARGING

BG109

GAS MANIFOLD ROOM

BG109A

STAFF TOILET

BG108

STAFF TOILET

BG107

REF AND SECURE STORES

BG116

12ø

16x12

12ø

10ø

12x12

T T

T T

10ø

10ø

10ø

12x12

14ø

14ø

14ø

14ø 14ø

12ø

1-TU-4

1-EV-3

1-TU-3

1-EV-1

1-TU-1

1-EV-2

1-TU-2

1-EV-4

M-301

14ø

14ø

14ø

12ø

10ø

P

P

1-TU-4

1-TU-3

1-TU-2

1-TU-1

12x10

WALL BELOW GRADE

H

10ø

12x12

12x10

12ø 10ø

12ø5

Engineers Architects

## KEY NOTES:

Revisions: Date

Drawing Title

Approved: Project Director

Project Title

Location

VA PROJECT NUMBER

Building Number

Drawing Number

Dwg of

VA FORM 08-6231

VA Southern Nevada Health

System (VASNHS)

CONSULTANTS: PROJECT MANAGER

SHEET NOTES:

Date Checked Drawn

FULLY SPRINKLERED

ACG Project Number

Headquarters:

Apogee Consulting Group, P.A.

1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.

/1

/2

:2

:2

P M

MH101

BASEMENT LEVEL HVAC PLAN

5 15

Tikisha Slan

PA, NAS

Renovate Logistics Space Design

6900 N. Pecos Road North Las Vegas, NV 89086

04/03/2020

100% CONSTRUCTION DOCUMENTS

593-18-30218-352

RBK

0 4 8 16

NORTH

PLAN

1 28" x 14" SA DUCT FROM RTU ON ROOF.

2 32" x 18" RA DUCT TO RTU ON ROOF.

3 SA DUCT DOWN FROM 19' TO APPROXIMATELY

15'.

4 RA DUCT UP FROM APPROXIMATELY 14' TO 19'.

5 DDC PANEL IN DELIVERY PREP ROOM.

6 28" x 14" SA DUCT TRANSITIONS FROM 46" x 11"

SUPPLY AIR OUTLET FROM RTU ON ROOF.

7 32" x 18" RA DUCT TRANSITIONS TO 46" x 11"

RETURN AIR INLET FROM RTU ON ROOF.

N

AREA OF WORK

SCOPE OUTLINE

KEY PLAN

SCALE: NO SCALE

Scale: 1/8" = 1'-0"

BASEMENT LEVEL HVAC PLAN

1. FOR DUCT SUPPORTS REFER TO

ARCHITECTURAL AND STRUCTURAL

DRAWINGS.

WD

WD1

WC

WB

WA

N.2

N

1 1

1 1

Engineers Architects

## KEY NOTES:

Revisions: Date

Drawing Title

Approved: Project Director

Project Title

Location

VA PROJECT NUMBER

Building Number

Drawing Number

Dwg of

VA FORM 08-6231

VA Southern Nevada Health

System (VASNHS)

CONSULTANTS: PROJECT MANAGER

SHEET NOTES:

Date Checked Drawn

FULLY SPRINKLERED

ACG Project Number

Headquarters:

Apogee Consulting Group, P.A.

1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.

/1

/2

:2

:2

P M

MH102

BASEMENT LEVEL HVAC REFLECTED

CEILING PLAN

6 15

Tikisha Slan

PA, NAS

Renovate Logistics Space Design

6900 N. Pecos Road North Las Vegas, NV 89086

04/03/2020

100% CONSTRUCTION DOCUMENTS

593-18-30218-352

RBK

N

AREA OF WORK

SCOPE OUTLINE

KEY PLAN

SCALE: NO SCALE

Scale: 1/8" = 1'-0"

BASEMENT LEVEL MECHANICAL REFLECTED CEILING PLAN 0 4 8 16

NORTH

PLAN

1 DIFFUSERS NEAR COLUMNS OR WALL SHALL

BE 3-WAY OR 2-WAY TYPE.

WD

WD1

WC

WB

WA

N.2

N

RTU-WH-1 (EX.)

1-RTU-1

RTU-WH-3 (EX.) RTU-WH-4 (EX.)

M-301

M-301

O.A.

E.A.

INTAKE HOOD

EXHAUST HOOD

NEW ROOF CURB

Engineers Architects

## KEY NOTES:

Revisions: Date

Drawing Title

Approved: Project Director

Project Title

Location

VA PROJECT NUMBER

Building Number

Drawing Number

Dwg of

VA FORM 08-6231

VA Southern Nevada Health

System (VASNHS)

CONSULTANTS: PROJECT MANAGER

SHEET NOTES:

Date Checked Drawn

FULLY SPRINKLERED

ACG Project Number

Headquarters:

Apogee Consulting Group, P.A.

1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.

/1

/2

:1

:4

P M

MH103

ROOF HVAC PLAN

7 15

Tikisha Slan

PA, NAS

Renovate Logistics Space Design

6900 N. Pecos Road North Las Vegas, NV 89086

04/03/2020

100% CONSTRUCTION DOCUMENTS

593-18-30218-352

RBK

0 4 8 16

NORTH

PLAN

1 INSTALL NEW RTU IN PLACE OF RTU-WH-2.

PROVIDE NEW 18" SEISMIC RATED ROOF

CURB FOR NEW RTU.

2 CONNECT NEW 1-1/4" S-15 & 1" CR-15 TO

STEAM DISPERSION SECTION IN NEW RTU.

PROVIDE STEAM TRAPS AT INLET AND OUTLET

OF HUMIDIFIER. SEE DETAIL 8/M-501 FOR

MORE INFORMATION.

3 CONNECT EXISTING CHWS/R & HWS/R TO

COOLING & HEATING COILS IN NEW RTU. SEE

DETAIL 4/M-501 FOR MORE INFORMATION

4 PROVIDE ALL NECESSARY OFFSETS AND

TRANSITIONS TO CONNECT EXISTING PIPING

TO NEW AHU. PROVIDE HEAT TRACING ON

HWS/R & CHS/R PIPING AND CONTROL VALVES

EXPOSED ON ROOF. HEAT TRACING SHALL BE

3 WATT PER LINEAR FOOT.

5 REUSE EXISTING ROOF PENETRATIONS FOR

NEW SUPPLY AND RETURN DUCT.

6 ROUTE 1-1/4" CONDENSATE DRAIN PIPING

FROM RTU COOLING SECTION TO EXISTING

CONDENSATE MAIN BELOW ROOF. SEE DETAIL

3/M-501 FOR MORE INFORMATION.

7 ROUTE 1" CONDENSATE DRAIN PIPING FROM

RTU HEAT EXCHANGER SECTION TO EXISTING

CONDENSATE MAIN BELOW ROOF. SEE DETAIL

3/M-501 FOR MORE INFORMATION.

N

AREA OF WORK

SCOPE OUTLINE

KEY PLAN

SCALE: NO SCALE

Scale: 1/8" = 1'-0"

ROOF HVAC PLAN

1. FOR RTU SUPPORTS, REFER TO STRUCTURAL

DRAWINGS.

2. REFER TO ARCHITECHTURAL DRAWINGS.

3. CHWS/R AND HWS/R PIPING SHALL BE HEAT

TRACED ON ROOF AND UPTO 3' INSIDE

WAREHOUSE. HEAT TRACE SHALL BE SW/LF.

4. REFER TO STRUCTURAL/ARCHITECTURAL

DRAWINGS FOR EQUIPMENT CURB

INSTALLATION. INSULATED ROOF CURB

PROVIDED BY CONTRACTOR SHALL BE PER

MANUFACTURER STANDARD. ROOF CURB TO BE

DESIGNED FOR LOCAL SITE CONDITIONS AND

STAMPED BY MANUFACTURER ENGINEER.

5. COOLING COIL AND HEAT EXCHANGER

CONDENSATE PIPING SHALL BE COPPER.

INSULATE WITH 1" THICK FG INSULATION.

WD

WD1

WC

WB

WA

N.2

N

1-CV-1

1-CV-2

1-CV-3

1-CV-4

1 1/4" S-15

SUPPLY SERVICE

WAREHOUSE

BG115

CLEAN STORAGE

BG105

DELIVERY PREP

BG104

PIPING ROOM

CB-7

CORRIDOR

CB-8

CORRIDOR

CB-9

BREAK OUT ROOM

BG106

CORRIDOR

CB-9

GAS STORAGE

BG113

GAS STORAGE

BG114

STOREKEEPER

BG110

UTILITY TRENCH ACCESS

ROOM

BE103

REPRODUCTION CENTER

BG101

MAIL

BG102

EQUIPMENT CHARGING

BG109

GAS MANIFOLD ROOM

BG109A

STAFF TOILET

BG108

STAFF TOILET

BG107

REF AND SECURE STORES

BG116

1" CR-15

3/4" HWS

3/4" HWR

2" D

T T

P

1-TU-4

1-TU-3

1-TU-1

1-TU-2

1-TU-4

1-TU-3

1-TU-2

1-TU-1 T T

PH

CWS/R, HWS/R & S/CR-15

CONTROL VALVES ARE

LOCATED ON ROOF.

Engineers Architects

## KEY NOTES:

Revisions: Date

Drawing Title

Approved: Project Director

Project Title

Location

VA PROJECT NUMBER

Building Number

Drawing Number

Dwg of

VA FORM 08-6231

VA Southern Nevada Health

System (VASNHS)

CONSULTANTS: PROJECT MANAGER

SHEET NOTES:

Date Checked Drawn

FULLY SPRINKLERED

ACG Project Number

Headquarters:

Apogee Consulting Group, P.A.

1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.

/1

/2

:1

:4

P M

MP101

BASEMENT LEVEL MECHANICAL PIPING

PLAN

8 15

Tikisha Slan

PA, NAS

Renovate Logistics Space Design

6900 N. Pecos Road North Las Vegas, NV 89086

04/03/2020

100% CONSTRUCTION DOCUMENTS

593-18-30218-352

RBK

0 4 8 16

NORTH

PLAN

1 ROUTE NEW 1 1/4" S-15 SERVICE UP TO NEW

RTU ON ROOF.

2 ROUTE 3/4" HWS/R TO EACH TERMINAL UNIT

AS INDICATED. SEE SHEET M-502 FOR MORE

INFORMATION.

3 ROUTE NEW 1" CR-15 UP TO NEW RTU ON

ROOF.

4 EXISTING 2" COIL CONDENSATE FROM RTU

ON ROOF.

5 DDC PANEL IN DELIVERY PREP ROOM.

N

AREA OF WORK

SCOPE OUTLINE

KEY PLAN

SCALE: NO SCALE

Scale: 1/8" = 1'-0"

BASEMENT LEVEL MECHANICAL PIPING PLAN

ROOF

0"

BASEMENT

-24' - 0"

ROOF

0' - 0"

BASEMENT

-24' - 0"

W10 W9 W8 W7 W6 W5 W4 W3

CEILING FRAMING

-12' - 0"

DELIVERY PREP

BG104

575 SF

CLEAN STORAGE

BG105

2396 SF

BREAK OUT ROOM

BG106

646 SF

28x1432x16

14ø 14ø

12ø 14ø

12x12

12x16

12x1212x12

ROOF

0"

BASEMENT

-24' - 0"

ROOF

0' - 0"

BASEMENT

-24' - 0"

WCWBWAN.2N

CEILING FRAMING

-12' - 0"

ROOF

0"

ROOF

0' - 0"

WB

2" D

2" CHWS

2" CHWR

1 1/4" HWS

1 1/4" HWR

2" D

1-RTU-1

14x28

16x32

22'-0"

1 1/4" S-15

1" CR-15

O.A. E.A.

ROOF

0"

ROOF

0' - 0"

W6

M-301

5'-2"

Engineers Architects

## KEY NOTES:

Revisions: Date

Drawing Title

Approved: Project Director

Project Title

Location

VA PROJECT NUMBER

Building Number

Drawing Number

Dwg of

VA FORM 08-6231

VA Southern Nevada Health

System (VASNHS)

CONSULTANTS: PROJECT MANAGER

SHEET NOTES:

Date Checked Drawn

FULLY SPRINKLERED

ACG Project Number

Headquarters:

Apogee Consulting Group, P.A.

1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.

/1

/2

:1

:1

P M

M-301

MECHANICAL SECTIONS

9 15

Tikisha Slan

PA, NAS

Renovate Logistics Space Design

6900 N. Pecos Road North Las Vegas, NV 89086

04/03/2020

100% CONSTRUCTION DOCUMENTS

593-18-30218-352

RBK

N

AREA OF WORK

SCOPE OUTLINE

KEY PLAN

SCALE: NO SCALE

Scale: 3/16" = 1'-0"

Section A-A

Scale: 3/16" = 1'-0"

Section B-B Scale: 1/4" = 1'-0"

Section C-C

Scale: 1/4" = 1'-0"

Section D-D

0 42 8

0 42 8 0 2 4 8 0 2 4 8

1 NEW ROOF CURB SHALL SERVE AS PLENUM

FOR RETURN AIR TO RTU.

2 SEE KEYNOTES ON SHEET MH103 FOR PIPING

CONNECTIONS TO NEW RTU.

1. PROVIDE INSULATED ROOF CURB. SEE DETAIL.

2. FOR ROOF INSULATION AND FLASHING DETAIL

REFER TO ARCHITECHTURAL SHEETS.

NOM. SIZE (IN.)

PIPE (FT.)

TUBING (FT.)

5 FT

THRU 3/4

1 1 1/4

1 1/2

HANGER ROD

INSULATION (VAPOR

BARRIER TYPE IS

REQUIRED FOR

LOW TEMPERATURE

PIPE)

PROVIDE HIGH

COMPRESSIVE

STRENGHT

INSULATION (9 PSF

MIN. DENSITY) UNDER

INSULATION SHIELD

INSULATION SHIELD AT

HANGER

WELD

SADDLE

ADJUSTABLE CLEVIS HANGER TYPE 1 - SEE

SPECIFICATIONS

ADJUSTABLE CLEVIS HANGER TYPE 43 - SEE

SPECIFICATIONS

1/2" DIA. HANGER RODS WITH 36"

MAX. SPACING ON EACH CHANNEL

BAND

1-5/8" 12 GAUGE CHANNEL

OR 2" x 2" x 1/4" ANGLE

NOTES:

SEE SPECIFICATIONS FOR

DETAILED HANGER

REQUIREMENTS. SIDE VIEW TRAPEZE HANGER

FOR UP TO 1000 LB. UNIFORM

LOAD

1" MAX.

PROVIDE INSULATION SHIELD &

INSERT FOR ALL PIPING (8" MIN.)

2 2 1/2 3 4 5 6 8 10 12

11 12 14 16 17 19 22 23

9 10 12 13 14 16 - -

NOTE: FOR TRAPEZE HANGER TAKE SPACING OF SMALLEST SIZE ON TRAPEZE

MAXIMUM PIPE/TUBING SUPPORT SPACING

PIPE AND INSULATION

INSULATION PROTECTION SHIELD

2" STEEL PIPE

2-1/2" STEEL PIPE

SEALANT

PROVIDE ALUMINUM JACKET

HIGH COMPRESSIVE

STRENGTH INSULATION

INSERT UNDER SHIELD

WELD PIPE SADDLE SUPPORT

TO PIPE. PROVIDE WATER

TIGHT CONNECTION

CLAMPING RING

PRE-MOULDED FLEXIBLE

PIPE COUNTER FLASHING

ROOF SYSTEM

INSULATION AND

MEMBRANE

ROOF SURFACE

CONCRETE ROOF SLAB

OR STEEL ROOF DECK

SECURE TO ROOF SLAB WITH

(4) 3/8" Ø EXPANSION BOLTS

OR WELD TO STEEL DECK

WELD PLATE TO PIPE

8" x 8" x 3/8" STEEL PLATE

M

IN

NOTES:

PROVIDE RESTRAINING CLAMPS 8'-0" O.C.

ABOVE 2" [50mm] DIA. PIPE 2" [50mm] DIA. & SMALLER

VERTICAL

2 1/2" [65mm] DIA.

ABOVE 2" [50mm] DIA. PIPE 2" [50mm] DIA. & SMALLER

HORIZONTAL

2 1/2" [65mm] DIA.

TYPICAL WATER

PIPING

REDUCER, IF REQUIRED

3/4" BALL

VALVE

ADAPTER TO 3/4" HOSE

THREAD. PROVIDE

HOSE CAP NUT

NOTES:

1. DRAIN ALL LOW POINTS AS INDICATED ABOVE.

2. WHERE SCALE POCKETS ARE SHOWN ON PIPE RISER DIAGRAMS

AND/OR PLANS, LOCATE DRAIN AT BOTTOM OF SCALE POCKET.

TYPICAL CHILLED WATER AND HOT WATER

PIPING DRAIN VALVE CONNECTIONS

ELEVATION:

THREADED PIPING

ELEVATION:

WELDED PIPING

1/4" COPPER TUBING

1/2" X 4" NIPPLE

AIR VENT

1/2" BALL VALVE

MV

OR

AV

CIRCULATING WATER

PIPING

ELEVATION

NOTES:

1. VENT ALL HIGH POINTS INDICATED ABOVE.

2. IF AUTOMATIC AIR VENTS ARE USED, PIPE DISCHARGE TO DRAIN.

TYPICAL MANUAL AIR VENT

DRAIN LINE SHALL BE AT LEAST THE

SAME SIZE AS THE NIPPLE ON THE

DRAIN PAN. PIPING SHALL BE RIGID

COPPER TYPE L OR TYPE M UNLESS

NOTE BELOW IS MET

PITCH DOWN TOWARD DRAIN

CLEANOUT

HUB DRAIN

DRAIN PAN

DIALECTRIC FITTING

NOTES:

1. CPVC PIPE MAY BE USED ONLY IF APPROVED BY LOCAL VA AND IS INDOORS AND DOES

NOT PASS THROUHG RATED BARRIERS.

2. DIALECTRIC FITTING TO BE USED WHEN TWO DISSIMILAR METALS ARE TO BE CONNECTED.

UNIT TYPE A B

WHERE X = STATIC PRESSURE IN PAN

DRAW THRU

BLOW THRU

2" PLUS X

1" MINIMUM

X

2X

B A

(SEE PLANS FOR LOCATION)

SEE DRAWINGS FOR PIPE SIZES

SCHEDULE 80

STEEL PIPE

BYPASS- INSTALL IN HORIZONTAL

PLANE LEVEL WITH TRAP OR IN

VERTICAL PLANE & BELOW TRAP

PIPE SIZE SHALL BE SAME SIZE

AS TRAP

PIPE SIZE SHALL BE SAME SIZE

AS TRAP

PIPE SIZE SHALL BE SAME SIZE

AS TRAP

TO RETURN MAIN

SCHEDULE 80 STEEL PIPE

1" GATE VALVE

INVERTED BUCKET

TRAP. SEE PLANS,

AND SCHEDULES

FLOW

DIELECTRIC FITTING

WHERE RETURN IS

COPPER PIPE

DRIP LEG OP EQUIPMENT

CONNECTION. MAKE THE

SAME SIZE AS THE SUPPLY

MAIN OR QUIPMENT

CONNECTION. SEE NOTE 1

" M

IN

. [3

0 m m

" M

IN

. [1 m m

M V

M V

M V

M V

MV

MV

M V

SINGLE COIL

DOUBLE COIL

WATER COIL

WATER COIL

WATER COIL

TI

FE

FE

TI

FLOW ELEMENT

TEMPERATURE

INDICATION TO ECC.

SEE CONTROL DIAGRAM

(TYP.)

DRAIN

AIR VENT WHEN COIL IS

NOT SELF-VENTING

(TYP.)

TEST PLUG (TYP.)

DRAIN WHEN COIL IS

NOT SELF-DRAINING

(TYP.)

DRAIN

PIPE HANGERS SHALL SUPPORT

PIPING INDEPENDENT OF COIL

(TYP.)

REDUCER, IF REQUIRED (TYP.)

NOTES:

1. WHEN COIL IS INCLUDED IN CASING MOUNTED ON VIBRATION ISOLATORS THE FIRST

TWO HANGERS FOR EACH PIPE SHALL BE SPRING & NEOPRENE TYPE. TYPE "H" 4" DIA.

PIPE & SMALLER. TYPE "H-P" FOR 5" DIA. PIPE & LARGER.

2. PIPING SHALL BE INSTALLED IN SUCH A MANNER THAT IT WILL NOT BLOCK THE

SWING OR USE OF ACCESS DOORS OR PANELS; NEITHER SHALL IT BLOCK THE

SERVICING OF FILTERS, VALVES, OR EQUIPMENT.

3. THE FLOW ELEMENT MAY BE INSTALLED IN THE SUPPLY PIPING IF THE REQUIRED

MINIMUM UPSTEAM AND DOWNSTREAM DIMENSIONS CANNOT BE OBTAINED IN THE

RETURN PIPING.

BALANCING VALVE

BALANCING VALVE

COIL

REDUCER IF REQUIRED

SHUTOFF VALVE

WATER RETURN

WATER SUPPLY

MODULATION CONTROL VALVE

MANUAL AIR VENT

TEST PLUG (TYP.)

UNION CONNECTIONS (TYP.)

DRAIN WITH HOSE

CONNECTION

MV

BALANCING VALVE

SEE MANUFACTURER'S

PIPING RECOMMENDATIONS

FOR FINAL LAYOUT

AHU CROSS SECTION1/3 MODULATING CONTROL VALVE

STEAM SUPPLY

MANIFOLD PIPE ADAPTERS

TO HUMIDISTAT

HUMIDIFIER CONTROL VALVE

F & T TRAP ASSEMBLY

SCALE POCKET

TEMPERATURE SWITCH

STEAM

CONDENSATE

RETURN

A H

U H

E

IG

H T

H

/3

H

M

IN

2/3 MODULATING CONTROL VALVE

Engineers Architects

Revisions: Date

Drawing Title

Approved: Project Director

Project Title

Location

VA PROJECT NUMBER

Building Number

Drawing Number

Dwg of

VA FORM 08-6231

VA Southern Nevada Health

System (VASNHS)

CONSULTANTS: PROJECT MANAGER

Date Checked Drawn

ACG Project Number

Headquarters:

Apogee Consulting Group, P.A.

1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.

/1

/2

:1

:1

P M

M-501

MECHANICAL DETAILS

10 15

Tikisha Slan

PA, NAS

Renovate Logistics Space Design

6900 N. Pecos Road North Las Vegas, NV 89086

04/03/2020

100% CONSTRUCTION DOCUMENTS

593-18-30218-352

RBK

Scale: No Scale

PIPE HANGER

Scale: No Scale

DETAIL FOR SUPPORTING PIPING ON ROOF

Scale: No Scale

INSTALLATION OF THERMOMETER WELLS

Scale: No Scale

DRAIN VALVE AND AIR VENT CONNECTIONS (HYDRONIC

SYSTEMS)

Scale: No Scale

AIR HANDLING UNIT DRAIN TRAP DETAIL

Scale: No Scale

INVERTED BUCKET STEAM TRAP ASSEMBLY

Scale: N.T.S.

WATER COILS - PIPING CONNECTIONS

Scale: N.T.S.

TERMINAL UNIT WATER COILS - PIPING CONNECTIONS

Scale: N.T.S.

STEAM HUMIDIFIER - PIPING CONNECTIONS

NOTE:

UNLESS OTHERWISE INDICATED ON PLANS, MAXIMUM ANGLES SHOWN SHALL APPLY.

TYPICAL DUCTWORK TRANSITION WITH

EQUIPMENT MOUNTED IN DUCT PLAN OR SIDE

VIEW

TYPICAL DUCTWORK TRANSITION

PLAN OR SIDE VIEW

AIRFLOW

AIRFLOWAIRFLOW

E Q

U

IP

M E

N T

M A

X

M

AX.

M A X

M A

X

M

AX.

M A

X

MAIN SUPPLY

DUCT

PROVIDE VOLUME

DAMPER

PROVIDE

VOLUME

DAMPER

1/4 W OR

4" MIN.

SUPPLY REGISTER OR

BRANCH DUCT

MAIN

SUPPLY

DUCT

SEE FLOOR PLAN

FOR SPLIT

DIMENSION

TURNING VANES

AIR FLOW

AIR FLOW

A

IR

F L O

W

AIR SPLIT DUCT TAKE-

OFF PLAN VIEW

BRANCH DUCT TAKE-OFF

PLAN VIEW

AIR FLOW

A

IR

F

LO

W

W

MAIN SUPPLY

DUCT

CONICAL TAP

TERMINAL UNIT DUCT TAKE-

OFF PLAN VIEW

AIR FLOW

A

IR

F

LO

W

W

SMACNA FIGURE 4-6 45°

LEED IN RIGID DUCT TO

AIR TERMINAL UNIT

MAIN SUPPLY

FLOW

F L O

W

PLAN VIEW

PROVIDE VOLUME

DAMPER AT EACH

BRANCH DUCT

1/4W OR 4" MIN.

BRANCH DUCT

MAIN EXHAUST OR RETURN

AIR FLOW

AIR FLOW

VD

W

PLAN VIEW

NOTES:

1. DELETE INSULATION STAND-OFF ON DUCTWORK WITHOUT EXTERIOR INSULATION.

2. DETAIL SHOWS SINGLE BLADE DAMPER. DAMPER INSTALLATION SHALL BE SIMILAR

FOR MULTI-BLADE DAMPERS & ROUND DAMPERS.

SECTIONSIDE ELEVATION

1/2" ROUND ROD PIN

1/8" CLEARANCE

ALL AROUND

INSIDE END

BEARING

INSULATION

STAND-OFF

DAMPER BLADE

HANDLE

WITH

LOCKING

QUADRANT

STIFFEN BLADE

AS REQUIRED

INSULATION SEE

SPECIFICATION

DUCT

OUTSIDE END BEARING

LOAD RATED

FASTENERS

BAND OF SAME

SIZE AS HANGER

STRAP

50"Ø & UNDER

HANGER RODS

BAND

OVER 50"Ø

NOTE:

TABULATED DATA FROM SMACNA

ALLOWS FOR DUCT REINFORCING AND

INSULATION, BUT NOT EXTERNAL LOAD

MAX

DUCT Ø

(IN.)

QUANTITY/SIZE (IN.) MAX LOAD

(LBS.)

MAX SPACING

(IN.)

ONE 1 x 22 GA STRAP

ONE 1 x 18 GA STRAP

ONE 1 x 16 GA STRAP

TWO 3/8 Ø RODS

TWO 1/2 Ø RODS

HANGER STRAPS OR RODS

NOTE:

1. NO FLEXIBLE DUCT FOR CLEAN STORAGE.

2. WHEN MOUNTED IN A GYPSUM BOARD CEILING PROVIDE, MANUFACTURERS SURFACE

MOUNT TRIM FRAME.

VOLUME DAMPER

W/LOCKING QUAD

SHEET

METAL

SADDLE

CEILING

TYPICAL DIFFUSER OR

REGISTER IN LAY-IN

CEILING

FLEXIBLE DUCT SIZE SAME

AS DIFFUSER INLET: 5'-0"

MAX. LENGHT

USE RIGID ELBOWS FOR

CHANGE OF DIRECTION

GREATER THAN 45°

SUPPORT SADDLE

FROM STRUCTURE

SEE SPECIFICATION

FOR CLAMPS AND

SEALANT (TYP.) THERMAL

INSULATION, SEE

SPECIFICATIONS

CONICAL OUTLET

BRANCH DUCT

12"

NOTES:

1. NO FLEXIBLE DUCT FOR CLEAN STORAGE.

2. RIGID STRAIGHT TERMINAL UNIT INLET LENGTH SHALL BE A MINIMUM OF 3 TIMES THE DIAMETER OF

INLET.

3. A FLEXIBLE AIR DUCT CONNECTOR IS NOT MANDATORY FOR INLET TO THIS BOX, BUT ALLOWED TO

ACCOMODATE MINOR OFFSETS. MAXIMUM LENGTH 3'-0".

4. A BRANCH DUCT SERVING AN INDIVIDUAL BOX MAY BE THE SAME SIZE AS THE BOX INLET, PROVIDED

THE EQUIVALENT LENGTH OF THE BRANCH DUCT, AS SHOWN, DOES NOT EXCEED 10 FEET. FOR

LONGER LENGTHS, INCREASE THE DUCT SIZE AND PROVIDE A DUCT TRANSITION TO MAINTAIN THE

DUCT STATIC PRESSURE DROP AT OR BELOW 0.2"/100'.

5. FLEXIBLE AIR DUCT CONNECTORS, WHEN USED FROM TERMINAL UNIT SUPPLY AIR DUCT TO DIFFUSER, SHALL NOT EXCEED 5'-0". USE RIGID ELBOWS FOR CHANGE OF DIRECTION GREATER THAN 45°.

6. COMPONENT ARRANGEMENT MAY VARY BY MANUFACTURER. PROVIDE INSULATION W/VAPOR BARRIER

FOR CONNECTING DUCT SECTIONS.

7. USE OF THE FLEXIBLE AIR DUCT CONNECTORS ARE NOT PERMITTED FOR THE DEDICATED AHU

SERVING THE SURGICAL SUITE.

AIR TERMINAL UNIT

(CV OR VAV)

SEE NOTE 5

SEE SPECIFICATIONS FOR

CLAMPS AND SEALANT (TYP.)

AIR DISTRIBUTION VARIES

WITH ROOM LAYOUT

FLEXIBLE AIR DUCT

CONNECTOR. SEE DETAIL

SOUND ATTENUATOR SEE

EQUIPMENT SCHEDULE

REHEAT COILSEE NOTE 1

SEE NOTE 2

SEE NOTE 3S

U

P P

L Y

A

IR

D U

C T

S E

E N

O T

E

NOTES:

1. ALL VANE ELBOWS SHALL BE CONSTRUCTED AND INSTALLED AS DETAILED BY SMACNA.

2. WHEN W1 DOES NOT EQUAL W2, VANE SHALL BE SINGLE THICKNESS VANE TYPE

REGARDLESS OF W DIMENSION.

3. ALL SINGLE THICKNESS VANES SHALL HAVE A 2" RADIUS, 1-1/2" MAXIMUM SPACE BETWEEN

VANES AND A 3/4" TRAILING EDGE.

4. WHEN W EQUAL W2 AND W1 IS GREATER THAN 20" VANES SHALL BE DOUBLE VANE TYPE.

W1

W

OA INTAKE

EXHAUST

AIR

NOTES:

1. THE INTERIOR SURFACE OF ALL RADIUS ELBOWS SHALL BE MADE ROUND.

2. ALL STANDARD ELBOWS CAN BE SUBSTITUTED WITH SHORT RADIUS ELBOWS.

ALL SHORT RADIUS ELBOWS SHALL HAVE VANES. VANES SHALL BE

CONSTRUCTED , SUPPORTED AND FASTENED AS RECOMMENDED BY SMACNA.

STANDARD RADIUS OR

LONG RADIUS ELBOW

SHORT RADIUS ELBOW

WITH ONE VANE

SHORT RADIUS ELBOW

WITH TWO VANES

R

SHALL

EQUAL OR

BE

GREATER

THAN 1/6 W

R

SHALL

EQUAL OR

BE

GREATER

THAN 1/3 W

R

SHALL

EQUAL OR

BE

GREATER

THAN W

R

W

W

2/3W

R

/3

W

/3

W

1/2W

VAN

E

VAN

E R

W

1/6W

Engineers Architects

Revisions: Date

Drawing Title

Approved: Project Director

Project Title

Location

VA PROJECT NUMBER

Building Number

Drawing Number

Dwg of

VA FORM 08-6231

VA Southern Nevada Health

System (VASNHS)

CONSULTANTS: PROJECT MANAGER

Date Checked Drawn

ACG Project Number

Headquarters:

Apogee Consulting Group, P.A.

1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.

/1

/2

:1

:1

P M

M-502

MECHANICAL DETAILS

11 15

Tikisha Slan

PA, NAS

Renovate Logistics Space Design

6900 N. Pecos Road North Las Vegas, NV 89086

04/03/2020

100% CONSTRUCTION DOCUMENTS

593-18-30218-352

RBK

Scale: No Scale

DUCTWORK TRANSITIONS (WITH EQUIPMENT MOUNTED IN

DUCT)

Scale: No Scale

SUPPLY DUCT TAKE-OFFS

Scale: No Scale

SUPPLY DUCT TAKEOFF - AIR TERMINAL UNITS

Scale: No Scale

EXHAUST OR RETURN BRANCH DUCTWORK

Scale: No Scale

VOLUME DAMPER DETAIL

Scale: No Scale

ROUND DUCT HANGERS

Scale: No Scale

FLEXIBLE AIR DUCT CONNECTOR

Scale: No Scale

DUCT CONNECTIONS - AIR TERMINAL UNITS

Scale: N.T.S.

DUCTWORK SQUARE VANE ELBOWS

Scale: 12" = 1'-0"

AHU ELEVATION DETAIL

Scale: N.T.S.

DUCTWORK RADIUS ELBOW

RETURN OR

EXHAUST AIR

CLEAN

STEAM

SUPPLY

MODULATING 1/3

CONTROL VALVE

V-2/1

STEAM

CONDENSATE

RETURN

10'-0" MIN.

SUPPLY AIR

V-0

RAH

TSH

ZC

PC

AFS HHL

STEAM HUMIDIFIER:

RETURN (OR EXHAUST) AIR HUMIDITY SHALL BE MONITORED.

ON A CALL FOR HUMIDIFICATION, HUMIDIFIER VALVE V-2/1 SHALL OPEN AND MODULATE TO

MAINTAIN THE RETURN (OR EXHAUST) AIR HUMIDITY SET POINT TO 30% (ADJUSTABLE).

ON CALL FOR ADDITIONAL HUMIDITY VALVE V-2/2 SHALL OPEN AND MODULATE TO

MAINTAIN THE HUMIDITY.

PRIOR TO ACTIVATION OF V-2/1, THE ON/OFF CONTROL VALVE V-0 SHALL BE ENABLED

THROUGH ECC AND JACKET TEMPERATURE SENSED BY TSH SHALL BE WARM ENOUGH TO

PREVENT CONDENSATION.

THE AIRFLOW SWITCH SHALL PROVE AIRFLOW BEFORE HUMIDITY CONTROLS ARE

ACTIVATED.

MODULATING 2/3

CONTROL VALVE V-2/2

SEQUENCE OF OPERATION FOR RTU:

1. GENERAL:

1.1. THE UNIT SHALL OPERATE 24/7.

1.2. H-O-A SWITCH SHALL BE KEPT IN “AUTO” POSITION AND “OFF” POSITION SHALL BE USED ONLY FOR MAINTENANCE.

1.3. WHEN THE UNIT IS OFF DAMPERS D-1, AND D-2 SHALL CLOSE AND STATUS SHALL BE AVAILABLE ON THE BMS SYSTEM VIA ACTUATOR END SWITCHES.

1.4. WHEN UNIT IS COMMANDED ON, DAMPERS D-1, AND D-2 SHALL OPEN (STATUS INDICATED ON BMS VIA END SWITCHES). AFTER SAFETIES CHECK UNIT SHALL START.

2. TEMPERATURE CONTROL:

2.1. SUPPLY AIR TEMPERATURE AND HUMIDITY SETPOINT (AS SET BY BMS), SET BY SENSOR TT-8 AND HT-4, SHALL BE MAINTAINED BY SEQUENCING VALVES V-1, V-2, AND V-3. VALVES SHALL OPEN BASED ON SUPPLY AIR CONDITIONS AND SHALL NOT OPEN SIMULTENOUSLY.

3. AIRFLOW CONTROL:

3.1. THE SUPPLY AIR FLOW SHALL BE CONTROLLED BY THE BMS, MODULATING THE SUPPLY FAN VFD TO MAINTAIN SUPPLY STATIC PRESSURE SENSED BY SPS-1.

3.2. THE SPACES SERVED BY RTU SHALL BE MAINTAINED AT PRESSURE DIFFERENTIAL AS INDICATED ON THE DRAWINGS. CONTRACTOR SHALL PROVIDE TWO NEW

DIFFERENTIAL PRESSURE SENSORS TO MONITOR PRESSURE DIFFERENCE BETWEEN CLEAN STORAGE AND WAREHOUSE AND BREAK OUT ROOM.

3.3. THE EXHAUST VALVES SHALL TRACK SUPPLY VAVS AND SHALL MAINTAIN SPACE PRESSURES AS INDICATED ON THE DRAWINGS.

3.4. THE SUPPLY FAN AND RETURN AIR FAN TOTAL AIR FLOW SHALL BE TRACKED, AS SENSED BY AFT-3 AND AFT-4, TO MAINTAIN SPACE PRESSURIZATION.

3.5. THE HIGH-PRESSURE SENSOR PSH SHALL PREVENT SUPPLY AIR FAN DEVELOPING OVER 3” STATIC PRESSURE. THE SENSOR SHALL BE HARD WIRED TO SUPPLY FAN

MOTOR. IF HIGHER PRESSURE IS DEVELOPED, THE FAN SHALL SHUT OFF. UNIT SHALL BE MANUALLY RESTARTED.

3.6. THE LOW-PRESSURE SENSOR PSL SHALL PREVENT RETURN AIR FAN FROM DEVELOPING OVER 3” OF NEGATIVE STATIC PRESSURE. THE SENSOR SHALL BE HARD

WIRED TO RETURN FAN MOTOR. IF HIGHER NEGATIVE PRESSURE IS DEVELOPED, THE FAN SHALL SHUT OFF. UNIT SHALL BE MANUALLY RESTARTED.

4. HUMIDITY CONTROL:

4.1. THE SUPPLY AIR, RETURN AIR, AND OUTSIDE AIR RELATIVE HUMIDITY SHALL BE COMPARED AND ACCORDINGLY, HUMIDITY IN SUPPLY AIR SHALL BE ADDED.

4.2. ON CALL FOR HUMIDITY INCREASE THE CONTROL VALVE V-2 AT HUMIDIFIER SHALL OPEN AND STEAM SHALL BE DISPERSED INTO THE AIR STREAM IN THE HUMIDIFIER

SECTION.

4.3. WHEN RETURN AIR DEW POINT IS HIGHER THAN 45 DEGREES F. (ADJ), VALVE V-2 SHALL CLOSE AND NO STEAM INJECTION WILL BE DONE.

4.4. FOR DEHUMIDIFICATION, TERMINAL REHEAT COILS SHALL BE USED TO MAINTAIN THE SPACE CONDITIONS.

5. FREEZE PROTECTION:

5.1. IF THE AIR TEMPERATURE AS SENSED BY TT-5 FALLS BELOW 40 DEGREES F. (ADJ), AN ALARM WILL BE GENERATED AT THE BMS FRONT END.

5.2. THE FREEZESTAT SHALL BE SET AT 32 F (ADJ). IF THE AIR TEMPERATURE FALLS BELOW 32 F (ADJ) THE UNIT SUPPLY AND RETURN FANS SHALL BE DE-ENERGIZED.

UNIT WILL SHUT OFF AND DAMPERS D-1 AND D-2 SHALL CLOSE. UNIT SHALL BE MANUALLY RESTARTED.

5.3. DURING NO-FLOW CONDITIONS AS SENSED BY FLOW TRANSMITTER FT-1 AND WHEN AIR TEMPERATURE AS SENSED BY TT-5 IS BELOW 35 DEGREES F. (ADJ), THE UNIT

WILL SHUT OFF AS STATED ABOVE. UNIT SHALL BE MANUALLY RESTARTED.

5.4. IF NO WATER FLOW IS DETECTED ON CALL FOR HEATING AS SENSED BY FT-1, AN ALARM WILL BE GENERATED AND ABOVE FREEZE PROTECTION SEQUENCE SHALL BE

FOLLOWED.

6. LOSS OF COOLING PROTECTION:

6.1. IF THE SUPPLY AIR TEMPERATURE AS SENSED BY TT-8 IS ABOVE 65 DEGREES F. (ADJ), AN ALARM WILL BE GENERATED AT THE BMS FRONT END. IF THE TEMPERATURE

RISES TO 70 DEGREES F. (ADJ), THE UNIT WILL SHUT OFF AS STATED ABOVE.

6.2. IF ON CALL FOR COOLING NO WATER FLOW IS DETECTED AS SENSED BY FLOW TRANSMITTER FT-2, AN ALARM WILL BE GENERATED AT THE BMS FRONT END AND

ABOVE SEQUENCE SHALL BE FOLLOWED.

7. AUTOMATIC SMOKE SHUTDOWN/RESTART:

7.1. IF SMOKE IS DETECTED BY ANY SMOKE DETECTOR SMD-1, OR 2, THE SUPPLY AND RETURN AIR FANS SHALL BE DEENERGIZED AND UNIT SHALL SHUT DOWN AS STATED

ABOVE.

7.2. THE UNIT SHALL BE STARTED MANUALLY.

8. EMERGENCY CONSTANT SPEED OPERATION:

8.1. UPON FAILURE OF ANY ONE VFD, FOR BOTH SUPPLY AND RETURN FAN ARRAYS, AN ALARM WILL BE GENERATED AND THE REMANING FANS WILL RAMP UP THEIR

SPEED TO MAINTAIN REQUIRED CFM.

9. HYDRONIC CONTROL:

9.1. THE HOT WATER SUPPLY AND RETURN TEMPERATURE FOR PREHEAT COIL SHALL BE MONITORED AT BMS FRONT END VIA TT-A AND TT-B. THE FLOW (GPM) SHALL BE

MONITORED VIA FT-1.

9.2. IF THE HOT WATER SUPPLY TEMPERATURE IS ABOVE 190 DEGREES F. (ADJ), AN ALARM SHALL BE GENERATED AT BMS FRONT END.

9.3. IF THE HOT WATER SUPPLY TEMPERATURE IS BELOW 150 DEGREES F, (ADJ), AN ALARM SHALL BE GENERATED AT BMS FRONT END.

9.4. THE CHILLED WATER SUPPLY AND RETURN TEMPERATURES FOR COOLING COIL SHALL BE MONITORED AT BMS FRONT END VIA TT-C AND TT-D. THE FLOW SHALL BE M

ONITORED VIA FT-2.

9.5. IF THE CHILLED WATER SUPPLY TEMPERATURE IS ABOVE 48 DEGREES F. (ADJ), AN ALARM SHALL BE GENERATED AT THE BMS FRONT END.

10. AIRFLITER MONITORING:

10.1. THE PRESSURE DROP ACROSS PREFILTER-1, 2 AND 3 AND FINAL FILTERS SHALL BE MONITORED AT THE CENTRAL BMS.

10.2. IF THE PRESSURE DROP EXCEED THE SETPOINT (TBD IN CONJUNCTION WITH VA), ALARM WILL BE GENERATED AT THE BMS FRONT END.

11. ENERGY MONITORING:

11.1. THE BMS SYSTEM SHALL MONITOR BOTH AIR SIDE AND WATER SIDE BTUS AND DEVELOP A CHART TO SHOW WEEKLY/MONTHLY BTU USE.

RTU POINT LIST

POINT DESCRIPTION POINT ID

ANALOG INPUT

(AI)

BINARY INPUT

(BI)

ANALOG OUTPUT

(AO)

BINARY OUTPUT

(BO)

AV BV TREND

ALARM

POINT

OTHER NOTES

AIR FLOW MEASUREMENT AFT-2 1 X

RA TEMPERATURE TT-1 1 X

RA DAMPER D-1 1

AIR FLOW MEASUREMENT AFT-1 1 X

OA TEMPERATURE TT-2 1 X

OA HUMIDITY HT-1 1 1 X 1

OA DAMPER D-2 1

SMOKE DETECTOR SMD-1 1

LOW PRESSURE SENSOR PSL 1 1 X 1

EA TEMPERATURE TT-3 1 X

EA FAN AIRFLOW AFT-3 3 X

EA FAN START/STOP (X2) 4 4

EA FAN STATUS (X2) 4

EA FAN VFD STATUS (X2) 4 4

EXHAUST AIR DAMPER D-3 1

SUPPLY AIR TEMPERATURE TT-4 1 X

SUPPLY AIR HUMIDITY HT-2 1 X

PREFILTER-1 PRESSURE DROP DPS-1 1 1 X 1

PREFILTER-2 PRESSURE DROP DPS-2 1 1 X 1

INLET AIR TEMPERATURE TT-4 1 X

HEATING CONTROL VALVE V-1 1 X

HW FLOW FT-1 1 X

HWS TEMP TT-A 1 1 X 1

HWR TEMP TT-B 1 X

FREEZE STAT TSL-1 1 1 1

HW COIL OUT AIR TEMPERATURE TT-5 1 X

COOLING COIL CONTROL VALVE V-3 1 X

CHW FLOW FT-2 1 X

CWS TEMP TT-C 1 1 X 1

CWR TEMP TT-D 1 X

CC INLET AIR TEMPERATURE TT-6 1 X

CC OUTLET AIR TEMPERATURE TT-7 1 X

SA FAN AIRFLOW AFT-4 1 X

SA FAN START/STOP (X2) 4 4

SA FAN STATUS (X2) 4

SA FAN VFD STATUS (X2) 4 4

AIR TEMPERATURE TT-8 1 X

FINAL FILTER PRESSURE DROP PDS-4 1 1 X 1

STEAM CONTROL VALVE V-2 1

HUMIDIFIER STATUS CSG-1 1 1

HIGH PRESSURE SENSOR PSH-1 1 1 1

SA SMOKE DETECTOR SMD-2 1 1

SA HUMIDITY HT-4 1 X

SA STATIC PRESSURE SENSOR

RETURN AIR HUMIDITY HT-5 1 X

SUPPLIED BY MC INSTALLED BY FA CONTRACTOR

SUPPLIED BY MC INSTALLED BY FA CONTRACTOR

SYSTEM GRAPHICS 1 NEW GRAPHICS ON EXISITNG FRONT END BMS

SPS-1 1 X

A F

M D

M E

R V

DPS

M E

R V

DPS

1 2

TT

OA

AFT

D-2

HT

HX

M E

R V

H W

H E

A T

IN

G

C H

W C

O O

L

IN

G

H U

M

ID

IF

IE

R

M E

R V

A F

M D

AFT

TT

D-1

RA

DPS

TT

TT

TT

TT

TT

PSL

HT

TSL

HT

V-1

TT

EXHAUST FAN

VFDAFMD

SMD

AFT

D-3

EA

FT

TT

B

TT

A

V-2 (x2)

V-3

FT

TT

D

TT

C

SUPPLY FAN

(TWO FAN ARRAY)

AFMDVFD

AFT

DPS

SA

HT

PSH

SMD

SPS

(2/3 rd DOWNSTREAM)

HT

SUPPLIED BY MC INSTALLED

BY FA CONTRACTOR

SUPPLIED BY MC INSTALLED

BY FA CONTRACTOR

Engineers Architects

Revisions: Date

Drawing Title

Approved: Project Director

Project Title

Location

VA PROJECT NUMBER

Building Number

Drawing Number

Dwg of

VA FORM 08-6231

VA Southern Nevada Health

System (VASNHS)

CONSULTANTS: PROJECT MANAGER

Date Checked Drawn

ACG Project Number

Headquarters:

Apogee Consulting Group, P.A.

1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.

/1

/2

:1

:1

P M

M-503

MECHANICAL CONTROLS

12 15

Tikisha Slan

PA, NAS

Renovate Logistics Space Design

6900 N. Pecos Road North Las Vegas, NV 89086

04/03/2020

100% CONSTRUCTION DOCUMENTS

593-18-30218-352

RBK

Scale: No Scale

STEAM HUMIDIFICATION CONTROLS

Scale: No Scale

RTU SEQUENCE OF OPERATION

Scale: No Scale

RTU CONTROL POINTS LIST

Scale: No Scale

RTU CONTROL SCHEMATIC

SUPPLY SERVICE

WAREHOUSE

BG115

CLEAN STORAGE

BG105

DELIVERY PREP

BG104

PIPING ROOM

CB-7

CORRIDOR

CB-8

BREAK OUT ROOM

BG106

UTILITY TRENCH ACCESS

ROOM

BE103

MAIL

BG102

STAFF TOILET

BG108

STAFF TOILET

BG107

SA: 2480 CFM

RA: 1740 CFM

SA: 840 CFM

RA: 1060 CFM

SA: 660 CFM

RA: 880 CFM370 CFM 370 CFM

150 CFM

150 CFM

DA

AO - REHEATING VALVE

HW

M

HWS HWR

T

AI - DISCHARGE AIR TEMP

AI - AIRFLOW

M

AO - ZONE DAMPER

SA

T AI - ZONE TEMP

AI - ZONE SETPOINT ADJUST

F

H AI - ZONE HUMIDITY

AI - ZONE HUMIDITY SETPOINT

ADJUST (FOR STORAGE ONLY)

ONLY FOR VAV

ONLY FOR VAV

BREAKOUT

CLEAN ROOM STORAGE

DELIVERY

PREP (DPS)

TO CONTROLLER

TO EF

AI - AIRFLOW

M

AO - ZONE DAMPER

EA

F

CONTROLLER

EV'S TO TRACK VAV'S TO

MAINTAIN PRESSURE

RELATIONSHIP.

VAV TERMINAL UNIT

VARIABLE AIR VOLUME - TERMINAL UNIT

RUN CONDITIONS - CONTINUOUS:

THE UNIT SHALL RUN CONTINUOUSLY TO MAINTAIN HEATING AND COOLING SET POINTS.

ALARMS SHALL BE PROVIDED AS FOLLOWS:

• HIGH ZONE TEMP: IF THE ZONE TEMPERATURE IS GREATER THAN THE COOLING SETPOINT BY A USER

DEFINABLE AMOUNT (ADJ.).

• LOW ZONE TEMP: IF THE ZONE TEMPERATURE IS LESS THAN THE HEATING SETPOINT BY A USER

DEFINABLE AMOUNT (ADJ.).

ZONE SETPOINT ADJUST:

T…